FEBRUARY 26, 2004
PROJECT NUMBER- 04-660
WAC GEOTECHNICAL
INC.
MR. KARL LOWREY (909) 721-0176
9550 HERMITAGE LANE RIVERSIDE, CA. 92503
SUBJECT: SUBSURFACE SOILS ENGINEERING INVESTIGATION FOR PROPOSED RESIDENTIAL
BUILDING CONSTRUCTION AND FOUNDATION EVALUATION FOR THE PROPERTY LOCATED AT
_ CARMElITA CIRCLE TEMECULA, CA.
A.P.N.919-082-002 LOT # 101 OF TRACT #3883
GENTLEMEN:
THE RESULTS OF OUR INVESTIGATION INDICATE THAT THE SOILS UNDERLYING THE PROPOSED
BUILDING AREA ARE COMPRISED OF SILTY FINE TO COARSE-GRAINED SANDS IN A DRY TO
MOIST, LOOSE TO MEDIUM DENSE TO DENSE STATE. BASED UPON INFORMATION SUPPLIED TO
THIS OFFICE (PLATE 1), IT IS PROPOSED TO CONSTRUCT A RESIDENTIAL STRUCTURE ON THE
SUBJECT PROPERTY.
GRADING WILL CONSIST OF CUTS AND FILLS ON THE ORDER OF 12-5 FEET RESPECTIVELY.
LOOSE SOILS SHALL BE REMOVED TO COMPETENT SUB-GRADE. SUCH REMOVED SOILS MAY BE
USED AS NEEDED FOR FILL MATERIAL. THE EXISTING GRADE IS TO BE INCREASED ON THE
ORDER OF APPROXIMATELY 5 FEET IN THE PROPOSED FILL AREA.
IT IS PROPOSED TO CONSTRUCT CONVENTIONAL SPREAD FOOTINGS FOR SLAB-ON-GRADE
RESIDENTIAL BUILDINGS. IT IS OUR OPINION THAT THE SITE SHOULD BE CONSIDERED SUITABLE
FOR THE PLANNED DEVELOPMENT, PROVIDED THE RECOMMENDATIONS PRESENTED HEREIN
ARE INCORPORATED INTO THE DESIGN AND IN CONSTRUCTION. ADEQUATELY CONSTRUCTED
SPREAD FOOTINGS FOUNDED INTO COMPETENT, FIELD APPROVED DENSE COMPACTED FILL
ARE EXPECTED TO PROVIDE NECESSARY SUPPORT FOR THE PLANNED RESIDENTIAL
STRUCTURE.
THIS REPORT HAS BEEN PREPARED IN ACCORDANCE WITH THE GENERALLY ACCEPTED
ENGINEERING STANDARDS CONSIDERED NECESSARY FOR THE PROPOSED DEVELOPMENT.
THANK YOU FOR THE OPPORTUNITY TO BE OF SERVICE ON YOUR PROJECT. SHOULD YOU HAVE
ANY QUESTIONS REGARDING THIS REPORT, PLEASE CALL THE UNDERSIGNED AT YOUR
CONVENIENCE.
RESPECTFULLY SUBMITTED,
WAC GEOTECHNICAL, INC.
~~
BRADLE . WORREL -::t!-z...I-f-
RCE 338114 DATE 7
EXP. 6130106
----
P.O. BOX 545 . NORCO, CA 92860
OFC: (909) 354-6500 . FAX: (909) 354-8600
'- I,'
.
.
~ .
.', ~ -r-
,
I~ to
~
I~ @ @
<S: :(l
~
, @ ~
8' t
!!
. k
:l M ,~
I IV "I
@ ,
~ "
hi
'u
I <9 @
~ ~
I
I ~
I
"" @l ~
~
orot'l:_7 -t
I 'K",,-:-o "J~
r \r,.:tIIl
. '-.J"
..
..
~ @
, ...
. G ~ sJof'oz,
" ..
f 0 ~
" G it
0
~
I ~
~
I
..~~ ~ !II
I ..
~
'-
.. ..
Cl
I (6,!) ~ ~
"
" .. <l
@ ~ 0;
. ~ )....
I ~ ....
'. II ~
~ 8
t 1'>
I @ fS ~
\0<:\
~ ~ 2-
Cli) ~ ~
I
I
rL-FfJ8 # 1
--
--
--
I
APN, # 9'9-082-002
LOT 101 - TRACT 3883
LOT AREA = 0.85 ACRES (GROSS)
0lSlUR8ED AREA = +/- 0.63 ACRES
--
I
----
:Ire'
~
,/
,
I _
-.
I . , I
. . --i----..-
" --+-- \ ";.
~- " " ~
_- . ",,,,of' " ~
\ :\,;.'" \, \,
~fl~ )
----
~
~
~
I
~
,/
~
~
/'
/
/
I
/'
/
/
/'
I
~
I
I
I'
/
/'
I
,
I
/
/
/'
/
/
I
I
I
I
:)RECISE GRADING PLAN,
I OWNER/APPLICANT ;,o'~
J2.f2' (JtJ
KARL LO\lollY 1J2.,
I 9550 HERMITAGE LANE
RIVERSIDE. CALIFORNIA 92503 . '.
(909) 72'.0176
I
LEGAL DESCRIPTION
I
EARTHWORK QUANTITIES
APPROX. CUT = ????? cu YO
APPROX, Fill = ????? CU YO
APPROX. IMPORT = 1111? CU YO
, J'
11.36.34' Tr
(".37.15') FG
I
L
I
I
LEGEND
'-'-'
..-
.. rt~ib = ~~'~~:~~~~,~~~:~=--;.
"'^ ~~
.~Ot-:('
('0/1')-0
~/~
~.~
PROPERTY LINE
FLOW LINE
--------------
I
Y-LY
3
SLOPE
OAYlIGHT LINE
Q CUT
"
"
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
E 0 E
E E ...... ~
-'" -'" -
-'"
I ~ 0 on s
~ on ~ ~ "
" . ~ .
0 E ~ i . ~
. 1; " Q) .
~~ b ~
i j " ! , - ! ~
." E . Q)
C") '" >. ~ N ." " 0'; . ..
~~ .
0 . . " ~ I , E ]
. III 0> . " ~ . 10 .
~ 1Il ~g I ~
0"0 Z 'i . .
. .. I . ..Q ft .
8'0 W ~. S <( [TIH I ,
I :
'" (!) :~ I ~ ..
O(!l i II "'/," 1;: I ! ~
-." W ~ . . !
. 211 .'.,: . ~
:5:a ..J .
~ c.,.. ::I
H \~". S i
~= . 8~ I
.
<a" <ll ~: 0
c.._
"'::0
0_
<a 0
"e "
0
~:gj
n; .~
00
tn
CD
C ...
0.<: cO
Ni:;;
:5 a
CD tl u>
Co) 3cO
... -~
_c:o>
.., 8.!!
O.5'lil
en......
. lD af
.. !8
<<Ill co
CD S .5
Z......
-8~
_ c:m
-J!l~
::lis i
<<I .!! c:
I&. ~:>
ES;
Q) .!!~
>i!'..
.- <;
ti
<C
"l:t
C?
o
4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, INC. PROJECT # 04-660 DATE: FEBRUARY 26,2004
1,0 INTRODUCTION
THE PURPOSE OF THIS EVALUATION IS TO DETERMINE THE NATURE AND ENGINEERING
PROPERTIES OF THE SUBSURFACE SOILS, AND TO PROVIDE NECESSARY GEOTECHNICAL
RECOMMENDATIONS FOR FOUNDATION DESIGN, SITE GRADING, UTILITY TRENCH BACKFILL, AND
FIELD REVIEW DURING CONSTRUCTION.
OUR EVALUATION INCLUDED SUBSURFACE EXPLORATION, SOIL SAMPLING, LABORATORY
TESTING, ENGINEERING ANALYSES AND PREPARATION OF THIS REPORT. THE
RECOMMENDATIONS CONTAINED HEREIN REFLECT OUR PROFESSIONAL OPINIONS FOR THE
SUBSURFACE SOIL CONDITIONS ENCOUNTERED DURING FIELD INVESTIGATION.
1.1 PROPOSED DEVELOPMENT
BASED ON THE INFORMATION,SUPPLlED TO THIS OFFICE, IT IS PROPOSED TO CONSTRUCT A
TWO-STORY RESIDENTIAL BUILDING, WITH SLAB-ON-GRADE FOUNDATION FOR THE SUBJECT
PROPERTY, CONVENTIONAL SPREAD FOOTINGS ARE PROPOSED FOR THE RESIDENTIAL
BUILDING AREAS. IT IS THE UNDERSTANDING OF THIS OFFICE THAT THE PROPERTY Will BE
SERVED BY A SUB-SURFACE SEWAGE DISPOSAL SYSTEM. IT IS OUR OPINION THAT THE SITE
SHOULD BE CONSIDERED SUITABLE FOR THE PLANNED DEVELOPMENT, PROVIDED THE
RECOMMENDATIONS PRESENTED HEREIN ARE INCORPORATED INTO DESIGN AND IN
CONSTRUCTION. ADEQUATELY CONSTRUCTED SPREAD FOOTINGS FOUNDED INTO
COMPETENT, FIELD APPROVED DENSE COMPACTED Fill ARE EXPECTED TO PROVIDE
NECESSARY SUPPORT FOR THE PLANNED RESIDENTIAL STRUCTURE.
1.2 SITE DESCRIPTION
THE SUBJECT PROPERTY IS LOCATED ON THE SOUTHEASTERLY SIDE OF CARMELlTA ROAD IN
THE CITY OF TEMECULA, COUNTY OF RIVERSIDE, CA. THE SUBJECT PROPERTY IS BORDERED
BY EXISTING RESIDENTIAL CONSTRUCTION. THE SUBJECT PROPERTY IS MANTLED WITH MINOR
NATIVE VEGETATION. DRAINAGE IS VIA SHEET FLOW TO THE SOUTH.
2.0 SCOPE OF WORK
GEOTECHNICAL INVESTIGATION FOR THE SUBJECT SITE INCLUDED SUBSURFACE EXPLORATION
UTILIZING A TRUCK MOUNTED MOBILE DRill B-34 AUGER DRILL RIG, SOIL SAMPLING,
LABORATORY TESTING, ENGINEERING ANALYSES AND PREPARATION OF THIS REPORT. IN
GENERAL, THE SCOPE OF WORK INCLUDED THE FOLLOWING TASKS:
. TWO EXPLORATORY BORINGS WERE EXCAVATED USING A B-34 DRILL RIG, ADVANCED TO A
MAXIMUM DEPTH OF 20 FEET BELOW THE EXISTING GRADE (SEE PLATE 1 AND BORING LOGS,
APPENDIX SECTION). DURING EXPLORATION, ENCOUNTERED SUBSURFACE SOILS WERE
LOGGED BASED UPON VISUAL AND TACTILE METHODS WITH BULK SAMPLES OBTAINED AT
SUBSURFACE ZONES AT OR NEAR THE PROPOSED PAD GRADE. COLLECTED SAMPLES WERE
TRANSFERRED TO A GEOTECHNICAL LABORATORY FOR TESTING AND ANALYSES.
DESCRIPTIONS OF ENCOUNTERED SUBSURFACE SOILS ARE PROVIDED ON THE BORING LOGS
IN THE APPENDIX SECTION. THE APPROXIMATE LOCATIONS OF THE TEST BORINGS ARE SHOWN
ON PLATE 1.
. LABORATORY TESTING WAS CONDUCTED ON SELECTED BULK AND REMOLDED SAMPLES
ACCORDING TO THE PROJECT REQUIREMENTS. THE LABORATORY TESTING INCLUDED
DETERMINATIONS OF MAXIMUM DRY DENSITY AND OPTIMUM MOISTURE CONTENT, SOIL SHEAR
STRENGTH AND EXPANSION INDEX. DESCRIPTIONS OF THE TEST PROCEDURES USED AND TEST
RESULTS ARE PROVIDED IN APPENDIX SECTION.
AJP~: 919-082-002
5$
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, INC. PROJECT # 04-660 DATE: FEBRUARY 26,2004
. BASED ON OBTAINED DATA RESULTING FROM OUR FIELD INVESTIGATION, LABORATORY
TESTING AND ENGINEERING ANALYSES, THIS REPORT PRESENTS THIS FIRMS
RECOMMENDATIONS FOR FOUNDATION DESIGN, SITE PREPARATION, GRADING AND FIELD
REVIEWS NECESSARY DURING SITE CONSTRUCTION.
3.0 SUBSURFACE CONDITIONS
OUR EVALUATION OF THE SITE SUBSOIL CONDITIONS ARE BASED UPON SUBSURFACE SOIL
EXPLORATION AND NOTED LABORATORY TESTING.
FOR THE DEPTHS EXPLORED, THE ENCOUNTERED 0 - 5 FEET OF SUB-SOILS, CONSISTS OF TAN
TO GRAYISH TAN SILTY TO COARSE GRAINED DECOMPOSED GRANITE AND ALLUVIUM.
BASED UPON OUR FIELD INVESTIGATION, SOIL SAMPLING AND SUBSEQUENT LABORATORY AND
ENGINEERING ANALYSES, THE FOLLOWING CHARACTERISTICS FOR THE' SITE SOILS ARE
OBSERVED:
IN GENERAL, THE UPPER 0 TO 3 FEET OF THE SITE SOILS ARE LOOSE AND COMPRESSIBLE.
THESE SUB-SOILS WILL REQUIRE REMOVAL TO COMPETENT BEARING SUB-GRADE FOR
FOUNDATION SUPPORT. SEE SECTION 4.1.1 FOR SPECIFIC REQUIREMENTS. THESE IN PLACE
SUB-SOILS MAY BE CONSIDERED SUITABLE FOR USE AS STRUCTURAL FILLS INTENDED TO
SUPPORT PROPOSED STRUCTURE OR FILL SLOPES. AT TIME OF CONSTRUCTION, ACTUAL FIELD
EXPOSURES WILL DICTATE SITE SUITABILITY BASED UPON FIELD REVIEW BY THE PROJECT
SOILS ENGINEERING CONSULTANT 1 REPRESENTATIVE.
LABORATORY SHEAR TESTS CONDUCTED ON THE UPPER BULK SAMPLES REMOLDED TO 90
PERCENT OF THE LABORATORY DETERMINED MAXIMUM DRY DENSITY INDICATE MODERATE
SHEAR STRENGTHS UNDER INCREASED MOISTURE CONDITIONS. RESULTS OF THE
LABORATORY SHEAR TESTS ARE PROVIDED IN THE APPENDIX SECTION.
3.1 EXCAVATIBILlTY
CONSIDERING THE STATE OF THE NON-LITHIFIED ALLUVIUM UNDERLYING CURRENT SURFACE
GRADE, IT IS OUR OPINION THAT GRADING AND EXCAVATION REQUIRED FOR THE PROJECT MAY
BE ACCOMPLISHED USING CONVENTIONAL CONSTRUCTION EQUIPMENT TO THE PROPOSED
DESIGN GRADES AND RECOMMENDED REMOVAL DEPTHS.
3.2 GROUNDWATER
GROUND WATER WAS NOT ENCOUNTERED IN OUR SUBSURFACE DRILLING EXCAVATION TO
DEPTHS UP TO 20 FEET. GROUND WATER IS NOT EXPECTED TO BE A PROBLEM FOR PROPOSED
GRADING AND RESIDENTIAL DEVELOPMENT.
OBSERVATION OF TRENCH WALLS EXPOSED DURING SUBSURFACE SOILS INVESTIGATION DID
NOT YIELD EVIDENCE OF SOIL MOTTLING WHICH WOULD SUGGEST A HIGHER GROUND WATER
CONDITION FOR THE SUBJECT PROPERTY.
3.3 SUBSURFACE VARIATIONS
BASED UPON THE RESULTS OF OUR SUBSURFACE INVESTIGATION AND ON PAST EXPERIENCE,
IT IS THE OPINION OF THIS FIRM THAT VARIATIONS IN THE CONTINUITY, DEPTHS OF SUBSOIL
DEPOSITS MAY BE EXPECTED. DUE TO THE NATURE AND CHARACTERISTICS OF THE SOILS
UNDERLYING THE SUBJECT SITE, CARE SHOULD BE EXERCISED IN INTERPOLATING OR
EXTRAPOLATING THE CONDITIONS AND PROPERTIES OF THE SUB-SOILS BEYOND THE BORING
LOCATIONS.
AJP~: 919-082-002
6
'"
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, INC. PROJECT # 04-660 DATE: FEBRUARY 26,2004
3.4 LIQUEFACTION
LIQUEFACTION IS CAUSED BY THE BUILD UP OF EXCESS HYDROSTATIC PRESSURE IN
SATURATED COHESIONLESS SOILS DUE TO CYCLIC STRESS GENERATED BY GROUND SHAKING
DURING AN EARTHQUAKE. THE SIGNIFICANT FACTORS ON WHICH LIQUEFACTION POTENTIAL OF
A SOIL DEPOSIT DEPENDS, AMONG OTHERS INCLUDE, SOIL TYPE, RELATIVE SOIL DENSITY,
INTENSITY OF EARTHQUAKE, DURATION OF GROUND SHAKING, AND DEPTH OF GROUND WATER.
GROUND WATER WAS NOT ENCOUNTERED IN OUR SUBSURFACE EXPLORATION PROGRAM.
UNDERLYING IN-PLACE ALLUVIAL MATERIALS CONSIST OF SILTY FINE TO COARSE I GRAINED
SANDS WITH UNDERLYING GRANITE IN VARIOUS LEVELS OF DECOMPOSITION.
BASED UPON AVAILABLE INFORMATION FROM THIS INVESTIGATION AND EXPERIENCE IN THIS
AREA, IT IS THE OPINION OF THIS FIRM THAT THE POTENTIAL FOR LIQUEFACTION IS MINIMAL
FOR THE SUBJECT PROPERTY.
3.5 POTENTIAL SEISMIC HAZARDS
SEISMIC DESIGN PARAMETERS BASED UPON 1997 UBC. THE PROJECT IS LOCATED IN SEISMIC
ZONE 4. THE SEISMIC DESIGN FAULT FOR THE SUBJECT PROPERTY IS THE ELSINORE FAULT,
GLEN IVY SEGMENT, WHICH IS LOCATED APPROXIMATELY 4 KILOMETERS SOUTHWESTERLY OF
THE SUBJECT PROPERTY. THE FAULT TYPE IS "B" THE MAXIMUM MAGNITUDE IS NOTED BY THE
UBC AS 6.8 THE SLIP RATE IS 5 MMIYR. THE NEAR-SOURCE FACTOR NA, IS NOTED AS 1.3. THE
NEAR-SOURCE FACTOR NV IS NOTED AS 1.6.
THE SOILS UNDERLYING THE SUBJECT SITE. FINE TO COARSE-GRAINED SAND IS ASSIGNED THE
SOIL TYPE PROFILE SD. THE SEISMIC ZONE FACTOR IS 0.40. THE SEISMIC COEFFICIENT, CA, IS
NOTED AS 0.44 NA; THE SEISMIC COEFFICIENT, CV, IS NOTED AS 0.64 NV.
4.0 EVALUATIONS AND RECOMMENDATIONS
4.1 GENERAL EVALUATIONS
BASED ON THIS FIRM'S FIELD INVESTIGATION, LABORATORY TESTING AND SUBSEQUENT
ENGINEERING ANALYSIS, IT IS OUR OPINION THAT, FROM A GEOTECHNICAL VIEWPOINT, THE
SITE SHOULD BE CONSIDERED SUITABLE FOR THE PLANNED DEVELOPMENT, PROVIDED THE
RECOMMENDATIONS PRESENTED HEREIN, ARE INCORPORATED INTO FINAL DESIGN AND IN
CONSTRUCTION.
SITE PREPARATION AND GRADING SHOULD BE PERFORMED IN ACCORDANCE WITH THE
ENCLOSED RECOMMENDATIONS OF SECTION 5, EARTHWORKlGENERAL GRADING
RECOMMENDATIONS OF THIS REPORT, EXCEPT AS MODIFIED IN THE MAIN TEXT AND WITH THE
APPLICABLE PORTIONS OF APPENDIX CHAPTER 33 OF THE CURRENT UBC OR APPLICABLE
LOCAL ORDINANCE.
STRUCTURAL DESIGN CONSIDERATIONS SHOULD INCLUDE THE PROBABILITY OF MODERATE TO
HIGH PEAK GROUND ACCELERATIONS FROM RELATIVELY ACTIVE NEARBY EARTHQUAKE
FAULTS, AS NOTED IN SECTION 3.5.
4.1.1 SUB-GRADE PREPARATIONS FOR STRUCTURAL PAD AREA
PROGRAMMED AREAS FOR RESIDENTIAL BUILDING SUPPORT WILL REQUIRE REMOVAL OF
LOOSE ALLUVIAL SOIL TO COMPETENT IN-PLACE, FIELD APPROVED SUB-GRADE. REMOVAL
SHALL BE VERIFIED IN THE FIELD BY A REPRESENTATIVE OF WAC GEOTECHNICAL, INC. PRIOR
TO REPLACING AND COMPACTING REMOVED MATERIAL. A REPRESENTATIVE OF WAC
GEOTECHNICAL, INC. SHALL VERIFY THAT ALL REPLACED MATERIAL HAS BEEN COMPACTED TO
AJP~: 919-082.002
7
1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, INC. PROJECT # 04-660 DATE: FEBRUARY 26,2004
AT LEAST 90% RELATIVE COMPACTION PER ASTM 0-1557-91 FOR STRUCTURAL SUPPORT OF
THE PROPOSED FILL AND FOUNDATIONS.
IT IS ANTICIPATED REMOVAL DEPTHS WILL AVERAGE APPROXIMATELY THREE TO FOUR FEET.
BASEMENT SOIL SHOULD BE SCARIFIED 6- INCHES AND MOISTURE CONDITIONED TO INSURE A
UNIFORM FILL MAT FOR BUILDING SUPPORT. OVER EXCAVATION SHOULD INCLUDE THE AREA 5-
FEET OUTSIDE THE BUILDING FOOTPRINT. ACTUAL DEPTH OF REMOVALS WILL BE PREDICATED
ON EXPOSED FIELD CONDITIONS AND APPROVAL BY A REPRESENTATIVE OF WAC
GEOTECHNICAL, INC.
ALL FILLS SHALL BE PLACED IN 6 TO 8 INCH LAYERS, MOISTURE CONDITIONED TO AT LEAST
OPTIMUM MOISTURE CONTENT AND COMPACTED TO 90% OF MAXIMUM DRY DENSITY PER ASTM
0-1557-91. FILL PLACEMENT SHALL BE OBSERVED BY, AND COMPACTION TESTING PERFORMED
BY A REPRESENTATIVE OF THE PROJECT SOILS ENGINEERING CONSULTANT AND AS NOTED IN
SECTION 5.0 "EARTH WORK I GENERAL GRADING RECOMMENDATIONS".
4.2 SPREAD FOUNDATION
FOR ADEQUATE SUPPORT, THE PROPOSED STRUCTURES MAY BE CONSTRUCTED ON
CONTINUOUS ANDIOR ISOLATED SPREAD FOOTINGS FOUNDED EXCLUSIVELY INTO FIELD
APPROVED COMPACTED FILL MATERIALS.
CONVENTIONAL SHALLOW FOUNDATION SYSTEM IS CONSIDERED SUITABLE FOR PLANNED
RESIDENTIAL AND ANCILLARY STRUCTURES. TYPE II CEMENT IS ACCEPTABLE FOR
CONSTRUCTION.
FOUNDATIONS MAY BE DESIGNED BASED UPON THE FOLLOWING VALUES:
ALLOWABLE BEARING: 1600 LBS.lSQ. FT.
LATERAL BEARING: 147 LBS.lSQ. FT. PER FOOT OF DEPTH TO A MAXIMUM OF 1500 LBS.lSQ. FT.
SLIDING COEFFICIENT: 0.23
ALLOWABLE BEARING MAY BE INCREASED TO 20 % OF THE ABOVE DESIGNATED VALUE FOR
EACH ADDITIONAL FOOT OF DEPTH, UP TO THREE TIMES THE DESIGNATED VALUE.
ADDITIONALLY, AN INCREASE OF 113 SHALL BE PERMITTED WHEN CONSIDERING LOAD
COMBINATIONS, INCLUDING WIND OR EARTHQUAKE LOADS, AS PERMITTED BY 1997 U.B.C.
SECTION 1612.3.2. LATERAL BEARING MAY BE INCREASED BY THE DESIGNATED VALUE FOR
EACH ADDITIONAL FOOT OF DEPTH NOT TO EXCEED 1500, PSF, PER 1997 U.B.C. TABLE 16-I-A.
MODIFIED.
2. OTHER DESIGN RECOMMENDATIONS
. FOOTING DEPTH
EXTERIOR - 12-INCHES BELOW LOWEST ADJACENT GRADE (IN APPROVED COMPACTED FILL
MATERIALS)
INTERIOR - 24-INCHES BELOW LOWEST ADJACENT GRADE (IN APPROVED DENSE
COMPACTED FILL MATERIALS)
. FOOTING WIDTH
EXTERIOR -12-INCHES MINIMUM FOR ONE-STORY, 15-INCHES MINIMUM FOR 2-STORY
INTERIOR - 12-INCHES MINIMUM FOR ONE AND 15-INCHES FOR 2-STORY, RESPECTIVELY.
AJP~: 919.082.002
8
g
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, INC. PROJECT # 04-660 DATE: FEBRUARY 26, 2004
. FOOTING REINFORCEMENT
EXTERIOR & INTERIOR - ALL CONTINUOUS; FOUR NO.4 BARS, TWO NEAR THE
TOP, TWO NEAR THE BOTTOM FOR EXTERIOR AND TWO NO.4 BARS ONE NEAR THE TOP AND
ONE NEAR THE BOTTOM FOR INTERIOR.
CONCRETE SLABS - SLAB THICKNESS: 4-INCHES REINFORCED WITH NO.3 BARS
AT 16- INCH ON CENTER EACH WAY OR APPROVED EQUIVALENT.
. UNDER-SLAB TREATMENT
LIVING AREAS - 6-MIL VISQUEEN; COVER WITH AT LEAST 2 INCHES OF SAND.
SUB-GRADE SOILS SHOULD BE PRESOAKED TO CONTAIN AT LEAST OPTIMUM MOISTURE
CONTENT IMMEDIATELY PRIOR TO PLACING VISQUEEN AND TO BE VERIFIED BY THE SOILS
ENGINEERING CONSULTANT. THE SAND COVER SHOULD BE MOISTENED PRIOR TO PLACING
CONCRETE.
GRADE BEAM - A GRADE BEAM REINFORCED CONTINUOUSLY WITH THE GARAGE
FOOTINGS SHOULD BE CONSTRUCTED ACROSS ALL GARAGE ENTRANCES, TYING TOGETHER
THE ENDS OF THE GARAGE FOOTINGS. THIS GRADE BEAM SHOULD BE EMBEDDED AT THE SAME
DEPTH AS THE ADJACENT PERIMETER FOOTINGS
GARAGE SLAB - OPTIMUM MOISTURE CONTENT IN SUB-GRADE SOIL VERIFIED BY
THE SOILS ENGINEERING CONSULTANT.
. FIREPLACE FOOTINGS - FIREPLACE FOOTINGS SHALL HAVE A MINIMUM
EMBEDMENT DEPTH OF 24-INCHES MEASURED FROM THE LOWEST RECOMMENDED
ADJACENT GRADE FOUNDED INTO COMPETENT SOIL AND SHOULD BE AN INTEGRAL
PART OF THE BUILDING FOUNDATION SYSTEM. FIREPLACE LABS SHALL BE TREATED IN
THE SAME MANNER AS THE LIVING AREA SLABS.
. PRIOR TO POURING FOOTINGS, SOILS SHOULD BE PRE-MOISTENED AND FIELD
APPROVED BY THE PROJECT SOILS ENGINEERING CONSULTANT OR HIS
REPRESENTATIVE.
THE SETTLEMENT OF PROPERLY DESIGNED AND CONSTRUCTED FOUNDATIONS SUPPORTED ON
APPROVED EARTH MATERIALS, CARRYING MAXIMUM ANTICIPATED VERTICAL LOADINGS, ARE
EXPECTED TO BE WITHIN TOLERABLE LIMITS. ESTIMATED TOTAL AND DIFFERENTIAL
SETTLEMENTS SHOULD BE NO MORE THAN 314 AND 112-INCH, RESPECTIVELY.
4.3 RESISTANCE TO LATERAL LOADS
RESISTANCE TO LATERAL LOADS CAN BE RESTRAINED BY FRICTION ACTING AT THE BASE OF
FOUNDATIONS AND BY PASSIVE EARTH PRESSURE. REFER TO SECTION 4.2 FOR VALUES.
THE MAXIMUM LATERAL PASSIVE EARTH PRESSURE IS RECOMMENDED NOT TO EXCEED 1500
POUNDS, FOR DESIGN, LATERAL EARTH PRESSURES OF LOCAL SOILS WHEN USED AS LEVEL
BACKFILL MAY BE ESTIMATED FROM THE FOLLOWING EQUIVALENT FLUID DENSITY:
ACTIVE: 48 PCF
PASSIVE: 200 PCF
AT REST: 69 PCF
AJP~:919-082-OO2
9 '\
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, INC. PROJECT # 04-660 DATE: FEBRUARY 26,2004
4.5 CONSTRUCTION CONSIDERATIONS
4.5.1 UNSUPPORTED EXCAVATION
TEMPORARY CONSTRUCTION EXCAVATION UP TO A MAXIMUM DEPTH OF 5 FEET MAY BE MADE
WITHOUT ANY LATERAL SUPPORT. IT IS RECOMMENDED THAT NO SURCHARGE LOADS SUCH AS
CONSTRUCTION EQUIPMENT, BE ALLOWED WITHIN A LINE DRAWN UPWARD AT 45 DEGREE
FROM THE TOE OF EXCAVATION. USE OF SLOPING FOR DEEP EXCAVATION MAY BE APPLICABLE
WHERE PLAN DIMENSIONS OF THE EXCAVATION ARE NOT CONSTRAINED BY ANY EXISTING
STRUCTURE.
4.5.2 SUPPORTED EXCAVATIONS
IF VERTICAL EXCAVATIONS EXCEEDING 5 FEET IN DEPTH BECOME WARRANTED, USE OF
SHORING TO SUPPORT SIDE WALLS IS RECOMMENDED.
4.6 SITE PREPARATION
SITE PREPARATIONS SHOULD INCLUDE CUT SUB EXCAVATIONS, IMPORT SOILS, AND
PLACEMENT OF SOILS AS ENGINEERED FILL. SUCH EARTH WORK SHOULD BE IN ACCORDANCE
WITH THE APPLICABLE GRADING RECOMMENDATIONS PROVIDED IN THE CURRENT UBC AND AS
RECOMMENDED IN SECTION 5.0 OF THIS REPORT.
THIS OFFICE SHOULD BE NOTIFIED 72 HOURS IN ADVANCE OF IMPORTING SOILS TO SITE FOR
PLACEMENT AS COMPACTED FILL. IT WILL BE NECESSARY FOR THE PROJECT SOILS
ENGINEERING CONSULTANT TO SAMPLE IMPORT SOILS WITH SUBSEQUENT LABORATORY
TESTING TO DETERMINE SUITABILITY OF IMPORT SOILS FOR PROJECT CONSTRUCTION. IT IS
STRONGLY RECOMMENDED THAT IMPORT SOILS BE SIMILAR TO SITE SOILS. THE USE OF
CLAYEY SOILS FOR PAD CONSTRUCTION IS PROHIBITED WITHOUT PRIOR APPROVAL OF THE
SOILS ENGINEERING CONSULTANT.
4.7 SOIL CAVING
DURING EXCAVATIONS FOR DEEP UTILITY TRENCHES, 'SOME' CAVING MAY BE EXPECTED. ALL
TEMPORARY DEEP EXCAVATIONS SHOULD BE MADE AT A 2:1 (HORIZONTAL TO VERTICAL)
SLOPE RATIO OR FLATTER, ANDIOR AS PER THE CONSTRUCTION GUIDELINES PROVIDED BY
CAL-OSHA.
4.8 RETAINING WALL
RETAINING STRUCTURES, IF PLANNED, SHOULD BE DESIGNED USING THE FOLLOWING
EQUIVALENT FLUID DENSITY:
SLOPE SURFACE OF RETAINED MATERIAL EQUIVALENT FLUID DENSITY (PCF)
(HORIZONTAL TO VERTICAL) IMPORTED LOCAL
CLEAN SAND SITE SOIL
LEVEL 30 35
2:1 35 43
AJP~:919-082-OO2
10
\0
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, me. PROJECT # 04-660 DATE: FEBRUARY 26,2004
ONLY FREE-DRAINING GRANULAR MATERIALS (SAND OR GRAVEL) ARE TO BE USED AS
RETAINING WALL BACKFILL. BACK-DRAINS AND I OR OMISSION OF HEAD JOINTS @ 32" O.C. IN
THE FIRST COURSE ABOVE GRADE ARE REQUIRED BEHIND ALL RETAINING WALLS.
4.9 UTILITY TRENCH BACKFILL
UTILITY TRENCH BACKFILL WITHIN THE STRUCTURAL PAD AND BEYOND, SHOULD BE PLACED IN
ACCORDANCE WITH THE FOLLOWING RECOMMENDATIONS:
* EXTERIOR TRENCHES ALONG A FOUNDATION OR A TOE OF A SLOPE AND EXTENDING BELOW A
1:1 IMAGINARY LINE PROJECTED FROM THE OUTSIDE BOTTOM EDGE OF THE FOOTING OR
TOE OF THE SLOPE, SHOULD BE COMPACTED TO A MINIMUM 90 PERCENT.
* ALL EXCAVATED TRENCHES SHOULD CONFORM TO THE REQUIREMENTS AND SAFETY AS
SPECIFIED BY CAL-OSHA.
4.10 PRE-CONSTRUCTION MEETING
IT IS RECOMMENDED THAT NO CLEARING OF THE SITE OR ANY GRADING OPERATION BE
PERFORMED WITHOUT THE PRESENCE OF A REPRESENTATIVE OF THIS OFFICE. AN ON-SITE
PRE-GRADING MEETING SHOULD BE ARRANGED BETWEEN THE SOILS ENGINEERING
CONSULTANT AND THE GRADING CONTRACTOR PRIOR TO ANY CONSTRUCTION.
4.11 SEASONAL LIMITATIONS
NO STRUCTURAL FILL SHALL BE PLACED, SPREAD OR ROLLED DURING UNFAVORABLE
WEATHER CONDITIONS. WHERE THE WORK IS INTERRUPTED BY HEAVY RAINS, FILL
OPERATIONS SHALL NOT BE RESUMED UNTIL MOISTURE CONDITIONS ARE CONSIDERED
FAVORABLE BY THE SOILS ENGINEERING CONSULTANT.
4.12 PLANTERS
TO MINIMIZE POTENTIAL SETTLEMENT TO FOUNDATIONS DUE TO MIGRATING IRRIGATION
WATER, PLANTERS REQUIRING IRRIGATION SHOULD BE RESTRICTED FROM USE IF ADJACENT
TO FOOTINGS. IF UNAVOIDABLE, PLANTER BOXES WITH SEALED BOTTOMS AND DRAIN OUTLETS
TO APPROVED AREAS AWAY FROM THE FOUNDATION, SHOULD BE CONSTRUCTED.
4,13 LANDSCAPE MAINTENANCE/DRAINAGE
ONLY THE AMOUNT OF IRRIGATION NECESSARY TO SUSTAIN PLANT LIFE SHOULD BE PROVIDED.
PAD DRAINAGE SHOULD BE DIRECTED TOWARDS STREETS AND lOR TO OTHER APPROVED
AREAS AWAY FROM FOUNDATIONS. SLOPE AREAS, WHEN APPLICABLE, SHOULD BE PLANTED
WITH DRAUGHT RESISTANT VEGETATION.
4.14 OBSERVATIONS AND TESTING DURING CONSTRUCTION
RECOMMENDATIONS PROVIDED IN THIS REPORT ARE BASED UPON THE ASSUMPTION THAT ALL
FOUNDATIONS WILL BE PLACED UPON FIELD APPROVED FILL MATERIALS FOR STRUCTURES.
EXCAVATED FOOTINGS SHALL BE FIELD REVIEWED, VERIFIED AND CERTIFIED BY SOILS
ENGINEERING CONSULTANT PRIOR TO FORMING, STEEL AND CONCRETE PLACEMENT TO
ENSURE THEIR SUFFICIENT EMBEDMENT AND PROPER BEARING ON APPROVED DENSE
COMPACTED FILL MATERIALS. ADDITIONAL FIELD REVIEWS BY SOILS ENGINEERING
CONSULTANT IS RECOMMENDED TO VERIFY FOOTING EXCAVATIONS BEING FREE OF LOOSE
AND DISTURBED MATERIAL. ALL STRUCTURAL BACKFILL SHALL BE PLACED AND COMPACTED
UNDER DIRECT OBSERVATION AND TESTING BY THIS FACILITY. EXCESS SOILS GENERATED
FROM FOOTING EXCAVATIONS SHOULD BE REMOVED FROM PAD AREAS AND SHOULD NOT BE
APN: 919~82~02
11
\\
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, INC. PROJECT # 04-660 DATE: FEBRUARY 26, 2004
ALLOWED ON SUB GRADES AS UN-COMPACTED FILL FOR AREAS PROGRAMMED TO RECEIVE
CONCRETE SLAB-ON-GRADE.
5.0 EARTH WORKlGENERAL GRADING RECOMMENDATIONS
STRUCTURAL BACKFILL:
DURING GRADING. EXCAVATED SITE SOILS MAY BE CONSIDERED SUITABLE FOR REUSE AS
BACKFILL MATERIAL. LOOSE SOILS, FORMWORK AND DEBRIS SHOULD BE REMOVED PRIOR TO
BACKFILLING THE WALLS. ON-SITE SAND BACKFILL SHOULD BE PLACED AND COMPACTED IN
ACCORDANCE WITH THE RECOMMENDED SPECIFICATIONS PROVIDED BELOW. WHERE SPACE
LIMITATIONS DO NOT ALLOW CONVENTIONAL BACKFILLING OPERATIONS, SPECIAL BACKFILL
MATERIALS AND PROCEDURES MAY BE REQUIRED. PEA GRAVEL OR OTHER SELECT BACKFILL
CAN BE USED IN LIMITED SPACE AREAS. RECOMMENDATIONS FOR PLACEMENT AND
DENSIFICATION OF PEA GRAVEL OR OTHER SPECIAL BACKFILL CAN BE PROVIDED DURING
CONSTRUCTION.
SITE DRAINAGE:
ADEQUATE POSITIVE DRAINAGE SHOULD BE PROVIDED AWAY FROM THE STRUCTURE TO
PREVENT WATER FROM PONDING AND TO REDUCE PERCOLATION OF WATER INTO SUBSOIL AT
FOUNDATION AREAS. A DESIRABLE SLOPE FOR SURFACE DRAINAGE SHOULD BE A MINIMUM OF
2 PERCENT IN LANDSCAPE AREAS AND 1 PERCENT IN PAVED AREAS. PLANTERS AND
LANDSCAPED AREAS ADJACENT TO BUILDING PERIMETER SHOULD BE AVOIDED OR DESIGNED
BY A QUALIFIED LANDSCAPE ARCHITECT UTILIZING A SEALED PLANTER BOX WITH DRAINS AWAY
FROM FOOTINGS TO MINIMIZE WATER FILTRATION INTO SUB-SOILS.
UTILITY TRENCHES:
BURIED UTILITY CONDUITS SHOULD BE BEDDED AND BACKFILLED AROUND THE CONDUIT IN
ACCORDANCE WITH THE PROJECT SPECIFICATIONS. WHERE CONDUIT UNDERLIES CONCRETE
SLAB-ON-GRADE AND PAVEMENT, THE REMAINING TRENCH BACKFILL ABOVE THE PIPE SHOULD
BE PLACED AND COMPACTED IN ACCORDANCE WITH THE FOLLOWING GRADING
SPECIFICATIONS.
GENERAL GRADING RECOMMENDATIONS:
RECOMMENDED GENERAL SPECIFICATIONS FOR SURFACE PREPARATION TO RECEIVE FILL AND
COMPACTION FOR STRUCTURAL AND UTILITY TRENCH BACKFILL AND OTHERS, ARE PRESENTED
BELOW.
1. AREAS TO BE GRADED, BACKFILLED OR PAVED, SHALL BE GRUBBED, STRIPPED AND
CLEANED OF ALL BURIED AND UNDETECTED DEBRIS, STRUCTURES, CONCRETE, VEGETATION
AND OTHER DELETERIOUS MATERIALS PRIOR TO GRADING.
2. WHERE COMPACTED FILL IS TO PROVIDE VERTICAL SUPPORT FOR FOUNDATIONS, ALL
LOOSE, SOFT AND OTHER INCOMPETENT SOILS SHOULD BE REMOVED TO FULL DEPTH AS
APPROVED BY SOILS ENGINEERING CONSULTANT, OR AT LEAST UP TO THE DEPTH AS
PREVIOUSLY DESCRIBED IN THIS REPORT. THE AREAS OF SUCH REMOVAL SHOULD EXTEND AT
LEAST 5 FEET BEYOND THE PERIMETER OF EXTERIOR FOUNDATION LIMIT OR TO THE EXTENT
AS APPROVED BY SOILS ENGINEERING CONSULTANT DURING GRADING.
3. THE REQUIRED COMPACTION FOR FILL TO SUPPORT FOUNDATIONS AND SLAB-ON-GRADE IS
90% OF THE MAXIMUM DRY DENSITY AT OR NEAR OPTIMUM MOISTURE CONTENT. TO MINIMIZE
ANY POTENTIAL DIFFERENTIAL SETTLEMENT FOR FOUNDATIONS AND SLAB-ON-GRADE
STRADDLING OVER DAYLIGHT LINES, THE CUT PORTION SHOULD BE OVER EXCAVATED A
AJP~:919-o82-o02
12
\2...
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, INC. PROJECT # 04-660 DATE: FEBRUARY 26,2004
MINIMUM OF 3 FEET AND REPLACED AS COMPACTED FILL, COMPACTED TO AT LEAST 90% OF
THE MAXIMUM DRY DENSITY AS DESCRIBED IN THIS REPORT.
4. UTILITY TRENCHES WITHIN BUILDING PAD AREAS AND BEYOND, SHOULD BE BACKFILLED
WITH GRANULAR MATERIAL AND SUCH SHOULD BE COMPACTED TO AT lEAST 90% OF THE
MAXIMUM DENSITY FOR THE MATERIAL USED.
5. COMPACTION FOR ALL STRUCTURAL FILLS SHALL BE DETERMINED RELATIVE TO THE
MAXIMUM DRY DENSITY AS DETERMINED BY ASTM D1557-90 COMPACTION METHODS. ALL IN-
SITU FIELD DENSITY OF COMPACTED FILL SHALL BE DETERMINED BY THE ASTM D1556
STANDARD METHODS OR BY OTHER APPROVED PROCEDURES.
6. ALL NEW IMPORTED SOILS, IF REQUIRED, SHALL BE CLEAN, GRANULAR, NON-EXPANSIVE
MATERIAL OR AS APPROVED BY THE SOILS ENGINEERING CONSULTANT.
7. ALL FILLS SHALL BE PLACED IN 6 INCH LAYERS, MOISTURE CONDITIONED TO AT LEAST
OPTIMUM MOISTURE CONTENT AND COMPACTED TO 90% OF MAXIMUM DRY DENSITY PER ASTM
D 1557-91
8. NO ROCKS OVER EIGHT INCHES IN DIAMETER, SHALL BE PERMITTED IN FILL SLOPES OR
WITHIN 3 FEET OF THE SURFACE WITHOUT PRIOR APPROVAL OF THE SOILS ENGINEERING
CONSULTANT.
9. NO JETTING ANDIOR WATER TAMPING MAY BE CONSIDERED FOR BACKFILL COMPACTION
FOR UTILITY TRENCHES WITHOUT PRIOR APPROVAL OF THE SOILS ENGINEERING CONSULTANT.
FOR SUCH BACKFILL, HAND TAMPING WITH FILL LAYERS OF 8 TO 12 INCHES IN THICKNESS, OR
AS APPROVED BY THE SOILS ENGINEERING CONSULTANT IS RECOMMENDED.
10. ANY AND ALL UTILITY TRENCHES AT DEPTH AS WELL AS CESSPOOL AND ABANDONED
SEPTIC TANKS WITHIN BUILDING PAD AREA AND BEYOND, SHOULD EITHER BE COMPLETELY
EXCAVATED AND REMOVED FROM THE SITE, OR SHOULD BE BACKFILLED WITH GRAVEL,
SLURRY OR BY OTHER MATERIAL, AS APPROVED BY SOILS ENGINEERING CONSULTANT.
11. ANY AND ALL IMPORT SOILS IF REQUIRED DURING GRADING, SHALL BE EQUIVALENT TO THE
SITE SOILS OR BETTER. SUCH SHOULD BE APPROVED BY THE SOILS ENGINEERING
CONSULTANT PRIOR TO IMPORT. AT LEAST 72 HOURS OF ADVANCE NOTICE IS REQUIRED PRIOR
TO IMPORTING SOILS FOR SITE USE TO ALLOW THE SOILS ENGINEERING CONSULTANT TIME TO
SAMPLE AND ANALYZE THE IMPORT SOILS.
12. ANY AND ALL GRADING REQUIRED FOR PAVEMENT, SIDEWALK OR OTHER FACILITIES TO
BE USED BY GENERAL PUBLIC, SHOULD BE CONSTRUCTED UNDER DIRECT OBSERVATION OF
SOILS ENGINEERING CONSULTANT, OR AS REQUIRED BY THE LOCAL PUBLIC AGENCIES.
13. A SITE MEETING (PRE-GRADE MEETING) SHALL BE HELD BETWEEN THE GRADING
CONTRACTOR AND SOILS ENGINEERING CONSULTANT PRIOR TO ACTUAL CONSTRUCTION.
THREE DAYS OF PRIOR NOTICE WILL BE REQUIRED FOR SUCH MEETING.
14. ALL FILL SLOPES ARE TO BE KEYED INTO FIELD APPROVED DENSE EARTH MATERIALS AND
APPROVED BY THE PROJECT SOILS CONSULTANTS. KEYWAY IS TO BE 1/2 THE SLOPE HEIGHT IN
WIDTH OR 15 FEET, WHICHEVER IS GREATER. HEEL SHALL HAVE A 1-FOOT DIFFERENTIAL FROM
TOE (SLOPING TO HEEL).
15. FILL OVER CUT SHALL BE BENCHED INTO APPROVED DENSE EARTH MATERIALS AND
FOUNDED UPON
A KEYWAY, A MINIMUM WIDTH OF 10-FEET WITH THE HEEL 1-FOOT DEEPER THAN TOE (SLOPING
TO HEEL).
AJPl': 919-082-002
I3
\3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, INC. PROJECT # 04-660 DATE: FEBRUARY 26,2004
16. FOR GRADIENTS STEEPER THAN 5:1, FILL SHALL BE BENCHED A MINIMUM OF 4-FEET
HORIZONTALLY INTO NATIVE EARTH MATERIALS FOR EVERY 4 VERTICAL FEET OF FILL PLACED.
6.0 CLOSURE
THE CONCLUSIONS AND RECOMMENDATIONS CONTAINED HEREIN, ARE BASED UPON THE
FINDINGS AND OBSERVATIONS MADE AT THE TIME OF THE SUBSURFACE INVESTIGATION. THE
RECOMMENDATIONS PRESENTED, SHOULD BE CONSIDERED "PRELIMINARY" SINCE THEY ARE
BASED ON SOIL SAMPLES ONLY. IF DURING CONSTRUCTION, THE SUBSOIL CONDITIONS
APPEAR TO BE DIFFERENT FROM THOSE DISCLOSED DURING FIELD INVESTIGATION. THIS
OFFICE SHOULD BE NOTIFIED TO CONSIDER ANY POSSIBLE NEED FOR MODIFICATION FOR THE
GEOTECHNICAL RECOMMENDATIONS PROVIDED IN THIS REPORT.
RECOMMENDATIONS PROVIDED ARE BASED ON THE ASSUMPTIONS THAT STRUCTURAL
FOOTINGS WILL BE ESTABLISHED EXCLUSIVELY INTO FIELD APPROVED COMPACTED FILL.
IT IS RECOMMENDED THAT FINAL PRECISE GRADING AND FOUNDATION PLANS SHOULD BE
REVIEWED BY THIS OFFICE WHEN THEY BECOME AVAILABLE (IF DIFFERENT THAN NOTED PLAN
REVIEW UTILIZED FOR THIS REPORT). SITE GRADING MUST BE PERFORMED UNDER REVIEW BY
GEOTECHNICAL REPRESENTATIVES OF THIS OFFICE. ALL FOOTING EXCAVATIONS SHOULD BE
FIELD REVIEWED (BY THIS OFFICE) PRIOR TO FORMING, STEEL AND CONCRETE PLACEMENT TO
ENSURE THAT FOUNDATIONS ARE FOUNDED INTO SATISFACTORY SOILS AND EXCAVATIONS
ARE FREE OF LOOSE AND DISTURBED MATERIALS.
THIS REPORT HAS BEEN PREPARED EXCLUSIVELY FOR THE USE OF THE ADDRESSEE FOR THE
PROJECT REFERENCED IN CONTEXT. IT SHALL NOT BE TRANSFERRED OR BE USED BY OTHER
PARTIES WITHOUT WRITTEN CONSENT BY WAC GEOTECHNICAL, INC. WE CANNOT BE
RESPONSIBLE FOR USE OF THIS REPORT BY OTHERS WITHOUT REVIEW OF THE GRADING
OPERATION BY OUR PERSONNEL.
SHOULD THE PROJECT BE DELAYED BEYOND ONE YEAR AFTER THE DATE OF THIS REPORT,
THE RECOMMENDATIONS PRESENTED SHALL BE REVIEWED TO CONSIDER ANY POSSIBLE
CHANGE IN SITE CONDITIONS OR CODE REQUIREMENTS.
THE RECOMMENDATIONS PRESENTED ARE BASED ON THE ASSUMPTION THAT THE NECESSARY
GEOTECHNICAL OBSERVATIONS AND TESTING DURING CONSTRUCTION WILL BE PERFORMED
BY A REPRESENTATIVE OF THIS OFFICE. THE FIELD OBSERVATIONS ARE CONSIDERED A
CONTINUATION OF THE GEOTECHNICAL INVESTIGATION PERFORMED. IF ANOTHER FIRM IS
RETAINED FOR GEOTECHNICAL OBSERVATIONS AND TESTING, OUR PROFESSIONAL LIABILITY
AND RESPONSIBILITY SHALL BE DEEMED TO HAVE BEEN ASSUMED BY THE FIRM REPLACING
WAC GEOTECHNICAL, INC. EXCEPT FOR LIABILITY ARISING FROM THE SOLE NEGLIGENCE OF
WAC GEOTECHNICAL, INC.
AJPl': 919-082-002
14 \4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, me. PROJECT # 04-660 DATE: FEBRUARY 26,2004
7.0 APPENDIX SECTION
BORING LOGS
B-1
0-5' SIW (0Al) MEDIUM BROWN TO TAN BROWN SANDS, SILTY FINE TO COARSE GRAINED
SANDS, FIRM TO VERY FIRM AND DRY.
5-20' SIW TANNISH- BROWN TO GRAYISH-TAN SANDS, FINE TO COARSE GRANITE SANDS,
DECOMPOSED GRANITE BEDROCK, FIRM TO DENSE AND DRY
B-2
0-6' SIW (OAL) MEDIUM BROWN TO TANNISH BROWN SANDS, SILTY FINE TO COARSE
GRAINED SANDS, FIRM TO VERY FIRM AND DRY.
6-20' SIW TANNISH-BROWN TO GRAYISH TAN SANDS. FINE TO COARSE GRAINED SANDS,
DECOMPOSED GRANITE BEDROCK. VERY FIRM TO DENSE AND DRY
AJP~:919-082-OO2
15
\$"
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
WAC GEOTECHNICAL, INC. PROJECT # 04-660 DATE: FEBRUARY 26,2004
8.0 APPENDIX B
LABORATORY TESTING
LABORATORY TESTS WERE CONDUCTED ON REPRESENTATIVE SOILS FOR THE PURPOSE OF
CLASSIFICATION AND FOR THE DETERMINATION OF THE PHYSICAL PROPERTIES AND
ENGINEERING CHARACTERISTICS. THE NUMBER AND SELECTION OF THE TYPES OF TESTING
FOR A GIVEN STUDY ARE BASED ON THE GEOTECHNICAL CONDITIONS OF THE SITE. A
SUMMARY OF THE VARIOUS LABORATORY TESTS PERFORMED FOR THE PROJECT IS
PRESENTED BELOW.
MOISTURE CONTENT ASTM D4643 AND DRY DENSITY
SOILS SAMPLES WERE OBTAINED USING A SPLIT SPOON SAMPLER. HOWEVER, RETRIEVED
SAMPLED SOILS WERE DISTURBED AND NOT CONSIDERED REPRESENTATIVE OF UNDISTURBED
SOIL SAMPLES.
DIRECT SHEAR (ASTM D 3080)
DATA OBTAINED FROM THIS TEST PERFORMED AT INCREASED MOISTURE CONDITIONS ON
REMOLDED TO 90 % SOIL SAMPLES WERE USED TO EVALUATE SOIL SHEAR STRENGTHS.
SAMPLES CONTAINED IN BRASS SAMPLER RINGS, PLACED DIRECTLY ON TEST APPARATUS ARE
SHEARED AT A CONSTANT STRAIN RATE UNDER A NORMAL LOAD, APPROPRIATE TO
REPRESENT ANTICIPATED STRUCTURAL LOADINGS. SHEARING DEFORMATIONS ARE
RECORDED TO FAILURE. PEAK AND/OR RESIDUAL SHEAR STRENGTHS ARE OBTAINED FROM
THE MEASURED SHEARING LOAD VERSUS DEFLECTION CURVE. TEST RESULTS, PLOTTED ON
GRAPHICAL FORM, ARE PRESENTED ON PLATE A-1 OF THIS SECTION.
SOIL SAMPLES ARE USUALLY UNDER LIGHT NORMAL LOAD CONDITIONS TO ACCOMMODATE
SEATING OF THE APPARATUS. SAMPLES WERE TESTED AT THE FIELD MOISTURE CONDITIONS
AT A PREDETERMINED NORMAL LOAD. POTENTIALLY MOISTURE SENSITIVE SOIL TYPICALLY
DEMONSTRATES SIGNIFICANT VOLUME CHANGE WITH THE INTRODUCTION OF FREE WATER.
THE RESULTS OF THE CONSOLIDATION TESTS ARE PRESENTED IN GRAPHICAL FORMS ON
PLATES B-1.
LABORATORY TEST RESULTS
MAXIMUM DRY DENSITYIOPTIMUM MOISTURE CONTENT RELATIONSHIP(ASTM D1557-91)
SAMPLE LOCATION
MAX. DRY DENSITY
OPT. MOISTURE CONTENT
B-1
132.5 (MAX. PCF)
126.0 (MAX. PCF)
8.2%
B-2
11.0%
PJP~: 919-082-002
16
,'-
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
.
'Da[e JiinkfeJ P/E. Inc.
RGE # 402
ReE# 23023
15510 Rockfield Blvd., Suite B
Irvine. California 92618
(949) 458-0498 Fax (949) 458-1918
E.mail: illNKLEPE@Aol.com
Federal!./).
33-0J/7087
February 26, 2004
Mr. David Ballinger
WAC, Inc.
2900 Adams Street, Suite B-4
Riverside, CA 92504
Dear Mr. Ballinger:
Re: Laboratory Test Results
Client: Lowrey, Karl
Carmenita Circle - Temecula
At your request, we have performed laboratory tests on soil samples selected by you for the
aoov'eCfeferen:ced Client. Tne test-resUlfsare iittached. Alltest8 wetq,etfortrled according to the
latest Riverside County and ASTM standards. The tests consisted of two Maximum Density
tests, two Direct Shear tests, and one Expansion test.
We hereby transmit the test results for your use.
If you have any questions regarding these test
\l
I
I
I
I
I
I 0
:!:
iii
0:
w
I ..J
><:
z
s:
W
..J
I <(
c
I
I :5
=>
"
w
I ::0
w
'....
W
..J
"
I ..J'"
",-
~"
;::
>-~z
Ww
I "'::0
~~
g"
;.:
"
I w
..,
0
'"
"-
I
I I/)
....
..J
=>
I I/)
w
'"
I/)
....
I/)
W
I ....
o.
0
>-
~~
I ::oW
::oal
=><(
1/)....
(9 ~
a: "-
w'"
al....
ffi~
I=~~
<< ~
WZ
>9
-I-
~:i
wo.
a:::E
,.0
o 0
>-
l- N<=!
v;;:
i:5~ 0:)::=
0
::E
=>o. "'0
0;0 NeD
X"- MN
::li ~~
Z
0
U5g, 00
'l!,,-
0
0
fB.e- "'...
0 NN
0-
~~
Z
0 o-
f: ''''
<< ~"-
0
::;
0
'" 0-
Z ''''
0 ,,"-
0
C!U5
"'''-
'" <qU5
NO.
~
~~
u:
~
~~
'"
~
l'!'"
'"
E;:i:=
0_ .
0"'5
ujr5:g
u::C1-
l'!
~~
~1!2~
...0
::E
w
~w (')(')
"-,,- <<
::;i': "''''
'"
,,; "''''
&r~ 06
0
w ~N
5~ chch
:I:
\~
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
DALE HINKLE PoE., INC.
TABLE 2
RESULTS OF EXPANSION TEST
KARL LOWREY
CARMENITA CIRCLE
TEMECULA
SAMPLE LOCATION ............................................... B-1
DEPTH (ft.) ........ ...... .......................... ..................... 0-6
INITIALMOISTURE(%) ............................................ 4.9
INITIAL DRY DENSITY (pet) .................................... 114.8
CLASSIFICATION SYMBOL ...................................... SM
RELATIVE COMPACTION (%) ................................... 86.7
FINALMOISTURE(%) ............................................. 18.0
PERCENTEXPANSION(%) ....................................... 2.6
EXPANSION INDEX ................................................ 26
POTENTIAL EXPANSION ......................................... LOW
\C\
I ' )
I
I
I
I
I
I 0
0
u
I Q
:J
u
-
I V>
1J
I
I
I
I
I
I
I
I
I
/Lo,,;oL-
14
OPTIMUM MOISTURE CONTENT "I. /I IiI
'\ , OPTIMUN DRY DENSITY p c I I z,..!,.,O
\ TESTED BY 65
I I Z/ Z-~/()'-I
I I I DATE TESTED
lIT
I
0 I I I Ii The American Society [or Testing and
I I I Materials (ASTH) has evaluated the
I ill precision o( the maximum density
I I I test ~ethod ASTH D1557-78) , and has
, indic:lted that variations in tho
, test rcsul ts enn occur. !lSTH
I I defines tho occcptancc range .r two
results in table , in the test "
ASTH 01557 78. The range is
I considered ' acceptable if the
0 I I I difference between any two results
I I expressed as a percentage o( "e
I. aVerag~ value or the two results
il III does not cxcec;d ,.. percent. As
" I , yet, ASTH has not reported precision
I values for field density that
I I ~ methods, but wo expect that.
I varia~ions in the field density text
I I I I , results could also occur.
I I " I r Accordingly, the accuracy .f the
p I I I I I ~ relative compaction values presented
, I I I , I I , in this report is dependent on the
, I I precision of the ASTIi test. method,
I I , I I and therc(ore, the test results r:ay
I I b. subject to variation.
I I I I I ; I
I I I
I I I I I
I I
I I I ,
I I ,
'T I I i
I
,
I I
Zero Air Void:!. Curve:!.
I I I
I , S,C, 2, ~O
I S.C. 2.50
I , I I
I I I I S.C.
I 2,60
I S.C. 2,70
I 1\ S.G ) . gO
,
,
I
I
,
I ~
,
..,,"
-..."' '.
,
..
I
150
13
1~
110
100
90
80
70
o
10
20
30
% Moisture
40
50
60
P"ERFORMED IN GENERAL ACCORDANCE WITH ASTM 01$57-78.
MAXIMUM DRY DENSITY
,v-
SCALE CHECKED BY DRAWN BY
DATE
PROJECT
H<Y...E NO.
DEPTH It
SAMPlE NO.
I
0-(,
DALE HINKLE P.E. INC.
20
I
'Y. 51',7_
1~'2.. S-
OPTIMUM
OPTIMUM
TESTED BY
DATE TESTED
MOISTURE CONTENT
DRY DENSITY p c f
b~
2/r:/o&-/
I
1
The Amcr lean' society (or Testing and
Hiltcrial~ (ASTM) has evaluated the
precision of the maximum density
test ~ethod ASTH OlS57-78), and has
indic~ted that variations in the
tC5t results C<ln occur. lI.5TH
de! incs the acceptance range of t....o
r.esults in table J in the test. of
ASTH 01557-78. The range is
considel:'ed . acceptable if the
difference between any two results
expressed as a percentage of the
average value of the t....o results
does riot exceed 4.0 percent. As
yet, ASTH has not reported precision
values for field density that
methods, but ....e expect that
varia~ions in the field density text
results could also occur.
Accordingly. the accuracy ot the
relativc: compaction valuc:s presented
in this report is dependent"on the
precision of the ",STH test method,
and therefore, the test results may
be subject to variation.
1
I
1
1
I
I.
Z.ro Air Void~ Curves
I
S.C, 2.QO
S.C. 2. SO
S.C. 2.60
S,C. 2.70
S . G ). gO
I
I
I
1
80
1
I
~t~'~
70
1
I
60
o
10
20
30
% Moisture
40
SO
I
(,'V".7
~RFORMED IN GENERAL ACCORDANCE WITH A$TM 01557-78.
MAXIMUM DRY a:NSITY
I
SCALE CHECKED BY DRAWN BY
DATE
PROJECT
HOLE NO.
DEPTH It,
SAMPlE NO.
1
DALE HINKLE P.E. INC.
2.\
1
1
1
1
1
I
1
I
I
I
I
I
1
1
1
1
1
I,
1
DALE HINKLE P .E. INC.
15510 ROCKFIELD BLVD., SUITE 8
IRVINE, CALIFORNIA 92618
LOCATION CARMENITA CIRCLE SATURATED % W
JOB NAME KARL LOWREY -WAC ANGLE OF INTERNAL FRICTION 25 DEG
HOLE NUMBER B-1 COHESION 0 P.S.F.
HOLE DEPTH 0-5' DRY DENSITY IOC,.'S'
SAMPLE TYPE: REMOLDED INITIAL FIELD MOISTURE 5".7
TESTED BY: DRK SATURATED DENSITY
1000 PSF
2000 PSF
N
Cl
/'
V
/> /'
V "\
V
,/ \
/' 25
17
/' V
/' /'
...
"'
..
..
..
..
N
...
en
en
::c
m
:1>0
::Ill
en
-I
::Ill
m ...
Z Cl
C)
-I
::c
-
."
~
-
en
...
"'
..
..
..
..
~
o
5
10
15
20
NORMAL PRESSURE (PSI)
2z.
I
1
1
1
I
I
I
I
I
I
1
1
I
1
1
1
I
1
I
DALE HINKLE P .E. INC.
15510 ROCKFIELD BLVD., SUITE B
IRVINE, CALIFORNIA 92618
LOCATION CARMENIT A CIRCLE SATURATED % W
JOB NAME KARL LOWREY -WAC ANGLE OF INTERNAL FRICTION 24 DEG
HOLE NUMBER B-2 COHESION 0 P,S.F.
HOLE DEPTH 0-5' DRY DENSITY 11>.0
SAMPLE TYPE: REMOLDED INITIAL FIELD MOISTURE 8."1
TESTED BY: DRK SATURATED DENSITY
1 DOO PSF
2DDD PSF
N
a
V
/'
--'\
/'
/' V 1\
/' /' 24
/,
V
/' /'
..
..
..
..
..
..
N
....
U1
en
::c
m
>
::1:1
en
...
::1:1
m ....
Z Cl
C)
....
::c
-
"'ll
!!!
-
U1
..
..
..
..
..
..
~
o
5
10
15
20
NORMAL PRESSURE (PSI)
2a
I
I
I
I
I
I
I
1
I
1
I
I
I
1
1
1
I
I
1
WAC GEOTECHNICAL, INC. PROJECT # 04-660 DATE: FEBRUARY 26, 2004
PROFESSIONAL LIMITATIONS
OUR INVESTIGATION WAS PERFORMED USING THE DEGREE OF CARE AND SKILL ORDINARILY
EXERCISED, UNDER SIMILAR CIRCUMSTANCES BY OTHER REPUTABLE SOILS ENGINEERS
PRACTICING IN THESE GENERAL OR SIMILAR LOCALITIES. NO OTHER WARRANTY, EXPRESSED
OR IMPLIED, IS MADE AS TO THE CONCLUSIONS AND PROFESSIONAL ADVICE INCLUDED IN THIS
REPORT.
THE INVESTIGATIONS ARE BASED ON SOIL SAMPLES ONLY, CONSEQUENTLY THE
RECOMMENDATIONS PROVIDED SHALL BE CONSIDERED 'PRELIMINARY'. THE SAMPLES TAKEN
AND USED FOR TESTING AND THE OBSERVATIONS MADE ARE BELIEVED REPRESENTATIVE OF
SITE CONDITIONS; HOWEVER, SOIL AND GEOLOGIC CONDITIONS CAN VARY SIGNIFICANTLY
BETWEEN TEST BORINGS. AS IN MOST MAJOR PROJECTS. CONDITIONS REVEALED BY
EXCAVATIONS MAY VARY WITH PRELIMINARY FINDINGS. IF THIS OCCURS, THE CHANGED
CONDITIONS MUST BE EVALUATED BY THE PROJECT SOILS ENGINEERING CONSULTANT AND
DESIGNS ADJUSTED AS REQUIRED OR ALTERNATE DESIGN RECOMMENDED.
THE REPORT IS ISSUED WITH THE UNDERSTANDING THAT IT IS THE RESPONSIBILITY OF THE
OWNER, OR OF HIS REPRESENTATIVE, TO ENSURE THAT THE INFORMATION AND
RECOMMENDATIONS CONTAINED HEREIN ARE BROUGHT TO THE ATTENTION OF THE PROJECT
ARCHITECT AND ENGINEERS. APPROPRIATE RECOMMENDATIONS SHOULD BE INCORPORATED
INTO STRUCTURAL PLANS. THE NECESSARY STEPS SHOULD BE TAKEN TO SEE THAT THE
CONTRACTOR AND SUBCONTRACTORS CARRY OUT SUCH RECOMMENDATIONS IN THE FIELD.
THE FINDINGS OF THIS REPORT ARE VALID AS OF THIS PRESENT DATE. HOWEVER. CHANGES IN
THE CONDITIONS OF A PROPERTY CAN OCCUR WITH THE PASSAGE OF TIME, WHETHER THEY
DUE TO NATURAL PROCESS OR THE WORKS OF MAN ON THIS OR ADJACENT PROPERTIES. IN
ADDITION, CHANGES IN APPLICABLE OR APPROPRIATE STANDARDS MAY OCCUR FROM
LEGISLATION OR BROADENING OF KNOWLEDGE. ACCORDINGLY, THE FINDINGS OF THIS
REPORT MAY BE INVALIDATED WHOLLY OR PARTIALLY BY CHANGE OUTSIDE OF OUR CONTROL.
THEREFORE, THIS REPORT IS SUBJECT TO REVIEW AND SHOULD BE UPDATED AFTER A PERIOD
OF ONE YEAR.
RECOMMENDED SERVICES
THE REVIEW OF GRADING PLANS AND SPECIFICATIONS, FIELD OBSERVATIONS AND TESTING BY
THE GEOTECHNICAL REPRESENTATIVE IS AN INTEGRAL PART OF THE CONCLUSIONS AND
RECOMMENDATIONS MADE IN THIS REPORT. IF WAC GEOTECHNICAL, INC. IS NOT RETAINED FOR
THESE SERVICES, THE CLIENT AGREES TO ASSUME WAC GEOTECHNICAL, INC. RESPONSIBILITY
FOR ANY POTENTIAL CLAIMS THAT MAY ARISE DURING AND AFTER CONSTRUCTION, OR DURING
THE LIFETIME USE OF THE STRUCTURE AND ITS APPURTENANT. THE REQUIRED TESTS,
OBSERVATIONS AND CONSULTATION BY THE GEOTECHNICAL CONSULTANT DURING
CONSTRUCTION INCLUDES. BUT NOT BE LIMITED TO:
A. CONTINUOUS OBSERVATION AND TESTING DURING SITE PREPARATION AND GRADING, AND
PLACEMENT OF ENGINEERED FILL.
B. OBSERVATION AND INSPECTION OF FOOTING TRENCH PRIOR TO STEEL AND CONCRETE
PLACEMENT,
C. CONSULTATIONS AS REQUIRED DURING CONSTRUCTION, OR UPON YOUR REQUEST.