HomeMy WebLinkAbout19-10 CC Resolution RESOLUTION NO. 19-10
A RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF TEMECULA AMENDING THE CAPITAL
IMPROVEMENT PROGRAM FISCAL YEARS 2019-23
AND AMENDING THE CAPITAL IMPROVEMENT
BUDGET FOR FISCAL YEAR 2018-19
THE CITY COUNCIL OF THE CITY OF TEMECULA DOES HEREBY RESOLVE AS
FOLLOWS:
Section 1. Recitals. The City Council hereby finds, determines and declares that:
A. On June 12, 2018, the City Council adopted Resolution No. 18-40"approving
the City of Temecula Capital Improvement Program Fiscal Years 2019-23"
(CIP).
B. Amend the Fiscal Years 2019-23 Capital Improvement Program to add the
I-15 Congestion Relief Project; the Pedestrian Signal Equipment Upgrade-
Citywide Project; and the Traffic Signal System Upgrade Project.
C. Amend the 2018-19 appropriation for the French Valley Parkway/I-15
Improvements-Phase III project, to allocate an additional $150,000 in
2018-19 from the Measure S Fund.
D. Appropriate $400,000 in 2018-19 to the I-15 Congestion Relief Project from
the General Fund.
E. Appropriate$38,000 in 2018-19 to the Pedestrian Signal Equipment Upgrade-
Citywide Project from the Measure S Fund.
F. Appropriate$38,000 in 2018-19 to the Traffic Signal System Upgrade Project
from the Measure S Fund.
G. On February 20, 2019, the Planning Commission found the Capital
Improvement Program consistent with the General Plan in accordance with
Government Code Section 65401 of State Planning and Zoning Law.
H. Adoption of these Amendments are categorically exempt from environmental
review under the California Environmental Quality Act (CEQA). Pursuant to
Sections 15262 and 15061 (b) (3) of the State Guidelines for Implementation
of CEQA, a project involving only feasibility or planning studies for possible
future actions because it can be seen with certainty that this prioritizing and
fund allocation program set forth in the Amendment cannot and does not have
the potential to cause a significant effect on the environment. No physical
activity will occur until all required CEQA review is conducted at the time the
physical improvements prioritized in the Amendment are undertaken. The
Council reaffirms and incorporates herein the findings set forth in Section 1 of
Resolution No. 18-40.
I. The budget and appropriation for these projects are set forth in Exhibit 1, and
are hereby approved.
Section 2. Certification: The City Clerk shall certify the adoption of this resolution.
PASSED, APPROVED, AND ADOPTED by the City Council of the City of Temecula
this 26th day of February, 2019.
Michael S.Naggar, Mayor
ATT •
Randi ohl, City Clerk
[SEAL]
2
STATE OF CALIFORNIA )
COUNTY OF RIVERSIDE ) ss
CITY OF TEMECULA )
I, Randi Johl, City Clerk of the City of Temecula, do hereby certify that the foregoing
Resolution No. 19-10 was duly and regularly adopted by the City Council of the City of Temecula
at a meeting thereof held on the 26th day of February, 2019,by the following vote:
AYES: 5 COUNCIL MEMBERS: Edwards, Rahn, Schwank, Stewart,
Naggar
NOES: 0 COUNCIL MEMBERS: None
ABSTAIN: 0 COUNCIL MEMBERS: None
ABSENT: 0 COUNCIL MEMBERS: None
Randi Johl, City Clerk
3
EXHIBIT 1
("7"'"'"‘...e/mkiett..::
R Capital Improvement Program
Fiscal Years 2019-23
FRENCH VALLEY PARKWAY/I-15 IMPROVEMENTS-PHASE III
Circulation Project
Project Description: This project includes the design and construction of the French Valley Parkway Interchange and the southbound
collector/distributor road system.
Benefit I Core Value: This project will address and improve traffic circulation in the City's northern area by providing a full service
interchange with on and off ramps in both directions. In addition,this project satisfies the City's Core Value of Transportation Mobility and
Connectivity.
Project Status: Based on funding availability,the design will begin once construction is complete for Phase II of the project.
Department: Public Works-Account No.210.265.728 Level: I
Prior Years FYE 2018 Midyear 2022-23
Project Cost: Actual Carryover 2018-19 2019-20 2020-21 2021-22 Projected and
Expenditures Budget Projected Projected Projected Projected Future Years Total Project Cost
Administration $ 100,000 $ 1,268,000 $ 1,368,000
Acquisition $ 50,000 $ 8,400,000 $ 8,450,000
Caltrans Oversight $ 15,200,000 $ 15,200,000
Construction $102,500,000 $ 102,500,000
Engineering $ 2,050,000 $ 2,050,000
Design/Environmental $ 10,460,000 $ 10,460,000
Totals $ - $ - $ 150,000 $ - $ - $139,878,000 $ - $ 140,028,000
Prior Years FYE 2018 Midyear 2022-23
Source of Funds: Actual Carryover 2018-19 2019-20 2020-21 2021-22 Projected and
Expenditures Budget Projected Projected Projected Projected Future Years Total Project Cost
Measure S $ 150,000 $ 150,000
TUMF(wRCOG)w $ 9,822,980 $ 9,822,980
TUMF(wRcoG)«' $ 43,480,000 $ 43,480,000
Unspecified"' $ 86,575,020 $ 86,575,020
Total Funding: $ - $ - $ 150,000 $ - $ - $139,878,000 $ - $ 140,028,000
Future Operation&
Maintenance Costs: 2018-19 2019-20 2020-21 2021-22 2022-23
I I I I I I I
(1) TUMF(WRCOG)-TUMF Zone Funding is eligible for construction of Winchester Interchange pursuant to 2009 Nexus-$9,822,980.00
(2)TUMF(WRCOG)-TUMF Zone Funding is eligible for construction of French Valley Interchange pursuant to 2009 Nexus-$43,480,000.00.
(3)The implementation for this project extends beyond FY 2022-23. Project cannot be constructed until a funding source is identified.
i R Capital Improvement Program
Fiscal Years 2019-23
I-15 CONGESTION RELIEF
Circulation Project
Project Description: This project includes the design and construction of a single auxiliary lane, northbound Interstate 15(1-15)
connecting the Temecula Parkway on-ramp to the Rancho California Road off-ramp.
Benefit/Core Value: This project provides an operational improvement to relieve congestion on northbound 1-15. It represents one
of several operational improvements identified by the Move 1-15 Regional Task Force to address congestion on 1-15. This project also
satisfies the City's Core Value of Transportation Mobility and Connectivity.
Project Status: Project development is set to commence on the later part of Fiscal Year 2018-19
Department: Public Works-Account No.210.265.609 Level: I
Prior Years FYE 2018 Midyear 2022-23
Project Cost: Actual Carryover 2018-19 2019-20 2020-21 2021-22 Projected and Total Project
Expenditures Budget Projected Projected Projected Projected Future Years Cost
Administration $ 50,000 $ 200,000 $100,000 $ 200,000 $ 550,000
Construction $1,250,000 $2,528,500 $ 3,778,500
Const Engineering $ 321,500 $ 321,500
Design/Environmental $350,000 $ 350,000
Totals $ - $ - $400,000 $1,450,000 $100,000 $3,050,000 $ - $ 5,000,000
Prior Years FYE 2018 Midyear 2022-23
Source of Funds: Actual Carryover 2018-19 2019-20 2020-21 2021-22 Projected and Total Project
Expenditures Budget Projected Projected Projected Projected Future Years Cost
General Fund $400,000 $ 200,000 $ 600,000
SHOPP(11 $1,250,000 $ 1,250,000
Unspecified') $100,000 $3,050,000 $ 3,150,000
Total Funding: $ - $ - $400,000 $1,450,000 $100,000 $3,050,000 $ - $ 5,000,000
Future Operation&
Maintenance Costs: 2018-19 2019-20 2020-21 2021-22 2022-23
(1)SHOPP-State Highway Operation and Protection Program and Minor Program
(2)Project cannot be constructed until a funding source is identified.
Capital Improvement Program
Fiscal Years 2019-23
PEDESTRIAN SIGNAL EQUIPMENT UPGRADE -CITYWIDE
Infrastructure/Other Project
Project Description: This project will install pedestrian countdown signal heads, ADA compliant pedestrian pushbutton
equipment and upgrade traffic signal controllers to improve safety and operations at signalized intersections Citywide including
the Butterfield Stage Road, Jefferson Avenue, Margarita Road, Redhawk Parkway, Pechanga Parkway, Rancho Califomia
Road,Temecula Parkway and Ynez Road corridors.
Benefit / Core Value: This project improves pedestrian safety and traffic circulation throughout the City. In addition this
project satisfies the City's Core Values of a Healthy and Livable Community and A Safe and Prepared Community.
Project Status: This project is estimated to be complete by June 30,2020.
Department: Public Works-Account No.210.265.518 Level:
2022-23
Project Cost: Prior Years FYE 2018 Midyear Projected Total
Actual Carryover 2018-19 2019-20 2020-21 2021-22 and Future Project
Expenditures Budget Projected Projected Projected Projected Years Cost
Administration $ 5,000 $ 5,000
Acquisition $ -
Construction $803,200 $803,200
Construction Engineering $105,000 $105,000
Design/Environmental $ 33,000 $ 33,000
Utilities $ -
Totals $ - $ - $ 38,000 $908,200 $ - $ - $946,200
Source of Funds: Prior Years FYE 2018 Midyear Total
Actual Carryover 2018-19 2019-20 2020-21 2021-22 2022-23 Project
Expenditures Budget Projected Projected Projected Projected Projected Cost
HSI P"' $908,200 $908,200
Measure S $ 38,000 $ 38,000
Total Funding: $ - $ - $ 38,000 $908,200 $ - $ - $ - $946,200
Future Operation&Maintenance
Costs: 2019-20 2020-21 2021-22 2022-23 2023-24
(1)Highway Safety Improvement Program
filt
( � Capital Improvement Program
Fiscal Years 2019-23
TRAFFIC SIGNAL SYSTEM UPGRADE
Circulation Project
Project Description: This project will install protected/permissive traffic signal heads, on new signal poles and signal mast arms,
relocate existing equipment and modify existing striping and raised medians at the following five(5) intersections: Margarita Road at
Verdes Lane, Ynez Road at Town Center North and Town Center South, Redhawk Parkway at Paseo Parallon/Overland Trail, and
Winchester Road at Enterprise Circle.
Benefit/Core Value: This project improves traffic safety and circulation throughout the City. In addition,this project satisfies the City's
Core Values of A Safe and Prepared Community,and Transportation Mobility and Connectivity.
Project Status: This project is estimated to be complete by June 30,2020.
Department: Public Works-Account No.210.265.610 Level: I
Project Cost: Prior Years FYE 2018 2022-23
Actual Carryover Midyear 2018- 2019-20 2020-21 2021-22 Projected and Total Project
Expenditures Budget 19 Projected Projected Projected Projected Future Years Cost
Administration $ 5,000 $ 5,000
Construction $481,900 $ 481,900
Construction Engineering $ 62,000 $ 62,000
Design/Environmental $ 33,000 $ 33,000
Totals $ - $ - $ 38,000 $543,900 $ - $ - $ - $ 581,900
Source of Funds: Prior Years FYE 2018
Actual Carryover Midyear 2018- 2019-20 2020-21 2021-22 2022-23 Total Project
Expenditures Budget 19 Projected Projected Projected Projected Projected Cost
HSIPol $489,510 $ 489,510
Measure S $ 38,000 $ 54,390 $ 92,390
Total Funding: $ - $ - $543,900 $ - $ - $ - $ 581,900
Future Operation&Maintenance
Costs: 2018-19 2019-20 2020-21 2021-22 2022-23
( 1 I [$ -I$ -I$ -I
(1)Highway Safety Improvement Program