HomeMy WebLinkAboutGeotechRoughGrading(Jul.1,2002) I _ PETRA OFFICES THROUGHOUT SOUTHERN CALIFORNIA I I I I I I I I I I I I I I I I I July 1,2002 J.N.241-01 PACIFIC CENTURY HOMES 40925 County Center Drive, Suite 110 Temecula, California 92591 Attention: Mr. Dave Parker Subject: Geotechnical Report of Rough Grading, Lots 1 through 84, 89 through 114, Slope Lots 116 through 122 and 126 and Park Site 123 (E), Tract 23143-6, City of Temecula, Riverside County, California This report presents a summary of the observation and testing services provided by Petra Geotechnical, Inc. (Petra) during rough-grading operations to complete the development of Lots 1 through 84, 89 through 114, Slope Lots 116 through 122 and 126 and Park Site 123 (E) within Tract 23143-6 located in the City of Temecula, California. Lots 85 and 86 were graded as a retention basin during this phase of grading and Lot 123 will be developed as Park "E". Conclusions and recommendations pertaining to the suitability of the grading for the proposed residential construction are provided herein, as well as foundation-design recommendations based on the as-graded soil conditions. REGULATORY COMPLIANCE Cuts, removals and recompaction of unsuitable low-density surface soils, lot overexcavations and placement of compacted fill under the purview ofthis report have been completed under the observation and with selective testing by Petra. The earthwork was performed in accordance with the recommendations presented in previous geotechnical reports by Petra (see References) and in accordance with the Grading Code of the City ofTemecula. PETRA GEOTECHNICAL, INC. 41640 Corning Place . Suite 107 . Murrieta . CA 92562 . Tel: (909) 600-9271 . Fax: (909) 600-9215 \ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 IN. 241-01 Page 2 The completed earthwork has been reviewed and is considered adequate for the construction now planned. On the basis of our observations, as well as field and laboratory testing, the recommendations presented in this report were prepared in conformance with generally accepted professional engineering practices and no further warranty is implied nor made. SUMMARY OF AS-GRADED SOIL AND GEOLOGIC CONDITIONS As-Graded Conditions Geologic conditions exposed during the process of grading were frequently observed and mapped by Petra's geologic staff. A lot-by-lot summary of soil conditions is presented in the attached Table 1. Geologic Units A general description of the soil and bedrock materials encountered during grading in the subject tract is provided below. . Compacted Engineered Fill (map symbol Afc) -- The compacted-fill soils placed onsite were derived from soil and bedrock materials. These materials generally consisted of fine-to coarse-grained sands, silty sand and sandy silts. . Compacted Artificial Fill (map symbol Afc,} -- Compacted artificial fill was encountered beneath portions of Lots 82 through 84, 89 through 102 and Paraguay Drive. Alluvial removals were previously accomplished to expose competent Pauba Formation bedrock during grading operations for Tract 23143-3 with geotechnical observation by Petra (Petra, 1999). Observation and testing are discussed in Petra's September 1999, report of rough grading for Tract 23143-3 (see References). During this phase of grading, alluvial removals were accomplished to Pauba Formation bedrock directly adjacent to the previously placed compacted fill. Fills were keyed and benched to achieve current design grades within Tract 23143-6. 'Z-- ~ ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July I, 2002 IN. 241-01 Page 3 . Quaternarv Alluvium (no map svmboJ) -- Quaternary alluvial deposits were present within the drainages and valleys throughout Tract 23143-6. These materials consisted of light to dark brown to yellow brown silty sand, clayey sand and gravelly sand. These materials were low in density, compressible and varied from 5 to 35 feet in thickness. Alluvial soils were completely removed in cut and fill areas to expose competent Pauba Formation bedrock. . Quaternary Colluvium/Topsoil Undifferentiated (no map svmbol) n Quaternary topsoil and colluvial deposits blanketed the ridgelines and the lower flanks of the hillsides throughout the site. These soils consisted of brown to dark brown silty sands and clayey sands. Thickness generally varied from 2 to 15 feet. These soils were completely removed in cut and fill areas to expose competent Pauba Formation bedrock. . Quaternary Pauba Formation (map symbol Qps) -- Pauba Formation bedrock underlies the entire site. The bedrock was observed to vary in color from grey brown and orange brown to yellow brown: The bedrock units generally consist of thickly to massively bedded sandstone, silty sandstone and sandy siltstone. Pauba Formation sandstone was typically fine- to very coarse-grained, micaceous, poorly indurated and locally very friable. The upper approximately 2 to 5 feet of the bedrock was noted to be weathered and to exhibit a slight to moderate degree of porosity. Below the weathered zone, the bedrock was typically noted to be damp to moist and dense to very dense. SUMMARY OF EARTHWORK OBSERVATIONS AND DENSITY TESTING Clearing and Grubbing At the time of grading, a majority of the tract was covered with a light to moderate growth of grasses and weeds. This vegetation was stripped and removed from the site prior to the beginning of rough grading. Ground Preparation Surficial materials (undocumented artificial fill, topsoil, colluvium and alluvium) were removed to expose competent Pauba Formation bedrock in cut areas and in fill areas prior to fill placement. ;, ~ ~ II I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1, 2002 J.N.241-01 Page 4 Prior to placing fill, exposed bottom surfaces in all removal areas were first observed to confirm complete removal of surficial materials by our project geologist. Following this observation, the exposed bottom surfaces were scarified to depths of approximately 6 to 8 inches, watered or air-dried as necessary to achieve a moisture content equal to or slightly above optimum moisture content and then recompacted in- place to a minimum relative compaction of90 percent. Lot Overexcavations To mitigate distrcss to residential structures related to the potential adverse effects of excessive differential settlement, the cut portion of cut/fill transition lots were overexeavated 3 to 15 feet below finish grade and replaccd with compacted fill. This lot treatment occurred on Lots 4, 9,14,18 through 23,32 through 36, 38 through 40, 45 through 48,56 through 59,71,76,77,100 through 102, 106 through 110 and 114 to depths presented in Table 1. Fill Placement and Testing All fill soils were placed in lifts reshicted to approximately 6 to 8 inches iil maximum thickness, watered or air-dried as necessary to achieve near-optimum moisture conditions, mechanically mixed to a uniform moisture content and then compacted in- place to a minimum relative compaction of90 percent based on ASTM Test Mcthod D1557. Compaction was achieved by wheel-rolling with an 824 rubber-tired dozer and loaded scrapers. The maximum vertical depth of fill placed within the subject lots is approximately 68 feet on Lot 68. Where compacted fiBs are 50 feet or more, the depth of fill below 50 feet was compacted to a minimum of 95 percent relative compaction. Lots 60 through 63 and 66 through 69 are underlain by fiBs of 50 feet or more. A. ~ ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July I, 2002 J.N.241-01 Page 5 Field density and moisture content tests were performed in accordance with nuclear- gauge test methods ASTM Test Methods D2922 and D3017, respectively. Occasional field density tests were also performed in aceordance with the sandcone method (ASTM Test Method DI556). Field density test results are presented on the attached Table II and approximate test locations are shown on the enclosed Geotechnical Map with Density Test Locations (Plates 1 through 6). Field density tests were taken at vertical intervals of approximately I to 2 feet and the compacted fills were tested at the time of placement to verify that the specified moisture content and minimum required relative compaction of90 percent had been achieved. At least one in-place density test was taken for each 1,000 cubic yards of fill placed and/or for each 2 feet in vertical height of compaeted fill. The actual number of tests taken per day varied with the project conditions, sueh as the number of earthmovers (scrapers) and availability of SUPP0l1 equipment. When field density tests produced results less than the required minimum relative compaction of 90 percent or if the soils were found to be excessively above or below optimum moisture content, the approximate limits of the substandard fill were established. The substandard area was then either removed or reworked in-place. Visual classification of earth materials in the field was the basis for detem1ining which maximum dry density value was applicable for a given density test. Single-point checks were performed to supplement visual classification. Fill Slopes Fill slopes were eonstructed at a 2:1 (horizontal:vertical [h:v]) slope ratio to a maximum height of approximately 42 feet within Tract 23143-6. The fill slopes are considered grossly and surfieially stable to the heights and inclinations at which they are constructed. 6' ~ ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 IN. 241-01 Page 6 Cut Slopes Cut slopes were constructed at a 2: 1 (h:v) slope ratio to a maximum height of approximately 4 feet within Tract 23143-6. The cut slopes are considered grossly and surficially stable to the heights and inclinations at which they are constructed. Stabilization Fills Where highly erodible, fiiable sands were exposed on design cut slopes, replacement stabilization fills were constructed. This situation occurred for the slopes located at the rear of Lots 74 and 75. A keyway (20 feet wide) was excavated to a minimum depth of 2 feet below toe grade, tilted-back into slope at a minimum gradient of 2 percent. Due to the very granular nature of the backcut and the bedrock exposed in the keyway, no intemal backdrains were installed. LABORATORY TESTING Maximum Dry Density Maximum dry density and optimum moisture content for each change in soil type observed during grading were determined in our laboratory in accordance with ASTM Test Method 01557. Pertinent test values for each phase of grading are summarized in Appendix A. Expansion Index Tests Expansion index tests were performed on representative samples of soil existing at or near finish-pad grade within the subject lots. These tests were performed in accordance with ASTM Test Method D4829. Test results are also summarized in Appendix A. (, tt1 ~ I I I I I I I I I I I I I I I I I 'I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1, 2002 J.N.241-01 Page 7 Atterber!: Limits Atterberg limits were determined for selected soil samples per ASTM Test Method D4318. Test results are presented in Appendix A. Soluble Sulfate Analyses Soluble sulfate analyses were determined for representative samples of soil existing at or near finish grade within the subject lots. These tests were performed in aecordance with California Test Method No. 417. Test results are summarized in Appendix A. FOUNDA nON-DESIGN RECOMMENDA nONS Foundation Types Based on as-graded soil and geologic conditions, the use of conventional slab-on- ground foundations is considered feasible for the proposed residential stmctures. Recommended design parameters are provided herein. Allowable Soil-Bearing Capacities An allowable soil-bearing capacity of 1,500 pounds per square foot (pst) may be used for 24-inch square pad footings and 12-inch wide continuous footings founded at a minimuin depth of 12 inches below the lowest adjacent final grade. This value may be increased by 20 percent for each additional foot of width or depth, to a maximum value of 2,500 psf. Recommended allowable soil-bearing values include both dead and live loads and may be increased by one-third when designing for short-duration wind and seismic forces. .., ~ ~ I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July I, 2002 IN. 241-01 Page 8 Anticipated Settlement I Based on the general settlement characteristics of the compacted fill soils, as well as the anticipated loading, it has been estimated that the maximum total settlement of building footings will be less than approximately 0.75 inch. Maximum differential settlement over a horizontal distance of 30 feet is expected to be about one-half the total settlement. The maximum anticipated differential settlement of 0.38 inch in 30 feet may be expressed as an angular distortion of 1 :960. I I I Lateral Resistance A passive earth pressure of250 psfper foot of depth to a maximum value of2,500 psf may be used to determine lateral-bearing resistance for building footings. Where structures such as masonry block walls and retaining walls are planned on or near desccnding slopes, the passive earth pressure should be reduced to 150 psfper foot of I I depth to a maximum value of 1,500 psf. In addition a coefficient of friction of 0.40 times the dead-load forces may also be used between concrete and the supporting soils to determine lateral-sliding resistance. An increase of one-third of the above values may also be used when designing for short-duration wind and seismic forces. I I I I I I I The above values are based on footings plaeed directly against compacted fill. In the case where footing sides are formed, all backfill against the footings should be compacted to a minimum of90 percent of maximum dry density. Settlement Monuments and Monitoring At the completion of rough grading, two settlement monuments were eonstructed on Lots 61 and 67 to monitor post-grading settlement of eompacted fill for Lots 60 through 63 and 66 through 69, where fill thicknesses are 50 feet or more. These monuments were initially installed on June 20, 2002, and will be re-surveyed on a regular basis at 2- and 4-week intervals. Settlement-monitoring data will be presented '8>tt1 ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1, 2002 J.N.241-01 Page 9 in a supplementary report at a later date. Construction on Lots 60 through 63 and 66 through 69 within Tract 23143-6 should be temporarily delayed until data indicates that primary settlement is complete. Footing Observations All footing trenches should be observed by a representative of Petra to verify that they have been excavated into competent bearing soils and to the minimum embedments recommended herein. The foundation excavations should be observed prior to the placement of fonns, reinforcement or concrete. The excavations should be trimmed neat, level and square. All loose, sloughed or moisture-softened soil and any construction debris should be removed prior to placing concrete. Excavated soils derived from footing and utility trench excavations should not be placed in slab-on-ground areas unless the soils are compacted to a minimum of 90 percent of maximum dry density. Expansive Soil Considerations Results of laboratory tests indicate onsite soil and bedrock materials exhibit VERY LOW and LOW expansion potentials as classified in accordance with 1997 Uniform Building Code (UBC) Table 18-1-B. A lot-by-Iot breakdown for the different levels of expansion is provided below. . Very Low Expansion Potential - Lots I through 37, 41 through 75, 85 through 114 and Park Site 123 . Low Expansion Potential - Lots 38 through 40 and 76 through 84 Design and construetion details for the various levels of expansion potential are provided in the following sections. q~ ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 J.N.241-01 Page 10 Very Low Expansion Potential (Expansion Index 0[20 or less) The following recommendations pertain to as-graded lots where the foundation soils exhibit a VERY LOW expansion potential as classified in accordance with 1997 UBC Table IS-I-B. For soils exhibiting expansion indices of less than 20, the design of slab-on-ground foundations is exempt from the procedures outlined in 1997 UBC Section 1815. Based on this soil condition, it is recommended that footings and floors be constructed and reinforced in accordance with the following minimum criteria. . However, additional slab thickness, footing sizes and/or reinforcement should be provided as required by the project architect or structural engineer. . Footings Exterior continuous footings may be founded at the minimum depths indicated in 1997 UBC Table 18-I-C (i.e., 12-inch minimum depth for one-story and IS- inch minimum depth for two-story construction). Interior continuous footings for both one- and two-story construction may be founded at a minimum depth of 12 inches below the lowest adjacent grade. All continuous footings should have a minimum width of 12 and 15 inches, for one- and two-story buildings, respectively and should be reinforced with two NO.4 bars, one top and one bottom. Exterior pad footings intended for the support of roof overhangs, such as seeond-story decks, patio eovers and similar construetion, should be a minimum of 24 inehes square and founded at a minimum depth of IS inches below the lowest adjacent final grade. No special reinforcement of the pad footings will be required. . Floor Slabs Living-area conerete- floor slabs should be 4 inches thick and reinforced with either 6-inch by 6-inch, No.6 by No.6 welded-wire fabric (6x6-W2.9xW2.9 WWF) or with NO.3 bars spaced a maximum of 24 inches on center, both ways. All slab reinforcement should be supported on eonerete chairs or bricks to ensure the desired placement near mid-depth. \0 tt1 ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1, 2002 J.N.241-01 Page 11 Living-area concrete-floor slabs should be underlain with a moisture-vapor barrier consisting of a polyvinyl chloride membrane, such as 6-mil Visqueen or equivalent. All laps within the membrane should be sealed and at least 2 inches of clean sand be placed over the membrane to promote uniform curing of the concrete. - Garage-floor slabs should be 4 inches thick and should be reinforeed in a similar manner as living-area floor slabs. Garage-floor slabs should also be placed separately from adjacent wall footings with a positive separation maintained with 3/S-inch-minimum, felt expansion-joint materials and quartered with weakened-plane joints. A 12-inch-wide grade beam founded at the same depth as adjacent footings should be provided across garage entrances. The grade beam should be reinforced with a minimum of two NO.4 bars, one top and one bottom. Prior to placing concrete, the sub grade soils below all concrete slab-an-ground should be prewatered to promote unifonn curing of the concrete and minimize the development of shrinkage cracks. Low Expansion Potential (Expansion Index of 21 to 50) The following reeommendations pertain to as-graded lots where the foundation soils exhibit a LOW expansion potential as classified in accordance with 1997 UBC Table IS-I-B. The 1997 UBC specifies that slab-on-ground foundations (floor slabs) resting on soils with an expansion index greater than 20 require special design considerations in accordance with 1997 UBC Section 1815. The design procedures outlined in 1997 UBC Section 1815 are based on the thickness and plastieity index of each different soil type existing within the upper 15 feet of the building site. For final design purposes we have calculated an effective plastieity index of 12 in accordanee with 1997 UBC Section 1815.4.2. The design and construction recommendations that follow are based on the above soil conditions and may be considered for minimizing the effects of slightly (LOW) expansive soils. These recommendations have been based on the previous experience \\ ~ ~ I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1, 2002 J.N.241-01 Page 12 of Petra on projects with similar soil conditions. Although construction performed in accordance with these recol1ll1lendations has been found to minimize post-construction movement and/or cracking, they generally do not positively mitigate all potential effects of expansive soil action. The owner, architect, design civil engineer, structural engineer and contractors must be made aware of the expansive-soil conditions which exist at the site. Furthermore, it is recommended that additional slab thicknesses, footing sizes and/or reinforcement more stringent than recommended below be provided as required or specified by the project architect or structural engineer. . Footings I I Exterior continuous footings may be founded at the minimum depths indicated in 1997 UBC Table 18-I-C (i.e., 12-inch minimum depth for one-story and 18- inch minimum depth for two-story eonstruction). Interior continuous footings for both one- and two-story construction may be founded at a minimum depth of 12 inches below the lowest adjacent grade. All continuous footings should have a minimum width of 12 and 15 inches, for one- and two-story buildings, respectively and should be reinforeed with two NO.4 bars, one top and one bottom. I I I I I I I Exterior pad footings intended for the support of roof overhangs, such as second-story decks, patio covers and similar construction, should be a minimum of 24 inches square and founded at a minimum depth of 18 inches below the lowest adjacent final grade. The pad footings should be reinforced with No.4 bars spaced a maximum of 18 inches on centers, both ways, near the bottom- third of the footings. . Floor Slabs - The project architect or structural engineer should evaluate minimum floor-slab thickness and reinforcement in accordance with 1997 UBC Seetion 1815 based on an effective plasticity index of 12. Unless a more stringent design is recommended by the architect or the structural engineer, we recommend a minimum slab thickness of 4 inches for both living-area and garage-floor slabs and reinforcing consisting of either 6-inch by 6-inch, No.6 by No.6 welded- wire fabric (6x6-W2.9xW2.9 WWF) or No.3 bars spaced a maximum of 18 \t.--........ .~ ~ I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 J.N.241-01 Page 13 inches on centers, both ways. All slab reinforcement should be supported on concrete chairs or bricks to ensure the desired placement near mid-height. Living-area concrete-floor slabs should be underlain with a moisture-vapor barrier consisting of a polyvinyl chloride membrane, such as 6-mil Visqueen or equivalent. All laps within the membrane should be sealed and at least 2 inches of clean sand be placed over the membrane to promote uniform curing of the concrete. Garage-floor slabs should also be placed separately from adjacent wall footings with a positive separation maintained with 3/8-ineh-minimum, felt expansion- joint materials and quartered with weakened-plane joints. A 12-inch wide grade beam founded at the same depth as adjacent footings should be provided across garage entrances. The grade beam should be reinforced with a minimum oftwo No.4 bars, one top and one bottom. I I I I Prior to placing concrete, the subgrade soils below all living-area and garage- floor slabs should be pre-watered to achieve a moisture content that is at least equal to or slightly greater than optimum-moisture content. This moisture content should penetrate to a minimum depth of 12 inches into the subgrade soils. POST-TENSIONIW SLABS I I I I I I I In lieu of the preceding reeolTImendations for conventional footings and floor slabs, post-tensioned slabs could be used. The actual design of post-tensioned slabs is referred to the project structural engineer who is qualified in post-tensioned slab design, using sound engineering practiees. The post-tensioned slab-on-ground should be designed in general eonformance with the design specification of 1997 UBC Section 1816. Alternate designs are allowed per 1997 UBC Section 1806.2 that addresses the effects of expansive soils when present. However, to assist the structural engineer in his design, the following parameters are recommended. \3 ~ ~ I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 IN. 241-01 Page 14 I I Expansion Index Very Low and Low (0 to 50) Assumed percent clay 30 Clay type Montmorillonite Approximate depth of constant suction (feet) 7.0 Approximate soil suction (pF) 3.6 Approximate velocity or moisture flow (inches/month) 0.7 Thornwaitc Index -20 A verage edge Center lift 4.6 Moisture variation depth, em (feet) Edge lift 2.2 Anticipated swell, y.,\ Center lift 1A (inches) Edl!e lift OA I I I I I I . Perimeter footings for either one- or two-story dwellings may be founded at a minimum depth of 12 inches below the nearest adjacent final-ground surface. Interior footings may be founded at a minimum depth of 12 inehes below the top of the finish-floor slab. I I . Post-tensioned foundations and slabs should be designed based on a minimum 15- foot unsupported length at the middle and 10 feet of unsupported cantilever length at the comers. It should be noted that the angular distortion in any case should not exceed 0.002. I I . A 12-inch wide grade beam founded at the same dcpth as adjacent footings should also be provided across thc garage entranee. I . All dwelling-area floor slabs constmcted on-ground should be underlain with a moisture-vapor barrier consisting of a polyvinyl chloride membrane, such as 6-mil Visqueen. A minimum of 1 ineh of clean sand should be placed over the mcmbrane to promote uniform curing of the concrete. I I . Presaturation of sub grade soils below slabs-on-ground will not be required. However, subgrade soils should be thoroughly moistened prior to placing concrete. . The design modulus of subgrade reaction (k) should be 300 tons per cubie foot. I \k ~ ~ I I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1, 2002 J.N.241-0I Page 15 RETAINING WALLS Footing Embedments The base of retaining-wall footings constructed on level ground may be founded at a minimum depth of 12 inches below the lowest adjacent final graqe. Where retaining walls are proposed on or within 15 feet from the top of any adjacent descending fill slope, the footings should be deepened sueh that a minimum horizontal setback ofH/3 (one-third the slope height) is maintained between the outside bottom edges of the footings and the slope face; however, the minimum footing setback should be 5 feet. The above-recommended minimum footing setbacks are preliminary and may require revision based on site-specific soil and/or bedrock conditions. All footing trenches should be observed by the project geotechnical consultant to verify that the footing trenches have been excavated into eompetent-bearing soils and/or bedrock and to the minimum embedments recommended above. These observations should be performed prior to placing forms or reinforcing steel. Active and At-Rest Earth Pressures An active lateral-earth pressure equivalent to a fluid having a density of 40 pounds per cubic foot (pc!) should tentatively be used for design of cantilevered walls retaining a drained, level backfill. Where the wall backfill slopes upward at 2: I (h:v), the above value should be increased to 63 pef. All retaining walls should be designed to resist any surcharge loads imposed by other nearby walls or structures in addition to the above active earth pressures. For design of retaining walls that are restrained at the top, an at-rest earth pressure equivalent to a fluid having density of 60 pcf should tentatively be used for walls supporting a level backfill. This value should be increased to 95 pcf for an ascending 2: 1 (h:v) backfill. \ ~ ........ ~ ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 J.N.241-01 Page 16 Drainage A perforated pipe-and-gravel subdrain should be installed behind all retaining walls to prevent entrapment of water in the backfill. Perforated pipe should consist of 4-inch minimum diameter PVC Schedule 40 or ABS SDR-35, with the perforations laid down. The pipe should be embedded in 1.5 cubic feet per foot of 0.75- to 1.5-inch open-graded gravel wrapped in filter fabric. Filter fabric may consist ofMirafi 140N or equivalent. In lieu of a pipe and gravel subdrain, weepholes or open vertical masonry joints may be considered for retaining walls not exceeding a height of approximately 3 feet. Weepholes, if used, should be 3 inches minimum diameter and provided at minimum intervals of 6 feet along the wall. Open vertical masonry joints, if used, should be provided at 32-inch minimum intervals. A continuous gravel fill, 12 inches by 12 inches, should be placed behind the weepholes or open masonry joints. The gravel should be wrapped in filter fabric to prevent infiltration of fines and subsequent clogging of the gravel. Filter fabric may consist of Mirafi 140N or equivalent. The backfilled portions of retaining walls should be coated with an approved waterproofing compound to inhibit infiltration of moisture through the walls. Temporary Excavations To facilitate retaining-wall construction, the lower 5 feet of temporary slopes may be cut vertical and the upper portions exceeding a height of 5 feet should then be eut back at a maximum gradient of 1: 1 (h:v) for the duration of construction. However, all temporary slopes should be observed by the projeet geotechnical consultant for any evidence of potential instability. Depending on the results of these observations, flatter temporary slopes may be necessary. The potential effects of various parameters such as weather, heavy equipment travel, storage near the tops of the temporary excavations \G:> ~ ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecnla July 1,2002 J.N.241-01 Page 17 and eonstruction scheduling should also be considered in the stability of ternporary slopes. Wall Backfill All retaining-wall backfill should be placed in 6- to 8-inch maximum lifts, watered or air-dried as necessary to achieve near-optimum-moisture conditions and compacted in plaee to a minimum relative compaction of90 percent. MASONRY BLOCK WALLS Construction on or Near the Tops of Descending Slopes Continuous footings for masonry block walls proposed on or within 7 feet from the top of any descending slope should be deepened such that a minimum horizontal clearance of 5 feet is maintained between the outside bottom edge of the footing and the slope face. The footings should be reinforced with a minimum of two No.4 bars, one top and one bottom. Plans for any top-of-slope block walls proposing pier and grade-beam footings should be reviewed by Petra prior to construction. Construction on Level Ground Where masonry block walls are proposed on level ground and at least 5 feet from the tops of descending slopes, the footings for these walls may be founded at a minimum depth of 12 inches below the lowest adjacent final grade. These footings should also be reinforced with a minimum of two NO.4 bars, one top and one bottom. Construction Joints In order to mitigate the potential for unsightly cracking related to the effects of differential settlement, positive separations (construction joints) should be provided in the walls at horizontal intervals of approximately 25 feet and at each corner. The \1. ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1, 2002 J.N.241-01 Page 18 separations should be provided in the blocks only and not extend through the footings. The footings should be plaeed monolithically with continuous rebars to serve as effective "grade beams" along the full lengths of the walls. CONCRETEFLATWORK Thickness and Joint Spacing To reduce the potential of unsightly cracking, concrete sidewalks and patio-type slabs should be at least 3.5 inches thick and provided with construction or expansion joints every 6 feet or less. Concrete driveway slabs should be at least 4 inches thick and provided with construction or expansion joints every 10 feet or less. Subgrade Preparation As a further measure to minimize cracking of concrete flatwork, the subgrade soils below concrete-flatwork areas should first be compacted to a minimum relative density of 90 percent and then thoroughly wetted to achieve a moisture content that is at least equal to or slightly greater than optimum moisture content. This moisture should extend to a depth of 12 inches below subgrade and maintained in the soils during placement of concrete. Pre-watering of the soils will promote unifonn curing of the eoncrete and minimize the development of shrinkage cracks. A representative of the project soils engineer should observe and verify the density and moisture content of the soils and the depth of moisture penetration prior to placing concrete. Cement Type Results of laboratory tests performed on representative samples indicate that of the onsite soils eontain from extremely low amounts (undetectable) to 0.2 percent water soluble sulfates. Therefore, aceording to 1997 UBC Table 19-A-4, Types I and 11 Portland cement will be satisfactory for concrete placed in contact with the onsite soils. \ a.... ~ ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 J.N.241-01 Page 19 Soil Corrosivity Representative soil samples have been tested to determine the potential for corrosion of metal pipes due to the soils on the site. The test results indicate that the soils are mild to highly corrosive to buried metal pipes. This conclusion is based on the following corrosive potential from resistivity level readings. Resistivitv Level Readin~ Corrosivitv Potential Over 10,000 Mild 5,000 - 10,000 Moderate 1,000 - 5,000 Corrosive 500-1,000 Very Corrosive Under 500 Extremely Corrosive Note: If additional information is needed, a Corrosion Engineer should be consulted. Representative soil samples have been tested to detennine chloride exposure for reinforcing steel within the site soils. The test results indicate that the soils have a moderate ehloride exposure. PLANTERS Area drains should be extended into all planters that are located within 5 feet of building walls, foundations, retaining walls and masonry bloek garden walls to minimize excessive infiltration of water into the adjacent foundation soils. The surface of the ground in these areas should also be sloped at a minimum gradient of 2 pereent away from the walls and foundations. Drip-irrigation systems are also recommended to prevent overwatering and subsequent saturation of the adjacent foundation soils. \~ ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 IN. 241-01 Page 20 UTILITY TRENCHES All utility-trench backfill within street right-of-ways, utility easements, under sidewalks, driveways and building-floor slabs, as well as within or in proximity to slopes should be compacted to a minimum relative density of 90 percent. Where onsite soils are utilized as backfill, mechanical compaction will be required. Density testing, along with probing, should be performed by the project soils engineer or his representative, to verify proper compaction. For deep trenches with vertieal walls, backfill should be placed in approximately 1- to 2-foot thick maximum lifts and then mechanieally compacted with a hydra-hammer, pneumatic tampers or similar equipment. For deep trenches with sloped-walls, backfill materials should be placed in approximately 8- to 12-inch thiek maximum lifts and then compacted by rolling with a sheepsfoot tamper or similar cquipment. As an alternative for shallow trenches where pipe may be damaged by meehanical compaction equipment, sueh as under building-floor slabs, imported clean sand having a sand equivalent value of 30 or greater may be utilized and jelled or flooded into place. No specific relative compaction will be required; however, observation, probing and, if deemed necessary, testing should be performed. To avoid point-loads and subsequent distress to clay, cement or plastic pipe, imported sand bedding should be plaeed at least I foot above all pipe in areas where exeavated trench materials contain significant cobbles. Sand-bedding materials should be thoroughly jetted prior to placement of backfill. Where utility trenches are proposed parallel to any building footing (interior and/or extcrior trenches), the bottom of the trench should not be located within a 1: I (h:v) plane projected downward from the outside bottom edge of the adjacent footing. -zo ~ ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 J.N.241-01 Page 21 SLOPE LANDSCAPING AND MAINTENANCE The engineered slopes within the subject tract are considered grossly and surficially stable and are expected to remain so under normal conditions provided the slopes are landscaped and maintained thereafter in aceordance with the following minimum recommendations. . Compacted-earth berms should be constructed along the tops of the engineered fill slopes to prevent water from flowing directly onto the slope surfaces. . The slopes should be landscaped as soon as practical when irrigation water is available. The landscaping should consist of deep-rooted, drought-tolerant and maintenance-free plant speeies. A landscape architect should be consulted to determine the most suitable groundeover. Iflandscaping cannot be provided within a reasonable period of time, jute matting (or equivalent) or a spray-on product designed to seal slope surfaces should be considered as a temporary measure to inhibit surface erosion until such time pennanent landscape plants have become well-established. . Irrigation systems should be installed on the engineered slopes and a watering program then implemented which maintains a uniform, near-optimum moisture condition in the soils. Overwatering and subsequent saturation of the slope soils should be avoided. On the other hand, allowing the soils to dry-out is also detrimental to slope perforn1ance. . Irrigation systems should be constructed at the surface only. Construction of sprinkler lines in trenches is not recommended. . During eonstruction of any terrace drains, downdrains or earth berms, care must be taken to avoid placement ofloose soil on the slope surfaces. . A permanent slope-maintenance program should be initiated for major slopes not maintained by individual homeowners. Proper slope maintenance must include the care of drainage and erosion control provisions, rodent control and repair of leaking or damaged irrigation systems. . Provided the above recommendations are followed with respect to slope drainage, maintenance and landscaping, the potential for deep saturation of slope soils is eonsidered very low. 2-\.. 1& ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 J.N.241-01 Page 22 . Property owners should be advised of the potential problems that can develop when drainage on the building pads and adjacent slopes is altered in any way. Drainage can be altered due to the placement of fill and construction of garden walls, retaining walls, walkways, patios, swimming pool, spas and planters. POST-GRADING OBSERVATIONS AND TESTING Petra should be notified at the appropriate times in order that we may provide the following observation and testing services during the various phases of post grading construction. . Building Construction Observe all footing trenches when first excavated to verify adequate depth and competent soil-bearing conditions. Re-observe all footing trenches, if necessary, if trenches are found to be excavated to inadequate depth and/or found to contain significant slough, saturated or compressible soils. Observe pre-soaking of subgrade soils below living-area and garage floor slabs to verify adequate moisture content and penetration. . Retaining-Wall Construction Observe all footing trenches when first excavated to verify adequate depth and competent soil-bearing conditions. Re-observe all footing trenches, if necessary, if trenches are found to be excavated to inadequate depth and/or found to contain significant slough, saturated or compressible soils. Observe and verify proper installation of sub drainage systems prior to placing wall backfill. - Observe and test placement of all wall backfill to verify adequate compaction. 2'Z-- ~ ~ I I I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 J.N.241-01 Page 23 . Masonry Block-Wall Construction Observe all footing trenehes when first excavated to verify adequate depth and competent soil-bearing eonditions. - Re-observe all footing trenches, if necessary, if trenches are found to be excavated to inadequate depth and/or found to contain significant slough, saturated or compressible soils. . Exterior Concrete-Flatwork Construction - Observe and test sub grade soils below all concrete-flatwork areas to verify adequate compaction and moisture content. . Utility-Trench Backfill Observe and test placement of all utility-trench backfill to verify adequate compaction. . Re-Grading Observe and test placement of any fill to be placed above or beyond the grades shown on the approved grading plans. ']..?:? tt1 ~ I II I I I I I I I I I I I I I I I I I PACIFIC CENTURY HOMES TR 23143-6/Temecula July 1,2002 J.N.241-01 Page 24 This opportunity to be of service is sincerely appreciated. If you have any questions, please eontact this office. Respeetfully submitted, PETRA GEOTECHNICAL, INC. mann al Geologist 348 # Stephen M. Pool Senior Associate' GE 692 Table I - Lot-By-Lot Summary of As-Graded Soil Conditions Table II - Field Density Test Results References Plates 1 - 6 - Geotechnical Maps with Density Test Locations (in pocket) Appendix A - Laboratory Test Criteria/Laboratory Test Data Distribution: (6) Addressee zA tt1 ~ I I I I I I I I I I I I I I I I I I I :z ~ - - - - - - - =~ ~ ~ ~ ~ W N _ 0 ~ 00 ~ ~ ~ ~ W N - ~~ " ~ .".. -. - =" W - N W N - - - W W W qo~. ~ 00 00 ~ ~ 0 ~ ~ ~ ~ 0 0 W ~ W W 0 ~~3 "C = 9'3 ..., S' :r ~ N - - - - - - ~~~~ N ~ N ~ _ N 00 0 ~ - 0 0 0 ~ 00 00 ~ C8=~ " - ~ -. ~ "'- W~~ - ~ ~ - - - - - - - - - - - - - - -~- \0 \0 \D \0 \0 \0 \0 \0 \0 \0 \0 \O\a \0 0 \0 \.b ;;-~3' ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3~~ o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ~~_ :::l _. r:> -:=.0. N N N N N N N N N N 00 00 00 00 00 ~ ~ _ ~ ~ ~ _ _ _ _ _ _ _ _ _ _ _ _ ~ _ o-~ L < < < < < < < < < < < < < < < < < ~~~Cf; 0 r r r r r r r r r r r r r r r r r :::l~:::l~ ~ o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 =-. ~ ~. - I .< :;: <: :< <: :< :< ::;:: :< < :< :< :< :< :< :< :;: :::.,--g t:c' ><: t- ..., 0 cng;"O ;....J ;- l!!. ~ r.n o-g..- C g. ~ ;:: ..., ~3~333~~333333333 ,> o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ~ ~ 0. 0... 0... 0... 0.. 0. 0... 0... 0... 0... 0... 0. 0... 0... 0. 0. 0. tT'ln ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ l . ~ .., ~ D t;,J po po Pol po t;,J D t;,J t;,J D D D t.J -c:::: 0 ~ (i) n ;:; (i) (; (i) 0- 0- 0- 0- ;:;- 0- 0- (i) 0- 0:- (j) ~ =; l~~ .................................,..-................_......................... c-.~- o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ""lc. [JJ :::. ::!. ~ :::. ::!. ::!" ;:!" :r ~ ::. :::. ::. :::. ::. ::. ::.:! ",l':l 0 ~ ~ ~ ~ ~ ~ ~ 00 00 00 00 00 00 00 00 00 00 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ (j :z z z z z z z z z Z Z z Z Z z Z z ~,,8 (1) (tl n (tl ('ll (tl (1l Ol (tl ('!l (tl (tl (tl (tI 0 (tl (tl ...:..n L.. ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ "C~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~ a ~ ~ ~ ~ ~ ~ 0 ~ ~ ~ ~ ~ ~ ~ ~ ~ (; ~ 0 Z rn ~Q o = Cf; N N N N N N N N N N N N N N N N N ~~~ ~ -- . 0 = " " 3 " ~ ;:; ..., '"l ., " '"' N ~ ..... .j;. ~ , "" ~ N "'OOC/'J(jMC") * 0-0 "-" ~ ~ t::J~ ~g ..............O........."Tl"TlS::l ;'.;':;;;'~ g s:~ OO;:;;><n::lOO ::l III ...., "t:l 0 0..;:; ....., (1I:tg~:::~~~ ~ g =. ~ ~ o'"Sti <: :T ~. ~ (11 o' ~ ~ a (tl g g. g.,::;I '='">., 0.: ~ I'll ::!l n "t:l Q ~ I'll o.l'l103l1lo:-,~ ~ en n ::;I ..... ..... {t, CD (11 r.l g. ~ ~ 2 ~ ::. (ii' a"::l ..... ::-. ~ 'C 0: ~ ~ 3' ~ g ~ ~ 3' :g ~..... 0 :.. Dl OQ _ 0 ::r III ..,..... ~ ~ o' 3 I'll So >-i Dl tti::l ~ _. ~ Ct> Q) ..... ('") 0.. ~ III C ..... 2: :;" ~ t/l (11 O::l1'I'llOQ ~ a.n -0 (II g-~.g'P::l -< ~gg.:;>~ ?? I'll a.::S N:::": "0 0.. C :;. _. III Q) (1) ('Jq V> ~ ;::. 8" V> .g ;:;: 3 o"t:l:::r (1) 9:;:=:~ S!. ;:tl g. rJ 0 ~ ...., ::l ~ >< ~ o {Il (1) "0 ::l g. (ii' g; () ~ 3 ~. ::r Vl 0 0 g (1) a. ::l ::>';'" g- 3 :;. ~ 3..... a. (1) Cb (1) ~ 3 ~ ~ ~ ~ Cb::r 0 ~ >< _. Q) ::l ~~ (b g- Cb ~ :: 3 ~"O ~ a. <: (1) ::l ~ ~:, N (; CQ) 0 a. o a" .-., >- 3' (; W ~ ~ ~ g. ~ ~ > g -N o , "" - CO - 00 CO 00 co_ .!... c.> ::: N o ~ o n o ~ 0: ~ ." ~ o iJ' or '" o o ~ ..., ~ :;; ~ " ~ ? o " "- """ V "- Co ~ ~ Iii ';'i - ..... I I I I I I I I I I I I I I I I I I I z w ~ w W W N N N N N N N N N N _ _ c3~ ~ w N ~ 0 ~ 00 ~ ~ ~ ~ W N - 0 ~ 00 a~ ~ ~ :=1:::: =" N N N 0 0 0 0 0 0 0 0 w N - - N N qo~. ~ 00 0 0 ~ 00 w w ~~3 ." " 5' 3 -l S' :: ~ _ _ _ _ _ ~n~ ~ ~ 0 0 0 0 0 0 0 0 0 0 0 00 ~ ~ _ ~~~~ -=-= ~ - ~ _. ~ ~ ~!?~ - - ~ - - - - - - - - - - - - - -~- .. .. .. .. .... -", _. ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3~g o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 "'=_ = 0". "' .....~a. - - - 0 0 0 0 0 0 0 0 ~ N N N N N ~.~ _ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ _ ~ ~ _ o-~ l < < < < < < < < < < < < < < < < < ~~~~ 0 r r r r r r r r r r r r r r r r r =ttl=_. ~ o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O".~:!l.- I " " " " " " " " " " " " " " " " "~-g 0: >< t- -l 0 {J"Jg""O ,.., ;- ~. ~ r/J c-~..- ~ 3. :::: :::: ..., 3300 300033 0003 >"- ~~~ ~~~ ~~~~ ~ ........ o 0 0 0 0 0 0 0 0 0 0 0 0 0 000 ~ _ a. a. a. a. a. a. a. a. a. a. a. a. a. a. a. a. a. ~~ ~ ~ ~~~~!!:~~~~~0;!:::~~~~~ ~~ r- * * ~ * * * 8 * * ~ * * * 8 ~ ~ ~ -gg. 0 M ....... ...... ....... ....... ....... ...... ....... ....... ...... ...... ,...,. ...... ....... ....... ..... ........... c::::!' ~ - ;';';';0;;;0;;;00;;; ~;-rf) ~. ~. ~ ~ ~ ~ ~. ~. ~. ~. ~. ~. ~. ~. ~ ~. ~ 8 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ n Z Z z Z Z Z Z Z Z Z Z Z Z' Z Z Z Z ~ 8 o "' "' "' "' n "' "' Q "' "' "' Q "' "' "'"' ~ CJ"J ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~ ~ [Jq [Jq [Jq (fO (TO [Jq [Jq C10 cro OQ cro (rQ <ro [Jq (fO [Jq (JQ '" ~ - ~ ~ z ~ Z Z z ~ Z ~ ~ ~ ~ z ~ ~ ~ ~~ j n n n n n n n n n n n n n n n n n n 0 Z C/l nQ c ~ en N N N N N N N N N N N N N N N N N ~~~ ~ -- * c ~ " ~ 3 " ~ ~ ..., ... ., " ..... N '" ..... -'" '" , C\ dfl. N '"Cl'OVl(jI:"1(') * C-o "-~ ~ ~ tJo ~g - - 0 - 'Tl 'Tj Si ::l ;' ~ -. ;; ~ g ~:.:< OO~x(l::lCO :J VI ...., "'0 0 a..;:: ......, nZg~~~~;;o ~ g =, ~ ~ o' ~ <' :;. ~. 2. n o' ~ ~ 3 ngg.~::l,::,,>""o: ~n~(")~~~p o a..nOO",(; <: ;!!. ~ g ...... :; ~ lJ:l ~. ~ o' (il a g __ ~ VI ::l...... -, ...... '0 a.. ~ ~ 5' ~ g ~ ~ 5" :g ~...... 0 ~_. D: C/O _ n ::r Ul ......,...., ~ p) n' 3 n C -l n tT;i::l '" _. 0' ~ p) ~ ("J a.. ~ VI C ......~5.~(/) n O"::l 1 n (JQ 1;, CTg.8 -0 ~ n=.::l'P:J '< 5i g e. ~ ~ ?? a. a. 2. N ~ 'tl C ::l _. p) n aq VI ~ ::+ 0- '" ~;:::o: 3 a.. ~"'O::r g =hg.~~ ...... 0' 0 to> n ~ ...., ::l CT X to> n VI 0"'0 ::l ~. Vi. ~ n ~ 3 ~. ~ '" 0 0 (") (b a.. ::l '" ~ S 3. :?: 3 c; ~ (b o 0 x 3 ~...., ~ ~ n:J"" n to> x _. t.> ::l ~~ ~ g. n ~ :: 3 ~"'O ~ a.. <: ~ :J ~ 2.-1 N n C to> 0 0- n CT _____ )> ::;. 0- ~ ~ ~::; &. ~ ~;);. g y ~ , IV "" - 0 - 00 0 00 0_ -'- w = N C, - C) n o o ~ 0: ~ ~ ~ o ;;;> cr" '" o o - :;J " ~ ~ ~ !:O c:, is 2.. s V - "- Co "2 ~ - lD 7i - '" I I I I I I I I I I I I I I I I I I I 2 ~ = t"' ~ .. .. .. .. .. .. .. .. .. .. w w w w w 3 0 - 0 ~ 00 ..., '" ~ .. W N - 0 ~ 00 ..., '" ~ or _ ~ ~ """, _. ~ =" .. ~ '0 - N N - >< ;;: N ~ 0 0 0 0 W ;:;; ..., 0 -, 0 _. 00 0 N - 0 00 -="'3 -= = 9'3 -3 52 or ~ w w - ..., '" ~ N 0 0 0 0 0 '" w 0 ;:; ;;: __;::;" ~ (;l N 0 - :::::>;I::"=:~ - = -::l ~ - ~ -. ~ !C ~S2t"'1 - - - ~ ~ - - - - - - - - - - - - - - - - ~- 'b -", _. ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3 '" '" '" '" '" '" '" '" '" '" '" '" '" '" '" '" '" 3 ~ " 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ~ = - :I 0"."' ......e:.c. ~ ~ ~ ~ ~ '" - - '" ..., ..., w w w 2'-~ I:'"' <: <: <: <: <: <: <: <: <: <: <: 00 00 00 <: <: <: ...... ::I "0 Vl 0 ? ? ? "' c. tl) Q r r r r t"' r r r r r r r r = "' = -. ..., r 0 0 0 0 0 0 0 0 0 0 0 0 0 e;.o: ~_- 0 0 ~ ~ ~ 0 0 , ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~--o 1:0 = -< , I:'"' ..., 0 ~ ..., on = ." ;' ~. 0 ff! C'" 0 ~ r-: = , ~ ~ 0. ~ ..., = 3 3 3 = 3 3 = 3 = = = = 3 3 3 .. .. " 0 0 0 " 0 0 " " 0 " " " " 0 0 0 ::<:I 1:0 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. "'n -< 0 0 0 0 0 0 0 0 n 0 0 0 0 0 0 0 !'i t"" ~ ~ " " " " p " " " " " " 0: " " ~ - " " " " " i". " " " '" i". " " " " -= :::. 0 t'l " " " " " 0 " " " " 0 0 " " " " " o 0 ~ ~ "'l " " " " " " " " " " " " " " " " " = _. >-< ~ 0. ff! a- a- a- a- a- a- a- a- a- a- a- a- a- a- a- a- o ~ 0 ,;q ,;q ,;q ,;q ,;q ,;q ,;q' ,;q ,;q ,;q ,;q ,;q ~ ,;q ,;q ,;q. ,;q. a- a- a- a- a- a- a- a- a- a- a- a- a- a- a- a- .... I:'"' (j z z z z Z Z Z Z Z Z Z Z Z Z Z Z Z ~on 0 ~ ~ ~ 0 0 0 0 0 n 0 n 0 0 ~ n ~ 0 Z 'e. 'e. 'e. 'e. 'e. 'e. 'e. 'e. 'e. 'e. 'e. 'e. 'e. 'e. 'e. 'e. 'e. -= = C ,;q. ,;q. ,;q. '" QO ~. reo ,;q ~. ,;q ,;q. ,;q ,;q QO ,;q ,;q ,;q o ::; .... ~ " & & & & & or or 2: or & & & & & & & & = - ..., ~ ~ >-< ;,- ;,- ;,- ;,- ;,- ;,- ;,- 0 0- 0- ;,- ;,- 0- 0- 0- ;,- ;,- ~ 0 Z ff! nQ o = on N N N N N N N N N N N '" '" '" N N N 0.0.0 no -'-' ~ -- * 0 = ::0 ~ 3 " ~ ". >-l ~ .., .. " ..... N .... ..... ... .... , ~ 1.;2 N"'COVl(]l:""\)* 0-0 "-~ o " (On ~2 ~::;:;9::;:;2'2'~.~ :J "'0 ....., l'1l .... C :::-. '< oo(;iXn::l<::lO ::3 III .... "0 0 Cl.;:: ....., (l):!:g~~a~?:;t ~ 9 =. ~ ~ o' ~ ~. ...... III e. 0 _. = ~ ('il ::r o' 0. 0 0 tIl (1l-"';; {tI :::l l'1l.....,:::l '::"l""l 0.: ~O::!:lo"OOl'tlo 0'" 0.. (\l 0 (3 ~ ;:; ~ ~~UR~::j~o::l o Pl o' @ n C ...... s. ;:n' 0'" = ...... ::r-. U \0 0: Pl ~ ::J" ~ g ~ ~ 5" :g ~ ...... 0 __. ~ {{Q _",::Tv>.....,.., ~ Pl o' 3 (1l C ...., 0 tti = Pl _.;y;; Pl ~ <J 0- ~~c-2:5'':7cn OO::l1'<'tlOQ ~ cra.n -0 "' o~.g'P= .:! ~gg.~;S ?? 8..o.=N~ "'0 C ::1 _. Pl (1l!)Q VI::;: ::+ o <Il ~ ;=;: 3 o"O::r "' e: c::-: gj ~ ~ g. Q 0 :=!' -. :::l s=: X Pl (1,) Vl (1) "0 ::I ~. c;;" ~ n ~ 3 ~. ~ V> 0 0 n o n. ::I ;>:; ~ ~ 5' ~ 3 0- f;- (1l l"lI 0 x 3 ~... ~ ~ o::r ('11 Pl X _. Pl :::I n (rQ ...... 0- n::r (1) C 8..~ ::. 3 UI "'0 g- 0.. <: ~ = ~ ~...., N n c Pl 0 0- (1) 0'" ___ >- ::iOn W ""Q -1- U ::.; Pl 'P _. Vl 2: )> g y o , N .. - 0 - 00 0 00 0_ -'- w = N o ~ o n o o ~ 5- ~ ::" n D- OT ;0 o o ~ :;l c ~ ~ n ~ '::0 i? n "- S V ..;. '" "2 "tJ iii - CI) -;-t - '" I I I I I I I I I I I I I I I I I I I :z '" '" '" '" '" '" '" '" '" ~ ~ ~ ~ ~ ~ ~ ~ ~ r- oo .... '" ~ ... w tv - 0 >a 00 .... '" ~ ... w tv 3 0 e"- ~ ~ ::;;:: =~ ~ '" ~ w ... ~ ~ ~ ~ W tv ~ 00 w tv tv ... -:; ~~. 00 ~ '" >a 00 tv ~ 00 '" w ... 0 00 ... 0 ~\'tl3 -0 ~ 5'3 ., ::? ". - ;:; ;::; :;;: tv W W tv ;;; ~ ;;; ;; ;;; ;::; tv ,-., ;:;.~~ - tv - W tv. .... ... 0 Es=':~ -= ~ - ~ -. ~ ~ W::?~ - - - - - - - - - - - - ~ - - - - - - - - -- '6 '6 '6 '6 '6 - \'tl -. >a >a >a >a >a >a >a >a >a >a >a >a ~ ~ 3 '" '" '" '" '" '" '" '" '" '" '" '" '" '" '" '" '" 3 ~ ~ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ~ = - = =. \'tl -e,o. 00 ... ... ... ... ... '" t"" '" '" '" '" '" '" '" .... .... .... .... ;c-~ <: <: <: <: <: <: <: <: <: <: <: <: <: <: <: <: <: _=-0 C/o 0 ~ 0. ~ ~ r r r r r r r r r r r r r- r- r r r = ~ = >-l 0 0 0 0 0 0 c. X!::;. ~ ~ ~ ~ ~ ~ 0 0 0 0 0 0 0 0 0 0 0 e:.,-"'o , ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ Ol = -< , t"" ..., 0 ~ >-l [f) = ." t;;" :!l. 0 [FJ c:r 0 ~ e = . ~ ::: 0. ::: ...., 3 3 3 3 3 3 3 3 3 3 3 3 = :>- :>- 0 " " " 0 0 " 0 0 0 0 0 0 0 0 0 " i1:I Ol n. n. n. n. n. n. n. n. n. n. n. n. n. n. n. n. n. "'n -< ~ ~ ~ ~ ~ ~ n 0 0 0 0 0 0 0 0 0 0 t"" - - - - - - - - - - - - - - - - ~ - ~ ~ ~ ~ ~ ~ ~ '" ~ ~ ~ ~ ~ ~ '" ~ ~ "'0 :=. 0 ("rj n n n n n n " 0 n n n n n n 0 n n 0 0 "'l ~ ~. ..... 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ~ ~ ;;; [FJ ". ". ". ". ". ". ". ". ". ". ". ". ". ". ". ~ 0 ~ ~ 00. ~ 00 00. 00 ~ 00 00 00 00. cii. 00. 00 00. 00. ". ". ". ". ". ". ". ". ". ". ". ". ". ..... t"" n z z z z z Z % % Z Z Z Z Z Z Z Z Z ~C/o 0 0 0 n 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Z <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. -0 ~ 1:1 o - 00. .ciO" 00. ~: 00' 00. ~ 00' cii' cii 00 00. cii. 00. 00 cii. cii. ~ ;;' ..... ~ Z .~ ~ Z Z C" 0' 0' 0' 0' 0' ~ 9: 0' 0' 0' ~ - >-l " " " " " " " " " ~ ~ ..... 0 0 0 0 0 0 0 0 ~ 0 Z [FJ nQ o = C/o N N N N N N N N N N N N N N N N N 0.0.0 r:> -'-. ~ -- * 0 = " ~ 3 ~ ~ '" ...., ~ .... ., '" ~ N W ..... ... W , a, <at. N "tlCfC/lC"'lrrl(J * 0-0 "-0 o - ton ~g ::;;;:;; 9::;; ~ ~ E..~ ::l "'0 ....., (\l '"1 c: _. o 0 ;::;> >< (") ::l C 0 ::l II> ....."'C 0 a.;::! ......, (\lhg~~~"'~ ~ g ::t. ::; s: o' -sti < ...... Vl p,;o (ll -'::l ~ 0 [ o' ;;:: 0 g VI ::!! ~. :::lO>'-+l '::'1'0- l}O:::!.lo-ogg;o o 0... (\I 0 a UI () - <: <;n () ::l ...... ...... ~ a:l ~ Pi g. ~ u ~ ~ ~ (11' ~ :. (t o' 2 ~ e- ~~::l8Pri'-l~ "2.. 0- :T \I"l ;::+; ~ c:: CJ (i' 3 (\l S...., ~ tti i5.. ~ Vi" 0' ;> g.. =. D 'r. _ ...... c ...... _::l' OJ"' (ll O::l 0/ (ll (fq ~ o-fr8\"Do ~ (\l :::-.:::l ,::l '-< ~ g g. ~;g ;:? 8.. 0. ~. IV ~ "'0 C :::l -. CJ (\l (fq Vl ~ ;:t 8" Ul .g :::;: 3 o u:::r (tl e.: c::-:!:j ~ ......,::t. n "'0 ~g 2:~ PJ (tl '" (\l -0 ::l ~. Vi' g; () =:.. 3 ~. ~ Vl 0 0 () co 0.. ::l 7;"" ~ @ :;j" s: :3..... 0.. (\l o ~ ~ :3 ~.... ~ ~ o:T (11 D X _. CJ ::l (1\J'Q ..... 0.. o::r 0 c (1) ~ ::. :3 a--o ~ 0... < (ll :::l CJ ::.~ N 0 C D 0 0.. (1) 0- .....-- ):.0- ::;" (b W "Q -l - n -. CJ \0 =. ~ ~),. g ~ o , tv .. - 0 - 00 0 00 0_ .'-. w = N C, ~ Cl o o " ~ 0: ~ ~ o '"' C" " o o - :;J ~ o ~ ? o ;;- "- <.:::.; v - >- 00 ..'2 "b iij Cil' ';"I - l>o. I I I I I I I I I I I I I I I I I I I z c r- oo 00 00 00 00 00 .... .... .... .... .... .... .... .... .... .... 0, 3 ., vo ... W N - 0 vo 00 .... 0, ~ ... W N - 0 vo 0-_ '" ~ ::l~ ;:::" Z;; N N N N ... ... ... w w 0 0 ;; ;; :0 ... 0, -:;; O~. 0, 0, 00 00 ~ ~ ~ ... N .... ... "zl'D3 -0 c 8'3 ..., 9- C" ~ 0 N :;;: - - W N ;; :0 :::; ~ ~ W N -- n' ~ ;;> 00 00 0 0, 0 0 N 0 ... Es::ril -c '" - ~ -. ~ "- ~9t"l'l - - - - - - - - - - - - - -~~ O;j;l: Zb Zb Zb vo vo vo vo vo vo Zb vo vo Zb Zb Zb Zb Zb '" ~ 3 0, 0, 0, 0, 0, 0, 0, 0, 0, 0, 0, 0, 0, 0, 0, 0, 0, 3 '" " 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 '" C _ ::l:-' !'ll ....e:.,c. vo N N N W W W W W W 0 0 00 00 00 00 00 .. '" t"' <: <: <: <: <: <: <: <: ., - ~ ... ... ... 0 0 0 0 0 0 .... ::I "'0 Vl 0 r r r r r r r r r !'ll Co ~ 0 r- r- r- r- r- r- r- r- = rt> ::I _. .., 0 0 ., 0 0 0 0 0 0 0 0 0 0 0 0 0 0 .......: "'- ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ E: -- o' , t:C C >< , t"' ..., 0 '" .., C/)C"" :;;' ~_ 0 en a- 0 :!i- t:: C , '" ::.: 0. ::.: ..., c 3 c c 3 3 3 3 3 3 3 3 3 3 3 3 c ;.. ;.. " 0 " " 0 0 0 0 0 0 0 0 0 0 0 0 " ::::I t:C 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. "'n >< ~ ~ ~ '" ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ t"' ,,; ~ ~ - " " " " " e: e: e: " " e: " " " e: -0"- 0 t'l ;; ;; " ;; ;; ;; ;; " " " ;; ;; " ;; ;; ;; " ., 0 ~ ~ ." .... 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 c -. ~ 0. en oc OT OT OT OT OT OT OT OT OT OT OT OT OT OT OT OT '" '" 0 '" uo. rjq" uo' uo. uo. uo. uo uo. uo. uo. uo. uo. uo. uo. uo uo OT OT OT OT OT OT OT OT OT OT OT OT OT OT OT OT OT ..... t"' n z z z z z z z z z z z z z z z z z ~C/) 0 " " '" '" " " '" " " " " " " " " '" '" Z <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. <e. " c 0 uo. uo. '" uo uo' uo uo uo uo uo uo uo uo uo uo uo uo. o ::;: ..... ~ ". <T <T 0- cr- <T <T cr- <T <T <T <T <T cr- <T <T <T <T c _ .., 0- 0- 0- 0- 0- 0- 0- 0- 0- 0- 0- 0- 0- 0- 0- 0- 0- ~ " ..... '" 0 Z en nQ o C C/) N '" '" '" '" '" '" '" '" '" N N N N N N N 0.0.., rtI -.-. ~ -- * ., C '" '" 3 " ~ ;:; ..., ..., ., n ..... N W ..... .j>. w , 0\ \a N "'COVl\'lrrl~-o* "-.0 '" - ':In ~g ~ ::;;9.:;;~ci'~.~ :J "0 ...., I'll ..... C _. o o(tiXO::lOO :J "".....-Ooo.:::I-+, rt> ;!:gs:;~e""2? g., g :=-. f; s:; 0'-;::' <:" :T :!!. ~ I'll o' ~ ~ a (tI g g-g,::l '::')"'1 5. t-' o~n'QQ~~1'll g-;;~g2-~~ro < --no....,. c (ll ro o' ~ !l ~ __:::..: -. cr:::l ~ -. ..... 10 0- OIl "" _. ro 0 C '0-' .g~:Jou:::l@.......~ ~oS-[J')~~~t>> o' 3 (tl So ~ ~ tti 5. ro _. 0' E)> Pl .... D 2: (/I c .... ~ 5'. (/) o o-::l 7 ('\I (1Q !;, crg-g -0 ~ o =.:::l "p ;:l '< ~gg.~Q ~ 3.. go 5' ~ fjl 'B (1) (fq C/'l::::: ;:::+ Ob:g~ ~ e: s:- =: 15 :::. ....., -. 0 ""0 ~g g.~ Pi rll U1;;;--o :::l ~.1ii' !5 n ~ 3 :!!. ~ ~ ~ g ~ ...... 0 _. ~t3 5. s: 3 0' ~ 3 go en 0 ........... ..... ..... o::r (1) ro x crq" e 5- O:::r (tl c g ~ :: 3 ~"'O E c... "'" n ::l t-" P ~ N (; C ~ 0 0- I'll U ---.. > 3";::; ;:r "Q -1- 0 :::..: r.> \0 :::t. Vl 2:> g ~N " , .;:. -. 0 - 00 0 00 0_ -'- w = N o ~ Cl n o ~ n: ~ .. ~ '" 0- '" o o ~ :;J c ~ ~ " ~ "'" a " "-. S V - <>- Co C2 "'tl iii en ';'i - U1 I I I I I I I I I I I I I I I I I I I z :; :; :; :; :; :; :; . '"' -a -a -a -a -a -a 'D -a -a -a 3 '" '" '-" ... W N - 0 -a 00 .... '" '-" ... W N - 0 or- ~ ~ ::1::: =~ w 0 0 0 .... N N w ... ... ... w w W N N N ';:;;0 ::::. ... - ... N '-" '" w - 0 0 "::;l'D3 " . 8'3 ..., S' ". - 0 0 0 0 w '" '" 00 ;:;; :::; :;;: 00 '-" 0 0 w -;:;"'Tlt;' .... E5::':~ -. ~ - ~ _. ~ !:. i(>!?~ - - - - - - - - - - - - - ~ - - - - - -- '" '" '" - ~ _. -a -a -a -a -a -a -a -a -a -a -a -a -a -a ~ ~ 3 '" '" '" '" '" '" '" '" '" '" '" '" '" '" '" '" '" 3 ~ ~ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ~ . - ::l O".rt> -e,o. 00 00 00 00 00 00 w w w w w w w -a 'D 'D '" 0 <: <: <: <: <: <: <: <: <: <: <: <: <: <: ~ <: ~_Ol'< t"' <: < ..... = "t:l fJJ 0 no Co fo' 0 '"' '"' '"' r '"' '"' r r r r r r r r r r r ::I l'D = _. .., a 0 a a a 0 0 0 a a a a a 0 a a a ::!; x ~.- , ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~---o tl:l = >< , t"' ..., 0 ~ .., CIl = ""0 ~!!l. 0 rFJ c:r 0 ~ e = , ~ ;:: c- ;:: ...., 3 3 3 = 3 3 3 3 3 3 3 = 3 > > a 6 0 0 6 0 6 a a a a a a 6 6 a 6 :>:I tl:l c- o. 0. 0. 0. 0. 0. 0. 0. 0. 0.. 0.. 0.. 0.. 0. 0.. 0. "'n >< ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ n ~ ~ ~ '1 ~ t"' il ~ ". ~ ~ ~ ~ ~ '" ~ ~ " ~ '" " '" " ~ " " - 0 t"l " " " " " n " " " " " n n n n " n o '" ~ ~ >rj .... " " " " " " " " " " " " " " " " " . 0: ~ ~ rFJ ". ". ". ". ". ". ". ". ". ". ". ". ". ". ". 0 00. ciQ" ([C" 00 00 00 00 00. 00 00. 00. 00' 00. 00' 00 00 00 ". ". ". ". ". ". ". ". ". ". ". ". ". ". ". ". ". .... t"' n Z Z z Z Z Z Z Z Z Z Z Z Z Z Z Z Z ~en 0 n " " " n n n " " " n " n " " " " 2: re. re. re. ~ re. re. re. re. re. re. re. re. re. re. re. re. re. " . ti 00 00 ciQ. ciQ 00 00 00. 00. 00. 00 00. 00. 00. 00. 00. 00. a ~ - 00 ~ v 0' 2: Z 0' 0' 0' 0' 0' 0' 0' 0' 0' 0' 0' 0' 0' . .., ~ ~ - n n n n .,- n .,- n n .,- .,- .,- .,- .,- .,- .,- .,- ~ 0 2: rFJ nQ a = en N N N N N N N N N N N N N N N N N CoC-a (to -'-' ~ -- . a = :=0 " 3 ~ ~ '" ...., ~ .... " '" - N W ...- .... W , ~ ~ N "tloc.n(j~() * "-0 "-." " ~ \)n ~g ...... -O-'T1'TJS::;I ;".;";:;;;' s: g E:-< 000;>:(')=00 ::s VI ..... -0 0 a.. ~ ......., ro :;: g 11 ~ e; "" :;0 2, g =. Ei ~ o' -;, :;::. ....... VI ~ ([) -'::1 <3 0 ::r o' 0. 0 0 CIl (tj-' Ul (ll =o....,;::l~'"'tn: !5-ro::::J<l-g:::g;p' oo.roOOv>li <: ;!!.. ~ ~ 0" :::; ~ CO ell tOI 0...... n C c: (ii" 0- = 2 :to U ::;; 5: "" ~ :;" ~ g ::; ~ :::;- ::g ~.... 0 ~_. ~ (fQ _ ('tI ::r CIl .....,..... c: t.l (=i" 3 n E. ..., ~ tti [ g. iii" 3' Pi' g. :t. D {/) ~ 0 5 'if ~~. ~ o-g-g::;o ~ n:t.;::l,= '< &; g g. ~;g ;.? (ll 0.::1 N::";' "'tJ 0. c: :;" _. [II PJ (tl ao CIl ~ ~ ;:; en ~ ;:;: 3 o 'O::r' (ll 9-:t::=:g ~ ~g.g(j) :E .... = ~ x "" (tI en 0"0 :::l ~. Vi" g n ~ 3 ~. ~ Vl 0 0 0 00.. :::I ^ ::;. ~ 5" s: 3 ~ ~ ([) (;l 0 x 3 =..... (JQ 0 ~ ~ ~ ('1I::r (ll t.J X _. t.l = (') (JQ .... 0- o::r (1l c: 2..~ :: 3 Vl '1::l Ef 0- <: ~ :::l e;. :::"-1 N 0 C t.l 0 0- ~. 2: (/) .f; ::l (tl ro ...., ~::; g ~ Z);. g ~ n , N ... - 0 - 00 0 00 0_ -'- w ~ N o ~ a " a = ~ 0: ~ =1' n ;;;> cr ;0 a a - :;J c ~ ~ .; "" 5 ii; "-. "'-; V - "- Co .52 ::!1 III ii) ";"I - 0> I I I I I I I I I I I I I I I I I I I z - - - - - c; c; c; co r- :;: ;:; N - C; 3 0 - 'D 00 ..., c-_ ~ ~ ~:s =~ w 0 0 0 ... ..., w w -::;, '='~. C ~ 3 -0 co 5'3 ..., !:? =- ~ - n' ~j;" 0 0 0 0 0 0 0 0 Es=:~ -= ~ :; ~ !:. W2~ ,- - - - ~ ~ - ~- <b "'0 <b <b <b - l'tl _. 'D 'D 'D ~ ~ 3 ~ ~ ~ ~ ~ ~ ~ ~ 3 ~ ~ 0 0 0 0 0 0 0 0 ~ = - :::I :::!: !tl _:=.O- 00 N N N ." '" t"" 0 0 0 0 -~ :;:: :;:: :;:: :;:: :;:: :;:: :;:: :;:: ;; = "'C [/) 0 l'tl c.. l:l) 0 r- r- r- r- r- r- r- r- :::I "' :::I _. .., 0 0 0 0 0 0 0 0 ..... ~ ~ - , ~ ~ ~ ~ ~ ~ ~ ~ ~;- -- o' t:I:l - = -< , t"' ..., 0 ~ .., V> = .. ~~. 0 (J) C"o~ d = , ~ ;:: 0. ;:: .., 3 3 = = 3 3 3 3 ~ ~ 0 0 " " 0 0 0 0 " O::l 0. 0. 0. 0. 0- 0- 0. 0. "'n -< ~ ~ 0 0 0 ~ ~ ~ t"' ~ ~ ~ ~ oi ~ ~ =- ~ ~ ~ ~ ~ ~ ~ -0 _ 0 i:"l ;; ;; ;; ;; ;; ;; ;; ;; 0 0 [; <3 [; ~ ~ >rj ... [; <3 [; [; [; co _. ~ 0. rfJ 0" 0" 0" 0" 0" 0" 0" ~ ~ 0 ",' ",' ",' ",' '" '" '" "" 0" 0" 0" 0" 0" 0" 0" =- .... t"' (") z z z z z z z z ~V> 0 ~ 0 0 0 0 0 0 0 Z ce. ce. ce. ce. ce. ce. ce. ce. -0 co 1:1 "'. QQ' QQ QQ QQ QQ QQ 0 ~ .... OO!, ~ iT iT iT iT iT iT iT c- co .., ~ ~ .... co co co ;;- co co co ;;- ~ 0 Z rfJ nQ o = V> N N N N N N N N 0.0.0 l'tl -. -. ~ -- * 0 = ::0 ~ 3 ~ ~ '" ,..., ~ ... ~ n .... N W ...... ~ w , 0\ \cz. N ""C'OVln~('") '* 0-0 0..0 ~ ~ tJn ~g ....... ..... 0 - '"lj 'TJ S ::l ;>';:;;;'s: g S:-< oo(Di><n::lOO ::J <II ..., "0 0 0..;:: ....., o1.g~~ev,;;o 8., g ~.!:; ~ o'"i:l:;:- :T ~. e. (1) o' ~ ~ ~ (1l g~2,;::I~"'to.: ~(1l::!:ln-oQgo oo..ooa",nY < <II n ::l ..... ..... ~ t:t:l ~p)g'~B.2~~ (J)' O":::l ..... _. U '00- ~ ~ ::i' ~ g E; ~ 5" "0 <II 0 - ('D ....(jq ~ (b S- VI ;:; ~ c:: Pl 0" 3 0 E. -i ~ tti ~ g. (ii" 0' ;> ~ ::r. -8 ,~ _ c..... _::l . v. 00::17(000 g, 0""8-8-0 ~ O=.::J'P::l '< ~gg-.~o ?? Oo.:JN::'; '0 0. C 5" _. '" t:.> (tI.(jq '" ~ ::4 o Vl .g ;=;: 3 e..-o::r (11 ~ 3-. ~ g ;:; ;;> 0 t:.> (J) "'tl ..., :::l ~ >< PJ 111 VI "' i:l :::I s..u;" g; n e. 3 ~. ::r VI 0 0 g (1l 0. ::l '" ~ ~ :;" '7 3* ~ ~ o 0 >< 3 ~..., ~ Q (l>::r (1l t:.> )( _. P :::l n (JQ ..... 0- ~ ~ ~ 5 ~~ g- ~ <: ~ ::l e 2-2 ~ 8.. (1) cr" ,--..., > 5" 0" ;{l "Q -l - n -. t:.> \0 ::r. ~ z>- g y o . N ... - 0 - 00 0 00 0_ '- w :::::: hi o ~ Cl ~ n o = ~ cc ~ ~ .. ~ ~ '" c- ::0 o o ~ ..., 2 ~ ~ o ~ ~ is " 0.. S V - "- Co "2 3! '" in ";"l - " I I.. I" I I I I I I I I I I I I I I I I TABLE II Field Density Test Results .... ,., ,. ....o....................",.. ."...."..."".."""'."",,, ",.. . _. ........." ".",..., tEST. .......TEST... .">TEST. ELEV MOISTURE DENSITY COMP ..... SOIL. DATE <NO. '..... .....LOCA,'IlON> (ft): ... '.'(%). .. ............... (pci).< (%f .iTYP~/ 03/13/02 03/13/02 03/13/02 03/13/02 03/13/02 03/13/02 03/13/02 03/13/02 03/13/02 03/13/02 03/13/02 03/13/02 03/13/02 03/13/02 03/08/02 03/08/02 03/08/02 03/08/02 03/08/02 03/08/02 03/08/02 03/08/02 03/08/02 03/] 1/02 03/11/02 03/] 2/02 03/12/02 03/12/02 03/12/02 03/12/02 03/12/02 03/12/02 03/14/02 03/14/02 03/16/02 03/16/02 03/16/02 03/16/02 03/16/02 03/16/02 03/16/02 03/16/02 311 Lot 12 3]2 Lot 12 313 Lot 17 3]4 Lot 17 315 Lot 60 3]6 RTNo.315 3] 7 Larry Lee Ln 3 I 8 Larry Lee Ln 3 I 9 Crowne Hill 320 Crowne Hill 32 I Larry Lee Ln 322 Larry Lee Ln 323 Lot 6] 324 Lot61 363 Lot 6] 364 Lot 61 365 RT No. 364 366 Lot 60 367 Lot 60 370 Crowne HiIl/Sta 39+70 371 Lot 61 372 Crowne HiIl/Sta 40+50 373 Lot GO 386 Lot 61 387 Crowne HiIl/Sta 39+70 392 Lot 60 393 Lot 61 394 Crowne HilI/Sta 40+40 395 Lot 59 396 RT No. 395 397 Lot 12 398 Lot 13 399 RT No. 398 400 Lot 17 452 Cinnamon Ln/Sta 10+65 453 Lot 79 454 Lot 69 455 Lot 78 456 Lot 67 457 Lot 69 458 Lot 78 459 Lot 68 PETRA GEOTECHNICAL, INC. J.N.241-01 1276.0 13.1 1 ]9.0 90 2 1277.0 12.6 118.5 91 4 1266.0 11.7 ]22.3 93 2 1267.0 12.7 117.6 90 4 ]260.0 13.2 ]]1.] 89 6 12.4 1 ]3.1 90 6 1277.0 9.9 120.8 92 2 1278.0 11.8 117.1 91 I 1265.0 9.5 117.6 90 4 ]266.0 10.1 117.] 9] 1 1280.0 10.4 121.7 92 2 1281.0 ] 0.4 123.4 93 2 1264.0 9.9 119.4 90 2 1265.0 8.9 118.] 91* 4 1237.0 10.4 122.4 96** 3 1238.0 9.7 120.] 94** 3 10.1 ]21.7 95** 3 1239.0 9.9 ]23.5 96** I 1239.0 7.8 125.1 97** 1 1249.0 9.7 118.8 91 4 1242.0 13.] 119.0 95** 6 ]250.0 12.4 120.7 97 6 1248.0 11.3 119.8 92 4 1251.0 9.8 1 ]5.3 9]* 7 ]262.0 9.5 121.6 92 2 1251.0 8.5 117.7 90 4 1259.0 8.8 123.6 94 2 1263.0 9.1 118.9 90 2 ]260.0 10.2 ] 16.6 89 4 11.4 118.0 90 4 1275.0 10.5 114.8 90 7 1270.0 7.2 ] 13.3 88 ] 1270.0 9.8 119.1 92 I 1265.0 7.9 ]25.8 95 2 1234.0 9.0 125.3 95** 2 1254.0 10.2 124.6 94 2 1236.0 6.5 126.] 95** 2 1226.0 7.3 121.3 91 2 1226.0 8.5 125.] 95** 2 1227.0 8.8 126.7 96** 2 1227.0 8.7 118.5 90 2 1238.0 9.2 123.5 95*,** 4 TR 23143-6 JULY 2002 . Sandcone T ABLE-II 1 ?;Z-- I . TEST ................J:J.I'...... .. ................................ i~~i6~ ... .. .. ...... ..... .EL(f)V. ~OJSt1JJlEIjE(NSl)ITy.. ............ ..C.....O.<%M}P..<..............TS..yp9ILEi........... ...DATE .... ... .................................. t.. .(%) ................. pc . . I . TABLE )I Field Density Test Results I 03/1 6/02 460 Lot 79 1238.0 9.5 121.1 93 4 03/18/02 461 Lot 68 1240.0 10.2 120.0 92** 4 03/1 8/02 462 RTNo.461 9.0 123.9 95** 4 03/1 8/02 463 Lot 79 1240.0 10.1 120.8 92 4 03/1 8/02 464 Cinnamon Ln/Sta 12+00 1242.0 8.6 124.4 95** 4 03/1 8/02 465 Lot 77 1242.0 9.2 122.7 94 4 03/1 8/02 466 Cinnamon Ln/Sta 10+90 1243.0 5.9 118.2 92** 3 03/1 8/02 467 RTNo.466 8.2 121.3 95** 3 03/1 8/02 468 Lot 78 1243.0 8.0 118.8 92** 3 03/1 8/02 469 Lot 77 1243.0 7.8 120.3 92 4 03/1 9/02 476 Lot 67 1244.0 10.8 120.0 91 2 03/1 9/02 477 CinnamonLane/Sta 11 +50 1245.0 9.8 123.9 95** 2 03/1 9/02 478 Lot 68 1245.0 9.5 123.0 94 4 03/1 9102 479 Lot 80 1245.0. 11.1 118.0 90 4 03/1 9/02 480 Lot 69 1246.0 9.8 122.9 94 4 03/1 9102 481 Lot 80 1246.0 98 121.8 93 4 03/1 9102 482 Lot 67 1248.0 10.7 111.9 87 3 03/1 9/02 483 RT No. 482 10.3 115.0 90 3 03/1 9/02 484 Lot 78 1249.0 14.3 118.3 92 4 03/1 9/02 485 Lot 79 1249.0 9.8 121.0 91 2 03/1 9/02 486 Lot 67 1251.0 9.2 119.4 92 I 03/1 9/02 487 Lot 78 1251.0 9.2 119.6 92 1 03/20/02 488 Lot 69 1252.0 8.4 120.5 91 2 03/20/02 489 Lot 76 1252.0 83 1243 94 2 03/20102 490 Lot 78 1252.0 8.4 123.2 93 2 03/20102 491 Lot 69 1254.0 10.1 116.8 91 3 03/20/02 492 Lot 78 1254.0 7.7 119.7 93 3 03/20/02 493 Lot 76 1256.0 9.0 118.5 92 3 03/20102 494 Lot 79 1256.0 8.7 118.3 92 3 03/20/02 561 Lot 76 1259.0 8.3 121.9 92 2 03/20/02 562 Lot 70 1260.0 8.4 120.0 91 2 03/20/02 603 Lot 67 1261.0 10.5 115.2 92 5 03/20/02 604 Lot 77 1262.0 10.9 113.7 91 5 03/21102 605 Lots 78 1264.0 7.6 118.0 90* 4 03/21102 606 Lot 77 1264.0 7.8 120.1 92** 4 03/21/02 607 Lot 62 1264.0 9.4 119.2 95 6 03/21102 609 Paraguay Dr/Sta 25+05 1217.0 9.8 119.6 92 1 03/21/02 610 Paraguay Dr/Sta 26+50 1215.0 10.7 119.7 92 1 03/21102 611 Paraguay Dr/Sta 28+50 1210.0 10.0 119.6 92 1 03/22/02 612 Lot 82 1215.0 13.0 120.8 93 4 03/22/02 613 Fox Rd/Sta 115+50 1217.0 8.8 120.5 92 4 03/22/02 614 Paraguay Dr/Sta 27+00 1217.0 10.1 118.0 91 5 PETRA GEOTECHNICAL, INC. TR 23143-6 JULY 2002 J.N.241-01 * Sandcone TABLE-II 2 ,?<:O I I I I I I I I I I I I I . ...~:~~~I ......... .........i~~~i6~ .. ........... .........E~:r ... ~()&~UR.~ .DE(~~~TY~?~J>."~~~~ I I I I I I I I I I I I I I I I I TABLE II Field Density Test Resu Its 03/22102 03/22/02 03/22102 03/22/02 03/22102 03/22/02 03/22/02 03/22/02 03/22/02 03/22/02 03/22102 03/22102 03/22/02 03/22/02 03/22/02 03/22/02 03/22/02 03/22102 03/22102 03/22/02 03/23/02 03/23/02 03/23/02 03/23/02 03/23/02 03/23102 03/23/02 03/23/02 03/23/02 03/23/02 03/23/02 03/26/02 03/26/02 03/26/02 03/26/02 03/26/02 03/26/02 03/26/02 03/26102 03/26/02 03/26/02 03/26/02 615 616 617 618 619 621 622 623 624 625 751 752 753 754 755 756 757 758 759 760 761 762 764. 765 766 768 770 771 772 774 775 776 777 778 779 780 781 782 783 784 785 786 Paraguay Dr/Sta 25+80 Paraguay Dr/Sta 25+30 Lot 84 Lot 83 Lot 82 Paraguay Dr/Sta 25+90 Paraguay Dr/Sta 25+30 Lots 83-84 Lot 82 Paraguay Dr/Sta 26+40 Paraguay Dr/Sta 25+60 Paraguay Dr/Sta 24+90 Paraguay Dr/Sta 25+60 Lot 84 Lot 82 Fox Rd/Sta 115+60 Paraguay Dr/Sta 25+90 Paraguay Dr/Sta 26+70 Lot 84 Lot 84 Lot 83 Paraguay Dr/Sta 25+00 Lot 82 Lot 83 Lot 84 RT No. 762 RT No. 764 RT No. 765 RT No. 766 Paraguay Dr/Sta 24+ 7 5 Lot 95 Lot 80 Lot 79 Lot 66 Lot 63 Lot 61 Lot 68 Lot 79 Paraguay Dr/Sta 23+20 Lot 95 Lot 96 Lot 95 1219.0 1220.0 1212.0 1214.0 1218.0 1221.0 1222.5 1216.5 1219.0 1218.0 1222.0 1221.0 1223.0 1215.0 1218.0 1220.0 1223.0 1220.0 1215.0 1217.0 1218.0 1223.0 1220.0 1218.0 1218.5 1219.0 1218.0 1249.0 1246.0 1250.0 1252.0 1252.0 1250.0 1251.0 1222.0 1221.0 1225.0 1224.0 PETRA GEOTECHNICAL, INC. J.N.241-01 TR 23143-6 * Sandcone 15.0 113.3 92 J 11.7 119.7 91 2 10.9 120.3 91 2 10.1 119.7 92 4 11.3 120.3 92 4 10.7 117.9 91 I 10.5 118.3 92 I 11.7 120.5 91* 2 12.1 120.7 91 2 9.9 119.9 92 4 13.1 116.7 91 9 12.7 116.1 90 9 10.9 119.9 91 2 11.3 120.3 91 2 12.1 119.7 91 2 9.9 117.1 91' 1 9.7 116.3 90 I 10.3 118.1 90 4 10.0 118.7 91 4 9.1 116.5 90 I 10.7 118.3 91 4 9.5 113.7 88 I 8.3 113.9 87 4 8.1 117.3 88 2 7.7 116.3 88 2 8.7 116.3 90 I 9.3 118.7 91 4 10.7 119.5 91 2 10.9 120.3 91 2 9.7 118.1 90 4 10.1 118.7 91 4 12.1 120.3 91 1 11.7 121.1 92 I 11.3 119.9 91 1 9.9 116.3 90 5 10.1 116.7 90 5 10.7 117.5 90 4 9.9 117.9 90 4 9.7 117.0 91 5 10.1 114.7 90' 7 10.5 115.3 91 7 11.3 120.7 91 1 JULY 2002 ?ft. TABLE-II 3 I I ..J~~~ ............~.... ........ ............I,~~~i()N.. ...... ........ ........E~:)V;dM~~o/1~RE<DE~~bT~.C~.:r~eili> I I I I I I I I I I I I I I I I I TABLE II Field Density Test Results 03/26/02 03/26/02 03/26/02 03/26/02 03/26/02 03/26/02 03/26/02 03/26/02 03/26/02 03/26/02 03/26/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 787 788 789 790 791 794 795 796 797 798 799 800 801 802 803 804 806 807 808 809 810 812 813 814 815 816 817 818 819 820 821 822 823 824 825 851 852 853 854 855 856 857 Paraguay Dr/Sta 25+75 Paraguay Dr/Sta 25+50 Paraguay Dr/Sta 26+40 Paraguay Dr/Sta 28+00 Lot 83 Lot 94 Lot 92 Paraguay Dr/Sta 23+90 Paraguay Dr/Sta 22+50 Lot 96 Lot 82 Paraguay Dr/Sta 26+85 Lot 83 Lot 9] Lot 94 Paraguay Dr/Sta 15+60 Lot 92 Paraguay Dr/Sta 26+00 Lot 93 Paraguay Dr/Sta 27+40 Lot 94 Lot 91 Lot 93 Lot 96 Paraguay Dr/Sta 22+90 Paraguay Dr/Sta 22+40 Lot 95 Lot 97 Lot 95 Lot 96 Lot 92 Lot 93 Lot 94 Paraguay Dr/Sta 22+20 Lot 96 Paraguay/Sta 28+40 Lot 93 Paraguay/Sta 27+20 Paraguay/Sta 25+00 Paraguay/Sta 28+30 Lotn Lot 94 PETRA GEOTECHNICAL, INC. J.N.241-01 1226.0 10.7 118.3 91 4 1226.0 10.3 118.7 91 4 1225.0 10.9 119.5 91 1 ]223.0 9.7 115.9 9] 7 1221.0 10.5 114.9 90 7 1228.0 10.1 118.7 91 4 12280 9.9 115.0 91 7 1227.0 . 10.7 114.7 90' 7 1225.0 11.5 119.7 91 I 1229.0 11.7 119.5 91 I 1225.0 12.3 114.0 90 8 1228.0 10.0 114.9 90 7 1227.0 11.7 119.9 91 2 1229.0 11.3 120.3 91 2 1230.0 10.9 120.0 91 2 1231.0 10.1 114.3 90 7 1232.0 9.7 116.7 90 5 1229.0 9.9 118.3 91* 4 1231.0 10.1 117.9 90 4 1232.0 11.3 115.1 91 7 1233.0 12.9 120.0 91 2 1227.0 9.3 117.7 90 4 1234.0 9.9 114.7 90 7 1225.0 10.1 114.5 90 7 1228.0 11.3 119.9 91 2 1227.0 9.9 118.1 90 4 1227.0 9.5 118.0 90 4 1231.0 10.0 116.9 91 5 1229.0 11.9 120.7 91 2 1231.0 12.1 121.3 92 2 1235.0 10.7 120.5 91 2 1237.0 9.9 114.5 90' 7 1236.0 10.3 115.0 9] 7 1232.0 10.1 117.9 90 4 1233.0 10.9 118.7 91 4 1230.0 10.7 119.7 93 5 1239.0 11.1 119.9 93 5 1237.0 11.3 118.0 90 4 1239.0 10.7 ] 17.5 90 4 1233.0 9.9 122.7 94 4 1240.0 10.5 117.1 91 5 1242.0 10.1 116.3 90 5 TR 23143-6 JULY 2002 ~ . Sandcone TABLE-II 4 I I .. ..;j~~li.~ .....>... .....iCi~iiioN ................. ....... i .... .~~:)v;.... MOI~~URE.. pE~~~TY .. (;~~P.<:%.~ii I I I I I I I I I I I I I I I I I TABLE II Field Density Test Results 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03/27/02 03127/02 03127/02 03/27/02 03127/02 03/28/02 03/28/02 03/28/02 03/28/02 03/28/02 03/29/02 03/28/02 03/28102 03/28/02 03/28/02 03/28102 03/28/02 03/28/02 03/28/02 03/28/02 03/28/02 03/28/02 03/28/02 03/28102 03/28/02 03/28/02 03/28/02 03/28/02 03/28/02 03/28/02 03/28/02 03/29102 858 859 860 861 862 863 864 865 866 867 868 869 870 871 872 873 874 875 893 894 899 926 927 928 929 930 931 932 933 934 935 936 937 938 939 940 941 942 943 944 945 946 Paraguay/Sta 27+60 Lot 93 Lot 91 Lot 93 Lot 94 Lot 94 Lot 92 Paraguay/Sta 26+20 RT No. 864 RT No. 865 Lot 66 Lot 79 Paraguay/Sta 22+80 RT No. 868 RT No. 870 Paraguay/Sta 22+90 Lot 96 Lot 95 Lot 1 Lot 3 Lot 2 Cinnamon Ln/Sta 10+20 Lot 79 Lot 66 Lot 68 RT No. 928 Lot 79 Lot 98 Lots 96-97 Lots 97-98 Paraguay Dr/Sta 21 +00 Lot 99 Lot 80 Lot 62 Cinnamon Ln/Sta 12+40 Lot 69 Lot 81 Lots 80-8 I Lot 81 Lot 97 Lots 61-62 Lot 65 PETRA GEOTECHNICAL, INC. J.N.241-01 1236.0 1242.0 1236.0 1240.0 1243.0 1243.0 1243.0 1242.0 1253.0 1250.0 1231.0 1235.0 1236.0 1237.0 1264.0 1264.0 1263.0 1254.0 ]253.0 1256.0 ]254.0 1238.0 1233.0 1239.0 1237.0 1241.0 1240.0 1255.0 1255.0 1264.0 1260.0 1235.0 1238.0 1241.0 1242.0 1257.0 ]255.0 TR 23143-6 * Sandcone 9.9 118.5 92* 5 11.3 120.3 91 2 10.7 119.7 91 2 9.9 118.] 90 4 10.1 119.3 91 4 10.3 116.7 90 5 8.1 115.0 89 5 7.7 114.3 88 5 9.7 116.9 91 5 10.3 117.3 91* 5 7.1 1] 5.5 88 4 10.1 ] 18.7 92 5 6.0 I] 3.1 86 4 10.] ] ]8.9 91 4 9.9 120.3 92 4 ]0.7 ]23.7 94 2 11.3 ] 21.3 92 2 9.7 ] 19.5 92* 4 9.2 117.7 91 I 9.3 119.7 93 I 15.0 112.3 90 10 12.7 115.5 92 8 12.9 114.7 91 8 13.3 1 ]2.1 88 8 9.7 121.5 91 II 11.7 1 ]6.5 92 8 9.9 118.1 92 5 10.3 117.1 91* 5 10.5 116.3 90 5 12.7 117.7 92 9 ]2.9 118.3 92 9 11.7 1] 8.1 92 5 11.3 116.3 90 5 13.5 117.9 92 9 12.1 115.3 90 9 11.4 120.5 90 11 9.9 116.9 92 7 10.7 114.3 90 7 10.9 116.9 91 5 10.7 116.5 90 5 11.5 114.9 90* 7 11.7 114.5 90 7 JULY 2002 ~ TABLE-II 5 I I . . ... . ...~~~i .... ..... ..~. ....... ....... ... ...Lb~~~iQN ...................... ...i >E~~V. .. MOI~l>URE .. DEfv~tTY ... ~~~p;>.t~~i. ... I I I I I I I I I I I I I I I I I TABLE II Field Density Test Results 03/29/02 947 Lot 70 03/29/02 948 Lot 97 03/29/02 949 Lot 70 03/29/02 950 Lot 77 04/01/02 964 Lot 65 04/01/02 966 Lot 92 04/01/02 967 Lot 69 04/01/02 968 Lot 80 04/01/02 970 RT No. 968 03/29/02 1104 Detention basin 03/29/02 1105 Detention basin 03/29/02 1106 Lot 84 03/29/02 1110 Lot 82 04/02/02 1117 Paraguay/Sta 25+40 04/02/02 1120 Lot 82 04/02/02 1122 Lot 98 04/02/02 1123 Lot 62 04/02/02 1124 Cinnamon Ln/Sta 11+30 04/02/02 1125 Lot 66 04/03/02 1127 RTNo.1120 04/03/02 1131 RTNo.1122 04/03/02 1136 Detention basin 04/04/02 1140 Lot 79 04104/02 1141 Lot 77 04/04/02 1142 Lots 79-78 04/04/02 1143 Detention basin 04/04/02 1144 Detention basin 04/04/02 1145 Detention basin 04/04/02 1146 Detention basin 04/05/02 1200 Park site 123 04/08/02 1201 Crowne Hill/Sta 50+90 04/08/02 1205 Park site 123 04/08/02 1206 Park site 123 04/08/02 1207 Park site 123 04/08/02 1208 RTNo.1207 04/09/02 1263 Lot 63 04/09/02 1264 Cinnamon Ln/Sta 10+00 04/09/02 1265 Lot 67 04/09/02 1266 Lot 66 04/09/02 1267 Lot 68 04/09/02 1268 Lot 61 04/1 0/02 1269 Lot 58 PETRA GEOTECHNICAL, INC. J.N.241-01 1255.0 1242.0 1263.0 1257.0 1250.0 1241.0 1255.0 1238.0 1206.0 1204.0 1212.0 1221.0 1231.0 1223.0 1243.0 1257.0 1257.0 1258.0 1205.0 1256.0 1255.0 1246.0 1207.0 1205.0 1207.0 1208.0 1252.0 1253.0 1254.0 1262.0 1256.0 1261.0 1264.0 1264.0 1263.0 1264.0 1263.0 1269.0 TR 23143-6 * Sandcone 9.9 119.9 93 5 10.7 116.1 90 5 9.3 122.5 92 11 9.7 124.7 93 II 9.5 ] 12.2 90 10 9.5 119.5 91 2 8.1 119.6 90 2 8.7 116.7 89 4 9.1 118.4 91 4 8.9 124.7 93 II 10.5 117.7 90 4 9.7 118.3 91 4 9.1 125.0 94 11 9.7 124.5 93 11 8.3 114.1 89 9 7.1 112.7 88 7 9.7 117.5 93 7 10.9 117.9 92* 9 11.1 118.3 92 9 12.3 116.7 91 9 ]0.1 114.7 90 7 10.3 ]20.7 91 2 9.3 124.1 93 11 11.7 ] 15.5 90 9 11.9 ] 15.9 9] 9 10.3 117.5 91 I 9.1 125.3 94 II 8.9 117.9 91* 1 10.9 I] 6.3 91 9 8.9 124.1 96*' 5 9.1 122.7 92** 12 10.5 115.0 91* 8 11.2 113.5 90' 8 9.6 110.6 88* 8 10.7 114.1 90* 8 10.1 120.2 90 12 9.3 118.2 91 4 8.9 121.3 91 12 11.2 121.9 91 12 8.5 119.9 90 12 10.7 122.2 92 12 11.9 109.9 90 14 JULY 2002 ?l TABLE-II 6 I TABLE II 1....iW~~5iI~!~ .............................................i.~f:i;:~...~;;:i;~~~;f~:;~;~~~~.~~~~~M~.........;99!V1llf......;........~9!~I ........DA."'E.......N"'... ................................".0. "'.......O.N .................................(~l). ......................................(m)....................( I.) ..sl. m).",u"E". I'.. .' ........ .'. ...........;6.......................i.P....y"'............. ................ ~'.'.' ........ 7~ .." .............pf.. ..........,? ..'i"'.'"..,..,.,.' I I I I I I I I I I I I I I I I 04/1 0102 1270 Lot 117 04/1 0102 1271 Crowne HiII/Sta 39+00 04/1 0/02 1272 Crowne HiII/Sta 39+00 04/1 0102 1273 Lot 58 04/1 0102 1274 Lot 59 04/1 0/02 1275 Crowne HiII/Sta 37+80 04/04/02 1279 Lot 84 04/04/02 1280 Paraguay DrlSta 29+00 04/04/02 1281 Detention basin 04/05102 1286 Detention basin 04/05/02 1287 Detention basin 04/05/02 1291 Detention basin 04/05/02 1294 Detention basin 04/05/02 1299 Detention basin 04/09102 1301 Park site 123 04/09102 1302 Park site 123 04/09102 1303 Park site 123 04/08102 1351 Detention basin 04/08/02 1360 Lot 83 04/08/02 1361 Detention basin 04/08/02 1362 Detention basin 04/08/02 1363 Paraguay DrlSta 28+60 04/08/02 1364 Paraguay DrlSta 28+70 04/09102 1373 Detention basin 04/1 0/02 1378 Park site 123 04/11/02 1393 Lot 122 04/11/02 1394 Park site 123 04/11/02 1395 Park site 123 04/11/02 1396 Park site 123 04/11/02 1397 Park site 123 04/11/02 1398 Park site 123 04/1 0/02 1401 Larry Lee Ln/Sta 10+50 04/1 0/02 . 1407 Lot 61 04/1 0/02 1408 Lot 60 04/1 0102 1409 Lot 62 04/1 0102 1410 Lot 117 04/1 0/02 1411 Lot 59 04/1 0102 1412 Cinnamon Lane 04/1 0102 1413 Lot 60 04/11/02 1414 CrowneHiII/Sta 37+50 04/11/02 1415 Lot 59 04/11/02 1416 Lot 60 PETRA GEOTECHNICAL, INC. J.N.241-01 1273.0 12.1 .111.3 91 14 1271.0 10.8 113.0 93 14 1272.0 13.2 110.5 91 14 1272.0 11.3 112.4 92 14 1272.0 13.6 1] 1.7 92 14 1275.0 14.1 113.4 93* 14 1209.0 10.3 119.9 93 5 1210.0 11.] 114.9 90 7 1207.0 11.7 115.7 91 7 1209.0 9.3 118.7 92 5 1210.0 9.9 118.3 92 5 121 00 11.9 115.7 93 10 1213.0 11.9 118.3 92 9 1215.0 11.1 117.7 92 9 1264.0 13.9 115.8 93* 10 1268.0 13.1 113.0 91* 10 1270.0 11.4 120.5 94' 9 1213.0 10.3 I J 5.3 90 3 1229.0 11.3 116.1 91 3 1217.0 10.3 124.3 93 12 1216.0 14.7 1141 91 6 1216.0 11.3 114.9 90 7 1219.0 11.1 115.5 91 7 1219.0 9.1 111.1 88 6 1260.0 14.1 108.6 90 13 1258.0 9.8 123. ] 92 12 1258.0 11.4 113.8 90 8 1264.0 11.7 114.5 91 8 1265.0 10.8 ] 13.5 90 8 1266.0 10.6 I 18.2 92' 9 1269.0 11.2 120.9 94' 9 1273.0 11.6 112.3 92 14 1269.0 12.2 112.9 93 14 1272.0 13.6 113.6 93 14 1263.0 11.4 113.2 93' 14 ]277.0 10.7 116.6 91 3 1275.0 11.9 118.1 92 3 1275.0 9.8 115.7 90 3 1276.0 8.7 117.4 92 3 1280.0 10.2 116.6 91 3 ]279.0 11.6 115.9 91 3 1271.0 9.9 1 ]5.5 90 3 TR 23143-6 JULY 2002 ?16 . Sandcone TABLE-II 7 I I .~;~~< ...to8~~1()kEi:r ... MOI~~])E(~~ATY~l~P.~~i I I I I I I I I I I I I I I I I I TABLE II Field Density Test Results 04/11/02 04/11/02 04/11/02 04/11/02 04/11/02 04/11/02 04/11/02 04/11/02 04/11/02 04/12/02 04112/02 04/11/02 04/11/02 04/11/02 04/11/02 04/12/02 04/12/02 04112/02 04/12/02 04/12/02 04112/02 04112/02 04112/02 04/09/02 04/09/02 04/09/02 04/09/02 04/09/02 04/09/02 04/09/02 04/09/02 04/09/02 04/09/02 04/1 0/02 04/1 0/02 04/1 0/02 04/1 0/02 04/1 0/02 04/1 0/02 04/16/02 04/16/02 04/15/02 1417 1418 1419 1420 1421 1422 1423 1424 1425 1460 1461 1476 1477 1478 1479 1480 1481 1482 1483 1484 1485 1486 1487 1504 1505 1506 1507 1508 1509 1510 1511 1516 1517 1518 1519 1520 1521 1524 1525 1574 1575 1582 Cinnamon Ln/Sta I 1+70 Crowne Hill/Sta 38+50 Lot 58 Lot 62 Cinnamon Ln/Sta 11 +00 Crowne HiII/Sta 12+40 Lot 60 Lot 62 Lot 60 Park site 123 Park site 123 Lot 69 Cinnamon Ln/Sta 10+05 Lot 61 Lot 63 Crowne HiII/Sta 39+25 Lot 63 Lot 64 Lot 67 Lot 70 Lot 77 Lot 67 Lot 65 RT No. 1373 Lot 82 Lot 83 Lot 84 Detention basin Lot 82 Lot 84 Lot 84 Lot 82 1271.0 9.0 117.4 92 3 1279.0 11.2 122.7 92 12 1281.0 9.6 124.7 93 12 1265.0 11.2 116.2 91 3 1265.0 9.1 121.7 91 12 1276.0 10.5 122.8 92 12 1280.0 9.4 120.6 90* 12 1268.0 11.0 116.3 91 3 1273.0 10.1 117.4 92 3 1259.0 14.8 113.3 91 15 12GO.0 15.1 114.3 92 15 1269.0 12.2 115.7 90 3 1266.0 12.5 115.2 90 3 1274.0 11.5 121.7 91 12 1270.0 9.8 122.6 92 12 1280.0 11.1 121.3 91 12 1272.0 10.3 120.6 90 12 1265.0 13.9 112.7 91 10 1267.0 14.4 114.7 92 10 1271.0 12.6 116.9 91 1 1268.0 10.9 121.7 91 12 1266.0 11.2 117.4 91 1 1264.0 12.1 117.2 91 1 14.1 114.7 92 6 1228.0 9.3 125.7 94 12 1232.0 10.7 116.5 92 7 1222.0 10.5 117.7 93 7 1221.0 11.3 IIG.3 92* 7 1231.0 12.1 118.7 92 5 1225.0 12.5 119.0 92 5 1228.0 14.0 111.1 92 13 1234.0 12.3 117.5 92 9 1223.0 12.7 117.7 92 9 123 1.0 11.5 118.9 93 9 1235.0 13.9 110.3 92 13 123G.0 9.7 118.9 92 1 1226.0 9.9 119.5 93 I 1234.0 10.3 119.7 93 1 1229.0 12.0 117.9 92 9 1265.0 8.9 113.5 90 8 1268.0 10.1 116.6 93 8 1267.0 9.2 118.7 92 5 TR 23143-6 JULY 2002 ~<\ . Sandcone TABLE-liS Detention basin Lot 84 Lot 83 Lot 82 Detention basin Lot 84 Detention basin Cinnamon Ln/Sta 10+20 Lot 63 Park site 123 PETRA GEOTECHNICAL, INC. J.N.241-01 I I I I I I I I I I I I I I I I I I TABLE II Field Density Test Results 04/15/02 1583 Park site 123 1261.0 10.0 119.4 04/15/02 1588 Park site 123 1269.0 10.7 114.3 04/15/02 1591 Park site 123 1262.0 9.8 109.7 04/16102 1594 RTNo.1591 15.2 ] 14.7 04/16/02 1601 Lot 58 1276.0 14.2 113.7 04/1 6102 1602 Lot 61 1274.0 9.0 ] 14.5 04/16/02 1603 Lot 64 1272.0 9.5 1 ]6.4 04/16102 1604 Lot 62 1276.0 10.2 123.7 04/1 6/02 1605 Lot ]9 12770 8.8 1 ]7.6 04/16/02 1606 Lot ]8 1278.0 10.0 119.4 04/16/02 1607 Lot 69 1268.0 12.] 114.5 04/1 7/02 1616 Lot 70 1272.0 7.2 1 ]4.9 04/17/02 1617 Lot 59 1276.0 11.3 121.0 04/17/02 1618 Lot 64 1274.0 9.1 125.] . 04/1 7/02 1619 Lot 63 1270.0 8.7 1218 04/17/02 1620 Lot 66 1270.0 7.5 121.0 04/17/02 1621 Lot 69 1276.0 7.1 115 ] 04/17/02 1622 Lot 60 ]278.0 13.0 116.7 04/17/02 1623 Lot 60 12770 11.5 117.4 04/1 7/02 1624 Lot 64 1271.0 8.9 123.3 04/1 7/02 1625 RTNo.1621 8.2 121.2 04/1 7102 1637 Park site 123 1266.0 11.8 117.0 04/17/02 1638 Park site 123 ]263.0 12.4 116.8 04/15/02 1654 Crowne HiIIISta 39+90 1282.0 11.7 122.4 04/15102 1655 Lot 63 ]270.0 9.9 120.9 04/1 1102 1676 Lot 99 1243.0 ]2.1 119.] 04/1 1102 1677 Lot 97 1245.0 ]1.9 118.7 04/11/02 1678 Lot 95 1241.0 8.7 125.3 04/1 1102 1679 Paraguay Dr/Sta 21 +00 ]250.0 9.9 119.7 04/11102 1680 Paraguay Dr/Sta 22+00 1246.0 9.5 124.7 04/12/02 1694 Lot 90 1227.0 11.3 118.0 04/12/02 1695 Lot 90 1230.0 11.5 ] 19.0 04/12/02 ]696 Lot 91 1238.0 11.5 ]20.1 04/12102 1697 Lot 90 1233.0 12.1 ] 19.7 04112102 1698 Lot 93 1244.0 9.3 118.5 04/12102 ]699 Lot 94 1245.0 9.9 119.7 04/12/02 1701 Lot 8] 1257.0 10.7 1 ]8.3 04/12/02 1702 Lot 77 1260.0 11.3 117.5 04/12102 1703 Lot 78 ]260.0 10.1 1 ]7.9 04/12/02 ]704 Lot 96 1244.0 ] 3.3 113.1 04/12102 1705 Lot 98 1247.0 9.9 ] 18.0 04/12/02 1706 Lot 81 1260.0 10.0 116.3 PETRA GEOTECHNICAL, INC. TR 23143-6 J.N.241-01 . Sandcone 93 5 91* 8 87 8 9] 8 90 8 91 8 90 5 93 12 90 4 91 4 90 7 91 7 91 12 94 12 91 1] 90 II 86 11 90 9 92 9 92 12 91 1 I 94 6 93 6 92 12 91 12 93 9 93 9 94 12 93 5 93 12 92 9 93 9 94 9 94 6 92 5 93 5 92 5 91 5 91 5 90 6 91 5 90 5 JULY 2002 TABLE-II 9 6{J I I II I I I I I I I I I I I I I I I I I TABLE II Field Density Test Results .. TEst TEST... ....TEST ...........< ELEV..M. O.IS. T. U..R..E... ..D.E. N.SITY... C.O.M...P;...........S.O...l.L.>........ ...':.._'_''':'-'-',:-':::-:-:-:,'-','-' .:,:.:.:,:.:::::.>.:::_:,::::::::,:::::::::_:::::),,::,::",:::,,::;::,,':,:,,:;';:;':.;.;.;.;.:.:.;.;.,.;.;.:.'.'," ..;.c..........._,','.,,:.;.,,_'.-,,:,:.,:,:_;,,',:::,':,-'_;_:_:_'::';_'_;:;_;:;:;_ _,.c,_,_,:-:,_,:-:-:.:,_-:,_,:-:-_,:-:-:-_-:-:,_-:-:-_." .. _... __ ._.. .._ _. ._._.___...._...._._..._. .,_._'_'_'_ - .... _,"_"'__'" _.._ un ....', DATE> NO.. .......> LOCATION .... ..... ... ......... .......... (ft) ........ .(%) .... . ... . (pd)<<%)Tvi'Fi i 04/12/02 04/12/02 12/15/02 12/15/02 12/15/02 12/15/02 12/15/02 12/15/02 04/17/02 04/1 7/02 04/17 /02 04/17/02 04/17/02 04/17/02 04/18/02 04/18/02 04/18/02 04/18/02 04/1 8/02 04/18/02 04/18/02 04/18/02 04/18/02 04/18/02 04/1 8/02 04/18/02 04/19/02 04/19/02 04/19/02 04/19/02 04/19/02 04/19/02 04/18/02 04/18/02 04/18/02 04/18/02 04/18/02 04/15/02 04/15/02 04/15/02 04/15/02 04/15/02 1707 1708 1711 1712 1713 1714 1724 1725 1751 1752 1753 1754 1755 1756 1757 1758 1759 1760 1761 1762 1763 1764 1765 1766 1767 1768 1769 1770 1771 1772 1773 1774 1790 1791 1792 1793 1794 1801 1802 1803 1804 1805 Lot21 Crowne HiIl/Sta 43+20 Lot 90 Lots 91-92 Lot 93 Lot 94 Lot 80 Lot 78 Lot 54 Lot 64 Lot 66 Lot 68 Cinnamon Ln/Sta 10+90 Crowne HiIl/Sta 42+05 Lot 64 Crowne HiIl/Sta 41 +05 Lot 67 Cinnamon Ln/Sta 1 1+80 RT No. 1757 RT No. 1759 Lot 65 Lot 62 Lot 68 Lot 67 Lot21 Crowne Hill/Sta 38+20 Lot 65 Crowne Hill/Sta 42+25 Lot 64 Lot 117 Lot 50 Lot 52 Park site 123 Park site 123 Park site 123 Park site 123 RT No. 1793 Lot 80 Lot 78 Lot 81 Lot 95 Lot 97 PETRA GEOTECHNICAL, INC. J.N. 241-01 1285.0 1277.0 1235.0 1240.0 1246.0 1248.0 1257.0 1262.0 1270.0 1272.0 1272.0 1270.0 1274.0 1277.0 1271.0 1274.0 1274.0 1277.0 9.7 125.1 94 12 10.3 116.9 91 5 10.3 124.7 93 12 9.9 117.5 91 5 10.1 118.0 91 5 10.7 115.9 91 7 9.3 125.7 94 12 9.7 123.3 92 12 8.0 116.2 90 1 7.9 118.0 91 1 11.6 119.6 92 4 11.9 114.2 91 8 12.0 113.5 90 8 9.5 119.8 91 2 6.2 113.8 89 7 11.1 120.3 90 12 5.8 116.1 87 12 10.9 ]20.5 90 12 11.0 120.4 90 ]2 8.8 1] 5.7 91 7 9.4 114.1 91 8 13.0 113.9 90 8 11.9 116.4 90 5 12.4 117.7 91 5 8.3 126.0 94 11 7.7 123.9 93 11 86 122.3 92 12 13.4 117.2 91 9 14.4 112.1 90 10 13.4 113.5 91 10 8.9 111.6 92 14 11.0 1l0.3 90 14 11.4 115.8 91 9 10.5 1 ]6.8 91 9 8.7 115.9 91 9 7.0 111.2 87 9 8.9 115.2 90 9 10.] 116.9 91 5 10.7 117.5 91 5 11.3 118.7 91 4 9.9 117.1 91 5 14.0 114.1 91 6 JULY 2002 AIv TABLE-II 10 1272.0 1278.0 1277.0 1272.0 1275.0 1277.0 1274.0 1279.0 1277.0 1278.0 1271.0 1272.0 1269.0 1268.0 1264.0 1266.0 1260.0 1264.0 1260.0 1246.0 1248.0 TR 23143-6 * Sandcone I I I I I I I I I I I I I I I I I II i I TABLE II Field Density Test Results ". TEST .,....TEN..O.~...,...... ...... . <TEST ....., .... .... ....... ... ELEV. ...M.O.I(S%T)tJRE......... .......D..E.(NpCSl)IT.......Y..:. c......O(..~).~.............................'....T.S...un.p......I.LE.............,',............. > DATE .......... ....r.;OCATlON.......<...(ft)..... _ _ YO He. 04/15/02 1806 Lot 99 1250.0 14.1 113.7 91 6 04/15/02 1807 Lots 97-98 1250.0 9.9 114.7 90 7 04/16/02 1808 Lot 96 1249.0 10.7 115.0 91 7 04/16102 1809 Lot 98 1253.0 10.3 114.3 90 7 04/16/02 1810 Lot 93 1245.0 10.7 ] 189 91 4 04/16/02 1811 Lot 78 1263.0 9.9 119.1 91 4 04/16/02 1812 Lot 80 1260.0 9.1 117.5 91 5 04/16102 1813 Lot 77 1263.0 9.3 116.7 90 5 04/16/02 1814 Lot 77 1263.0 9.9 117.0 91 5 04/16/02 1815 Lot 67 1267.0 10.7 119.3 91 4 04/1 6/02 1816 Cinnamon Ln/Sta 9+90 1260.0 10.3 1177 91 5 04/16/02 1817 Lot 77 1265.0 10.9 117.5 9] 5 04/16/02 1818 Lot 79 1262.0 10.0 114.3 90 7 04/16/02 1819 Lot 99' 1255.0 9.9 115.0 91 7 04/1 6/02 1820 Lot 97 1253.0 10.1 118.0 91 5 04/1 6/02 1821 Lot 95 1249.0 9.7 117.9 91 5 04/1 6102 1822 Lot 97 1255.0 10.7 117.7 91 5 04/1 6102 1823 Lot 99 1258.0 8.9 125.1 94 12 04/16/02 1824 Lots 97-98 1258.0 12.9 114.0 91 6 04/19/02 1851 Park site 123 1265.0 12.2 1118 90 15 04/19/02 1852 Park site 123 1265.0 13.4 114.2 92 15 04/19/02 1853 Park site 123 1266.0 ]4.2 ] 13.6 92 IS 04/19/02 1854 Park site 123 1268.0 12.8 113.0 91 15 04/19/02 1856 Park site 123 1270.0 14.9 109.9 91 13 04/22102 1861 Crowne HiIl/Sta 42+50 1280.0 9.2 115.0 90 7 04/22/02 1862 Lot 59 1282.0 7.2 107.1 85 7 04/22/02 1863 RTNo.1862 10.0 115.3 91 7 04/22/02 1864 Lot 78 1266.0 8.7 116.2 91 3 04/22102 1865 Lot 80 1270.0 6.6 114.0 89 3 04/22102 1866 RT No. 1865 9.2 117.5 92 3 04/23/02 1867 Crowne HiIl/Sta 41 +00 1284.0 10.0 118.2 92 5 04/23102 1868 Lot 62 1286.0 9.8 117.3 91 5 04/23102 1869 Lot 58 ]287.0 9.2 117.0 91 5 04/23102 1870 Lot 66 1278.0 8.7 116.5 90 5 04/25102 1871 Lot 60 1287.0 10.5 117.2 91 17 04/25/02 1872 Lots 63-64 1287.0 11.2 119.4 92 17 04/26/02 1873 Lot 65 1280.0 15.1 106.8 91 16 04/26/02 1874 Lot 70 1282.0 16.2 108.2 92 16 04/26102 1875 Lot 77 1272.0 14.4 110.1 94 16 04/19/02 1876 Park site 123 1270.0 10.6 117.9 90 4 04/19/02 1877 Park site 123 1270.0 9.4 118.6 91 4 04/19/02 1878 Park site 123 1270.0 13.1 106.8 86 10 PETRA GEOTECHNICAL, INC. TR 23143-6 JULY 2002 ~ J.N.241-01 . Sandcone TABLE-II 11 I I I I I I I I I I I I I I I I I II II TABLE II Field Density Test Results . >DTEA.. .TSTE. .............. 'fEN.. .OST................... ..... .. ................... ....L. ....O.TC.. EASTT1.0.. .N.. ...... ..... ... ... ..... ... ELEV.... MOISTURE · DENSITy....... .... ..c....O(%M)p,~()Ir;; ...... ... .. ...... (n) ... .(%) .. . ........... . (pet) ..TYFE 04/19/02 04/19/02 04/19/02 04/19/02 04/19/02 04/19/02 04/19/02 04/19/02 04/19/02 04/22/02 04/22/02 04/22/02 04/22/02 04/16/02 04/16/02 04/16/02 04/23/02 04/23/02 04/26/02 04/26/02 04/27/02 04/29/02 04/29/02 04/30/02 04/30/02 04/30/02 04/30/02 04/30/02 04/30/02 04/30/02 04/30/02 05/02/02 05/01/02 05/01/02 05/01/02 05/01/02 05/01/02 05/02/02 05/02/02 05/02/02 05/02/02 05/02/02 1879 1893 1894 1895 1896 1897 1898 1899 1900 1935 1936 1937 1938 1955 1956 1957 2005 2006 2010 2011 2024 2083 2097 2127 2128 2137 2138 2139 2159 2160 2161 2171 2206 2208 2209 2210 2215 2222 2223 2224 2276 2277 RT No. 1878 Lot 69 Lot 66 Lot 64 Crowne Hill/Sta 42+50 Lot 62 Lot 77 Lot 70 Lot 77 Park site 123 Park site 123 Crowne Hill/Sta 50+70 Crowne Hill/Sta 50+71 Lot 99 Lot 95 Lot 98 Park site 123 Park site 123 RT No. 2005 Park site 123 Park site 123 Park site 123 Crowne Hil1/Sta 50+95 Park site 123 Lot 122 Park site 123 Park site 123 Park site 123 Lot 33 Park site 123 Park site 123 Lot 122 Crowne Hill/Sta 49+50 Park site 123 Park site 123 Crowne Hill/Sta 49+40 RT No. 2206 Park site 123 Park site 123 Lot 122 Park site 123 Park site 123 PETRA GEOTECHNICAL, INC. J.N.241-01 12.9 113.4 91 10 1278.0 9.2 124.7 93 11 1279.0 9.0 123.0 92 II 1279.0 8.5 125.1 94 11 1280.0 9.9 119.7 93 5 1284.0 10.2 118.7 92 5 1265.0 9.5 121.7 94 5 1279.0 12.0 1180 92 8 1277.0 11.8 117.6 91 8 12640 12.7 117.3 92 3 1265.0 16.1 112.2 90 10 1265.0 13.8 116.9 94 10 1264.0 15.0 110.2 90 14 1261.0 12.3 113.0 90 6 1255.0 13.7 114.1 91 6 1261.0 9.9 125.1 94 12 1265.0 16.3 112.0 89 5 1266.0 14.0 112.3 90 10 13.1 105.7 90 16 1266.0 11.9 ]07.5 92 lG 1267.0 13.3 I 17.4 92 7 1267.0 16.0 112.6 92 14 1270.0 11.0 115.0 91 7 1269.0 15.1 110.9 91 14 1270.0 13.2 118.3 92 5 1270.0 15.0 114.4 90 7 1270.0 9.1 112.9 91 10 1269.0 10.6 117.2 91 5 1275.0 10.0 123.7 93 11 1275.0 10.5 124.7 93 11 1275.0 10.0 122.3 92 11 1277.0 8.9 123.9 93 12 1273.0 ]5.7 115.0 89 5 1272.0 ]4.2 109.9 90 14 1271.0 ]1.9 116.5 92 7 1273.0 10.8 115.9 91 7 15.5 11G.2 90 5 1276.0 12.9 117.6 93* 7 1275.0 ]1.1 120.6 92 4 1276.0 15.4 109.8 90 14 1272.0 9.4 115.4 91 7 1273.0 6.6 120.2 93 2 TR 23143-6 JULY 2002 * Sandcone TABLE-II 12 At?J I I · . TEST TEST .......... ..... .<i1'EST .... ..... ...... ELEV . M. O. ..r(s01~.) .... E......... D. .....E(NpSC.t)ITY.... ...... ...C.. O..(~)P.. ; .S()~ l.riATE. .... .. ... NO'. ...... ..... ...... . LOCATION ....... ......... ... .... ........ ... (ft) .'./. _ 7. . . .. ....TVPE I I I I I I I I I I I I I I I I 05/02/02 05/02/02 05/02/02 05/02/02 05/02/02 05/02/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/03/02 05/04/02 05/04/02 05/04/02 05/04/02 05/04/02 05/04/02 05/04/02 05/04/02 05/04/02 05/04/02 05/04/02 05/04/02 05/04/02 05/04/02 05/04/02 2278 2287 2289 229] 2293 2294 2360 236] 2362 2542 2544 2545 2546 2550 2626 2627 2628 2629 2630 2631 2632 2633 2634 2635 2636 2637 2639 2640 264] 2642 2643 2644 2645 2646 2647 2648 2649 2650 2655 2656 2657 2658 TABLE II Field Density Test Results Lot 33 Lot 34 Park site 123 Park site 123 RT No. 2287 RT No. 2289 Park site 123 Park site 123 Park site] 23 Lot 75 Lot 79 Lot 77 Lot 81 Lot 81 Lot 66 Lot 69 Lot 50 Lot 65 Lot6] Lot 64 Lot 52 Lot 65 Lot 69 Pliance Wy/Sta 11 +50 Lot 80 Lot 70 Lot 80 Lot 77 Lot 64 Lot 60 Lot 51 Lot 55 Lot 8] Lot 64 Lot 60 Lot ]20 Crowne HiII/Sta 40+90 Lot 80 Lot 50 Lot 80 Lot 78 Lot 75 1274.0 1273.0 1275.0 1276.0 1277.0 1276.0 1276.0 1258.0 1263.0 1264.0 1258.0 1260.0 1262.0 1264.0 1262.0 1260.0 1260.0 ]2610 1262.0 1264.0 1266.0 1265.0 1263.0 1266.0 1265.0 1266.0 1263.0 1263.0 1265.0 ]264.0 1267.0 1265.0 1266.0 1262.0 1265.0 1267.0 1264.0 1266.0 ]266.0 1267.0 PETRA GEOTECHNICAL, INC. J.N.241-01 TR 23143-6 . Sandcone 9.2 120.2 90 12 8.9 ]08.9 88 ]4 7.3 1 ]5.6 89 4 6.2 114.3 90 7 10.9 110.7 91 14 8.8 118.9 91 4 9.6 122.1 94 4 110 121.4 91 12 9.5 124.5 93 12 119 114.0 92* 15 9.0 123.9 93 ]2 13.3 113.3 91 6 10.9 115.7 90 9 9.7 118.5 91 4 13.3 1 ]4.1 91 6 13.7 113.7 91 6 10.1 118.1 90 4 9.7 124.7 93 12 10.9 116.1 91 9 9.9 118.5 91 4 10.0 118.9 91 4 9.1 ]25.1 94 12 12.3 1 ]5.3 90 9 11.7 115.9 91 9 14.1 114.0 91 6 10.9 116.0 91 9 10.0 117.9 90 4 10.7 116.1 91 9 11.5 117.3 92 9 13.7 113.3 91 6 14.9 112.7 90 6 10.9 116.5 91 9 9.3 124.0 93 12 9.] 123.9 93* ]2 8.9 124.7 93* ]2 10.9 116.5 91 9 9.7 118.0 90 4 11.5 116.] 91 9 9.7 117.9 90 4 ]3.9 114.3 9]* 6 ]1.1 118.5 93* 9 9.3 124.3 93 ]2 JULY 2002 ~ TABLE-II 13 I I . ... . . ..TEST ..... .'fEsr. ......................... ...<L......OCTEAST.Tl. .0.. ..N....<EL(E)V.M. O....I(~TUR.)...En. E(Np.cSf)IT.Y... ...C.O..(!!).p;......................TS..YOpIL.E........................... ... DATE ........... NO;i ..... ..... ..... ...... ... ..... . ... ... ......... ...... ft. _/. _ _ 7<_ I I I I I I I I I I I I I I I I TABLE II Field Density Test Results 05/04/02 2659 Lot 70 ]268.0 05/06/02 2660 Lot 71 12690 05/06/02 266] CinnamonlSta ]2+70 ]266.0 05/06/02 2662 Lot 60 1267.0 05/06/02 2663 Lot 63 1267.0 05/06/02 2664 Lot 64 1267.0 05/06/02 2665 Lot 120 1267.0 05/06/02 2666 Lot 17 1269.0 05/06/02 2667 Crowne HiII/Sta 42+00 1274.0 05/06/02 2668 Lot 117 1268.0 05/06/02 2669 Lot 65 1267.0 05/06/02 2670 CinnamonlSta 10+40 1264.0 05/06/02 2671 Lot 81 1269.0 05/06/02 2672 Lot 79 1268.0 05/06102 2673 Lot 77 1269.0 05/06/02 2674 Lot 75 1268.0 05/06/02 2675 Lot 69 1270.0 05/09/02 2685 Lot 76 1275.0 05/09/02 2686 Lot 79 12770 05/09/02 2687 Lot 65 1275.0 05109/02 2691 Lot 50 1279.0 05/09/02 2692 Lot 53 1214.0 05/09/02 2693 Lot 52 1274.0 05/09/02 2694 Lot 51 1281.0 05/09/02 2697 Lot 50 1283.0 05/09/02 2698 Lots 53-54 12770 05/09/02 2699 Pliance Wy/Sta 10+50 1278.0 05/09/02 2700 Lot51 1281.0 05/07/02 2926 Lot 74 1271.0 05/07/02 2927 Lot 76 1273.0 05/07/02 2928 Lot 78 1271.0 05/07/02 2929 Lot 81 1272.0 05/07/02 2930 Lot 69 1273.0 05/07/02 2931 Lot 66 1270.0 05/07/02 2932 Lot 60 1270.0 05/07/02 2933 Lot 63 ]270.0 05/07/02 2934 Lot 64 1272.0 05/07/02 2935 Cinnamon LnlSta 10+00 1270.0 05/07/02 2936 Lot 54 1268.0 05/07/02 2937 PIiance Wy/St ]0+90 1270.0 05/1 0/02 2942 Lot 51 1271.0 05/1 0/02 2943 PIiance Wy/Sta 10+00 1275.0 PETRA GEOTECHNICAL, INC. TR 23143-6 J.N.241-01 * Sandcone 10.7 118.5 91 4 ]2.1 116.1 91 9 10.9 ] 18.1 90 4 12.7 114.1 91 6 11.3 116.0 91 9 11.7 1 ]6.9 91 9 13.1 113.9 91 6 9.9 118.9 91 4 10.7 118. I 90 4 11.5 ] 17.0 91 9 12.3 116.7 91 9 12.1 116.5 9] 9 9.9 124.1 93 12 9.7 123.7 93 "12 10.1 118.7 91 4 11.3 116.9 91 9 9.7 118.3 91 4 10.7 117.9 90 4 11.3 118.3 91 4 9.7 124.7 93 12 9.3 125.3 94 12 14.1 114.1 91 6 9.7 1 J 8.5 91 4 9.5 117.9 90 4 9.9 115.7 91 7 10.3 116.3 92 7 10.7 118.9 91 4 14.0 114.5 92 6 10.7 118.1 90 3 99 119.3 91 3 10.1 115.5 91 7 9.3 125.1 94 '1 9.7 118.7 91 3 13.3 114.0 91' 6 14.1 I I 3.1 90' 6 10.5 1 15.1 9]' 7 10.7 114.7 90' 7 9.9 118.3 91 3 10.3 117.9 90 3 10.7 ] 18.9 91 3 J2.7 113.0 90 6 9.7 118.5 91 3 JULY 2002 ~ TABLE-II 14 I I I I I I I I I I I I I I I I I I TABLE II Field Density Test Results 05/1 0/02 05/1 0/02 05/1 0/02 05/10/02 05/16/02 05/16/02 05/11/02 05/11/02 05/1 1/02 05/11/02 05/11/02 05/11/02 05/11/02 05/11/02 05/11/02 05/11/02 05/11/02 05/11/02 05/11/02 05113/02 05113/02 05/13/02 05113/02 05/13/02 05/13/02 05/13/02 05/13/02 05113/02 05/13/02 05/13/02 05/13/02 05/13/02 05113/02 05/13/02 05/13/02 05113/02 05/14/02 05/14/02 05/14/02 05/14/02 05/14/02 05/14/02 2947 2948 2949 2950 2952 2957 2978 2979 2981 2982 2983 2984 2985 2986 2987 2988 2989 2990 2991 2992 2993 2994 2995 2996 2997 3000 3002 3005 3006 3007 3008 3009 3010 3011 3012 3013 3014 3015 3016 3017 3018 3019 Lot 59 Lot 61 Lot 63 Cinnamon Ln/Sta 12+00 Lot 34 Lot 35 PIiance Wy/Sta II +40 Lot 50 Lot 80 Lot 78 Lot 70 Cinnamon Ln/Sta 12+00 Lot 61 Lot 64 Lot 65 Lot 69 Lot 79 Lot 71 Cinnamon Ln/Sta 12+20 Lot 60 RT No. 2990 RT No. 2991 Lot 69 Lot 80 Lot 53 Lot 50 Lot 39 Pliance Wy/Sta 10+00 Lot 53 Lot 55 Lot 55 Lot 54 Lots 5 I-52 Lot 100 Lot 102 Lot 102 Lot 76 Lot 76 Lot 110 Lot 109 Lot 108 Lot 109 1275.0 1273.0 1274.0 1275.0 1284.0 1283.0 1280.0 12850 1277.0 1274.0 1275.0 1278.0 1276.0 1276.0 1278.0 1277.0 1278.0 1273.0 1280.0 1275.0 1277.0 1279.0 1279.0 1283.0 1285.0 1285.0 1283.0 1272.0 1275.0 1280.0 1284.0 1262.0 1254.0 1257.0 1255.0 1257.0 1285.0 1273.0 1275.0 1275.0 PETRA GEOTECHNICAL, INC. J.N.241-01 TR 23143-6 * Sandcone 12.7 113.5 91 6 9.9 118.5 91 3 10.3 119.3 91 3 9.1 123.9 93 12 11.4 114.4 92 6 11.2 125.1 94 12 9.7 117.9 90 4 9.5 118.3 91 4 10.7 116.7 90 5 10.3 . 117.0 91 5 14.7 112.5 90 6 9.9 118.7 91 4 10.3 117.9 90* 4 10.0 117.7 91" 5 9.5 118.1 92" 5 13.3 113.1 90 6 9.1 118.0 91 5 8.7 117.7 88 12 93 1133 86 4 10.0 1179 91 5 9.5 121.7 91 12 9.1 117.5 90 4 12.7 113.3 91 6 9.9 117.7 91 5 9.3 124.3 93 12 10.0 117.1 91 5 10.3 117.7 90 4 13.3 114.5 92 6 10.7 119.0 92 5 10.3 123.9 93 12 9.9 118.7 92 5 9.7 117.7 90 4 10.0 118.3 92 5 9.1 124.1 93 12 9.7 117.9 91 5 9.9 117.9 90 4 9.7 118.3 91 4 10.3 118.9 91 4 10.3 118.3 92 5 12.7 114.1 91 6 11.1 118.5 92 5 13.5 113.7 91 6 JULY 2002 4fp TABLE-II 15 I I TEST TEST. .......... ......:.... ....... ...... ...L: ....O..TEC... .ASTTI...O..:.N.. .... :.. ...... .:..< ......EL(.~)V..<.::M. ::. O. :..I(~:U).. ..R.E.....:.DE(NpSC..l)IT....y...:.... ... (;OMP.~9IL< I DATE <NO; . .. ... . ...... .. .... . . .... ..........:................t .. _7<_ _ ~ :.....: {%) .....<"TVPE< I I I I I I I I I I I I I I I I TABLE II Field Density Test Results 05/14/02 05/14/02 05/14/02 05/14/02 05/14/02 05/14/02 05/14/02 05/14/02 05/15/02 05/15/02 05/15/02 05/15/02 05/15/02 05/15/02 05115/02 05/15/02 05/15/02 05/15/02 05/15/02 05/15/02 05/15/02 05/15/02 05/16/02 05116/02 05/16/02 05/16/02 05/16/02 05/1 6/02 05/16/02 05/16/02 05/16/02 05/17/02 05/17/02 05/17/02 05/17/02 05/1 7/02 05/17/02 05/17/02 05117/02 05/17/02 05/17/02 05117/02 3020 3021 3022 3023 3024 3025 3054 3055 3056 3057 3058 3059 3060 3061 3062 3063 3064 3065 3066 3067 3068 3069 3070 3074 3075 3077 3080 3081 3082 3083 3084 3085 3086 3087 3088 3089 3090 3091 3092 3093 3094 3095 Lot 114 Lot 102 Lot 101 Lot 100 Lot 102 Lot 102 Pliance Wy/Sta 10+00 Lot 53 Lot 55 Lot 51 Lot 81 Lot 80 Lot 77 Lot 70 Lot 68 Lot 66 Lot 59 Lot 61 Cinnamon Ln/Sta 11+12 Cinnamon Ln/Sta 10+00 Lot 65 Crowne HilIlSta 39+50 Lot 117 Pliance Wy/Sta 10+00 Lot 52 Lot 49 Lot 52 Lot 55 Plianee Wy/Sta 11 +50 Lot 81 Lot 80 Lot 59 Lot 61 Cinnamon Ln/Sta 11+12 Lot 63 Cinnamon Ln/Sta 10+00 Lot 68 Lot 70 Lot 80 Lot 79 Lots 77-78 Lot 70 PETRA GEOTECHNICAL, INC. J.N.241-01 1284.0 10.7 119.1 91 4 1260.0 9.1 125.0 94 12 1263.0 9.7 119.1 92 5 1265.0 9.3 118.7 92 5 1265.0 9.9 118.1 90 4 1266.0 13.9 113.9 91 6 1288.0 9.1 124.1 93 12 1286.0 14.7 ] 15.0 92 6 1275.0 9.9 119.0 91 4 1286.0 10.3 118.1 90* 4 1275.0 9.7 123.7 93* 12 1277.0 9.7 116.5 90 5 1274.0 10.1 116.7 90 5 1276.0 10.0 117.0 91 5 1274.0 14.0 113.7 91 6 1281.0 9.9 118.3 91 4 1277.0 9.3 118.7 91* 4 1279.0 9.1 117.7 90* 4 1277.0 8.7 125.0 94 12 1273.0 9.3 117.9 91 5 1282.0 9.5 118.0 91 5 1279.0 9.0 124.7 93 12 1276.0 12.7 114.0 91 6 1289.0 11.3 116.9 91 5 1288.0 10.1 118.9 91 4 1288.0 9.9 119.3 91 4 1289.0 13.3 113.5 91 6 1283.0 9.7 117.0 91 5 1285.0 9.9 119.0 91 4 1278.0 13.7 114.3 91 6 1282.0 13.1 114.1 91 6 1280.0 10.9 117.7 91 17 1279.0 11.7 118.0 91 17 1283.0 9.3 124.0 93 12 1279.0 10.1 117.9 91 5 1283.0 12.3 118.3 92 17 1279.0 9.7 118.7 91 4 12 77. 0 10.9 117.7 91 17 1283.0 11.5 118.3 92 17 1281.0 9.7 124.0 93 12 1277.0 99 118.3 91 4 1279.0 10.7 119.0 91 4 TR 23143-6 JULY 2002 ~'1 * Sandcone TABLE-II 16 I I TJ!)Sl\ /'I'ES1.1N......O> .......................................................................................................................................................................L.........OT.~.~..........~. T...liO../N................................ .I......II:..............J!)L(...~I....)V:;........................................M......................................O..........................l.....(?..m.......T.2)...rm................. ...............E................................................................D...........................E.................(Np........c..s.......l)~;r.............y.......................................r.................0....i.....%.....N... ~p.....................:....IILE i 11)1\111'/......., ... .. .... ..... .. . ... ... .......R~~.. ..... ...i/// ",._ . .. _ Co- \l/"",lC...I' I I I I I I I I I I I 1 I I I I TABLE II Field Density Test Results 05/17/02 3096 Cinnamon Ln/Sta 10+70 1283.0 05/17/02 3097 Lots 75-76 1278.0 05/17/02 3098 Lot 61 1281.0 05/17/02 3099 Lot 62 1280.0 05/18/02 3100 Lot 58 1279.0 05/18/02 3103 Lot 49 1290.0 05/18/02 3105 Pliance Wy/Sta 11+00 1291.0 05/18/02 3107 Lot 50 1287.0 05/18/02 3108 Lots 51-52 1290.0 05/18/02 3109 Lot 50 1290.0 05/18/02 3110 Lot 51 1289.0 05/18/02 3111 Lot 54 12870 05/18/02 3112 Lot55 1283.0 05/18/02 3113 Lot 64 1280.0 05/18/02 3114 Lot 64 1283.0 05/18/02 3115 Lot 65 1284.0 05/18/02 3116 Cinnamon Ln/Sta 10+00 1284.0 05/18/02 3117 Lot 81 1281.0 05/18/02 3118 Lot 81 1285.0 05/18/02 3119 Lot 79 1284.0 05/18/02 3120 Lot 75 1281.0 05/18/02 3121 RTNo.3109 OS/20/02 3122 Lot 58 1281.0 OS/20/02 3123 Lot 59 1283.0 OS/20/02 3124 Lot 61 1284.0 OS/20/02 3125 Lot 63 1283.0 OS/20/02 3153 Lot 49 1291.0 OS/20/02 3154 Lot 50 1295.0 OS/20/02 3155 Pliance LnlSta 10+70 1294.0 OS/20/02 3156 Lot 55 1286.0 OS/20/02 3157 Lot 53 1292.0 OS/20/02 3158 Lot 55 1289.0 OS/20/02 3159 Lot 52 1292.0 OS/20/02 3160 Lot 50 ]292.0 OS/20/02 3]61 Lot 48 ]295.0 OS/20/02 3]63 Lot 49 1294.0 OS/20/02 3164 Lot 50 1296.0 OS/20/02 3165 Lot 54 1290.0 OS/20/02 3166 Lot 55 1292.0 OS/20/02 3167 Lot 51 ]296.0 OS/20/02 3168 Lot 57 1280.0 OS/21/02 317] Lot 60 ]285.0 PETRA GEOTECHNICAL, INC. TR 23143-6 J.N.241-01 * Sandcone 10.9 118.7 92 10.9 117.9 91 9.1 124.3 93 13.5 114.1 91 9.7 119.1 91 11.5 117.3 91 10.9 117.0 91 10.9 117.7 91 10.1 1185 91 12.3 116.0 89 10.7 116.7 90 11.3 117.1 91 9.9 118.9 91 13.1 115.0 92 10.7 117.7 91 11.5 1 ]7.0 91 9.1 118.9 91 12.7 114.5 92 9.7 123.7 93 10.1 118.3 92 10.9 117.9 91 9.3 119.0 91 10.7 122.4 92 10.6 118.8 92 15.0 114.4 90 11.4 121.1 91 9.3 119.5 92 8.9 122.9 92 10.7 118.4 92 11.5 118.1 92 11.3 117.8 91 13.5 114.3 91 ]5.0 114.4 90 11.4 121.1 91 11.0 116.8 90 13.2 1 16.2 90 8.8 118.1 90 11.8 117.7 92 9.3 123.3 92 12.9 116.4 91 13.7 1] 8.4 93 10.9 124.1 93 17 17 12 6 4 17 17 17 4 17 17 17 4 6 17 17 4 6 12 17 17 4 11 17 7 12 4 12 17 17 17 6 7 12 17 17 4 9 12 9 9 12 JULY 2002 TABLE-II 17 ~ I I Field Density Test Results I I I I I I I I I I I I I I I I OS/21/02 OS/21/02 OS/21/02 OS/21102 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/20/02 OS/21/02 OS/21/02 OS/21102 OS/21102 OS/21/02 OS/21/02 OS/21/02 OS/21/02 OS/21102 OS/21/02 OS/21/02 OS/21/02 OS/2 I /02 OS/21102 OS/21102 OS/21/02 OS/21102 OS/21/02 OS/21102 OS/21/02 3172 3173 3174 3175 3176 3177 3194 3195 3201 3202 3203 3204 3205 3206 3207 3208 3209 3210 321 I 3212 3213 3214 3223 3251 3252 3253 3254 3255 3284 3285 3286 3287 3288 3289 3290 3291 3292 3293 3294 3295 3296 3297 Lot 63 Lot 65 Lot 68 Lot 71 Lot 34 Lot 34 Lot 36 Lot36 Lot 93 Lot 94 Lot 95 Lot 96 Lot 97 Lot 98 Lot 99 Paraguay Dr/Sta 26+75 Paraguay Dr/Sta 24+00 Paraguay Dr/Sta 22+50 Paraguay Dr/Sta 2 I +00 Lot 100 Lot 101 Lot 102 RT No. 3205 Lot 82 Lot 83 Lot 84 detention basin fs detention basin fs Lot 66 Lot 73 Lot 71 Lot 72 Lot 71 Lot 71 Lot 72 Lot 69 Lot 81 Lot 79 Lot 64 Crowne HiIllSta 41 +50 Crowne Hill/Sta 40+00 Crowne Hill/Sta 38+70 PETRA GEOTECHNICAL, INC. J.N. 241-01 TABLE " 1286.0 11.7 118.5 93 9 1287.0 12.0 120.8 90 12 1282.0 9.7 124.1 93 12 1276.0 10.3 123.3 92 12 1291.0 11.6 123.0 92 12 1290.0 11.1 121.2 91 12 1291.0 10.4 123.0 92 12 1292.0 96 122.1 91 12 FG 7.7 122.8 92 11 FG 7.9 122.0 91 11 FG 8.2 126.3 94 II FG 6.2 117.5 88 II FG 8. I 119.1 89" II FG 5.2 115.2 86 II FG 8.0 125.8 94 11 1240.0 8.3 121.9 91 11 1251.0 7.8 121.7 91 11 1256.0 9.0 115.9 90 3 1259.0 10.2 116.7 91 3 FG 9.2 122.9 92* 12 FG 96 120.7 90* 12 FG 7.2 123.2 92* 12 10.2 124.9 93 11 FG 10.2 118.2 90 20 FG 10.4 119.1 91 20 FG 9.4 117.9 90 20 1227.0 7.9 116.3 90 19 1240.0 6.8 l1G.8 90 19 1284.0 11.7 118.1 92 17 1283.0 12.3 117.3 91 17 1279.0 11.1 116.9 91 17 1284.0 10.9 117.5 91 17 1282.0 10.1 117.7 91 17 1282.0 9.3 123.1 92 12 1286.0 9.7 124.7 93 12 1284.0 10.0 124.5 93 12 1288.0 10.3 118.5 91 4 1287.0 11.7 116.9 91 17 1286.0 12.1 117.4 91 17 1280.0 11.9 117.9 91 17 1272.0 9.3 123.7 93 12 1270.0 10.0 122.9 92 12 TR 23143-6 JULY 2002 ~ * Sandcone TABLE-II 18 I I .......................~.s.........w.............. /......TJt.$'I1}i/ ./.......................}i...TJt~m............... .................................../..../I<l)jI<lVi ........1\4(jJS~~..~~..~~!~V.....................................C............................O.i......."'...~)p.........................<....................................................................................m...~........e..i........p...~..ll.....E...........:....................................................... I.PATE.NQ;!.iL()€ATI()N..)(ft)t%)/(P~f)i ,7< . ... .~.~. . OS/21/02 3298 Lot 67 I OS/21/02 3299 Cinnamon Ln/Sta 10+60 OS/21102 3300 Lots 65-64 OS/22102 332 I Lot 92 I OS/22102 3326 Lot 33 OS/22/02 3327 Lot 33 OS/22/02 3328 Lot 35 I OS/22/02 3329 RT No. 3328 OS/22/02 3340 Lot 32 I OS/22/02 3345 Lot 13 OS/22/02 3348 Lot 14 OS/22/02 3349 Lot 12 I OS/22/02 3350 Lot 13 OS/23/02 3369 Lot 49 OS/23/02 3370 Lot 48 I OS/23/02 3371 Lot 47 OS/23102 3372 Lot 46 OS/23102 3373 Lot 45 I OS/23/02 3374 Lot 46 OS/23/02 3375 Lot 47 OS/29/02 3394 Lot 20 I OS/29/02 3395 Lot 19 OS/29/02 3396 Lot 20 I OS/29/02 3397 Lot 21 OS/29102 3398 Lot 22 OS/29102 3399 Lot 19 I OS/29102 3400 Lot 20 OS/23/02 3417 RTNos. 3169 & 3204 OS/28/02 3438 Lot 91 I OS/28102 3439 Lot 92 OS/28102 3440 Lot 89 OS/28102 3441 Lot 81 finish slope I OS/29/02 3442 Lot 66 OS/29/02 3443 Lot 67 OS/29102 3444 Lot 68 I OS/29102 3445 Lot 69 OS/29102 3449 Lot 106 I OS/29/02 3450 Lot 107 OS/23102 3476 Lot 49 OS/23102 3477 Lot 55 I OS/23/02 3478 Lot 50 OS/23102 3479 Lot 54 PETRA GEOTECHNICAL, INC. J.N. 241-01 TABLE II Field Density Test Results I 1285.0 11.5 118.0 91 17 1286.0 9.9 1 ]8.7 91 4 1290.0 10.4 119.0 91 4 1241.0 9.7 115.7 91 7 1297.0 11.2 120.5 93 17 1298.0 10.9 118.9 92 17 1298.0 11.6 115.2 89 17 10.3 118.9 92 17 1302.0 9.8 118.9 90 2 1285.0 9.7 122.2 91 11 1285.0 9.8 120.1 90 11 1288.0 8.6 120.7 90 11 1288.0 9.2 120.9 90 11 1297.0 10.0 1 ]9.0 92 19 1298.0 9.0 119.5 92 4 1296.0 10.0 119.5 92 19 1296.0 8.5 123.7 93 12 1298.0 90 119.0 91 4 1298.0 10.0 118.7 92 19 1299.0 10.0 118.1 92 19 1286.0 10.4 118.9 91 4 1287.0 10.6 120.6 92 4 1288.0 9.5 119.5 91 4 1287.0 9.8 116.9 90 17 1288.0 9.4 116.5 90 17 1290.0 9.0 118.4 91 17 1292.0 11.6 118.0 91 17 8.6 122.6 92 II FG 7.4 120.6 90* 11 FG 6.8 124.1 93 II FG 6.4 123.0 92* 11 1287.0 8.3 118.3 92 19 FG 8.2 120.2 93 19 FG 9.2 118.9 92* 19 FG 9.8 120.2 92 20 FG 10.5 119.2 91* 20 FG 10.0 117.6 91 19 FG 10.3 118.2 92* 19 1299.0 10.7 119] 91 4 1295.0 11.3 118.0 91 17 1299.0 11.7 117.1 91 17 1295.0 9.] 124.7 93 12 TR 23143-6 JULY 2002 tP * Sandcone TABLE-II 19 I I TESTTE~ ... ..... .>l;EST < ........ ELEV. MOISTURE DENSITY. COMP SOIL ... DATE.. .... .... NO; .... .. ... ........ .... .. LOCATION. ... ........ . .. ... (ft) . .. ..(%) ... ... ........ (pcl). ...... ....... .. (%) . ~.TYP~ I I I I I I I I I I I I I I I I I TAB LE II Field Density Test Results OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/23/02 OS/24/02 OS/24/02 OS/24/02 OS/24/02 OS/24/02 OS/24/02 OS/24/02 OS/24/02 OS/28/02 OS/28/02 OS/28/02 OS/28/02 OS/28/02 OS/28/02 OS/28/02 OS/28/02 OS/28/02 OS/28/02 OS/28/02 OS/28/02 OS/29/02 3480 3481 3482 3483 3484 3485 3486 3487 3488 3489 3490 3491 3492 3493 3494 3495 3496 3497 3498 3499 3500 3501 3502 3503 3504 3505 3506 3507 3508 3530 3531 3532 3533 3534 3535 3536 3537 3538 3539 3540 3541 3575 Lot 51 Lot 52 Lots 53-54 Lot 56 Lot 57 Lot 58 Lot 59 Lot 62 Lot 70 Lot 68 Lot 65 Lot 60 Lot 62 Lot 64 Lot 65 Lot 69 Lot 67 Lot 101 Lot 58 Lot 62 Lot 66 Lot 14 Lot 15 Lot 16 Lot 10 Lot II Lot 12 Lot 10 Lot 14 Lot II Lot 16 Lot 17 Larry Lee Ln/Sta 12+45 Larry Lee Ln/Sta 12+30 Larry Lee Ln/Sta 11+75 RT No. 3530 RT No. 3531 Lot 12 Lot 15 Lot 18 Lot 15 Lot 9 PETRA GEOTECHNICAL, INC. J.N. 241-01 1299.0 1295.0 1298.0 1282.0 ] 283.0 ]282.0 1286.0 12870 1285.0 1287.0 1287.0 1288.0 1290.0 1293.0 1290.0 1287.0 1290.0 1266.0 ]285.0 1293.0 1292.0 1289.0 1294.0 1294.0 1287.0 ]286.0 1287.0 1290.0 1292.0 1292.0 1293.0 1294.0 1285.0 1283.0 1287.0 1293.0 1294.0 1293.0 1295.0 1285.0 TR 23143-6 * Sandcone 9.9 119.0 91 4 10.3 ] 19.5 92 4 11.4 117.5 91 17 9.7 1190 91 4 10.3 ] 18.5 91 4 11.0 ] 19.1 91 4 12.5 117.0 91 17 95 123.9 93 12 10.9 116.7 90 17 9.3 118.5 91 4 10.5 1170 91 17 10.3 ] 18.1 90 4 11.4 117.7 90 4 9.7 116.7 90 19 10.1 117.0 91 ]9 11.5 116.9 91 17 9.7 124.5 93 12 10.1 117.9 90 4 11.3 117.7 90 4 9.9 118.9 91 4 10.9 116.9 91 17 10.5 118.7 91 4 11.4 117.3 9] ]7 12.1 116.9 91 17 11.5 116.7 90 17 9.7 117.9 90 4 9.9 118.3 91 4 10.2 118.1 90 20 10.5 119.3 91 20 8.0 115.1 88 4 7.1 113.5 87 4 9.9 119.4 91 4 10.7 120.3 92 4 10.4 118.5 90 4 11.2 123.8 93 2 11.5 118.1 90 4 10.] 119.0 91 4 8.7 121.6 93 4 9.0 119.4 91 4 9.3 123.6 94 4 11.3 119.8 91 4 10.0 121.4 93 4 JULY 2002 5\ TABLE-II 20 I I . ....'....DTAETS. ..TE ., ..'f.ES'r, .< 'J.'E~J'>ELEV; MOISTUR..E... .. ..D. ..~(NpSCf)IT...~. ... C.O.(m.Mo.)P. . SOIL I ........'..NQ.u.>.>LOCATION .... .... ....... .....' .(ft) . .... (%) _ 7< ... ....TypE< I I I I I I I I I I I I I I I I OS/29/02 3585 Lot 33 OS/29/02 3586 Lot 36 OS/29/02 3601 Lot 106 OS/29/02 3602 Lot 107 OS/29/02 3603 Lot 108 OS/29/02 3604 Lot 109 OS/29/02 3605 Lot 56 OS/29/02 3606 Lot 57 OS/29/02 3607 Lot 58 OS/29/02 3608 Lot 59 OS/29/02 3609 Lot GO OS/29/02 3610 Lot 61 OS/29/02 361 I Lot 62 OS/29/02 3612 Lot 63 OS/29/02 3613 Lot 64 OS/29/02 3614 Lot 65 05/30/02 36 I 5 Lot 79 finish slope 05/30/02 3616 Lot 77 finish slope 05/30/02 3617 Lot 75 finish slope 05/30/02 3618 Lot 74 finish slope 05/30/02 3619 Lot 23 05/30/02 3620 Lot 114 05/30/02 3621 Lot 70 05/30/02 3622 Lot 71 05/30/02 3623 Lot 72 05/30/02 3624 Lot 73 05/30/02 3625 Cinnamon Ln/Sta 12+50 05/30/02 3677 Lot 32 05/30/02 3678 Lot 32 05/30/02 3701 Lot 9 05/30/02 3702 Lot 9 05/30/02 3703 Lot 9 05/30/02 3704 Lot 9 05/30/02 3705 Lot 10 05/30/02 3706 Lot 8 05/30/02 3708 Lot 2 05/30/02 3709 Lot 3 05/30/02 3710 Lot 4 05/30/02 371 I Lot 4 05/30/02 3712 Lot 2 05/31/02 3795 Lot 50 05/31/02 3796 Lot 51 PETRA GEOTECHNICAL, INC. J.N.241-01 TAB LE II Field Density Test Results 1299.0 11.4 121.0 92 20 1300.0 9.2 ] 17.6 91 19 FG 6.0 119.7 92 4 FG 5.7 118. ] 91 4 FG 7.3 113.7 90 8 FG 6.2 115.6 92 8 FG 8.7 116.0 91 9 FG 7.2 114.2 91 8 FG 6.3 113.4 90 8 FG 7.7 114.2 91 8 FG 9.5 119.5 92 4 FG 7.9 113.7 91 8 FG 7.7 130.0 97 II FG 90 120.2 92 4 FG 7.3 114.8 91 8 FG 8.8 ] 15.4 90 9 1275.0 G.I 115.0 91 8 1280.0 6.7 111.1 91 14 1285.0 6.4 115.4 92 8 1283.0 7.0 113.6 90 8 FG 5.1 113.6 90 8 FG 5.8 114.6 9] 8 FG 6.7 1172 92 9 FG 7.0 110.7 91 14 FG 7.0 112.1 92 14 FG 6.7 114.7 91 8 1284.0 10.4 ] 14.0 91 8 1299.0 13.0 120.1 92 20 1300.0 12.4 119.0 91 20 1287.0 10.1 119.7 91 20 1289.0 10.7 120.9 92 20 1291.0 10.4 121.2 92 20 1293.0 10.9 122.0 93 20 1294.0 8.4 121.4 92 20 1292.0 10.2 122.9 93 20 1279.0 9.9 123.5 94 20 1282.0 9.5 121.0 92 20 1284.0 12.8 115.2 92 20 ]286.0 13.7 112.6 90 20 ]282.0 11.7 117.2 94 20 FG 10.2 118.2 92* 19 FG 10.0 117.6 91 19 TR 23143-6 JULY 2002 6t-' * Sandcone TABLE-II 21 I I T$$J' ...................................................................................$E............N..............h..~........................................................................................... .........................................................................................................................L..............O...................~.............~..............;;."'.........~.......I.......O...................N...................... .(............t.............,.........I-EIIE;yi...........~~!~~PR-E...P~l'-l~l.1!"1C......G()MP;t...~g!Ji I..... ...jjA1!E . '" "'a..... II...(III?.............i...((t)(. I.........................i(%) ..i...iI..(i.........(p!!f) ..?.....?...I%)?.(ll~E..?? I I I I I I I I I I I I I I I I TABLE II Field Density Test Results 05/31/02 3797 Lot 52 FG 9.2 116.5 90' 19 05/31/02 3798 Lot53 FG 9.4 117.3 91 19 05/31/02 3799 Lot 54 FG 8.7 119.0 92' 19 05/3 1/02 3800 Lot 55 FG 9.1 118.7 92 19 05/3 1/02 3801 LotS FG 12.9 119.2 92* 17 05/31/02 3804 Lot 8 FG 11.7 1188 90 20 05/31/02 3805 Lot 9 FG 11.3 118.3 90* 20 05/31/02 3806 Lot 10 FG 9.9 119.2 91 20 05/31/02 3807 Lot 11 FG 8.8 122.2 93* 20 05/31/02 3808 Lot 12 FG 96 121.3 92 20 05/31/02 3809 Lot 13 FG 9.4 123.7 94* 20 05/31/02 3810 Lot 14 FG 11.1 123.3 94 20 05/31/02 3811 Lot 15 FG 10.9 121.2 92' 20 05/31/02 3812 Lot 16 FG 10.6 121.8 93 20 05/31/02 3814 Lot 3 1284.0 10.6 123.5 94 20 05/31/02 3815 Lot 4 1286.0 10.4 124.5 95 20 05/31/02 3816 Lot 2 1285.0 9.6 117.6 91 19 06/0 I /02 3888 Lot I 1275.0 12.0 116.7 90 17 06/01/02 3889 Lot 2 1286.0 11.4 119.1 92 17 06/0 I /02 3890 Lot 3 1286.0 11.8 119.5 92 17 06/01/02 3891 Lot I 1280.0 12.5 118.0 91 17 06/01/02 3892 Lot 2 1287.0 12.2 118.3 91 17 06/01/02 3893 Lot I 1284.0 12.7 119.7 92 17 06/0 I /02 3900 Lot I 1285.0 11.0 121.6 94 17 06/0 I /02 3904 Lot 81 1258.0 10.3 121.4 93 20 06/01/02 3905 Lot 79 1261.0 10.9 120.6 92 20 06/0 I /02 3906 Lot 77 1264.0 9.7 122.0 93 20 06/01102 3907 Lot 90 FG 9.2 125.2 94 12 06/05/02 3917 Lot 81 FG 8.8 112.5 90' 6 06/05/02 3918 Lot 80 FG 9.1 115.5 90* 3 06/05/02 3919 Lot 79 FG 8.6 113.2 91* 6 06/05/02 3920 Lot 78 FG 13.4 105.5 90' 16 06/05/02 . 3921 Lot 77 FG 13.6 105.5 90' 16 06/05/02 3922 Lot 76 FG 6.5 115.4 90* 3 06/04/02 3993 Lot 17 FG 9.3 119.3 92* 17 06/04/02 3994 Lot 18 FG 8.5 121.5 94* 17 06/04/02 3995 Lot 19 FG 9.0 120.0 93* 17 06/04/02 3996 . Lot 22 FG 8.9 119.1 92' 17 06/04/02 3997 Lot21 FG 7.3 119;.7 92* 17 06/04/02 3998 Lot 20 FG 8.1 122.0 94' 17 06/05/02 4047 Park site 123 1283.0 11.4 114.0 91 6 06/05/02 4048 Park site 123 1284.0 11.8 116.0 93 6 PETRA GEOTECHNICAL, INC. TR 23143-6 JULY 2002 -5~ J.N. 241-01 . Sandcone TABLE-II 22 I I I I I I I I I I I I I I I I 'I I I TABLE II Field Density Test Results TEST . . TEsT>>TIi:~T. .<>iELEV;. MO.ISTUREDENSITYCOMP;SOlL< . ...DA. ..T.E ..... ...... .N.O.. ..... .. ..... ......... ........ .......L. .OC.A.T. "ON... ...... ........i... ..... ........ .......... ... ...(ft)..("')( .1).. ..(%) ... .TVP E.. . ...... .. .. ...7........pc...................:. ...>i...... 06/05/02 4049 Lot 122 1285.0 14.0 114.5 92 6 06/05/02 4050 Lot 122 1286.0 14.1 113.0 90 6 06/04/02 4051 Lot 1 1286.0 11.8 116.5 90 17 06/04/02 4052 Lot3 1287.0 10.9 118.4 91 17 06/04/02 4053 Lot 2 1288.0 10.3 119.7 92 17 06/04/02 4054 Lot I 1289.0 10.7 1]8.9 92 ]7 06/04/02 4055 Lot 3 1290.0 9.4 117.0 90 17 06/04/02 4056 Lot 4 1291.0 10.8 117.3 90 17 06/05/02 4065 Lot 1 1290.0 10.2 122.3 94 17 06/05/02 4066 Lot 3 1291.0 9.6 119.1 92 17 06/1 0/02 4185 Lot 5 FO 7.9 116.3 90 17 06/1 0/02 4186 Lot 8 FO 10.1 117.0 91 17 06/1 0/02 4187 Lot9 FO 9.8 116.5 90 17 06/06/02 4256 Park site 123 1274.0 12.6 119.2 92 17 06/06/02 4257 Park site 123 1277.0 12.4 117.8 91 17 06/06/02 4258 Park site 123 1380.0 11.8 117.5 91 17 06/06/02 4262 Park site 123 1284.0 11.2 119.8 92 17 06/07/02 4269 Park site 123 1280.0 13.2 109.3 90 13 06/07/02 4270 Park site 123 1283.0 13.7 109.5 90 13 06/07/02 4271 Park site 123 1284.0 14.5 113.3 94 13 06/07/02 4272 Park site 123 1286.0 14.0 114.2 94 13 06/07/02 4276 Park site 123 1287.0 11.3 1193 92 17 06/07/02 4277 Park site 123 1288.0 9.7 117.8 91 17 06/07/02 4278 Park site 123 1289.0 9.2 116.7 90 17 06/07/02 4279 Park site 123 1290.0 10.4 118.9 92 17 06/07/02 4280 Crowne HilI/Sta 50+90 1291.0 10.2 ] 19.0 92 17 06/07/02 4281 Crowne HiII/Sta 51_30 1292.0 14.1 114.7 92 10 06/0 7/02 4282 Lot 122 1294.0 13.3 113.6 9] 10 06/07/02 4283 Lot 122 1295.0 12.8 114.1 92 10 06/1 0/02 4363 Park site 123 1284.0 9.4 120.2 93 17 06/1 0/02 4364 Park site ]23 1286.0 11.8 119.7 92 17 06/1 0/02 4365 Park site 123 1288.0 12.6 117.8 91 17 06/1 0/02 4366 Park site 123 183.0 13.0 116.7 90 17 06/1 0/02 4367 Park site] 23 1288.0 13.8 116.4 90 17 06/11/02 4431 Park site 123 1286.0 11.4 118.1 92 9 06/11/02 4434 Park site 123 1286.0 ]2.2 121.0 94 9 06/11/02 4435 Park site 123 1288.0 11.9 118.8 92 9 06/11/02 4436 Park site 123 1288.0 10.1 116.1 90 9 06/11/02 4437 Park site] 23 1292.0 11.2 120.0 93 9 06112/02 4443 Park site 123 1293.0 10.7 119.6 93 9 06/12/02 4444 Park site 123 1294.0 10.9 121.9 95 9 06/12/02 4445 Park site 123 1295.0 13.3 121.3 94 9 PETRA GEOTECHNICAL, INC. TR 23143-6 JULY 2002 ~A. J.N. 241-01 * Sandcone TABLE-II 23 I I ....'.~1......~:~11I~111. ....................~~:)I;...?lll{~;~:(~~ijl~......:~~~;II6I. I I I I I I I I I I I I I I I I I TABLE II Field Density Test Results 06/12/02 06/12/02 06/12/02 06/12/02 06/12/02 06/12/02 06/12/02 06/12/02 OG/12/02 06/12/02 06/12/02 06/12/02 06/12/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/13/02 06/18/02 06/18/02 06/18/02 06/13/02 06/13/02 4477 4478 4479 4480 4481 4482 4483 4491 4492 4493 4494 4495 4496 4497 4498 4499 4500 45.01 45.02 45.03 45.04 45.05. 45.08 45.09 45.10 451 I 4512 4651 465.2 465.3 465.4 465.5. 465.6 4657 465.8 465.9 4660 4785. 4786 4787 4689 4690 Lot 97 Lot 96 RT No. 4477 RT No. 4478 Lot 95. Lot 94 Lot 93 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 Park site 123 RT No. 465.3 RT No. 465.4 RT No. 465.5. RT No. 465.6 Park site 123 Park site 123 Park site 123 Crowne HilI/Sta 37+00 Crowne HilI/Sta 40+00 125.9.0 125.7.0 7.7 111.8 84 12 7.7 106.4 82 1 8.3 122.8 92 12 9.2 118.4 92 1 7.7 120.4 93 1 8.4 119.7 93 1 8.1 1180 91 1 13.8 1]5..9 90 17 12.9 116.7 90 17 12.1 119.6 91 20 11.4 119.1 91 20 ]2.7 120.1 92 20 9.2 119.9 92 20 12.0 115..8 92 8 11.2 114.7 91 8 10.8 116.9 93 8 11.7 114.0 90 8 ILl 116.0 90 9 12.3 119.0 93 9 12.4 120.8 94 9 10.6 122.0 95. 9 10.8 121.3 94 9 12.6 118.8 92 17 11.4 ]20.9 93 17 11.6 121.5. 94 17 13.0 ] 17.8 91 17 13.3 118.2 9] 17 13.3 114.1 92 15 14.7 115..7 93 15. 6.7 113.3 88 17 6.3 111.3 86 17 8.0 114.0 88 17 10.1 112.6 87 17 8.0 118.6 92 17 9.7 117.9 91 17 11.7 119.9 93 17 12.5. 122.0 95 17 88 120.6 90 12 8.2 123.1 92 12 86 121.4 91 12 8.8 122.2 92 21 8.4 121.5. 92 21 JULY 2002 ~ TABLE-II 24 125.4.0 1249.0 1245..0 1291.0 1292.0 1294.0 1295..0 1296.0 ]297.0 1298.0 1299.0 1297.0 ]298.0 ]293.0 1291.0 1294.0 1295.0 1293.0 1296.0 1294.0 1298.0 . ]300.0 1302.0 1298.0 1299.0 1301.0 1300.0 1300.0 1299.0 1299.0 1301.0 1300.0 1285.0 1289.0 PETRA GEOTECHNICAL, INC. J.N. 241-01 TR 23143-6 * Sandcone I I Field Density Test Results I I I I I I I I I I I I I I I I I TABLE /I 06/13/02 4691 Crowne HilIlSta 43+00 1292.0 8.0 121.2 91 21 06/13/02 4692 Cinnamon LnlSta 10+00 1293.0 11.2 116.8 91 19 06/13102 4693 Cinnamon LnlSta 13+00 1284.0 10.7 116.3 91 19 06113/02 4694 Paraguay Dr/Sta 14+00 1282.0 8.4 122.1 93 20 06/18102 4901 Lot I FG 6.1 126.2 94 22 06118/02 4902 Lot 2 FG 9.1 114.9 90 7 06118/02 4903 Lot 3 FG 7.5 121.5 90 22 06118/02 4904 Lot 4 FG 7.6 1189 92 1 06119/02 4976 Lot 32 FG 8.6 119.2 92 17 06119/02 4977 Lot 33 FG 8.2 119.2 92 17 06119102 4978 Lot 34 FG 8.9 120.1 93 17 06119102 4979 Lot 35 FG 9.2 120.1 93 17 06119/02 4980 Lot 36 FG 9.4 120.4 93 17 06/28/02 5651 Lot 38 FG 9.6 118.5 92 17 06/28102 5652 Lot 39 FG 9.2 116.8 90 17 06/28/02 5653 Lot 40 FG 8.7 117.9 91 17 PETRA GEOTECHNICAL, INC. J.N.241-01 TR 23143-6 * Sandcone JULY 2002 TABLE-II 25 ~ I 1/ Ii ~. I f II ~ ~ ~ Ii ~ ~ ~ ~ II ~ ~ >,.. r '. - REFERENCES Blake, T.F., 1998/1999, "UBCSEIS" Version 1.03, A Computer Program for the Estimation of Uniform Building Code Coefficients Using 3-D Fault Sources. Internationa] Conference of Building Officials, 1997, "Uniform Building Code," Volume 2, Structural Engineering Design Provisions, dated April 1997. Earth Research Associates, Inc., 1987, Evaluation of Faulting and Liquefaction Potential, Portion of Wolf Valley Project, Rancho California, County of Riverside, California, J.N. 298-87, dated November 20,1987. , 1988, Prehminary Soils Engineering and Engineering Geologic Investigation, Red Hawk Project, Rancho California Area, County of Riverside, California, IN. 298-87, dated February 2, 1988. Kennedy, M.P., 1977, Recency and Character of Faulting Along the Elsinore Fault Zone in Southern Riverside County, California, CDMG Special Report 131. Petra Geotechnical, Inc., 1989, Supplemental Soils Engineering and Engineering Geologic Invc.stigation, Portion of Redhawk Project, Vesting Tentative Tract Map Nos. 23064, 23065, 23066 and 23067, Rancho California, County of Riverside, CalifornIa, Volumes I and II, J.N. 298-87, dated May 8,1989. , 1999, Geotechnical Rep0l1 of Rough Grading, Phases 2 through 5 -- Tract 23143-2, Lots I and 2,7 through 16,23 through 56 and 64; Phases 2 through 8 -- Tract 23143-3, Lots 9 through 21 and 28 through 98; and Phases 2 through 8 -- Tract 23] 43-4, Lots 18 through 80, Crowne Hill, City of Temecula, Riverside County, CaliforniaJor Richmond American Homes, J.N. 444-98, dated September 7,1999. , 2001 a, Geotechnical Investigation of Tracts 23142 and 26941 and Preliminary Sewage-Disposal Feasibility Evaluation of Crowne Hill Estate Lots, Tract 26941, City of Temecula, Riverside County, California, J.N. 24101, dated June 4,2001. , 200]b, Geotechnical Review of Rough-Grading Plans for Tracts 23143-1,23143-6 through 23143-1 I, 23143-F, Crown Hill Park Site (Tract 23145-5) and Park Site 'A' (Lot 104 of Tract 23143-F), City of Temecula, Riverside County, California, J.N. 241-01, dated October 31, 2001. , 2001c, Settlement Characteristics of Fill Soils for Tract 23143, City of Temecu1a, Riverside County, California, J.N. 24t-01, dated December 10, 2001. ' ,2001d, Reliance Letter for Tracts 23]43-1, 23143-6 through 23143-11, 23143-F, Crowne Hill Park Site (Tract 23145-5) an d Park Site "A" (Lot 104 of Tract 23143-F), City of Temecula, Riverside County, CaliforniaJor Lowe Enterprises Residential Advisors, IN. 241-01, dated December 11,2001. ,2002a, Geotechnical Recommendations for Removal Depths, Park Site A within Tract 23143-F and Park Site F within Tract 23143-5, City of Temecula, Riverside County, California, J.N. 24] -0], dated January 24, 2002. ,2002b, Geotechnical Report of Rough Grading, Proposed Elementary School Site, Tract 23143-5, City of Temecula, Riverside County, California, J.N. 241-01, dated May 8, 2002. PETRA GEOTECHNICAL, INC J.N. 241-01 JULY 2002 :51 I I II I I I I I I I I I I I I I I I I I I REFERENCES (Continued) ,2002c, Supplemental Geotechnical Investigation, Lots 1,3 and 5, Tract 29641, Estate Lots, City ofTemecula, Riverside County, California, J.N. 219-02, dated May 14, 2002. , 2002d, Geotechnical Report of Rough Grading, Lots 1 through 105 and Slope Lot 106, Tract 23143-8, City ofTemecula, Riverside County, California, J.N. 241-01, dated June 21, 2002. PETRA GEOTECHNICAL, INC f.N. 241-01 JULY 2002 5e I I I I I I I I I I I I I I I I I I I APPENDIX A LABORATORY TEST CRITERIA Laboratorv Maximum Drv Densitv Maximum dry density and optimum moisture content were determined for selected samples of soil and bedrock materials in accordance with ASTM Test Method D1557. Pertinent test values are given on Plate A-I. Exoansion Potential Expansion index tests were performed on selected samples of soil and bedrock materials in accordance with ASTM Test Method D4829. Expansion potential classifications were determined from 1997 UBC Table 18-I-B on the basis of the expansion index values. Test results and expansion potentials are presented on Plates A-2 and A-3. Soil Chemistrv Chemical analyses were performed on selected samples of onsite soil to determine concentrations of soluble sulfate and chloride, as well as pH and resistivity. These tests were performed in accordance with California Test Method Nos. 417 (sulfate), 422 (chloride) and 643 (pH and resistivity). Test results are included on Plate A-4. PETRA GEOTECHNICAL, INC. J.N.241-01 JULY 2002 g.. I I I I I I I I I I I I I I I I I I I LABORATORY MAXIMUM DRY DENSITY' /ii Optiinum: f:::',}'ia~JIQ": Sample No. MUlY~' Moisture " Dry Density (%) (pel) I Medium brown Silty fine SAND 8.5 129.0 2 Light brown Silty SAND 9.0 132.0 3 Yellow-brown Silty fine to coarse SAND 9,0 128.0 4 Olivc brown Clayey tine to medium SAND 9.0 130.5 5 Very light brown to yellow Sandy SILT 9.0 129.0 6 Very light brown Silty fine SAND 12.0 125.0 7 Light brown Silty fine to coarse SAND 9.5 127.0 8 Very light brown Silty medium to coarse SAND with trace Clay 10.5 126.0 9 Brown Silty fine to medium SAND 10.5 ]28.0 10 Very light brown fine Sandy SILT 11.5 ]24.5 II Medinm dark brown Silty SAND with trace Clay 8.0 133.5 12 Medium brown Silty fine to coarse SAND with trace Clay 8.5 133.5 13 Light brown to very light brown Sandy SILT 13.5 120.5 14 Very light brown Silty very tine to fine SAND/Silty SAND/Sandy 11.5 122.0 SILT 15 Light brown to very light brown Silty CLA Y with trace fine 11.5 124.0 Gravel ]6 V cry light brown fine to medium SAND with trace coarse Sand 13.0 ]17.0 17 Olive brown Silty fine SAND/Sandy SILT 10.0 129.0 18 Yellowish light brown fine to medium SAND 10.5 123.0 19 Reddish brown Silty medium to coarse SAND 9.5 129.0 20 Reddish light brown Silty Clayey SAND 8.5 131.0 21 Medium brown Silty/Clayey fine to coarse SAND 8.5 132.5 (1) PER ASTM TEST METHOD Dt557 PETRA GEOTECHNICAL, INC. J.N.241-01 JULY 2002 Platf~ A-I f90 I I I I I I I I I I I I I I I I I I I EXPANSION INDEX TEST DATA Sairijlle .i". . ... Rejlresentative Lots Expansion2; Expansi,on~ .L6t .... .. Index Potential. 3 I through 5 9 Very Low 7 6 and 7 1 Very Low ]2 8 through 16 2 Very Low 19 17 through 22 2 Very Low 23 23 and 114 5 Very Low 29 24 through 31 0 Very Low 34 32 through 36 II Very Low 37 37 6 Very Low 39 38 through 40 38 Low 43 41 through 44 I Very Low 47 45 through 49 5 Very Low 52 50 through 55 17 Very Low 59 56 through 62 16 Very Low 65 63 through 67 4 Very Low 70 68 through 73 8 Very Low 74 74 aud 75 0 Very Low 78 76 through 81 30 Low 82 82 through 84 24 Low 90 89 through 92 9 Very Low 93 93 through 95 3 Very Low 99 96 through 99 3 Very Low 101 100 and 102 8 Very Low 104 103 through 104 8 Very Low 108 106 through] 10 10 Very Low 112 III through ] 13 2 Very Low PETRA GEOTECHNICAL, INC. J.N. 241-01 JULY 2002 Plate A-2 (P\ I I I I I I I I I I I I I I I I I I I EXPANSION INDEX TEST DATA (Continued) Park site west side 123 Park site east side 123 (2) PER ASTM TEST METHOD D4829 (3) PER 1997 UBe TABLE 18-I.B Expansion' Index 9 6 Expansion' Potential Very Low Very Low PETRA GEOTECHNICAL, INC J.N. 241-01 JULY 2002 Plate A-3 ~v I I SOIL CHEMISTRY I I I I I I I I I I I I I I I I I "., / " ~:i'."...li~.:PHff/\i ltesi~tivit~7 .... ~ ..:......., ,.,.,..,.,.".: '.(DDml</:. (ohrn-crn) 8 through 16 ND 6.8 2,000 concrete: negligible steel: -- 17 through 22 ND 63 7.2 6,000 concrete: negligible steel: mile 24 through 3] ND concrete: negligible steel: -- 32 through 36 ND 114 6.9 2,000 concrete: negligible steel: moderate 4] through 44 ND concrete: negligible steel: -- 56 through 62 ND 225 6.7 1,600 concrete: negligible steel: high 63 through 67 0.003 200 7.5 concrete: negligible steel: -- 68 through 73 ND 110 6.5 ],900 concrete: negligible steel: high 76 through 81 ND 7.5 2,000 concrete: negligible steel: moderate 82 through 84 -- 223 7.6 1,500 concrete: -- steel: high 96 through 99 0.003 315 7.4 1,700 concrete: negligible steel: high 106 through 110 0.0018 concrete: negligible steel: -- (4) PER CALIFORNIA TEST METHOD NO. 417 (5) PER CALIFORNIA TEST METHOD NO. 422 (6) PER CALIFORNIA TEST METHOD NO. 643 (7) PER CALIFORNIA TEST METHOD NO. 643 PETRA GEOTECHNICAL, INC. J.N. 241-01 JULY 2002 Plate A-4 (;b