HomeMy WebLinkAboutTract Map 20879-1 Lot 71 Hydro ReportAPPROVED BY CITY OF TEMECULA PUBLIC WORKS david.pina 11/07/2024 11/07/2024 11/07/2024 11/07/20 Hydrology Report for The Shine Residence 31920 Vineyard Ave Temecula CA 92591-4921 Table of Contents Project Description 3 Project Setting 3 Pre-Project 3 Post Project 3 Interim Condition 3 Hydrology 4 Purpose 4 Description of Watershed 4 Methodology 4 Summary of Findings 5 Project Description The resident of 31920 Vineyard Ave in Temecula,California,is proposing installing a swimming pool and terrace area on their property.The pool and terrace area will be located in the back of the property. Project Setting The project is located in a predominantly residential area of Temecula.Most of the area is composed of single-family homes. Pre-Project The site is flat around the existing single-family residence.It also has a small hill towards the back of the property.The property elevation goes from 1,240 feet in the front to 1,256 feet in the back.The majority of the property is flat.Most of the property is landscaped and covered with grass,with the rest covered in hardscape and concrete. The property's current drainage pattern goes from the back toward the front street.The property sheet flows from the northeast corner toward the southwest corner. Post Project When the proposed pool and terrace construction is complete,the property will have approximately 2750 square feet of additional concrete surfaces.Additionally,4"drainage pipes will be installed to help convey flows through the property.However,with the additional concrete surfaces and the installation of the drainage pipes within the property,there will not be a significant increase in the amount of flow from the property. Interim Condition For the construction of the proposed swimming pool and the proposed terrace area,the existing hill will be graded to accommodate the installation.The existing embankment will be excavated approximately 15.5 feet,and a 6-foot tall retaining wall will be constructed.Another 17.5 feet of the embankment will be excavated and graded to form the raised terrace area,and an 8-foot tall retaining will be built abutting the adjacent property. Currently,there are no known drainage issues on the property. Hydrology Purpose The purpose of this report and analysis is to discuss the before and after conditions of the project. Description of Watershed The project is located within one residential property.The project site in the pre project condition has a C value of 0.3.This was determined since the majority,about 90%,of the project site is of landscaped character.In the post project condition the C value of the project was determined to be 0.5.The site changed from a landscape mainly composed of grass to a more paved landscape. The C values of 0.3 to 0.5 are values that fit within the description of the project.The project site is characterized as a residential;single family areas. Methodology The determination of the flow rates of the project site were done using the rational method.Given the project site size of 0.25 acres,this method was appropriate.The rational method is based on the following: Q =CIA where, Q =peak discharge -cubic feet per second (cfs) C =Coefficient of Runoff I =Rainfall Intensity (inches /hour)corresponding to the time of concentration A =Area (acres) The time of concentration of the project was assumed to be 5 minutes.And the storm events used for the analysis of the project was for the 10 year and 100 year storm events.Which yielded the following intensities respectively;2.94 inches /hour and 4.94 inches /hour. The area of the project was determined through map measurements and found to be 0.25 acres. Summary of Findings Pre Project Post Project Difference 10 Year -Q (cfs)0.2205 0.3675 0.147 100 Year -Q (cfs)0.3705 0.6175 0.247 The analysis shows that there was less run off in the pre-project condition.This was due to the project being mainly landscape.In the post project condition was an increase of 0.147 cfs in the 10 year storm event and an increase of 0.247 cfs in the 100 year storm event.The increase in run off is due in part that landscape of the project increasing impervious areas with the addition of the pool area and the raised terraces.The increases in runoff from the property to the improve are not significant increases that would cause an adverse effect on any adjacent properties or road infrastructure. NOAA Atlas 14, Volume 6, Version 2 Location name: Temecula, California, USA* Latitude: 33.5159°, Longitude: -117.1029° Elevation: 1242 ft** * source: ESRI Maps ** source: USGS POINT PRECIPITATION FREQUENCY ESTIMATES Sanja Perica, Sarah Dietz, Sarah Heim, Lillian Hiner, Kazungu Maitaria, Deborah Martin, Sandra Pavlovic, Ishani Roy, Carl Trypaluk, Dale Unruh, Fenglin Yan, Michael Yekta, Tan Zhao, Geoffrey Bonnin, Daniel Brewer, Li-Chuan Chen, Tye Parzybok, John Yarchoan NOAA, National Weather Service, Silver Spring, Maryland PF_tabular | PF_graphical | Maps_&_aerials PF tabular AMS-based point precipitation frequency estimates with 90% confidence intervals (in inches/hour)1 Duration Annual exceedance probability (1/years) 1/2 1/5 1/10 1/25 1/50 1/100 1/200 1/500 1/1000 5-min 1.58 (1.33-1.91) 2.39 (2.00-2.88) 2.94 (2.44-3.58) 3.70 (2.96-4.67) 4.31 (3.37-5.56) 4.94 (3.77-6.55) 5.63 (4.16-7.68) 6.59 (4.67-9.41) 7.38 (5.04-10.9) 10-min 1.14 (0.954-1.37) 1.71 (1.43-2.06) 2.11 (1.75-2.56) 2.65 (2.12-3.34) 3.08 (2.41-3.98) 3.55 (2.70-4.70) 4.03 (2.98-5.50) 4.73 (3.35-6.74) 5.29 (3.61-7.82) 15-min 0.916 (0.768-1.10) 1.38 (1.16-1.66) 1.70 (1.41-2.07) 2.14 (1.71-2.70) 2.49 (1.94-3.21) 2.86 (2.18-3.78) 3.25 (2.40-4.44) 3.81 (2.70-5.44) 4.26 (2.91-6.31) 30-min 0.702 (0.588-0.844) 1.06 (0.884-1.27) 1.30 (1.08-1.58) 1.63 (1.31-2.06) 1.90 (1.49-2.46) 2.19 (1.67-2.90) 2.49 (1.84-3.39) 2.91 (2.06-4.16) 3.26 (2.23-4.83) 60-min 0.539 (0.452-0.649) 0.811 (0.679-0.979) 0.998 (0.829-1.22) 1.26 (1.00-1.58) 1.46 (1.14-1.88) 1.68 (1.28-2.22) 1.91 (1.41-2.61) 2.24 (1.58-3.19) 2.50 (1.71-3.70) 2-hr 0.386 (0.324-0.465) 0.576 (0.482-0.695) 0.704 (0.584-0.857) 0.876 (0.701-1.10) 1.01 (0.791-1.30) 1.15 (0.877-1.52) 1.30 (0.960-1.77) 1.50 (1.06-2.14) 1.66 (1.14-2.46) 3-hr 0.313 (0.263-0.377) 0.466 (0.390-0.562) 0.568 (0.471-0.691) 0.703 (0.563-0.888) 0.809 (0.633-1.04) 0.918 (0.700-1.22) 1.03 (0.763-1.41) 1.19 (0.842-1.70) 1.31 (0.897-1.94) 6-hr 0.225 (0.189-0.271) 0.334 (0.280-0.403) 0.406 (0.337-0.494) 0.501 (0.401-0.632) 0.574 (0.449-0.741) 0.649 (0.495-0.861) 0.727 (0.538-0.993) 0.834 (0.590-1.19) 0.918 (0.626-1.36) 12-hr 0.149 (0.125-0.180) 0.222 (0.186-0.268) 0.270 (0.224-0.329) 0.333 (0.266-0.420) 0.381 (0.298-0.492) 0.430 (0.328-0.570) 0.480 (0.355-0.656) 0.550 (0.389-0.784) 0.604 (0.412-0.893) 24-hr 0.097 (0.085-0.112) 0.146 (0.129-0.169) 0.178 (0.156-0.208) 0.221 (0.187-0.266) 0.253 (0.210-0.312) 0.287 (0.232-0.361) 0.321 (0.253-0.416) 0.368 (0.279-0.496) 0.405 (0.297-0.564) 2-day 0.057 (0.050-0.066) 0.089 (0.078-0.103) 0.111 (0.097-0.129) 0.140 (0.118-0.169) 0.163 (0.135-0.201) 0.188 (0.152-0.237) 0.214 (0.169-0.277) 0.250 (0.190-0.337) 0.280 (0.205-0.389) 3-day 0.040 (0.035-0.046) 0.064 (0.056-0.074) 0.081 (0.070-0.094) 0.104 (0.088-0.125) 0.123 (0.102-0.151) 0.143 (0.116-0.180) 0.165 (0.130-0.213) 0.196 (0.149-0.264) 0.222 (0.163-0.309) 4-day 0.033 (0.029-0.038) 0.053 (0.046-0.061) 0.067 (0.059-0.078) 0.087 (0.074-0.105) 0.104 (0.086-0.128) 0.122 (0.099-0.153) 0.141 (0.111-0.183) 0.170 (0.129-0.229) 0.194 (0.142-0.269) 7-day 0.022 (0.019-0.025) 0.035 (0.031-0.041) 0.045 (0.040-0.053) 0.059 (0.050-0.072) 0.071 (0.059-0.087) 0.084 (0.068-0.105) 0.097 (0.077-0.126) 0.118 (0.089-0.159) 0.135 (0.099-0.188) 10-day 0.016 (0.014-0.019) 0.027 (0.024-0.031) 0.035 (0.030-0.041) 0.046 (0.039-0.055) 0.055 (0.045-0.067) 0.065 (0.052-0.081) 0.075 (0.059-0.098) 0.091 (0.069-0.123) 0.105 (0.077-0.146) 20-day 0.010 (0.009-0.012) 0.017 (0.015-0.020) 0.022 (0.019-0.026) 0.029 (0.025-0.035) 0.035 (0.029-0.044) 0.042 (0.034-0.053) 0.049 (0.039-0.064) 0.060 (0.045-0.081) 0.069 (0.051-0.096) 30-day 0.008 (0.007-0.009) 0.014 (0.012-0.016) 0.018 (0.015-0.021) 0.024 (0.020-0.029) 0.029 (0.024-0.035) 0.034 (0.027-0.043) 0.040 (0.031-0.052) 0.049 (0.037-0.066) 0.056 (0.041-0.078) 45-day 0.006 (0.005-0.007) 0.011 (0.009-0.012) 0.014 (0.012-0.016) 0.019 (0.016-0.022) 0.022 (0.019-0.028) 0.027 (0.022-0.034) 0.031 (0.025-0.041) 0.038 (0.029-0.052) 0.044 (0.032-0.062) 60-day 0.005 (0.005-0.006) 0.009 (0.008-0.011) 0.012 (0.010-0.014) 0.016 (0.013-0.019) 0.019 (0.016-0.024) 0.023 (0.019-0.029) 0.027 (0.021-0.035) 0.033 (0.025-0.044) 0.038 (0.028-0.053) 1 Precipitation frequency (PF) estimates in this table are based on frequency analysis of annual maxima series (AMS). Numbers in parenthesis are PF estimates at lower and upper bounds of the 90% confidence interval. The probability that precipitation frequency estimates (for a given duration and annual exceedance probability) will be greater than the upper bound (or less than the lower bound) is 5%. Estimates at upper bounds are not checked against probable maximum precipitation (PMP) estimates and may be higher than currently valid PMP values. Please refer to NOAA Atlas 14 document for more information. Back to Top PF graphical Back to Top Maps & aerials Small scale terrain Large scale terrain Large scale map Large scale aerial Back to Top US Department of Commerce National Oceanic and Atmospheric Administration National Weather Service National Water Center 1325 East West Highway Silver Spring, MD 20910 Questions?: HDSC.Questions@noaa.gov Disclaimer + – 3km 2mi + – 100km 60mi + – 100km 60mi + – 100km 60mi Project Location Project Location