HomeMy WebLinkAboutParcel Map 30798 Parcel 11 Hydrology & Drainage Study I I I I I I I I I I I I I I I I I I I w., 3o'Q8 HYDROLOGY STUDY Rancho Community Church Site Highway 79 South Temecula, California December 19, 2001 PURPOSE The purpose of this study is to determine peak nmoff values at certaiu points in the Rancho Community Church (RCC) property to support design of an onsite street and storm drain system. to determine the allowable nmoff into the existing storm drain in Hwy 79, and to determine the increase in nmoff due to development. DESCRIPTION OF THE WATERSHED The proposed development site is in the City of Temecula, on the north side ofHwy 79 South. approximately a mile and a half east of the 1-15 freeway. between Jedediah Smith Road and Margarita Road. The watershed extends northerly across De Portola Road to a ridge midway to Jedediah Smith Road. The watershed is approximately 141 acres in size, of typically irregular shape. The terrain is steep in the upper reaches to fairly flat downstream. Maximum relief is 191 feet, from elevation 1208 down to 1017:!:. The maximum flow length is 6700 feet. in a southerly direction to the northeast property corner of Ihe RCC site. westerly throngh the site to its southwest corner, then continuing westerly to a box culvert at Jedediah Smith Road & Highway 79. The RCC site is 53 acres. essentially rectangular, long in the east-west direction, with 4000 feet of frontage on Hwy 79. Soil types, read from Plate C-1.61 of the Riverside COUIlty Flood Control and Water Conservation District (RCFC& WCD) Hydrology Manual, range from D to B. The Type B soil was not actually labeled: it was deduced by eliminating the soil types represented in abutting areas, and by assuming it is not Type A. Present land use in the basin tributary to the RCC site from the north and east is single-family residential on 2 lIZ-acre lots. and is about half developed. There is also some vacant commercially zoned land to the east. The RCC site is presently vacant. Runoff flows through natural channels to De Portola Road, which is paved and has a 4" to 5" AC dike on both sides. then along the road to a graded earth channel to the RCC site. Flow through tlle site is overland through broad, shallow terrain. The south half of Constance Street is tabled to the Hwy 79 storm drain. according to Trans-Pacific Consultants. who prepared the related drainage study (which cannot be found). That area is 1.7 acres. Historically a portion of the flow drained from the northeast corner of the RCC property westerly along the northern portion of the site to an existing watercourse east of Jedediah Smith Road. That flow pattem was changed. some time in the past. before the church acquired the property. The existing condition is that all nmoff flows to the southwest corner of the RCC property, which pattern is maintained in tlle proposed development. All of the area is tabled into the box culvert at ledediall Smith Road & Highway 79 per the hydrology map of AD 159. METHODOLOGY The basin was analyzed by the Rational Method as prescribed in the current (1978) RCFC& WCD Hydrology Manual Calculations were perfonned using software developed by the writer. named "RMH" (for Rational Method Hydrology). version 6Ab. The analysis was based on both the 100-year and lO-year frequency stann models of the Hydrology Manual, for both the existing and proposed conditions. Streets and storm drains were assumed for the proposed cnndition of the HYDROLOGY STUDY, RCC Church Site 12/19/01 Page 1 "V I I I I I I I I I I I I I I I I I I I commercial offsite area to the east. For both proposed and existing conditions the residential area of 2 \I,-acre parcels on the north was assumed built out but with existing improvements. The design criteria are that the 10-year water surface not exceed top of curb. and that the 100-yr water surface remain I' below building finished floors. SUMMARY The developed-condition peak 100-yr flow rate (QIOO) entering the RCC at the northeast corner is 107 cubic feet per second (cfs). This is from an area of 42.3 acres (2.54 cfs/acre) at a time of concentration (T,) of 11.6 minutes. QIlkl entering the east side of the site is 26.1 cfs from 12.6 acres (2.07 cfslacre) at a tinte of concentration of 19.8 minutes. It is proposed to carry the entire flow unattenuated in cha1lIlels and pipes westerly and southerly along the north and west perimeter of the RCC site. Reducing the peak by utilizing the upper ball field as a flow-by detention basin was considered but discarded because of its effect on the usability of the field for sports at flooding occurrences. The channel is a trapezoidal earth channel witll 1.5: I side slopes. bottom widths of3 to 10 feet. A Manning's n of.03 was assumed to allow for vegetation growth. The developed QIOO to the southwest corner of the site is 308 cfs from 140 acres (2.19 cfslacre). at T,=2 U minutes. From that point the flow will be conveyed generally along the path of a watercourse that existed prior to the recently constrncted Highway 79 road improvements, to the inlet of a recently constructed box culvert. The inlet i,; at the northeast corner of Jedediah Smith Road and Hwy 79. That watercourse was replaced by a small concrete V-ditch. approximately 30" wide by 12" deep, in the parkway. That small ditch can contain only a very small portion of the flow. The great majority would flow in the street. tile parkway and a portion of La I 47. Tract 3752. It is proposed to convey tile flow in a uew earth channel across Lot 47. aloug the south edge of the lot. witllin the easement for future highway purposes offered for dedication by tile map of that tract. Therefore it IS recommended tl13t the City accept the dedication to provide for construction of the proposed channel Only the southerly portion of tile easement need be accepted. CONCLUSIONS The conceptual grading plan by TEC and tlus drainage sludy were developed togetller. Therefore tile stret:t and drainage system shown on the present plan, and the calculations and conclusions of this report, are in concert. The water surfaces of 10-year flows witllin tile streets do not exceed top of curb. Water surfaces of 100-year flows are below building finish floors. Development of the RCC site and tile offsite commercial area to tile east increase peak flows as tabulated below. lOO-year: Proposed Q ~ 308,9 Ratio ------ ~ 1.21 Existing Q 254.3 Proposed Q 194,2 ------ 1. 27 Existing Q ~ 152.9 lO-year: It must be recognized that not all of the increase is from tile RCC site within the Jinuts of tile CUP application: it includes the offsite commercial property east of the RCC property as well as tile commercial parcels within the RCC property . An equivalent of 1. 70 acres is piped into the existing stann draiu in Hwy 79. 11lis area is tile SOUtll half of Constance Street. which is tabled into the storm draiu. TIus equivalency is calculated as 1.70 acres times the average Qfr,"q""y iu cfslacre flowing to the onsite storm drain pipe to be connected to the existing catch basiu in Hwy 79. Q,o ~ 3.32 cfs. QlOO ~5.02 cfs. See records 40 and 41 of the hydrology calculations. HYDROLOGY STUDY. RCC Church S.e Page 2 :? 12/19/01 I I I I I I I I I I I I I I I I I I- I APPENDIX: WATERSHED DATA, CALCULATIONS and MAPS Soil map Rainfall i-d chart Hydrology printouts: schematics, calculations 100-yr proposed 1O-)T proposed IOO-)T existing 1O-)T existing Drainage maps (4) in pocket: Offsite proposed/existing condition Map # I Onsite proposed condition Map #2 Onsite existing condition Map #2 Map of historical drainage pattern at NE corner of RCC site HYDROLOGY STIJDY, RCC Church Site 10/27/00 Pag<: 3 A.. I I I I I I I I I I I I I I I I I I~ I o ~'_. .-~'0 ? f'I.r-- ~.~. .___ t)." ,.1 C,,,..r.,,~.~ ... - A BC BC A B I I I I I I I I I I I I I I I I I I I 0::: :::l o :r: 0::: W a.. CJ) w :r: u z I >- r- CJ) z w r- z -.J -.J ~ Z <( 0:: co ~x ..." I ;;-~ \ aa:, '" , x ~, ! '-, > ... -' -' . > > " z ... " o ... a ~ a oc 0... -> CloD__. ~.""DCl ........ .. I"lrl,",,","" .,......0....0- ""1Il,,,""N ........ .. I'IolNNNN c.,.....tIl~ c....,..""I'I ........ .. ----- O_fl,j"'. ----- Net-eN IfINOC.... ........ .. ......1"'11"1 fPl.....,.,M CoCli/l."" ........ .. NI\INNN O_NI'"'I. ----- ...OClCIIG o-Cl""II't... ........ .. NNN....N ",...0>110I.0 O<c.......o ........ .. ----- C_Nt'"l... ----- c. lClCoI'l_O' ...",...OIlEl ........ .. r"l"'l"lI"lN I ""....P'I....c I"'IN_C1O' ........ .. NNNN_ ~'O'" N f"'I... \.j---- cllllNOe> _O'c....o ........ .. t"lNNNN .0......-... ..Cl........"" ........ .. ...---- O_N,...... ......--- RCFC 8 WCD HYDROLOGY Iv]ANUAL ~ _ Z a o~ a _... ... >> ~ c" az ,,- ex a > oc " 0... z _> ... ~ " " 0 Z ... a ... a: 0" a: ..._10.1 ~ > ~ . Z -" Olll . -... ~ >~ c" aZ ,,- ex e " a e Z > " Z ... " o ... a ~ Z e~ -... >> c" az ,,- ox f'\ > " z ... " o ... a ~ ~~\ "Z. "a ...0 x~ ...- >-' c ,,, z O~ -... >> ." az ,,- e. . z e -' . a > " z ... " o ... a ~ % z e~ -... >> c" az ,,- e% a oc -... > ..._...00.. "''''110I00- ........ .. NNNN_ 01'1.0...11I0' oDC"'II'I_ ....OIl'l_Cl "''':'11I11'I''' f"IOICI\I_ N=...NO ........ .. ,..r"ll"ll"ll'") ltloC....cO< a oc 0... -> .000_0<0 ......II'IN_ ........ .. "'l"'HO'l,",,", a oC -... > ....,.,..."'.... 1'-1/1,",_0 ...... ... NNNNN 11'I.0"" cO' a oc 0'" -> 0_.....0- _"'110I0'.0 ........ .. 1fI.....,...1"I a oc -... > 1f\l'W.......O "'_C,",,1fI ........ .. ,",I"INNN II'I<I"'co- a oc 0... -> C... III O'Cl .0......"" ........ .. .....1"11"11"1 a o. -... > ......._Cl ClIt\I"lNCI ........ .. NNNNN li"l~"'CO' _.IIlN'" N_OOO' .... . NNAlN_ . "'IltI_... on..."" .... . -....-....- "'~...moo m.NNN "'.""N_ .... . """"""""f"l ""one_", N_OOO' .... . NNNN_ ""~P-IIlO' ---....- o NItl O'1"l .""N__ .... . NNNNN OItlOoClN oCllfl...... ... . ----- 1tl.op-mO' o-o-ON'" "'oCloClVl. .... . NNI,,,,,..N "'N.o_oCl cc,..P-<CI .... . ----- 1tl~p-eO' ON."'_ lI'I.....NN .... . NN"''''N Cf"loe.c 1I'l....... .... . ----- lfIoClP-Cf> Nt-lll'l"'ro'l O'CP-"""" .... . ----- ......e.... ~NN__ .... . ----- ON.""" NNNNN ~"'NO'" oe,.<CI. .... . ....NNI\IN ",O'ON.o CP-,..oClltl .... . ----- ON..cC NNNNN C1eONoCl OO'OoClP- .... . N____ o-I\IoClI\IP- """"NN_ ON..oCO NNNNN lI?.olll.oe t-lN_OD' .... . "'N^,I\I_ -....."''''. .oll'l.~t-l .... . ----- CN..cll? NNNNN "'.1l'l....0 _oo-eel .... . NN___ ",o-.oe. ro'lNl"W__ .... . ----- ON..,e NNNNN P-NC"O 6l'l1Il..... .... . ----- 0.0 f"l OCl _00000 .... . ---- ON."'CC I"It-lro'lro'l.... O'ONlI'lo- t-ll"lN_O ... . NNNN.... 0'."'.0 ....I"ll"lro'l .... . ----- ON"''''Cl t-ll""ll'"tt"'l"" 0...O'V1- ",<D1fl1ll1fl .... . ----- I"lO.o...-._ __000 ON'" "'Ill ""t"'It"'Il"'I"" O.C1N,.. o-IEI.......'O .... . ----- O".OP-~ NNN__ .. . ----- ON....olll f'O)~I"'l""f"'l I"l"'N",t-l ....oD.ollltfl 0.01"10.... _0000- .... . ---... C,......"'CI ,..,t-lf"'ll"tt-l "'0''''''''''' ....NN..._ .. . -, - - -- Il\Olfl_Cl "'O'ce.... .... . 0"'0 li"l 0 ....onon"" NO'CCCO OC",.ooCl .... . N____ ....e_.nO N__QO .... . ----- 01l'l01l\0 ...\1'1"'''' ,.. 0-'_"'0 .........,NN .... . ----- CNC-ro O'o-ClIOCl .... . 011'I011"'I0 ......"'1/'\.0 ,.. NN,..oo' .Q 11'I" l"'I 1"1\ . . . . ~ . I --'--1-. II 0.... I'" N~Cl! :~ ::I~J. [ .. ~ ~l~ 0-0.......00 ... 4'Plfl.dU .... . --.......-... "'0'''0.0 O'C1 110 C1'" .... . 0""'0....0 ..If'III"'I.o 1Il...0.... 000.. .... . "'''"'011I''' ........,..oCl,j) .... . ",,011I01/1 'O.......ClID "'''''-11'I- "'......l"tl"t .... . ----- II"'I_CII'IN o-O"ClClCl .... . lit 0 lI\O 11'I ""...r-ClC iI'I_......._ _ _,0 0 0 .... . ----- ......"'0'.... ............"""" . ... II'IQII'IClIfI .o,,"COll? ...0'11'I_.... N__...O .... . ---........ ......Clfl,.., com......,.. . . 1l'l0lflClII'I "'......Cll) li"l_"''''0 __000 .... . ---...- l"'lO..lI'I..... .........oCl.c .... . 1I'l01l\0*" ""....,.CCl o .. . . ... ~ o -' ~ o m ~ . . w ~ e -' ~ o o ~ . w ~ e -' ~ .' \ , 0' ~I i 11'I i I' ~ I 01 ~! o ~ '" . ... ~ o -' ~ STANDARD INTENSITY - DURATION CURVES DATA PLATE 0-4.1 (4 of 6) ~ I I I I I I I I I I I II I I I I I I I v I I I I I I I I I I I I I I I I I I I RMH RC ver 6.4b Nov. 2000 RATIONAL METHOD HYDROLOGY Riverside County (C) Copyright 1999 Jack P. Norris, Tel 909-676-5816, Fax 676-0016 SiN 0 Jack P. Norris, RCE, 33055 Vino Way, Temecula CA 92591 909-676-5816 File: RCC07-C.DAT 50 records Runtime: 10-26-2000 09:48 Page 1 By JPN Work code 8 Job# RCC +----------------------------------------------.-------------------------------+ Rancho Community Church site, Hwy 79S, Temecula Proposed condition, Config #7 100-yr ~ 10-1' +-----------------------------------------------------------------------------+ Schematic diagram. Legend: Node number/ Link text: record number + process name Streams: 2 3 4 5 6 '7 ------- ------- ------- ------- ------- ------- ------- 101 201 lInit 4Init 102 202 2Chan 5Chan 103 203 3Stre 6Stre 104 <_no' 8Stre 105 9Stre 111 <--- <-------' 16Chan J.12 c--- <------ <-------, 21Chan 403 23Chan 404 c--- <------ <------ <-------'. 32Pipe 405 34Pipe 40'7 36Pipe 409 37Chan 121 c--- <------ <------ <------ c------ <----_-,-' 46Chan 122 4SChan 123 49Chan 124 50Chan 190 I <;'\ C~<U\ ",J..3.1i.<.~ ('2.. '201)\ \'1 I 301 llInit 302 12Chan 303 13Stre 504 17Init 505 ISStre 50S 19Chan 510 25Init 511 26Stre 512 27Stre 513 2SStre 513 .5 29Pipe 514 30Pipe 516.2 516.1 38Init ~41User 516.3 j517 39Stre '12Stre 515 518 40Stre 43Stre 516 ~ 520 44Vall override. ~ I 1,- ,I a I I I I I I I I I I I I I I I I RMH RC ver 6.4b Nov. 2000 RATIONAL METHOD HYDROLOGY Riverside County (C) Copyright 1999 Jack P. Norris, Tel 909-676-5816, Fax 676-0016 SiN 0 Jack P. Norris, RCE, 33055 Vino Way, Temecula CA 92591 909-676-5816 File: RCC07-C.DAT 50 records Runtime: 10-26-2000 09:25 Page 1 By JPN Work code 8 Job# RCC +--------------------------------------------------_..-------------------------+ Rancho Community Church site, Hwy 79S, Temecula Proposed condition, Config #7 100-yr +---------------------------------------------------_.-------------------------+ Frequency: 100 - yr. I =12.357 TcA-.550 Min. pipe size: 18" Legend: (i)=input (c)=computed 100-yr 1-hr D= 1.3" (i), -Loglog slope of I-D curve = .55 (i) Initial subarea Tc by Kirpich formula: Tc = k (DiscA3 I deltaH)A.2 ***************************************************'t*************************** Record 1 Subarea 1 Node 101 to node Elev 1208.50 to elev Subarea: .64 acre Development type 4 = Stream 1 Process 1: Initial subarea 102 1158.00 delta H = 50.50' Lengch= 210' Soil: D, RI= 75 0.4 dwelling lacre ai=.l Slope<= .24048 -----------------------------------------------------.-------------.------------- k = .487 Tc = 5,50 min. I = 4.840"/hr A(total) = 0.640 ac Fp = 0.407"/hr C=.1332 Q(subarea) = 2.58 cfs Q(total) = 2,58 cfs -- - - - - - -- -- - - - - -- -- - - - - -- - - - - - -- - - - Summary - - -- -- -. .. - - - - - - - - - - - -- .. - -- - -- - - -- - - Stream 1 to node 102 Length= 210 ft. 4.03 cfs/acre avg. A(tot)= 0.64 acres Tc<= 5.50 min Q.- .. 2.58 cfs ===================================================~==============:;============ Record 2 Subarea 2 Stream 1 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 102 to node 103 Elev 1158.00 to elev 1119,00 delta H = 39.00' Length= 320' Slope.. .12188 Subarea: 2.2 acres Soil: D, RI= 75 Development type 4 = 0,4 dwelling lacre ai=.l V avg = 7.90'/sec for avg Q of 6.71 cfs ------------------------------------------------------------------.------------- Tc = 5.50 + 0.67 = 6.17 min. I = 4,541"/hr A(total) = 2.840 ac Fp = O.405"/hr C=.1l28 Q(subarea) = 8.27 cfs Q(total) = 10.85 cfs - - -- - -- - -- -- -- .. - - - -- -- - - - - - - - - .. - - - - Summary - -- - -- - .. .. - - - - - - .. - - - - -- .- -- - -- - - -- - -- Stream 1 to node 103 Length= 530 ft. 3.82 cfs/acre avg. A(tot)= 2.84 acres Tc.. 6.17 min Q= 10,85 cfs ===================================================::==============:============= <\ I 1--, I a I I I I I I I I I I I I I I I File RCC07-C.DAT Runtime 10-26-2000 09:25 Job# RCC Page 2 Record 3 Subarea 3 Stream 1 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach, Remark: Verde Drive Node 103 to node Elev 1119.00 to elev Subarea: 1.22 acres Development type 4 = Street template 0 CF = 6" Batter= Xfall = .02 'I' Tt= 0.97 min. based on Qavg= 6.37 Davg=0.19' Aavg= 1.85 s,f. Vavg= At end of reach: D = 0.20' (0.203) Flow area = 2.07 s,f. Flooded Flow exceeds crown. 104 1077.00 delta H = 42.00' Soil: B, RI= 56 0.4 dwelling /acre ai=.l Half-width = 10' n = .015 .25 h/v Gutter width = 0" Length= 400' Slope.. .10500 2 sides Hike = 0.0" Lip = .00" cfs on each side of street. 6.89'/sec V = 7.05'/sec. D*V = 1.43 width = 19.85' Sf = ,10527 ___________________________________________________0____________________________ Tc = 6,17 + 0,97 = 7.14 min. I = 4.192"/hr A(total) = 4.060 ac Fp = 0.838"/hr C=.738 Q(subarea) = 3.77 cfs Q(total) = 14.62 cfs _ _ _ __ __ _ _ .. -- .. - - - -- -- - - - -- - - - - -- - -- - Summary -- - -- - - .. - - - - - - -- -- - -- -- - -- - - - - - - -- - Stream 1 to node 104 Length= 930 ft. 3.60 cfs/acre avg. A(tot)= 4.06 acres Tc- 7.14 min Q= 14.62 cfs This stream is designated for confluence with 1 other by record 6 ===================================================~===============:============ ***************************************************x**************~.* New Stream Record 4 Subarea 4 Node 201 to node Elev 1201.00 to elev Subarea: 1.84 acres Development type 4 = Stream 2 Process 1: Initial subarea 202 1123..00 delta H = 78.00' Length= 300' Soil: D, RI= 75 0.4 dwelling /acre ai=.l Slope.. ,26000 ---------------------------------------------------.----------------------------- k = .487 Tc = 6.24 min. I = 4.513"/hr A(total) = 1.840 ac Fp = O.405"/hr C=.El27 Q(subarea) = 6.87 cfs Q(total) = 6.87 cfs .. - -- -- - -- - .. .. -- - --" - - - -- -" - - -- - -- .... - Summary -.. - - - - .. ... - - - .. - -- - .. - -- - .. - --" -- - .. - - - .. Stream 2 to node 202 Length= 300 ft. 3.73 cfs/acre avg. A(tot)= 1.84 acres Tc= 6,24 min ===================================================::===============:============ Q., -' 6.87 cfs \0 I I ,I ,. '. . I I I I I I I I I I I I I- I File RCC07-C.DAT Runtime 10-26-2000 09:25 Job# RCC Page 3 Record 5 Subarea 5 Stream 2 Process 7: Channel flow - Natural Valley Subarea Q enters stream unifonnly distributed a.long reach. Node 202 to node 203 Elev 1123,00 to elev 1079.00 delta H = 44.00' Len'l't.h= 520' Slope= .08462 Subarea: 3.86 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling lacre ai=.l V avg = 7.74'/sec for avg Q of 12.72 cfs ----------------------------------------------------.--------------------------- Tc = 6.24 + 1.12 = 7.36 min. I = 4.121"/hr A(total) = 5.700 ac Fp = 0.835"/hr C=,736 Q(subarea) = 11.71 cfs Q(total) = 18.58 cfs _ __ _ __ _ _ __ __ __ __ _ _ __ .. - - -- - - .. - -- .. - - - Summary - -- -- - ... .. .. - -- .. -- - .. - - -- -- - - .. - -- - - - .. -- Stream 2 to node 203 Length= 820 ft. 3.26 cfs/acre avg. A(tot)= 5.70 acres Tc= 7.36 min Q= 18,58 cfs -------------------------------------------------------------------------------- ----------------------------------------------------.--------------------------- Record 6 Subarea 6 Stream 2 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach, Node 203 to node 104 Elev 1079.00 to elev 1077,00 delta H = 2.00' Length= 100' Slope= .02000 Subarea: .72 acre Soil: B, RI= 56 Development type 4 = 0.4 dwelling lacre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width = Xfall = .02 'I' 8' pkwy @ .02 'I' Tt= 0.37 min. based on Qavg= 19.63 cfs on one side of street. Davg=0.41' Aavg= 4.38 s.f. Vavg= 4.48' Isec At end of reach: D = 0.42' (0.420) V = 4,47' Isec. D*V = 1.88 Sf = ,02001 Flow area = 4.63 s.f. Street flooded width one side = 21.14' Flow exceeds top of curb. Parkway flow: 4.31' wide x 0.09' deep, Q= 0.8 ai= ,1 .015 1 side 0" Hike" 0.0" Lip .0011 ---------------------------------------------------..--------------------------- Tc = 7.36 + 0,37 = 7.74 min. I = 4,Oll"/hr A(total) = 6,420 ac Fp = O.831"/hr C=.732 Q(subarea) = 2.11 cfs Q(total) = 20.69 cfs .... _ _ __ _ __ _ _ __ _ __ __ _ _ _ _ _ __ __ __ _ __ __ _ Summary _ __ __ - -.. .. - -- - -- - .. - - .. - u - -- .. -- .. - ---- Stream 2 to node 104 Length= 920 ft. 3.22 cfs/acre avg. A(tot)= 6,42 acres Tc= 7,74 min Q= 20.69 cfs This stream is designated for confluence with 1 other by record 3 ===================================================================:============ \\ I I .1 I I I I I I, I I I I I I I I 1-- I File RCC07-C,DAT Runtime 10-26-2000 09:25 Job# RCC Page 4 Record 7 Confluencing 2 streams at node 104 Process 9 Confluence Constituent streams: Stream 1: Q= 14.62 Stream 2: Q= 20.69* Tc= Tc= 7.14 7.74 1= 4.192 1= 4.011 @ Tc Stream 1 + Stream 2 = Confluenced 7.74 Q= Ratio= 13.99 + 12/Il 20,69 = 34.68 cfs Qpeak = 34.68 cfs at Tc = 7.74 minutes Confluenced streams will be designated as stream # 1 to continue downstream. ___________________________________ Summary -------..--------------.------------ Stream 1 at node 104 Length= 930 ft, 3,31 cfs/acre avg. (c) A(tot)= 10.48 acres Tc= 7.74 min Q_. -. 34.68 cfs ----------------------------------------------------.---------------.------------ ----------------------------------------------------.---------------.------------ Record 8 Subarea 7 Stream 1 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Remark: De Portola Rd Node 104 to node 105 Elev 1077.00 to elev 1075.90 delta H = 1.10' Length= 70' Slope= .01571 Subarea: 3.14 acres Soil: B, R1= 56 Development type 4 0.4 dwelling /acre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width = Xfall = .02 'I' Flow designated on 1 side but crown exceeded. Street flowing full. Tt based on 39.19 cfs avg in full street. At end of reach: D = 0.42' (0.421) V = 4.87'/sec. D*V = 2,05 Sf' = .01962 Flow area = 4.48 s.f. Flooded width one side = 21,28' Flow exceeds top of curb. Plane of curb face extended up, pkwy ponded. ai= .1 .015 1 side 0" Hike = 0,0" Lip = .00" ---------------------------------------------------..---------------.------------ Tc = 7.74 + 0.27 = 8.00 min. I = 3.937"/hr A(total) = 13,620 ac A(contrib) = 13,620 ac Fp = 0.827"/hr C=.730 Q(subarea) = 9.02 cfs Q(total) = 43.70 cfs - -- - -- -- -- - - -- - - - - -- -- - - -- -- -- - -.. -- Summary - - -- -- - .. - - - - .. - - - -- - - - -- - -- - - - - -- - - - Stream 1 to node 105 Length= 1000 ft. 3.21 cfs/acre avg. (c) A.(tot)= 13.62 acres Tc= 8.00 min Q~' 43.70 cfs ==================================================================::============ \1,; . I '. '. I I I I I I I I I I I I I I I , File RCC07-C.DAT Runtime 10-26-2000 09:25 Job# RCC Page 5 Record 9 Subarea 8 Stream 1 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Remark: to catch basin @ villa del Sur Node 105 to node 111 Elev 1075.90 to elev 1055,50 delta H = 20.40' Length= 800' Slope= ,02550 Subarea: 7.72 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling lacre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width Xfall = .02 'I' 8' pkwy @ .02 'I' Flow designated on 1 side but crown exceeded. Street flowing full. Tt based on 52.94 cfs avg in full street. At end of reach: D = 0.44' (0.438) V = 6.06'/sec. D*V = 2,66 Sf = .03515 Flow area = 5.13 s.f. Street flooded width = 44.00' Flow exceeds top of curb, Parkway flow: 5.25' "ide x 0.11' deep, Q= 3.3 ai= .1 ,015 1 side 0" Hike., 0.0" Lip = .0011 __________________________________________________h____________________________ Tc = 8,00 + 2,57 = 10,57 min. I = 3,379"/hr A{total) = 21.340 ac A{contrib) = 21.340 ac Fp = 0.800"/hr C=.708 Q{subarea) = 18.47 cfs Q(total) = 62.18 cfs ----------------------------------- Summary ------..---------------------------- Stream 1 to node 111 Length= 1800 ft. 2.91 cfs/acre avg, Ic) A{tot)= 21.34 acres Tc= 10.57 min Q= 62.18 cfs This stream is designated for confluence with lather by record 13 ~;~~:=;============================================:============================ Process 8: Add a subarea at last node Record 10 Subarea 9 Stream 1 Remark: Flow down Villa del Sur At node 111 Subarea: 6,7 acres Soil: D, RI= Development type 4 = 0,4 dwelling 75 lacre ai= ,1 ------------------------------------------------------------------------------- Tc = 10,57 min. I = 3,379"/hr A(total) = 28.040 ac A{contrib) = 28.040 ac Fp = 0.393"/hr C=,806 Q(subarea) = 18,24 cfs Q(total) = 80.42 cfs ----------------------------------- Summary ----------------------------------- Stream 1 to node 111 Length= 1800 ft. 2,87 cfs:/acre avg. (c) A(tot)= 28.04 acres Tc= 10.57 min Q= 80.42 cfs ===================================================,============================ \~ I I I I I I I I I I I I I I I I I I I File RCC07-C.DAT Runtime 10-26-2000 09:25 Job# RCC Page 6 ******************************************************************** New Stream Record 11 Subarea 10 Stream 3 Process 1: Initial subarea Node 301 to node 302 Elev 1121.00 to elev 1068.00 delta H = 53.00' Length= 620' Slope= ,08548 Subarea: 1,35 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre ai=.l ------------------------------------------------------------------------------- k = .487 Tc = 10.43 min. I = 3.404"/hr A(total) = 1.350 ac Fp = 0.801"/hr C=.709 Q(subarea) = 3.26 cfs Q(total) = 3.26 cfs ___________________________________ Summary ---------..------------------------- Stream 3 to node 302 Length= 620 ft. 2.41 cfs/acre avg. A(tot)= 1.35 acres Tc= 10.43 min Q= 3.26 cfs -------------------------------------------------------------------.------------ -------------------------------------------------------------------.------------ Record 12 Subarea 11 Stream 3 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 302 to node 303 Elev 1068.00 to elev 1060.00 delta H = 8.00' Length= 230' Slope= ,03478 Subarea: .92 acre Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre ai= ,1 v avg = 3.80'/sec for avg Q of 4.30 cfs -----------------------------------------------------.------------------------- Tc = 10.43 + 1.01 = 11,43 min. I = 3,235"/hr A(total) = 2.270 ac Fp = O,791"/hr C=.702 Q(subarea) = 2.09 cfs Q(total) = !;,35 cfs _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - - - - - - - - - - - - - - Summary - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - Stream 3 to node 303 Length= 850 ft. 2,36 cfs/acre avg. A(tot)= 2.27 acres Tc= 11.43 min Q= 5,35 cfs -----------------------------------------------------.-------------------------- ---------------------------------------------------.---------------------------- \b... I I I I I I I I I I I I I I I I I I I File RCC07-C.DAT Runtime 10-26-2000 09:25 Job# RCC Page 7 ,~ :. Record 13 Subarea 12 Stream 3 Process 3: Street fl.ow Subarea Q enters stream unifo~ly distributed along reach. Remark: along De Porto1a to catch basin @ villa del Sur Node 303 to node 111 Elev 1060.00 to elev 1055.50 delta H = 4,50' Lengch= 540' Slope= .00833 Subarea: 6.82 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width = Xfall = .02 '/' Flow designated on 1 side but crown exceeded. 3.08 cfs spills to other side. Q on 1 side= 15.66 cfs for Tt of 2.77 min. Aavg=4.81 Davg=0.44' Vavg= 3.25 !'.t end of reach: D = 0.44' (0.437) V = 3.25' /sec. D*V = 1.42 Sf = ,01179 Flow area = 4.S1 s.f. Flooded width one side = 22.05' Flow exceeds top of curb. Plane of curb face extended up, pkwy por,ded, ai= .1 .015 1 side 0" Hike = 0,0" Lip = .00" -----------------------------------------------------.-------------------------- Tc = 11.43 + 2.77 = 14,20 min. I = 2,S72"/hr A(total) = 9.090 ac Fp = O.76S"/hr C=,6E3 Q(subarea) = 13.39 cfs Q(total) = l8.73 cfs __ _ _ _ - - -- -- - - - -- - - -- -- - - -- - - - - - - - - - Surrunary -- - -- - -.... - - - -- - - - - - - -- - - - -- -- -- - -- - Stream 3 to node 111 Length= 1390 ft. 2.06 cfs/acre avg. A(tot)= 9.09 acres Tc= 14.20 min Q= lS,73 cfs This stream is designated for confluence with 1 other by record 9 :;;;=========================================================================== Record 14 Remark: catch basin @ De Portola & Confluencing 2 streams at node 111 Process 9 Confluence Villa del Sur Constituent streams: Stream 1: Q= 80,42* Stream 3: Q= lS.73 Tc= 10.57 Tc= 14.20 1= 3,379 1= 2.S72 @ Tc Stream 1 + Stream 3 = Confluenced 10.57 Q= SO.42 + Ratio= 13.94 = TC1/Tc3 94,36 cfs Qpeak = 94,36 cfs at Tc = 10.57 minutes Confluenced streams will be designated as stream # 1 to continue downstream. ----------------------------------- Surrunary ---------.-------------------------- Stream 1 at node 111 Length= 1800 ft. 2,54 cfs/acre avg. (c) A(tot)= 37.13 acres Tc= 10.57 min Q= 94.36 cfs ====================================================================:=========== \~ I I I I I I I I I I I I I I I I I I I File RCC07-C.DAT Runtime 10-26-2000 09:26 Job# RCC Page 8 Record 15 Subarea 13 Stream 1 Process 8: Add a subarea at last node Remark: Half of DePortola Rd itself, although some drains into 2 or 3 driveways At node 111 Subarea: .63 acre Soil: C, RI= 69 Development type 4 = 0,4 dwelling /acre ai=.l -----------------------------------------------------.-------------------------- Tc = 10,57 min. I = 3.379"/hr A(total) = 37.760 ac A(contrib) = 37.760 ac Fp = O.509"/hr C=.778 Q(subarea) = 1.66 cfs Q(total) = 96.02 cfs ___________________________________ Summary ---------..------------------------- Stream 1 to node 111 Length= 1800 ft. 2.54 cfs/acre avg. (c) A(tot)= 37.76 acres Tc= 10,57 min Q= 96.02 cfs =====================================================::========================= Record 16 Subarea 14 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at downstream node. Remark: to NE RCC prop cor. Node 111 to node 112 Elev 1055,50 to elev 1049.40 delta H = 6.10' Length.. 420' Slope=. 01452 Subarea: 4.57 acres Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.l Max d = 2' Bottom width = 3' Sideslope Z = 1.5:1 (h:v) n = .03 * Channel is overfull. Tt based on V= 6.6 for Q = 79.77 at Dn = d(full) -----------------------------------------------------.-------------------------- Tc = 10.57 + 1.05 = 11.62 min. I = 3.207"/hr A(total) = 42.330 ac A(contrib) = 42.330 ac Fp = O.505"/hr C=.'772 Q(subarea) = 11.32 cfs Q(total) = 107.34 cfs _ _ _ _ __ __ __ _ _ _ _ _ - - - - - - - - - - - - - - - - - - - - Summary - - - - - - - - -- - - - - - -- - -- - - - - - - - - - - - - - - - Stream 1 to node 112 Length= 2220Jft, 2.54 "cfs/acre avg. (c) A(tot)= 42.33~acres Tc= 11.62'min Q= 107.34Jcfs This stream is designated for confluence with 1 other by record 19 ===================================================:============================ *T************************************************~**k************** New Stream Record 17 Subarea 15 Stream 4 Process 1: Initial subarea Node 504 to node- 505 Elev 1063.00 to elev 1054,50 delta H = 8.50' Len9th= 700' Slope=. 01214 Subarea: 4.59 acres Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.l ------------------------------------------------------------------------------- k = .487 Tc = 16,17 min. I = 2.674"/hr A(total) = 4.590 ac Fp "' O.489"/hr C=.752 Q(subarea) = 9,23 cfs Q(tota1) = 9.23 cfs ___________________________________ Summary ----------------------------------- Stream 4 to node 505 Length= 700 ft. 2.01 cfs/acre avg. A(tot)= 4.59 acres Tc= 16,17 min Q= 9,23 cfs ===================================================:============================ \tg I I ,-r-"',. I I I I I I I I I I I I I I 1 I' I File RCC07-C.DAT Runtime 10-26-2000 09:26 Job# RCC Page 9 4 Process 3: enters stream pattern Street flow uniformly distributed along reach. Record 18 Subarea 16 Stream Subarea Q Remark: Assumed future street Node 505 to node 508 Elev 1054.50 to elev 1048.00 delta H = 6.50' Lenqth= 670' Slope= ,00970 Subarea: 8,01 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 Street template 5 Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfall=,02'1' Tt= 3.67 min. based on Qavg= 8.83 cfs on each side. of street. Davg=O,49' Aavg= 5.82 s,f. Vavg= 3,04'/sec At end of reach: D = 0.54' (0.543) V = 3.32'/sec. D*V = 1.80 Sf = .00971 Flow area = 7.87 s.f. Flooded width one side = 19,39' Flow exceeds top of curb. Plane of curb face extended up, pkwy ponded. 2 sides Hike = 2.0" Lip = .3811 -----------------------------------------------------.-------------------------- Tc = 16,17 + 3,67 = 19.84 min, I = 2,389"/hr A(total) = 12.600 ac Fp = 0.479"/hr C=,882 Q(subarea) = 16.88 cfs Q(total) = 26,10 cfs ___________________________________ Summary ----------------------------------- Stream 4 to node 508 Length= 1370 ft. 2,07 cfs/acre avg. A(tot)= 12.60 acres Tc= 19.84 min Q= 26.10 cfs =====================================================.~========================= Stream 4 112 1046.00 Process 7: Channel flow - Improved Record 19 Subarea 0 Node 508 to node E1ev 1048.00 to elev Subarea: 0 acre Bottom width = 3' Sideslope Z = 1,5:1 (h:v) Q= 26.10 cfs. Ca1c'd flow depth, D = 1.45 ft. delta H = 2.00' Len~'th= 360' Slope= .00556 n = .03 v= 3.48'/sec, ------------------------------------------------------------------------------- Tc = 19.84 + 1,72 = 21.57 min. A(tota1) = 12.600 ac I = 2.282"/hr Q(total) = 26.10 cfs ___________________________________ Summary ----------------------------------- Stream 4 to node 112~ Length= 1730 ft. 2,07 cfs/acre avg. A(tot)= 12.60 acres Tc= 21.57 min Q= 26,10 cfs This stream is designated for confluence with 1 other by record 16 ---------------------------------------------------.---------------------------- ---------------------------------------------------.---------------------------- \'\ I I I I I I I I I I I I I I I 1 I I'. '.- I File RCC07-C.DAT Runtime 10-26-2000 09:26 Job# RCC Page 10 Record 20 Confluencing 2 streams at node 112 Process 9 Confluence Constituent streams: Stream 1: Q= 107.34* Stream 4: Q= 26.10 Tc= 11.62 Tc= 21.57 I= 3.207 I= 2.282 @ Tc Stream 1 + Stream 4 = Confluenced 11.62 Q= 107.34 + Ratio= 14.06 = Tcl/TC4 121.40 cfs Qpeak = 121.40 cfs at Tc = 11.62 minutes Confluenced streams will be designated as stream # 1 ~o continue downstream. ___________________________________ Summary ----------------------------------- Stream 1 at node 112 Length= 2220 ft, 2.21 cfs/acre avg. (c) A(tot)= 54.93 acres Tc= 11.62 min Q= 121.40 cfs ---------------------------------------------------.---------------------------- ---------------------------------------------------.---------------------------- Record 21 Subarea 17 Stream 1 Process 7: Channel flow - Improved All subarea Q enters: s~ream at downstream node. Node 112 to node 403 Elev 44.30 to elev 40.85 delta H = 3.45' Subarea: 7.05 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre ai= Bottom width = 3' Sideslope Z = 1.5:1 (h:v) Q=121.40 cfs. Calc'd flow depth, D = 3.15 ft, Lensth= 690' Slope= .00500 .1 n = ,03 v= 4,99' /sec, ------------------------------------------------------------------------------- Tc = 11,62 + 2,31 = 13,93 min. I = 2.903"/hr A(total) = 61.980 ac A(contrib) = 61.980 ac Fp = O.770"/hr C=.685 Q(subarea) = 14,02 cfs Q(total) = 135.42 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 403 Length= 2910 ft. 2.18 cfs/acre avg. lc) A(tot)= 61.98 acres Tc= 13.93 min Q= 135,42 cfs ===================================================:============================ Record 22 Subarea 18 Stream 1 Process 8: Add a subarea at last node At node 403 Subarea: 2,44 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 ------------------------------------------------------------------------------- Tc = 13,93 min. I = 2.903"/hr A(total) = 64,420 ac A(contrib) = 64.420 ac Fp = O.497"/hr C=.885 Q(subarea) = 6.27 cfs Q(total) 141.69 cfs __ _ _ _ _ _ _ __ _ __ - - -- -- - - - - - - - - - -- - - - - - Summary - -- - - - .. - -- - - - - -- -- -- - -- - - -- - - - -- - - - Stream 1 to node 403 Length= 2910 ft. 2.20 cfs/acre avg. (c) Altot)= 64,42 acres Tc= 13,93 min Q= 141.69 cfs ================================================================================ \% I I I- I I I I I I I I 1 I I I I I I'" I File RCC07-C.DAT Runtime 10-26-2000 09:26 Job# RCC Page 11 Record 23 Subarea 19 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at downstream node. Node 403 to node 404 Elev 40.85 to elev 39.50 delta H = 1.35' Subarea: 3.67 acres Soil: BC, RI= 63 Development type 4 = 0.4 dwelling /acre ai= Bottom width = 3' Sideslope Z = 1.5:1 (h:v) Q=141,69 cfs. Calc'd flow depth, D = 3.38 ft. Length= 270' Slope= .00500 .1 n = .03 v= 5.19' /sec, --------------------------------------------------~---------------------------- Tc = 13,93 + 0,87 = 14.79 min. I = 2.808"/hr A(total) = 68.090 ac A(contrib) = 68.090 ac Fp = 0.612"/hr C=.723 Q(subarea) = 7.45 cfs Q(total) = 149.14 cfs _ _ _ _ __ _ __ _ _ _ _ _ _ _ _ _ __ - - -- - - - -- - - - - - - Summary - - - - - - .. - -- - - - - - - - - - - - -- - - - - - - - - - - - - Stream 1 to node 404 Length= 3180 ft. 2,19 cfs/acre avg. (c) A(tot)= 68.09 acres Tc= 14.79 min Q= 149.14 cfs This stream is designated for confluence with 1 other by record 30 ===================================================:============================ Record 24 Subarea 20 Stream 1 Process 8: Add a subarea at last node At node 404 Subarea: 1.01 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 __________________________________________________n____________________________ Tc = 14,79 min. I = 2,808"/hr p..(total) = 69.100 ac A(contrib) = 69.100 ac Fp = 0.494"/hr C=.884 Q(subarea) = 2.51 cfs Q(total) = 151.65 cfs _ _ _ _ __ _ _ _ _ _ __ _ __ _ _ - - -- - - - - - - - - - - - - - Summary - - - - - - .. - - - - -- - - - -- - - -- - - - - - - - - - - --- Stream 1 to node 404 Length= 3180 ft. 2,19 cfs/acre avg. (c) A(tot)= 69,10 acres T'> 14.79 min Q= 151.65 cfs ==================================================:============================= T**************************************************i**************** New Stream Record 25 Subarea 21 Stream 5 Process 1: Initial subarea Remark: Roof of future building, Node 510 to node 511 Elev 51.00 to elev 50.00 delta H = 1.00' Lenqth= 100' Slope= ,01000 Subarea: .1 acre Soil: C, RI= 69 Development type 14 = Commercial ai= .9 ----------------------------------------------------.--------------------------- k = .304 Tc = 4.82 min, I = 5,204"/hr A(total) = 0,100 ac Fp = 0.537"/hr C=.891 Q(subarea) = 0.46 cfs Q(total) = 0.46 cfs ___________________________________ Summary -------..--------------------------- Stream 5 to node 511 Length= 100 ft. 4.64 cfs/acre avg. A(tot)= 0,10 acres Tc= 4,82 min Q_. - 0.46 cfs =====================================================:=============;:============ \C\ I I I I I I I I I I I I I I I I I I- I File RCC07-C.DJl.T Runtime 10-26-2000 09:27 Job# RCC Page 12 Record 26 Subarea 22 Stream 5 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Remark: Future onsite driveway / parking bay with curb & gtr. Node 511 to node 512 Elev 50.00 to elev 48.20 delta H = 1.80' Length= 360' Slope= ,00500 Subarea: .9 acre Soil: C, RI= 69 Development type 14 = Commercial ai= Street template 0 Half-width = 40' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfall = .02 '/' Tt= 3.56 min, based on Qavg= 2.00 Davg=0.36' Aavg= 1.20 s.f. vavg= At end of reach: D = 0.42' (0,415) Flow area = 1.87 s,f. Flooded .9 1 side HH:e = 2.0" Lip = .3811 cfs on one side of street. 1. 69' /sec V = 1.89'/sec. width one side = Sf = .00500 D*V = 0.79 12.98' -------------------------------------------------------------------------------- Tc = 4,82 + 3,56 = 8,38 min. I = 3,839"/hr A(total) = 1.000 ac Fp ,,0.518"/hr C=.888 Q(subarea) = 3,07 cfs Q(total) = 3.53 cfs _ _ _ __ _ _ _ _ _ _ _ __ _ __ _ - - -- - - - -- - - -- - - - - Summary - - - - -- .. - - -- -- -- - - - - -- - - - - - - - -- - - - - - Stream 5 to node 512 Length= 460 ft, 3.53 cfs/acre avg. A(tot)= 1.00 acres Tc= 8.38 min Q= 3.53 cfs -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- Record 27 Subarea 23 Stream 5 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Node 512 to node 513 Elev 48.50 to elev 47.44 delta H" 1.06' Length= 210' Slope= ,00505 Subarea: 2.19 acres Soil: C, RI= 69 Development type 14 = Commercial ai= Street template 5 Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfall = .02 'I' Tt= 1,81 min. based on Qavg= 3.44 Davg=0.41' Aavg= 3.58 s.f. Vavg= At end of reach: D = 0,46' (0.458) Flow area = 4.95.s. f. Flooded .9 2 sides Hike = 2.011 Lip = .3811 cfs on each side of street. 1. 93' Isec V = 2.07'/sec. width one side " Sf = ,00505 D*V = 0.95 15,14' __________________________________________________n____________________________ Tc = 8.38 + 1.81 = 10.19 min. I = 3.447"/hr A(total) = 3.190 ac Fp = 0.510"/hr C=.887 Q(subarea) = 6,69 cfs Q(tota1) = 10,22 cfs ___________________________________ Summary ______n____________________________ Stream 5 to node 513 Length= 670 ft. 3.21 cfs/acre avg. A(tot)= 3,19 acres Tc= 10.19 min Q= 10,22 cfs ==================================================;============================= j;O \ I . ,- ~. I II i i I i i .- i " .. ~ k. . ~ . " .. , " \; .. :f l:. '. '. ^ ~ < , . ~ File RCC07-C.DAT Runtime 10-26-2000 09:27 Job# RCC Page 13 Record 28 Subarea 24 Stream 5 Process 3, Street flow Subarea Q enters stream uniformly distributed along reach. Node 513 to node 513.5 Elev 47.44 to elev 45.70 delta H = 1.74' Length= 248' Slope= .00702 Subarea: 3.02 acres Soil: C, RI= 69 Development type 14 = Commercial ai= Street template 5 Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfall = .02 'I' Tt= 1.60 min. based on Qavg= 7,24 cfs on each sidE, of street, Davg=0.48' Aavg= 5.61 s.f. Vavg= 2.58'/sec At end of reach: D = 0,52' (0.518) V = 2.71' /sec. D*V = 1.40 Sf = .00702 Flow area = 6.92 s. f. Flooded width one side :~ 18.12' Flow exceeds top of curb, Plane of curb face extended up, pkwy ponded, .9 2 sides Hike ,: 2. 0" Lip = .3811 ------------------------------------------------------------------------------- Tc = 10,19 + 1.60 = 11,79 min, I = 3,182"/hr A(total) = 6.210 ac Fp :, 0.504"/hr C=,886 Q(subarea) 8,51 cfs Q(total) = 18.74 cfs ___________________________________ Summary ------..---------------------------- Stream 5 to node 513.5 Length= 918 ft. 3.02 cfs/acre avg. A(tot)= 6.21 acres Tc= 11.79 min Q= 18.74 cfs ===================================================:============================ Record 29 Subarea 25 Stream 5 Process 5: Pipe flow, Program-selected size All subarea Q enters stream at downstream node. Remark: Some park, but all tabled as all commerciaJ.. Node 513.5 to node 514 Pipeslope = 1 * groundslope. n = ,013 Elev 41.00 to elev 39.00 delta H = 2.00' Length= 560' Slope= .00357 Subarea, 6.96 acres Soil: C, RI= 69 Development type 14 = Commercial ai= ,9 18.74 cfs in 1 30" pipe (d = 2.50') Depth, D=1.63' D/d=.652 Sf = .00361 Hv=V^2/2g= 1.85' 1.2Hv= 2.22' 1.5Hv= 2,77' Travel time X-Sect A= 3.39 sf, V= 5.53' /sec, Tt= J.,69 min. -------------------------------------------------_.~---------------------------- Tc = 11.79 + 1.69 = 13,48 min. I = 2,956"/hr A(total) = 13.170 ac Fp - 0.498"/hr C=.E85 Q(subarea) = J.8,20 cfs Q(total) = 36,94 cfs ___________________________________ Summary -------..--------------------------- Stream 5 to node 514 Length= J.478 ft. 2.80 cfs/acre avg, A(tot)- 13,17 acres Tc= 13.48 min Q_. -. 36.94 cfs ===================================================================:============ 1-" I I I I I I I I I I I I I I I I I I I File RCC07-C.DAT Runtime 10-26-2000 09:27 Job# RCC Page 14 Stream 5 Process 404 Pipeslope = 36.20 delta H = 5: Pipe flow, program-selected size 1 * ground~:lope. n = ,013 1.80' Length= 360' Slope= .00500 Record 30 Subarea 0 Node 514 to node Elev 38.00 to elev Subarea: 0 acre 36.94 cfs in 1 33" pipe (d = 2.75') Depth, D=2.22' D/d=.806 Hv=V^2/2g= 0.81' 1.2Hv= 0.97' 1.5Hv= 1.21' Travel time X-Sect A= 5,13 sf, V= 7.20'/sec, Tt= 0.83 min. Sf = .00503 ------------------------------------------------------------------------------- Tc = 13.48 + 0.83 = 14.31 min. A(total) = 13.170 ac I = 2.860"/hr Q(total) = 36.94 cfs ___________________________________ Summary ----------------------------------- Stream 5 to node 404 Length= 1838 ft. 2.80 cf~:/acre avg. A(tot)= 13.17 acres Tc= 14.31 min Q= 36.94 cfs This stream is designated for confluence with 1 other by record 23 ===================================================:============================ Record 31 Confluencing 2 streams at node 404 Process 9 Confluence Constituent streams: Stream 1: Q= 151.65* Stream 5: Q= 36.94 Tc= 14,79 Tc= 14.31 1= 2.808 1= 2.860 @ Tc Stream 1 + Stream 5 = Confluenced 14.79 Q= Ratio= 151. 65 + 36.27 = n/15 187.92 cfs Qpeak = 187.92 cfs at Tc = 14.79 minutes Confluenced streams will be designated as stream # 1 to continue downstream. ___________________________________ Summary -------.---------------------------- Stream 1 at node 404 Length= 3180 ft. 2,28 cfs/acre avg. (c) A(tot)= 82.27 acres Tc= 14.79 min Q= 187.92 cfs ==================================================::============================ 1-~ I ,I I' I I I I I I I I I I I I I I 1'- I File RCC07-C.DAT Runtime 10-26-2000 09:27 Job# RCC Page 15 Record 32 Subarea 26 Stream 1 Process 5: Pipe flow, program-selected size All subarea Q enters stream at downstream node, Remark: 1/2 Hardscape, 1/2 Play area. Node 404 to node 405 Pipeslope = 1 * groundslope. n = ,013 Elev 34.20 to elev 30.59 delta H = 3.61' Length= 530' Slope= ,00681 Subarea: 2.8 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 187.92 cfs in 1 60" pipe (d = 5.00') Depth, D=3.62' D/d=,724 Sf .00682 Hv=V^2/2g= 2,54' l,2Hv= 3.05' 1.5Hv= 3.81' Travel time X-Sect A= 15.22 sf, V=12.34' /sec, Tt= 0,72 min. --------------------------------------------------..---------------------------- Tc = 14.79 + 0.72 = 15.51 min. I = 2.736"/hr A(total) = 85,070 ac A(contrib) = 85.070 ac Fp 0' O,491"/hr C=.884 Q(subarea) = 6.77 cfs Q(total) = 194,69 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 405 Length= 3710 ft. 2.29 cfs/acre avg. (c) A(tot)= 85.07 acres Tc= 15.51 min Q= 194.69 cfs =;:==;========;=====;==============================::=========================== Record 33 Subarea 27 Stream 1 Process 8: Add a subarea at last r,.ode Remark: Inlet for residential lots. At node 405 Subarea: 4.39 acres Soil: BC, RI= 63 Development type 4 = 0,4 dwelling /acre ai=.l ---------------------------------------------------..--------------------------- Tc = 15.51 min. I = 2,736"/hr A(total) = 89.460 ac A(contrib) = 89.460 ac Fp '0 0.609"/hr C=.720 Q(subarea) = 8.65 cfs Q(total) 203,34 cfs .___________________________________ Summary -------..--------------------------- Stream 1 to node 405 Length= 3710 ft. 2,27 cfs/acre avg. (c) A(tot)= 89,46 acres Tc= 15,51 min Q- 203.34 cfs ===================================================================:============ Record 34 Subarea 28 Stream 1 Process 5: Pipe flow, program-selected size All subarea Q enters stream at downstream node. Node 405 to node 407 Pipeslope = 1 * groundslope, n Elev 30.59 to elev 27.26 delta H = 3.33' Leng~h= 490' Subarea: 6.22 acres Soil: BC, RI= 63 Development type 4 = 0.4 dwelling /acre ai=.l 203,34 cfs in 1 60" pipe (d = 5.00') Depth, D=3.87' D/d=.774 Hv=V^2/2g= 2.71' 1.2Hv= 3.25' 1.5Hv= 4,06' Travel time X-Sect A= 16.31 sf, V=12.47' /sec, Tt= 0,65 min. = .013 Slope- .00680 Sf .00683 -----------------------------------------------------------------_.~------------ Tc = 15.51 + 0,65 = 16,16 min. I = 2.674"/hr ]:..(total) = 95.680 ac A(contrib) = 95.680 ac Fp = 0.606"/hr C=.717 Q(subarea) = 11.92 cfs Qltotal) = 215.26 cfs ___________________________________ Summary --------..-------------------------- Stream 1 to node 407 Length= 4200 ft. 2,25 cfs/acre avg. (c) A(tot)= 95.68 acres Tc= 16,16 min Q= 215,26 cfs =======;;;;;;;;;;;;;;;=;;============;;;;;;;;;;;;=;;==;;==;=;;;;;;;;;;;=;===;;; 7> I - I I I I I I I I I I I I I I I I. I File RCC07-C.DAT Runtime 10-26-2000 09:28 Job# RCC Page 16 Record 35 Subarea 29 Stream 1 Process 8: Add a subarea at last node At node 407 Subarea: 1.28 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 ------------------------------------------------------------------------------- Tc = 16,16 min. I = 2.674"/hr A(total) = 96.960 ac A(contrib) = 96.960 ac Fp = O.489"/hr C=.884 Q(subarea) = 3.02 cfs Q(total) 218,28 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 407 Length= 4200 ft. 2.25 cfs/acre avg. (c) A(tot)= 96.96 acres Tc= 16.16 min Q= 218.28 cfs ==================================================='============================ Record 36 Subarea 30 Stream 1 Process 5: Pipe flow, Program-selected size All subarea Q enters: stream at downstream node. = .013 Slope= .00682 Node 407 to node 409 Pipeslope = 1 * groundo:lope. n Elev 27.26 to elev 24,60 delta H = 2.66' Length= 390' Subarea: 3,75 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 218.28 cfs in 1 63" pipe (d = 5.25') Depth, D=3.66' D/d=.735 Hv=V^2/2g= 2,75' 1.2Hv= 3.30' 1.5Hv= 4,13' Travel time X-Sect A= 17,06 sf, V=12.80'/sec, Tt= 0.51 min. Sf = .00683 ------------------------------------------------------------------------------- Tc = 16.16 + 0.51 = 16.67 min. I = 2.629"/hr ]dtotal) = 100.710 ac A(contrib) = 100.710 ac Fp = O.488"/hr C=.883 Q(subarea) = 8,71 cfs Q(total) = 226.99 cfs _ _ _ __ __ _ __ _ _ - - - - - -- -- - - -- -- - - - - - - - - Summary - - -- - - - - - - - -- - - - - - - -- - - - - - - - - - - - - - - Stream 1 to node 409 Length= 4590 ft. 2.25 cfs/acre avg, Ic) A(tot)=100.71 acres Tc= 16.67 min Q= 226.99 cfs ---------------------------------------------------.---------------------------- ---------------------------------------------------.---------------------------- Record 37 Subarea 31 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at downstream node. Node 409 to node 121 Elev 24.60 to elev 24.00 delta H = 0.60' Length= 120' Slope= ,00500 Subarea: 4.35 acres Soil: BC, RI= 63 Development type 4 = 0.4 dwelling /acre ai= ,1 I~ax d = 4' Bottom width = 5' Sideslope Z = 1.5:1 (h:v) n = .03 Q=226.99 cfs. Calc'd flow depth, D = 3,70 ft. V= 5.82' /sec, ------------------------------------------------------------------------------- Tc = 16.67 + 0.34 = 17.02 min. I = 2.600"/hr ll.(total) = 105.060 ac A(contrib) = 105.060 ac Fp = 0.602"/hr C=.713 Q(subarea) = 8,06 cfs Q(total) = 235.05 cfs _ _ _ _ -- - - - -- -- - - - - - -- - - -- -- - - - -- - - - - Summary - -- - - -- - - - - - - - - -- - - - -- - - - -- - - - - - - - - Stream 1 to node 121 Length= 4710 ft. 2.24 cfs/acre avg. Ic) A(tot)=105.06 acres Tc= 17.02 min Q= 235.05 cfs This stream is designated for confluence with 1 other by record 44 ---------------------------------------------------.---------------------------- -------------------------------------------------------------------------------- 1,.~ I I I I I I I I I I I I I I I I I t I File RCC07-C.DAT Runtime 10-26-2000 09:28 Job# RCC Page 17 **T***********************************************~***************** New Stream Record 38 Subarea 32 Stream 6 Process 1: Initial subarea Node 516,2 to node 516,3 Elev 43.60 to elev 42.00 delta H = 1.60' Length= 180' Slope= .00889 Subarea: .38 acre Soil: C, RI= 69 Development type 14 = Commercial ai= .9 ---------------------------------------------------.---------------------------- k = .304 Tc = 6,24 min. I = 4.514"/hr A(total) = 0,380 ac Fp ,,0.529"/hr C=.889 Q(subarea) = 1.53 cfs Q(total) = 1.53 cfs _ _ _ __ __ _ -- -- -- - -- - - -- -- -- - - - - - - - - - - Summary - - - - - - .. - - -- - -- - -- - - - - - - - - - - - - - - - - - - Stream 6 to node 516.3 Length= 180 ft. 4,01 cis/acre avg. A(tot)= 0.38 acres Tc= 6.24 min Q= 1,53 cfs ---------------------------------------------------.---------------------------- -------------------------------------------------------------------------------- Record 39 Subarea 33 Stream 6 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Node 516.3 to node 515 Elev 42.00 to elev 38.60 delta H = 3.40' Length= 450' Slope= .00756 Subarea: 1,66 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 Street template 5 Half-width = 24' n = .015 CF = 6" Batter= ,25 h/v Gutter width = 24" Xfall = .02 '/' Tt= 3.78 min. based on Qavg= 2.04 Davg=0.34' Aavg= 2.06 s,f. Vavg= At end of reach: D = 0.39' (0.387) Flow area = 3.04 s.f. Flooded :: sides Hike = 2.0" Lip .3811 cfs on each side of street. 1.98'/sec V = 2.19' /sec, width one side " Sf = .00756 D*V = 0.85 11. 55' ----------------------------------.--------------------------------------------- To = 6,24 + 3.78 = 10.02 min. I = 3.478"/hr A(total) = 2.040 ac Fp ,,0.511"/hr C=.887 Q(subareaJ = 5,12 cfs Q(total) = 6.65 cfs ___________________________________ Summary ----------------------------------- Stream 6 to node 515 Length= 630 ft. 3.26 cfs/acre avg. A(tot)= 2.04 acres Tc= 10.02 min Q= 6.65 cfs ===================================================,============================ , 'J,.? I I I I I I I I .1 I I I I I I I I I" I File RCC07-C. D,lI.T Runtime 10-26 -2000 09: 28 Job# RCC Page 18 Record 40 Subarea 34 Stream 6 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach, Node 515 to node 516 Elev 38,60 to elev 36.50 delta H = 2,10' Length= 275' Slope= .00764 Subarea: 4,88 acres Soil: C, RI= 69 Development type 14 = Commercial ai= ,9 Street template 5 Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfall = ,02 'I' Tt= 1.75 min. based on Qavg= 6.76 cfs on each side of street. Davg=0.47' Aavg= 5.20 s.f, Vavg= 2,62'/sec At end of reach: D = 0.52' (0.524) V = 2,85'/sec. D*V = 1.50 Sf = .00764 Flow area = 7,15 s.f, Flooded width one side = 18.44' Flow exceeds top of curb, Plane of curb face extended up, pkwy ponded. 2 sides Hike = 2.0" Lip = .3811 --------------------------------------------------..---------------------------- Tc = 10.02 + 1.75 = 11.78 min. I = 3,183"/hr A(total) = 6.920 ac FD '0 0.504"/hr C=.886 Q(subarea) = 13.76 cfs Q(total) = 20.41 cfs ___________________________________ Summary -------,--------------------------- Stream 6 to node 516 Length= 905 ft. 2.95 cfs/acre avg. A(tot)= 6.92 acres Tc~ 11.78 min Q= 20.41 cfs ===================================================~=========================== ***************************************************T**************** New Stream Record 41 Subarea 35 Stream 7 Process 2: User-specified info at node Remark: Part of flow to C.B. into Hyw 79 S,D: 1.70"ac @ 2.95 cfs/ac = 5.02 cfs At node 517 A(total)= 5.210 acres Tc = 11.78 minutes Q = 15.39 cfs ================================================================================ "/;~ I I I I , I I I I I I I I I I I I I- I File RCC07-C.Di'.T Runtime 10-26-2000 09:28 Job# RCC Page 19 Record 42 Subarea 36 Stream 7 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach, Node 517 to node 518 Elev 36,60 to elev 34.13 delta H = 2.47' Length= 495' Slope= .00499 Subarea: 2.05 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 Street template 5 Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width ~ 24" Xfall ~ .02 'I' Tt= 3.41 min. based on Qavg= 8.95 cfs on each side of street. Davg=0.53' Aavg= 7.40 s,f, Vavg= 2.42'/sec At end of reach: D = 0,56' (0.557) V = 2.43'/sec. D*V = 1.35 Sf = .00499 Flow area ~ 8.40 s.f, Flooded width one side = 20.07' Flow exceeds top of curb. Plane of curb face extended up, pkwy ponded. ;~ sides HH:e ~ 2,0" Lip = .3811 -------------------------------------------------------------------------------- Tc = 11.78 + 3.41 = 15.19 min. I = 2.768"/hr A(total) ~ 7.260 ac Fp'" 0.492"/hr C=.884 Q(subarea) = 5,02 cfs Q(total) = 20.41 cfs _ _ _ _ _ __ _ .. _ _ _ .. .. _ _ _ _ __ -- - - - .. - - -- - - - - - Summary - - - - - - .. - - - - - - - - - - - - - -- - -- - - - - - - - - - - Stream 7 to node 518 Length= 495 ft, 2.81 cfs/acre avg. A(tot)= 7,26 acres Tc~ 15.19 min Q~ 20.41 cfs ==================================================::============================ Record 43 Subarea 37 Stream 7 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Node 518 to node 520 Elev 34.14 to elev 30.50 delta H = 3,64' Len9th= 330' Slope~ .01103 Subarea: 2.66 acres Soil: C, RI= 69 Development type 14 ~ Commercial ai= Street template 5 Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width ~ 24" Xfall ~ .02 'I' Tt= 1.57 min, based on Qavg= 11.74 cfs on each side of street, Davg~0.51' Aavg= 6.70 s.f. Vavg= 3.51'/sec F.t end of reach: D = 0.54' (0,536) V = 3,50'/sec. D*V = 1.87 Sf ~ .01104 Flow area = 7.59 s.f. Flooded width one side ~ 19.03' Flow exceeds top of curb. Plane of curb face extended up, pkwy ponded. .9 2 sides Hike = 2.011 Lip ~ ,38" ------------------------------------------------------------------------------- TC = 15.19 + 1.57 = 16,76 min. I = 2.622"/hr i',,(tota1) = 9,920 ac Fp = 0.488"/hr C=.f83 Q(subarea) ~ 6.16 cfs Q(tota1) = 26,57 cfs _ _ _ __ _ _ __ _ _ _ _ __ _ _ - -- - - - - -- - - - -- -- - - Summary - - - - - -." .. - - - - - - - - - -- - -- - -- - - - - - --.. - - Stream 7 to node 520 Length= 825 ft. 2,68 cfs/acre avg, A(tot)= 9.92 acres Tc" 16.76 min Q_. -. 26,57 cfs ===================================================::===============:============ "J,.\ I I I I I I j I / I I I I I I I I . i-- I File RCC07-C.DAT Runtime 10-26-2000 09:29 Job# RCC Page 20 Record 44 Subarea 38 Stream 7 Process 4: Valley gutter section f~ow Subarea Q enters stream uniformly distributed a:,ong reach. Node 520 to node 121 Elev 30.50 to elev 28.10 delta H = 2.40' Length= 300' Slope= .00800 Subarea: 1.71 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 Valley gutter template 2 Section width = 24' n = .015 Gutter width = 3' Hike = 1.5" Lip = .38" Pav';: X-fall = .02 .' /' Tt based on Qavg= 28.47 cfs Davg=0.54' Aavg= 7.24 sf. Vavg= 3,93 fps At end of reach: D = 0,54' (0,538) V = 4.20'/sec. D*V = 2,26 Sf = .00806 Flow area = 7.24 s,f. Flooded width = 24.00' Flow exceeds edge of pavement. Vertical curbs assumed both sides. ______________________________________________________-------______0__---------- Tc = 16.76 + 1,27 = 18.03 min. I = 2.519"/hr i'.(total) = 11.630 ac Fp = O.484"/hr C=.8133 Q(subarea) = 3.80 cfs Q(total) = 30.37 cfs __ _ _ __ _ _ _ _ _ _ __ _ __ _ _ __ _ - - -- - - - - - - - - - Summary - - - -- - - - - .. -- - .... .. - .. - - - -- .- - - - - .. .. - .. - - - Stream 7 to node 121 Length= 1125 ft. 2.61 cfs/acre avg. A(tot)= 11.63 acres Tc= 18.03 min Q= 30.37 cfs This stream is designated for confluence with 1 other by record 37 =====================================================~=============::=========== Record 45 Confluencing 2 streams at node 121 Process 9 Confluence Constituent streams: Stream 1: Q= 235.05* Stream 7: Q= 30.37 Tc= 17.02 Tc= 18,03 I= 2,600 I= 2.519 @ Tc Stream 1 + Stream 7 = Confluenced 17.02 Q= 235.05 + Ratio= 28.66 = TC1/Tc7 263.71 cfs Qpeak = 263.71 cfs at Tc = 17,02 minutes Confluenced streams will be designated as stream # 1 to continue downstream, _ _ _ _ _ .. _ __ _ _ _ __ _ _" .. -- - - -- ...... .. - - - -- .. - Summary .. - - .. - -- .. - --- - - .. .. - - .... - -- - - -- .. .. - .. - - - .. - Stream 1 at node 121 Length= 4710 ft. 2.26 cfs/acre avg. (c) A(tot)=116.69 acres Tc= 17.02 min Q= 263.71 cfs =============================================================================== '),~ I I I I I I I I I I , I I I I I I I .1 File RCC07-C.DAT Runtime 10-26-2000 09:29 Job# RCC ?age 21 Record 46 Subarea 39 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at downstream node. Node 121 to node 122 Elev 24.00 to elev 21.48 delta H = 2.52' Len~th; 505' Slope= .00499 Subarea: 3.15 acres Soil: Be, RI= 63 Development type 4 = 0.4 dwelling /acre ai=.l Max d ; 4' Bottom width = 5' Sideslope Z = 1.5:1 (h:v) n = .03 Q=263.71 cfs. Calc'd flow depth, D = 3.98 ft. V= 6,04' /sec, -----------------------------------------------------.-------------------------- Tc = 17.02 + 1.39 = 18.41 min. I = 2,490"/hr A(total) = 119.840 ac A(contrib) = 119.840 ac Fp = 0.596"/hr C=.706 Q(subarea) = 5,54 cfs Q(total) = 269.25 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 122 Length= 5215 ft. 2.25 cfs/acre avg. (c) A(tot)=119.84 acres Tc= 18.41 min Q; 269.25 cfs ---------------------------------------------------.---------------------------- ---------------------------------------------------.---------------------------- Record 47 Subarea 40 Stream 1 Process 8: Add a s:ubarea at last node At node 122 Subarea: 3.08 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 ------------------------------------------------------------------------------- Tc = 18.41 min. I = 2.490"/hr A(total) = 122.920 ac A(contrib) = 122.920 ac Fp = 0.483"/hr C=.883 Q(subarea) = 6,77 cfs Q{total) 276.02 cfs _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ - - - - - - - - - - - - - - Summary - - - -- - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - Stream 1 to node 122 Length; 5215 ft. 2.25 cfs/acre avg. (c) A{tot);122.92 acres Tc= 18.41 min Q= 276,02 cfs ===================================================:============================ flow - stream soccer Improved at dOlomstream fields. node. Record 48 Subarea 41 Stream 1 Process 7: Channel )>.11 subarea Q enters Remark: To NE cor ball fields. Not including ball I< Node 122 to node 123 Blev 21.48 to elev 20.00 delta H = 1.48' Length; 290' Subarea: 5,01 acres Soil: BC, RI= 63 Development type 4 = 0.4 dwelling /acre ai;.l Bottom width = 5' Sideslope Z = 1.5:1 (h:v) Q=276.02 cfs. Calc'd flow depth, D = 4.05 ft. Slope= .00510 n = ,03 V= 6,15' /sec, --------------------------------------------------..---------------------------- Tc = 18,41 + 0.79 = 19,19 min. I; 2.433"/hr A(total) = 127.930 ac A(contrib) = 127.930 ac Fp = 0.592"/hr C=.703 Q(subarea) = 8.57 cfs Q(total) = 284.59 cfs __ __ _ _ _ _ _ _ _ _ _ __ _ _ - - -- - - - - - - - - -- - - - - SUlThl1ary - - - - - - .. - - - - - - - - - - - - - - - - -- - -- - -- - - - - Stream 1 to node 123 Length= 5505 ft. 2.22 cfs/acre avg. (e) A(tot)=127,93 acres Tc= 19.19 min Q= 284.59 cfs ==================================================:;~==============;============ 'l-o... I I I I I I I I I I I I I I I I I I I Por, File RCC07-C,DAT Runtime 12-18-2001 17:08 ,Job# RCC I 00 -~I' Page 22 Record 49 Subarea 42 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at dOlOnstream node, Node 123 to node 124 Elev 20.00 to elev 18.20 delta H = 1.80' Length= 360' SlO])e= ,00500 Subarea: 3.15 acres Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai= ,1 Max d = 4' Bottom width = 8' Sideslope Z = 1.5:1 (h:v) n = .03 Q=284.59 cfs. Calc'd flow depth, D = 3.53 ft. V= 6.06'/sec, Tc = 19.19 + 0.99 = 20,18 min. A(total) = 131.080 ac A(contrib) = Q(subarea) = 5.49 cfs I = 2.367"/hr 131,080 ac Fp = O,478"/hr C=.736 Q(total) = 290.08 cfs - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Surrnnary - - - -" -.' - -" - - - - - - - - - -.."" " - - - - - - - - - -" Stream 1 to node 124 Length=5, 865' 2.21 cfs/acre avg. (c) A (tot) =131. 08 acres Te:= 20.18 min Q= 290.08 cfs -------------------------------------------------'------------------------------- -------------------------------------------------'------------------------------- Record 50 Subarea 43 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at downstream node, Remark: 25% park, 75% corrnnercial. Node 124 to node 190 Elev 18.20 to elev 16.00 delta H = 2.20' Length= 470' Slope= .00468 Subarea: 9.07 acres Soil: C, RI= 69 Development type 15 = User's fraction / mix ai= .7125 Max d = 4' Bottom width = 10' Sideslope Z = 1,5:1 (h:v) n = ,03 Q=290.08 cfs. Calc'd flow depth, D = 3.31 ft. V= 5.86'/sec, Tc = 20.1S + 1.34 = 21.52 min. A(total) = 140.150 ac A(contrib) = Q(subarea) = 17.54 cfs I = 2.285"/hr 140.150 ac Fp = 0.475"/hr C=.846 Q(total; = 307.61 cfs - - - - - - - - - - - - - --""" - -" - - - - -- - - -"""" - Surrnnary -"""" -.. - -" -" - - - - - - -".."" -" - - -- - - - - -" Stream 1 to node 190 Length=6, 335' 2,19 cfs/acre avg, (c) A(tot)=140.15 acres Tc= 21.52 min Q= 307.61 cfs .-------------------------------------------------.---.----.--------.--------------- ----------.---------------------------------------"---------------.--------------- Record 51 Stream 1 Process 7: Channel All subarea Q enters Smith Rd. & Hwy 79 flow - Improved stream at downstream node. Subarea 44 Remark: To exist. RCB @ Jed. Node 190 to node 191 Elev 16.00 to elev 11.56 delta H = 4.44' Length= 370' Slope= .01200 Subarea: ,78 acre Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai= ,1 Max d = 4' Bottom width = 10' Sideslope Z = 2:1 (h:v) n = .015 Q=307.61 cfs. Calc'd flow depth, D = 1.74 ft. V=13.11'/sec, Tc = 21.52 + 0.47 = 21.99 min, A(total) = 140.930 ac A(contrib) = Q(subarea) = 1,29 cfs I = 2.25S"/hr 140.930 ac Fp = O,473"/hr C=.73D Q(total; = 308.90 cfs _ __ __ __ _ _.. _ _ __ __ _" n" _ _ __ _ _ _ _ _ __ _ __ surrunary "n" - n _ _ __ _ __ _" u.. _.. _ _ __" _ u -- - - - - Stream 1 to node 191 Length=6, 705' 2.19 cfs/acre avg, (c) A(tot)=140,93 acres Tc= 21.99 min Q= 308.90 cfs ================================================================:=============== ~~e;p ?P I I I I I I I I I I I I I I I I I I I +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Other: Stream 2 : Len= 920' Atot= 6.42 ac Tc= 7.74 min Q= 20.69 cfs Stream 3 : Len= 1390' Atot= 9.09 ac Tc= 14 .20 min Q= 18.73 cfs Stream 4 : Len= 1730' Atot= 12.60 ac Tc= 21. 57 rnin Q= 26.10 cfs Stream 5 : Len= 1838' Atot= 13 .17 ac Tc= 14.31 min Q= 36.94 cfs Stream 6 : Len= 905' Atot= 6.92 ac Tc= 11.78 min Q= 20.41 cfs Stream 7 : Len= 1125' Atot= 11.63 ac Tc= 18.03 min Q= 30.37 cfs ----------------------------------------------------------------.--------------- ----------------------------------------------------------------.--------------- End of RMH run for file RCC07-C.DAT 7/\ I I I I I I I I I I I I I I I I I I I RMH RC ver 6,4b Nov. 2000 RATIONAL METHOD HYDROLOGY Riverside County (C) Copyright 1999 Jack P. Norris, Tel 909-676-5816, Fax 676-001E SIN 0 Jack P. Norris, RCE, 33055 Vino Way, Temecula CA 92591 905-676-5816 File: RCC07-C.DAT 50 records Runtime: 10-26-2000 09:48 Page 1 By JPN Work code 8 Job# RCC +------------------------------------------------.-----------------------------+ Rancho Community Church site, Hwy 79S, Temecula Proposed condition, Config #7 100-yr ~ 10 -1r +----------------------------------------------.-------------------------------+ Schematic diagram. Legend: Node number/ Link text: record number + process name Streams: 2 3 4 5 6 7 101 201 lIni t 4Ini t 102 202 2Chan 5Chan 103 203 3Stre 6Stre 104 <----' 8Stre 105 9Stre 111 <--- <-------' 16Chan 112 <--- <------ <-------' 21Chan 403 23Chan 404 c--- c------ <------ <-------' 32Pipe 405 34Pipe 407 36Pipe 409 37Chan 121 c--- <------ c------ <------ <------ <------.-' 46Chan 122 48Chan 123 49Chan 124 50Chan 190 I 1\ . l~ ~QI)'\ 5\ C~""{\ "~"''I.<.1. '- c tC\,! 301 11Init 302 12Chan 303 13Stre 504 17Init 505 18Stre 508 19Chan 510 25Init 511 26Stre 512 27Stre 513 28Stre 513.5 29Pipe 514 30Pipe 516.2 516.1 38Init ~41user 516.3 _17 39Stre 42Stre 515 518. 40Stre 43Stre 516 - 520. 44Vall 0llerr<'d e. ?5L- I I ;,1 I I I I I I I I I I I I I I I I RMH RC ver 6.4b Nov. 2000 RATIONAL METHOD HYDROLOGY Riverside County (C) Copyright 1999 Jack P. Norris, Tel 909-676-5816, Fax 676-0016 SiN 0 Jack P. Norris, RCE, 33055 Vino Way, Temeculo. CA 92591 909-676-5816 File: RCC07-10.DAT By JPN Work code 8 50 records Job# RCC Runtime: 10-26-2000 09:36 Page 1 +------------------------------------------------------------------------------+ Rancho Community Church site, Hwy 79S, Temecula proposed condition, Config #7 10-yr +-----------------------------------------------------------------------------+ Frequency: 10 - yr. I = 8.385 TC^-.551 Min. pipe size: 18" Legend: (i)=input (c)=computed 10-yr 1-hr I= .88 (i), 10-yr 10-min I= 2,36 (i) 10-yr 1-hr depth= 0.880" (c) -Loglog slope of I-L1 curve = 0,5506 (c) Initial subarea Tc by Kirpich formula: Tc = k (DiE:t^3 / deltaH) ^ . 2 ******************************************************************************* Record 1 Subarea 1 Node 101 to node Elev 1208.50 to elev Subarea: .64 acre Development type 4 = Stream 1 Process 1: Initial subarea 102 1158,00 delta H = 50.50' Length= 210' Soil: D, RI= 75 0.4 dwelling /acre ai=.l Slope= .24048 ------------------------------------------------------------------------------- k = .487 Tc = 5.50 min. I = 3,281"/hr Altotal) = 0.640 ac Fp :c O,391"/hr C=.803 Q(subarea) = 1.69 cfs Q(total) = 1.69 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 102 Length= 210 ft. 2.64 cfs/acre avg. A(tot)= 0,64 acres Tc= 5.50 min Q= 1.69 cfs ===================================================:============================ Record 2 Subarea 2 Stream 1 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 102 to node 103 Elev 1158.00 to elev 1119.00 delta H = 39.00' Length= 320' Slope= ,12188 Subarea: 2,2 acres Soil: D, RI= 75 Development type 4 =0.4 dwelling /acre ai=.l V avg = 7.14'/sec for avg Q of 4.37 cfs --------------------------------------------------..---------------------------- Tc = 5.50 + 0.75 = 6,25 min. I = 3.058"/hr A(total) = 2.840 ac Fp" 0.388"/hr C=.797 Q(subarea) = 5.36 cfs Q(total) = 7.05 cfs ___________________________________ Summary ______n____________________________ Stream 1 to node 103 Length= 53D ft. 2.48 cfs/acre avg. A(tot)= 2.84 acres Tc= 6.25 min Q= 7.05 cfs ==================================================::~=========================== ~ I 1,-_ ,I ~I 'I I I I I I I I I I I I I 1'- I File RCC07-10.DAT Runtime 10-25-2000 14:52 Job# RCC Page 2 Record 3 Subarea 3 Stream 1 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Remark: Verde Drive Node 103 to node Elev 1119.00 to elev Subarea: 1.22 acres Development type 4 = Street template 0 CF = 6" Batter= Xfall = .02 '/' Tt= 1.04 min. based on Qavg= 4.11 Davg=0.16' Aavg= 1.29 s.f. Vavg= At end of reach: D = 0.17' (0.173) Flow area = 1.51 s.f. Flooded 104 1077.00 delta H = 42.00' Soil: B, RI= 56 0.4 dwelling /acre ai=.l Half-width = 10' n = .015 .25 h/v Gutter width = 0" Length= 400' Slope.. .10500 2 sides Hike = 0.0" Lip = .00" cfs on each side of street. 6.40'/sec V = 6.22' /sec. width one side = Sf = .10516 D*V = 1.08 8.70' ---------------------------------------------------..---------------.------------ Tc = 6.25 + 1.04 = 7.29 min. I = 2.809"/hr A(total) = 4.060 ac Fp = O.763"/hr C=.680 Q(subarea) = 2.33 cfs Q(total) = 9.38 cfs _ _ _ __ __ _ __ __ _ _ _ _ _ _ - -- -- - - -- - - -- - - - - Summary - -- -- - - ... - " - - - -- - " - - " --- -- - -- -- - - - .. - Stream 1 to node 104 Length= 930 ft. 2.31 cfs/acre avg. A(tot)= 4.06 acres Tc~ 7.29 min Q= 9.38 cfs This stream is designated for confluence with 1 other by record 6 ==================================================================:~============ ******************************************************************** New Stream Record 4 Subarea 4 Node 201 to node Elev 1201.00 to elev Subarea: 1.84 acres Development type 4 = Stream 2 Process 1: Initial subarea 202 1123.00 delta H = 78.00' Length= 300' Soil: D, RI= 75 0.4 dwelling /acre ai=.l Slope" .26000 ------------------------------------------------------------------.------------- k = .487 Tc = 6.24 min. I = 3.059"/hr A(total) = 1.840 ac Fp = O.388"/hr C=.'797 Q(subarea) = 4.49 cfs Q(total) = 4.49 cfs __ _ _ _ _ __ _ _ .. _ __ _ _ - - - - - --" - - - - - -.. -- -- Summary -" -- - - - - .. - - - - - - - - - -- - -.- - - -- -- - .. - - - - Stream 2 to node 202 Length= 300 ft. 2.44 cfs/acre avg. A(tot)= 1.84 acres Tc= 6.24 min Q." '" 4 .49 cis ==================================================================:;============ ~ II I~ ,I I I I I I I I I I I I I I I I~ I File RCC07-10.DAT Runtime 10-25-2000 14:52 Job# RCC Page 3 Record 5 Subarea 5 Stream 2 Process 7: Channel flow - Natural VaLley Subarea Q enters stream uniformly distributed aLong reach. Node 202 to node 203 Elev 1123.00 to elev 1079.00 delta H = 44.00' Length= 520' Slope= ,08462 Subarea: 3.86 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling lacre V avg = 6.90'/sec for avg Q of 8.10 cfs ai= .1 ----------------------------------------------------.---------------.------------ Tc = 6.24 + 1.26 = 7.50 min. I = 2.765"/hr A(total) = 5.700 ac Fp = O.760"/hr C=.6'77 Q(subarea) = 7.23 cfs Q(total) = 1l.. 72 cfs _ u _ _ _ _ _ u _ u _ _ _ _ _ u _ _.. - - - - - - - - - - - - Summary - - - - - - u_ - - - - .. u - - - - - - -.. - -.. - - u - - - - Stream 2 to node 203 Length= 820 ft. 2.06 cfs/acre avg. A(tot)= 5.70 acres Tc= 7.50 min Q= 11.72 cfs ====================================================:===============:============ Record 6 Subarea 6 Stream 2 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach, Node 203 to node 104 Elev 1079.00 to elev 1077.00 delta H = 2.00' Length= 100' Slope= .02000 Subarea: .72 acre Soil: B, RI= 56' Development type 4 = 0.4 dwelling lacre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width = Xfall = ,02 'I' 8' pkwy @ ,02 'I' Tt= 0.39 min. based on Qavg= 12.37 cfs on one side of street. Davg=O,34' Aavg= 2.91 s.f. vavg= 4.26' Isec At end of reach: D = 0.35' (0.349) V = 4.23'/sec. D*V Flow area = 3.08 s.f. Street flooded width onE side Flow exceeds top of curb. Parkway flow: 0.78' wide x ai= .1 ,015 1 side 0" Hike = 0.0" Lip = .0011 = 1.A7 Sf = .02001 = 17.62' 0.02' deep, Q= D.O -----------------------------------------------------.-------------------------- Tc = 7.50 + 0,39 = 7.89 min. I = 2,689"/hr A(total) = 6.420 ac Fp . 0.754"/hr C=.673 Q(subarea) = 1.30 cfs Q(total) = 13.02 cfs ___________________________________ Summary ----------------------------------- Stream 2 to node 104 Length= 920 ft. 2.03 cfs/acre avg. A(tot)= 6.42 acres Tc= 7.89 min Q= 13,02 cfs This stream is designated for confluence with 1 other by record 3 ===================================================:============================ -# I I~ - -\ J I I I I I I I I I I I I I I I~ I File RCC07-10.DAT Runtime 10-25-2000 14:52 Job# RCC Page 4 Record 7 confluencing 2 streams at node 104 Process 9 Confluence constituent streams: Stream 1: Q= 9.38 Stream 2: Q= 13.02* Tc= Tc= 7.29 7.89 1= 2.809 1= 2.689 @ Tc' Stream 1 + Stream 2 = Confluenced ------------ 7.89 Q= Ratio= 8.98 + 12/11 13.02 = 22.00 cfs Qpeak = 22.00 cfs at Tc = 7.89 minutes Confluenced streams will be designated as stream # 1 to continue dcwnstream. ___________________________________ Summary ------..---------------------------- Stream 1 at node 104 Length= 930 ft. 2.10 cfs/acre avg, (c) A(tot)= 10.48 acres Tc= 7.89 min Q= 22,00 cfs ==================================================:;============================ Record 8 Subarea 7 Stream 1 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Remark: De Portola Rd Node 104 to node 105 Elev 1077.00 to elev 1075.90 delta H = 1.10' Length= 70' Slope= .01571 Subarea: 3.14 acres Soil: B, R1= 56 Development type 4 0.4 dwelling /acre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width = Xfall = .02 '/' Flow designated on 1 side but crown exceeded. 6.05 cfs spills to other side. Q on 1 side= 21.50 cfs for Tt of 0.26 min. Aavg=4.81 Davg=0.44' Vavg= 4.47 At end of reach: D = 0.44' (0.437) V = 4.47'/sec. D*V = 1,95 Sf = ,02582 Flow area = 4.81 s.f. Flooded width one side = 22.05' Flow exceeds top of curb. Plane of curb face extended up, pkwy ponded. ai= .1 .015 1 side 0" Hike:, O. 0" Lip = ,00" ------------------------------------------------------------------------------- Tc = 7.89 + 0.26 =. 8.15 min. I = 2.641"/hr A(total) = 13.620 ac A(contrib) = 13.620 ac Fp" 0.750"/hr C=.670 Q(subarea) = 5.56 cfs Q(totall = 27.56 cfs ___________________________________ Summary -------..--------------------------- Stream 1 to node 105 Length= 1000 ft. 2,02 cfs/acre avg. (cl A(tot)= 13.62 acres Tc= 8.15 min Q-' -. 27.56 cfs ===================================================~===============:============ ~ I 1 Ih I I I II I I I I I I I I I I 1 I", . .. I File RCC07-10.DAT Runtime 10-25-2000 14:52 Job# RCC Page 5 Record 9 Subarea 8 Stream 1 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Remark: to catch basin @ villa del Sur Node 105 to node 111 Elev 1075.90 to elev 1055.50 delta H = 20.40' Lensrth= 800' Slope= .02550 Subarea: 7.72 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling lacre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width = Xfall = .02 'I' 8' pkwy @ .02 'I' Flow designated on 1 side but crown exceeded. 12.71 cfs spills to other side, Q on 1 side= 26.13 cfs for Tt of 2.59 min. Aavg=4.81 Davg=0.44' Vavg= 5.14 At end of reach: D = 0.44' (0.437) V = 5.14'/sec. D*V = 2.25 Sf = .05683 Flow area = 5.08 s.f. Street flooded width one side = 22.00' Flow exceeds top of curb. Parkway flow: 5.17' wide x 0,10' deep, Q= 2,0 ai= .1 .015 1 side 0" Hike = 0,0" Lip = .00" --------------------------------------------------..---------------------------- Tc = 8,15 + 2.59 = 10.74 min. I = 2.269"/hr A(total) = 21.340 ac A(contrib) = 21.340 ac Fp = 0.717"/hr C=.644 Q(subarea) = 11.28 cfs Q(total) = 38.84 cfs ___________________________________ Summary ______n____________________________ Stream 1 to node 111 Length= 1800 ft, 1,82 cfs/acre avg. (c) A(tot)= 21.34 acres Tc= 10.74 min Q= 38.84 cfs This stream is designated for confluence with 1 other by record 13 ~=================================================:;============================ Process 8: Add a subarea at last nc.de Record 10 Subarea 9 Stream 1 Remark: Flow down Villa del Sur At node 111 Subarea: 6.7 acres Soil: D, RI= Development type 4 = 0.4 dwelling 75 lacre ai= .1 --------------------------------------------------.----------------------------- Tc = 10.74 min. I = 2.269"/hr A(total) = 28.040 ac A(contrib) = 28,040 ac Fp. 0.372"/hr C=.767 Q(subarea) = 11.66 cfs Q(total) = 50.50 cfs ___________________________________ Summary -------..--------------------------- Stream 1 to node 111 Length= 1800 ft. 1,80 cfs/acre avg. (c) A(tot)= 28.04 acres Tc= 10.74 min Q= 50.50 cfs ===================================================================:============ ;>\ I I ~I :1 I I I I I I I I I I I I I I~ I File RCC07-10.DAT Runtime 10-25-2000 14:52 Job# RCC Page 6 ******************************************************************** New Stream Record 11 Subarea 10 Stream 3 Process 1: Initial subarea Node 301 to node 302 Elev 1121.00 to elev 1068.00 delta H = 53,00' Length= 620' Slope= .08548 Subarea: 1.35 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre ai=.l --------------------------------------------------.----------------------------- k = .487 Tc = 10.43 min. I = 2.306"/hr A(total) = 1.350 ac Fp '" 0.720"/hr C=.E47 Q(subarea) = 2.01 cfs Q(total) = 2.01 cfs ___________________________________ Summary ------..---------------------------- Stream 3 to node 302 Length= 620 ft. 1.49 cfs/acre avg. A(tot)= 1.35 acres Tc= 10.43 min Q= 2.01 cfs ==================================================:============================= Record 12 Subarea 11 Stream 3 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed ;;.long reach. Node 302 to node 303 Elev 1068.00 to elev 1060.00 delta H = 8.00' Len<J'th= 230' Slope= .03478 Subarea: .92 acre Soil: B, RI= 56 Development type 4 = 0,4 dwelling /acre ai=.l V avg = 3.41'/sec for avg Q of 2,65 cfs ------------------------------------------------------------------------------- Tc = 10.43 + 1.12 = 11.55 min, I = 2.180"/hr A(totalj = 2,270 ac Fp '" 0.708"/hr C=,E,37 Q(subarea) = 1.28 cfs Q(total) = 3.29 cfs ________________________~__________ Summary ~~---~-..----------------~---------- Stream 3 to node 303 Length= 850 ft. 1,45 cfs/acre avg. A(tot)= 2.27 acres Tc= 11.55 .min Q- - 3.29 cfs ===================================================================:============ ,,!/'b I I, 'I I I I I I I I I I I I I I I I ,~ I File RCC07-10.DAT Runtime 10-25-2000 14:52 Job# R.CC Page 7 R.ecord 13 Subarea 12 Stream 3 Process 3: Street flow SubareaQ enters stream uniformly distributed along reach, Remark: along De portola to catch basin @ Villa del Sur Node 303 to node 111 Elev 1060.00 to elev 1055.50 delta H = 4.50' Length= 540' Slope= .00833 Subarea: 6.82 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width = Xfall = .02 '/' Tt= 3.31 min. based on Qavg= 7.25 cfs on one side of street. Davg=0.33' Aavg= 2.67 s.f. Vavg= 2.72'/sec l-.t end of reach: D = 0.39' (0,385) V = 2.99' /sec. D*V = 1.15 Sf = .00834 Flow area = 3.75 s,f. Flooded width one side" 19.45' Flow exceeds top of curb. Plane of curb face extended up, pkwy pcnded. ai= .1 .015 1 side 0" Hike = 0.0" Lip = .00" --------------------------------------------------..---------------------------- Tc = 11.55 + 3.31 = 14.86 min, I = 1.898"/hr A(total) = 9.090 ac Fp = 0.675"/hr C=.612 Q(subarea) = 7.92 cfs Q(total) = 11,21 cfs ___________________________________ Summary ------.----------------------------- Stream 3 to node 111 Length= 1390 ft. 1.23 cfs/acre avg. A(tot)= 9.09 acres Tc= 14.86 min Q= 11.21 cfs This stream is designated for confluence with 1 other by record 9 ==================================================:;~==============;============ Record 14 Remark: catch basin @ De Portola & Confluencing 2 streams at node 111 Process 9 Confluence Villa del Sur Constituent streams: Stream 1: Q= 50.50* Stream 3: Q= 11.21 Tc= 10.74 Tc= 14.86 1= 2.269 1= 1. 898 @ Tc Stream 1 + Stream 3 = Confluenced ------ -------- -------- 10.74 Q= 50.50 + 8.11 = Ratio= TC1/Tc3 58.61 cfs Qpeak = 58.61 cfs at Tc = 10.74 minutes Confluenced streams will be designated as stream # 1 to continue downstream. _ __ _ _ _ __ _ __ _ _ __ __ __ _ _ _ _ _ - - - -- - - -- - - Summary - - - - - - - .. .. - - - - - - - - - - - - - .. - -- - - - - - - -- - Stream 1 at node 111 Length= 1800 ft. 1.58 Cfs/acre avg. (c) A(tot)= 37,13 acres Tc- 10.74 min Q.- ,. 58.61 cfs ==================================================================::============ 1:>C\. I I _I I I I I I I I' I 1 I I I I I I'. '- I File RCC07-10.DAT Runtime 10-25-2000 14:52 Job# RCC Page 8 Record 15 Subarea 13 Stream 1 Process 8: Add a subarea at last node Remark: Half of DePortola Rd itself, although some drains into 2 or 3 driveways At node 111 Subarea: .63 acre Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.l __________________________________________________n____________________________ Tc = 10,74 min. I = 2_269"/hr A(total) = 37.760 ac A(contrib) = 37.760 ac Fp = O,474"/hr C=.731 Q(subarea) = 1.04 cfs Q(total) = 59.65 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 111 Length= 1800 ft. 1. 58 cfs/acre avg. (c) A(tot)= 37.76 acres Tc= 10.74 min Q= 59.65 cfs ==================================================::============================ Record 16 Subarea 14 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at downstream node. Remark: to NE RCC prop cor. Node 111 to node 112 Elev 1055.50 to elev 1049.40 delta H = 6.10' Length= 420' Slope= .01452 Subarea: 4.57 acres Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.l Max d = 2' Bottom width = 3' Sideslope Z = 1.5:1 (h:v) n = .03 Q= 59.65 cfs. Calc'd flow depth, D = 1.73 ft. v= 6.16' /sec, --------------------------------------------------.----------------------------- Tc = 10.74 + 1.14 = 11.88 min. I = 2.146"/hr A(total) = 42.330 ac A(contrib) = 42.330 ac Fp = 0.468"/hr C=.723 Q(subarea) = 7.09 cfs Q(total) = 66.75 cfs ___________________________________ Summary ------..---------------------------- Stream 1 to node 112 Length= 2220 ft. 1.58 cfs/acre avg. (c) A(tot)= 42,33 acres Tc= 11,88 min Q= 66,75 cfs This stream is designated for confluence with 1 other by record 19 ==================================================:;============================ ***************************************************1'**************** New Stream Record 17 Subarea 15 Stream 4 Process 1: Initial subarea Node 504 to node. 505 Elev 1063.00 to elev 1054.50 delta H = 8.50' Length= 700' Slope= .01214 Subarea: 4.59 acres Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.l ----------------------------------------------------.----------------~---------- k = .487 Tc = 16.17 min. I = 1.811"/hr A(total) = 4,590 ac Fp = O.450"/hr C=.E-99 Q(subarea) = 5.81 cfs Q(total) = 5.81 cfs ___________________________________ Summary -------..--------------------------- Stream 4 to node 505 Length= 700 ft. 1.27 cfs/acre avg. A(tot)= 4.59 acres Tc= 16.17 min Q-. -. 5.81 cfs ==;=;;====;===;=====;==============================~===============:============ AO I I I I I I I I I I I I I I I I I I'" I File RCC07-10.DAT Runtime 10-25-2000 14:52 Job# RCC Page 9 . , 4 Process 3: enters stream pattern Street flow uniformly distributed along reach. Record 18 Subarea 16 Stream Subarea Q Remark: Assumed future street Node 505 to node 508 Elev 1054.50 to elev 1048.00 delta H = 6.50' Subarea: 8.01 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 Street template 5 Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfall = .02 '/' Tt= 3,96 min. based on Qavg= 5.72 Davg=0.43' Aavg= 4.08 s.f. Vavg= At end of reach: D = 0.48' (0.482) Flow area = 5.70 s.f. Flooded Length= 670' Slope= .00970 ;: sides Hike = 2.0" Lip ;; .3811 cfs on each sidE! of street. 2.82' /sec V = 3.00'/sec. D*V = 1.44 width one side = 16.34' Sf = .00971 ---------------------------------------------------.---------------------------- Tc = 16.17 + 3.96 = 20,13 min. I = 1.606"/hr A(total) = 12.600 ac Fp ,,0.436"/hr C=,876 Q(subarea) = 11.26 cfs Q(total) = 17.07 cfs ___________________________________ Summary ------,---------------------------- Stream 4 to node 508 Length= 1370 ft. 1.35 cfs/acre avg. A(tot)= 12.60 acres Tc= 20.13 min Q= 17.07 cfs ==================================================::============================ Stream 4 112 1046,00 Process 7: Channel flow - Improved Record 19 Subarea 0 Node 508 to node Elev 1048.00 to elev Subarea: 0 acre Bottom width = 3' Sideslope Z = 1.5:1 (h:v) Q= 17.07 cfs. Calc'd flow depth, D = 1.16 ft. delta H = 2.00' Len9th= 360' Slope= .00556 n = .03 V= 3.10'/sec, --------------------------------------------------..---------------------------- Tc = 20.13 + 1.93 = 22.06 min. A(total) = 12.600 ac I = 1.527"/hr Q(total) = 17.07 cfs ___________________________________ Summary ------...--------------------------- Stream 4 to node 112 Length= 1730 ft. 1.35 cfs/acre avg, A(tot)= 12.60 acres Tc= 22.06 min Q" 17.07 cfs This stream is designated for confluence with 1 other by record 16 ===================================================================:============ J>.. \ I , I ,I I I I I I I I I I I I I I I I I File RCC07-10.DAT Runtime 10-25-2000 14:53 Job# RCC Page 10 Record 20 . " Confluencing 2 streams at node 112 Constituent streams: Stream 1: Q= 66.75* Stream 4: Q= 17.07 Process 9 Confluence Tc= 11. 88 Tc= 22.06 I= 2.146 I= 1. 527 @ Tc Stream 1 + Stream 4 = Confluenced ------------ ------ -------- 11.88 Q= 66.75 + Ratio= 9.19 = Tc1/Tc4 75.94 cfs Qpeak = 75.94 cfs at Tc = 11.88 minutes Confluenced streams will be designated as stream # 1 to continue downstream. _ _ __ _ _ _ _ _ __ _ __ _ _ _ _ _ _ __ __ _ __ -- - -- -- - Summary - -- - - - - --- - - - - - - - - - - - - - -" - - - - -- -- - -- Stream 1 at node 112 Length= 2220 ft. 1.38 cfs/acre avg. (c) A(tot)= 54.93 acres Tc= 11.88 min Q= 75.94 cfs ====================================================;:==============::=========== Record 21 Subarea 17 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at downst:ream node. Node 112 to node 403 Elev 44.30 to elev 40.85 delta H = 3.45' Subarea: 7.05 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre ai= Bottom width = 3' Sideslope Z = 1.5:1 (h:v) Q= 75,94 cfs. Calc'd flow depth, D = 2.52 ft. Length= 690' Slope= .00500 .1 n = .03 v= 4.44' /sec, ----------------------------------------------------..--------------.------------ Tc = 11.88 + 2.59 = 14.47 min. I = l,926"/hr A(tota1) = 61.980 ac A(contrib) = 61.980 ac Fp = O.679"/hr C=.615 Q(subarea) = 8.34 cfs Q(tota1) = 84.28 cfs ___________________________________ Summary ---------..------------------------- Stream 1 to node 403 Length= 2910 ft. 1.36 cfs/acre avg. (c) A(tot)= 61,98 acres Tc= 14.47 min Q= 84.28 cfs =============================================================================== Record 22 Subarea 18 Stream 1 Process 8: Add a subarea at last node At node 403 Subarea: 2.44 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 -----------------------------------------------------.-------------------------- Tc = 14.47 min. I = 1.926"/hr A(total) = 64.420 ac A (contrib) = 64.420 ac Fp = O.457"/hr C=.879 Q(subarea) = 4.13 cfs Q(total) = 88.41 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 403 Length= 2910 ft. 1.37 cfs/acre avg. (c) A(tot)= 64.42 acres Tc= 14.47 min Q= 88.41 efs ==================================================;:============================ ~7/ I I- I , I I I , I I I I I I I I - It I File RCC07-10.DAT Runtime 10-25-2000 14:53 Job# RCC Page 11 Record 23 Subarea 19 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at downst.ream node. Node 403 to node 404 Elev 40.85 to elev 39.50 delta H = 1.35' Subarea: 3.67 acres Soil: BC, RI= 63 Development type 4 = 0.4 dwelling /acre ai= Bottom width = 3' Sideslope Z = 1.5:1 (h;v) Q= 88.41 cfs, Calc'd flow depth, D = 2.71 ft. Length= 270' Slope= .00500 .1 n = .03 v= 4.62'/sec, -----------------------------------------------------.---------------.----------- Tc = 14.47 + 0.97 = 15,44 min. I = 1.858"/hr A(total) = 68.090 ac A(contrib) = 68.090 ac Fp = 0.551"/hr C=.660 Q(subarea) = 4.50 cfs Q(total) = 92.91 cfs _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - - - - - - - - - Summary - - - - - - - - .. - - - - - - - - - - - - - -.. - - - - - - - - - - - Stream 1 to node 404 Length= 3180 ft. 1.36 cfs/acre avg. (c) A(tot)= 68.09 acres Tc= 15,44 min Q= 92.91 cfs This stream is designated for confluence with 1 other by record 30 ;===================================================~=========================== , Record 24 Subarea 20 Stream 1 Process 8; Add a subarea at last node At node 404 Subarea: 1,01 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 ----------------------------------------------------..--------------..----------- TC = 15,44 min. I = 1.858"/hr A(total) = 69.100 ac A(contrib) = 69.100 ac Fp = 0.453"/hr C=.B78 Q(subarea) = 1,65 cfs Q(total) = 94.56 cfs _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - -.. - - - - - - - - Summary - - - - - - - -.... - - - - - - - - - - - - -.. - - - - - - - - - - - Stream 1 to node 404 Length= 3180 ft. 1.37 cfs/acre avg. (c) A(tot)= 69,10 acres Tc= J.5.44 min Q= 94.56 cfs ----------------------------------------------------.---------------.------------ ----------------------------------------------------.---------------.------------ ****************************************************'***************~ New Stream Record 25 Subarea 21 Stream 5 Process 1: Initial subarea Remark: Roof of future building. Node 510 to node 511 Elev 51.00 to elev_ 50.00 delta H = 1,00' Length= 100' Slope= .01000 Subarea; .1 acre Soil:C, RI= 69 Development type 14 = Commercial ai= .9 ------------------------------------------------------------------------------- k = .304 Tc = 4.82 min. I = 3,528"/hr A(total) = 0.100 ac Fp = 0.512"/hr C=.887 Q(subarea) = 0.31 cfs Q(total) = 0.31 cfs ___________________________________ Summary ---------..------------------------- Stream 5 to node 511 Length= 100 ft. 3.13 cfs/acre avg. A(tot)= 0.10 acres Tc= 4.82 min Q= 0.31 cfs ;;;=;=;;;========;===;===;====;==;;======;==;;==;=:;=::========================= A,?:> I File RCC07-10.DAT Runtime 10-25-2000 14:53 Job# RCC 11_. Record 26 Subarea 22 Stream 5 Process 3: Street flow . Subarea Q enters stream uniformly distributed a:',ong reach, '1, Remark: Future onsite driveway / parking bay with curb & gtr. Node 511 to node 512 Elev 50.00 to elev 48.20 delta H = 1.80' Length= 360' Slope= .00500 Subarea: .9 acre Soil: C, RI= 69 Development type 14 = Commercial ai= Street template 0 Half-width = 40' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfall = .02 '/' Tt= 3.93 min. based on Qavg= 1.32 Davg=0.32' Aavg= 0.87 s.f. Vavg= At end of reach: D = 0.37' (0.372) Flow area = 1.35 ~~ Flooded Page 12 'I J I I I I I I I I I I I J I .9 1 side Hike = 2.0" Lip = .38" cfs on one side of street. 1.53' /sec V = 1. 72' / sec ' width one side = D*V = 0.64 HI. 81' Sf = .00501 ----------------------------------------------------..--------------.------------ Tc = 4.82 + 3.93 = 8.75 min. I = 2,540"/hr A(total) = 1.000 ac Fp = O.485"/hr C=,8133 Q(subarea) = 2.02 cfs Q(total) = 2.33 cfs _ _ _ _ _ _ _ __ _ _ _ __ __ _ __ _ _ __ -- - - - - - - - - - - Summary - - - -- - -- ... - - - - - - -- - - - - - .- - - - - - - - - - -- Stream 5 to node 512 Length= 460 ft. 2.33 cfs/acre avg. A(tot)= 1.00 acres Tc= 8.75 min Q= 2.33 cfs =============================================================================== Record 27 Subarea 23 Stream 5 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach, Node 512 to node 513 Elev 48,50 to elev 47.44 delta H = 1.06' Length= 210' Slope= .00505 Subarea: 2.19 acres Soil: C, RI= 69 Development type 14 = Commercial ai= Street template 5 Half-width = 24' n = ,015 CF = 6" Batter= ,25 h/v Gutter width = 24" Xfall = ,02 '/' Tt= 1,95 min. based on Qavg= 2.26 Davg=0.36' Aavg= 2.54 s,f. Vavg= At end of reach: D = 0.41' (0.409) Flow area = 3. 58 s~'{.- Flooded .9 2 sides Hike ,. 2.0" Lip = .3811 cfs on each side of 1.80'/sec V = 1. 88' / sec. width one side = street. D*V = 0.77 12.68' Sf = .00506 ------------------------------------------------------------------------------- Tc = 8.75 + 1.95 = 10.70 min. I = 2.274"/hr A(total) = 3.190 ac Fp = 0.474"/hr C=,881 Q(subarea) = 4.39 cfs Q(total) = 6.72 cfs ___________________________________ Summary ----------------------------------- Stream 5 to node 513 Length= 670 ft. 2.11 cfs/acre avg. A(tot)= 3.19 acres Tc= 1D,7D min Q= 6.72 cfs ===================================================:============================ I M I I ./ ~--. i.1 ., I I I I I I I I I I I I I J 'I File RCC07-10,DAT Runtime 10-25-2000 14:54 Job# RCC Page 13 Record 28 Subarea 24 Stream 5 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Node 513 to node 513.5 Elev 47.44 to elev 45.70 delta H = 1.74' Length= 248' Slope= .00702 Subarea: 3.02 acres Soil: C, RI= 69 Development type 14 = Commercial ai= Street template 5 Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfall = .02 '/' Tt= 1.77 min. based on Qavg= 4.75 Davg=0.43' Aavg= 4.08 s.f. Vavg= At end of reach: D = 0.46' (0.461) Flow area = 5.01 s~f-:--' Flooded .9 2 sides Hike" 2.0" Lip = .3811 cfs on each side of street. 2.33'/sec V = 2.45'/sec. width one side " Sf = ,00702 D*V = 1.13 15.25' ------------------------------------------------------------------------------- Tc = 10.70 + 1,77 = 12.47 min. I = 2.090"/hr A(total) = 6,210 ac Fp ,,0.466"/hr C=.880 Q(subarea) " 5.55 cfs Q(total) = 12,27 cfs ___________________________________ Summary ---------.------------------------- Stream 5 to node 513.5 Length= 918 ft. 1.98 cfs/acre avg. A(tot)= 6,21 acres Tc= 12.47 min Q= 12.27 cfs =====================================================:========================== Record 29 Subarea 25 Stream 5 Process 5: Pipe flow, program-selected size All subarea Q enters stream at downstream node. Remark: Some park, but all tabled as all commercial. Node 513.5 to node 514 Pipeslope = 1 * grounds lope , n = .013 Elev 41.00 to elev 39.00 delta H = 2,00' Lenqth- 560' Slope= .00357 Subarea: 6.96 acres Soil: C, RI= 69 Development type 14 " Commercial ai= .9 12.27 cfs in 1 24" pipe (d = 2.00') Depth, D=1.49' D/d=.745 Sf" .00360 Hv=VA2/2g= 1.43' l,2Hv= 1.72' 1.5Hv= 2.15' Travel time X-Sect A= 2.51 sf, V= 4.89'/sec, Tt= 1.91 min. ------------------------------------------------------------------------------- Tc = 12.47 + 1.91 = 14.38 min. I" 1.932"/hr A(total) = 13.170 ac Fp = 0.457"/hr C".879 Q(subarea) " 11.82 cfs Q(total) = 24.09 cfs ___________________________________ Summary ------.---------------------------- Stream 5 to node 514 Length= 1478 ft. 1,83 cfs/acre avg, A(tot)= 13.17 acres Tc" 14.38 min Q" 24.09 cfs ===================================================:============================ ~-5 I ,~ I I I I I I I I I I I I I I I I- I File RCC07-10,DAT Runtime 10-25-2000 14:54 Job# 11CC Page 14 Stream 5 Process 404 Pipeslope = 36.20 delta H = 5: Pipe flow, Program-selected size 1 * groundslope. n = .013 1.80' Len9th= 360' Slope= .00500 Record 30 Subarea 0 Node 514 to node Elev 38,00 to elev Subarea: 0 acre 24.09 cfs in 1 30" pipe (d = 2,50') Depth, D=1.73' D/d=.692 Hv=VA2/2g= 0.69' 1.2Hv= 0.82' 1.5Hv= 1.03' Travel time X-Sect A= 3.62 sf, V= 6.65'/sec, Tt= 0.90 min. Sf = .00507 --------------------------------------------------..---------------------------- Tc = 14,38 + A(total) = 0.90 = 13.170 ac 15.28 min. I = 1.868"/hr Q(total) = 24.09 cfs ___________________________________ Summary ------.----------------------------- Stream 5 to node 404 Length= 1838 ft. 1.83 cfs/acre avg, A(tot)= 13.17 acres Tc= 15.28 min Q= 24.09 cfs This stream is designated for confluence with 1 other by record 23 ==================================================:=~=========================== Record 31 Confluencing 2 streams at node 404 Process 9 Confluence Constituent streams: Stream 1: Q= 94.56* Stream 5: Q= 24.09 Tc= 15.44 Tc= 15.28 l= 1. 858 l= 1. 868 @ Tc Stream 1 + Stream 5 = Confluenced 15.44 Q= 94.56 + Ratio= 23.95 = I1/l5 118,51 cfs Qpeak = 118,51 cfs at Tc = 15,44 minutes Confluenced streams will be designated as stream # ], to continue downstream. _ __ _ _ _ __ _ _ _ _ - - - - -- - - - -- - - - - - - - -- - - - Summary - - - -- - - - - - - - - - - -- - - - - -- - - - - - - -- - - - - Stream 1 at node 404 Length= 3180 ft. 1,44 cfs/acre avg. (c) A(tot)= 82.27 acres Tc= 15.44 min Q- 118.51 cfs ===================================================~===============,============ Afa II I t "I t , I I I I , I I I I I I I I File RCC07-10.DAT Runtime 10-25-2000 14:54 Job# RCC Page 15 Record 32 Subarea 26 Stream 1 Process 5: Pipe flow, Program-selected size All subarea Q enters stream at downstream node. 'Remark: 1/2 Hardscape, 1/2 Play area. Node 404 to node 405 Pipeslope = 1 · groundslope. n = .013 Elev 34.20 to elev 30.59 delta H = 3,61' Length= 530' Slope= ,00681 Subarea: 2.8 acres Soil: C, RI= 69 Development type 14 = Commercial ai= ,9 118,51 cfs in 1 51" pipe (d = 4,25') Depth, D=3.01' D/d=.708 Sf = ,00682 Hv=V^2/2g= 2.04' 1.2Hv= 2.44' 1.5Hv= 3,05' Travel time X-Sect A= 10.74 sf, V=11.03'/sec, Tt= 0.80 min. -----------------------------------------------------..------------------------- Tc = 15.44 + 0.80 = 16.24 min, I = 1,807"/hr A(total) = 85.070 ac A(contrib) = 85.070 ac Fp = 0.450"/hr C=.878 Q(subarea)'= 4.44 cfs Q(total) = 122.95 cfs ___________________________________ Summary ---------,.------------------------- Stream 1 to node 405 Length= 3710 ft. 1.45 cfs/acre avg. (c) A(tot)= 85.07 acres Tc= 16.24 min Q= 122.95 cfs -----------------------------------------------------.-------------------------- -----------------------------------------------------.-------------------------- Record 33 Subarea 27 Stream 1 Process 8: Add a subarea at last node Remark: Inlet for residential lots. At node 405 Subarea: 4.39 acres Soil: BC, RI= 63 Development type 4 = 0.4 dwelling /acre ai=.1 -----------------------------------------------------.-------------------------- Tc = 16.24 min. I = 1.807"/hr A(total) = 89.460 ac A(contrib) = 89.460 ac Fp = O.546"/hr C=.655 Q(subarea) = 5,20 cfs Q(total) = 128,15 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 405 Length= 3710 ft. 1.43 cfs:/acre avg. (c) A(tot)= 89,46 acres Tc= 16.24 min Q= 128,15 cfs ===================================================:============================ Record 34 Subarea 28 Stream 1 Process 5: Pipe flow, Program-selected size All subarea Q enters stream at downstream node, = .013 Slope= .00680 Node 405 to node. 407 Pipeslope = 1 . groundslope. n Elev 30.59 to elev 27.26 delta H = 3.33' Length= 490' Subarea: 6.22 acres Soil: BC, RI= 63 Development type 4 = 0.4 dwelling /acre ai=.1 128.15 cfs in 1 51" pipe (d = 4.25') Depth, D=3.21' D/d=.755 Hv=V^2/2g= 2.15' 1.2Hv= 2.58' 1.5Hv= 3.23' Travel time X-Sect A= 11.50 sf, V=11.15' /sec, Tt= 0.73 min. Sf = .00682 --------------------------------------------------..---------------------------- Tc = 16.24 + 0,73 = 16.97 min. I = i.764"/hr A(total) = 95.680 ac A(contrib) = 95.680 ac Fp = 0.542"/hr C=.651 Q(subarea) = 7.14 cfs Q(total) = 135.29 cfs ___________________________________ Summary ______n____________________________ Stream 1 to node 407 Length= 4200 ft. 1. 41 cfs/acre avg. (c) A(tot)= 95.68 acres Tc= 16.97 min Q= 135,29 cfs ==================================================:;===============;:============ 1\"\ I 1- " ,. J I - I . .,. I - i . I i I i i ~. I i .. File RCC07-10.DAT Runtime 10-25-2000 14:54 Job# RCC Page 16 Record 35 Subarea 29 Stream 1 Process 8: Add a subarea at last node At node 407 Subarea: 1.28 acres Soil: C, RI= 69 Development type 14 = Commercial ai= ,9 ------------------------------------------------------.------------------------- Tc = 16.97 min. I = 1. 764"/hr A(total) = 96.960 ac A(contrib) = 96.960 ac Fp = O.447"/hr C=.877 Q(subarea) = 1.98 cfs Q(total) = 137.27 cfs ___________________________________ Summary ---------..------------------------- Stream 1 to node 407 Length= 4200 ft. 1.42 cfs/acre avg. (c) A(tot)= 96.96 acres Tc= 16.97 min Q= 137,27 cfs ====================================================~========================== Record 36 Subarea 30 Stream 1 Process 5: Pipe flow, program-selected size All subarea Q enters stream at downscream node. Node 407 to node 409 Pipeslope = 1 * groundslope. n = .013 Elev 27.26 to elev 24.60 delta H = 2.66' Length" 390' Slope= .00682 Subarea: 3.75 acres Soil: C, RI= 69 Development type 14 = Commercial ai= ,9 137.27 cfs in 1 51" pipe (d = 4.25') Depth, D=3.42' D/d=.805 Sf = .00683 Hv=V^2/2g= 2.12' 1.2Hv= 2.54' 1.5Hv= 3.18' Travel time X-Sect A= 12.24 sf, V=11.21'/sec, Tt= 0.58 min. ------------------------------------------------------------------------------- Tc = 16.97 + 0.58 = 17.55 min, I = 1.731"/hr A(total) = 100.710 ac A(contrib) = 100,710 ac Fp = O,445"/hr C=.877 Q(subarea) = 5.69 cfs Q(total) = 142.96 cfs ___________________________________ Summary ---------..------------------------- Stream 1 to node 409 Length= 4590 ft. 1.42 cfs/acre avg. (c) A(tot)=100.71 acres Tc= 17.55 min Q= 142.96 cfs =====================================================:========================== Record 37 Subarea 31 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at downstream node. Node 409 to node 121 Elev 24.60 to elev 24.00 delta H = 0.60' Length" 120' Slope= ,00500 Subarea: 4.35 acres _ Soil: BC, RI= 63 Development type 4 = 0.4 dwelling /acre ai=.l Max d = 4' Bottom width = 5' Sideslope Z = 1.5:1 (h:v) n = .03 Q=142.96 cfs. Calc'd flow depth, D = 2.95 ft. V= 5.14'/sec, ------------------------------------------------------------------------------- Tc = 17,55 + 0.39 = 17,94 min. I = 1.710"/hr A(total) = 105.060 ac A (contrib) = 105.060 ac Fp = 0.537"/hr C=.646 Q(subarea) = 4.80 cfs Q(total) = 147.76 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 121 Length= 4710 ft. 1.41 cfs/acre avg. Ic) A(tot)=105.06 acres Tc= 17.94 min Q= 147.76 cfs This stream is designated for confluence with 1 other by record 44 ===================================================:============================ .1,'0 I 1__ I 'I I I I I I I I ~ I I I I I I I-- I File RCC07-10.DAT Runtime 10-25-2000 14:55 Job# ReC Page 17 ******************************************************************~* New Stream Record 38 Subarea 32 Stream 6 Process 1: Initial subarea Node 516.2 to node 516.3 Elev 43.60 to elev 42.00 delta H = 1.60' Length= 180' Slope., ,00889 Subarea: .38 acre Soil: C, RI= 69 Development type 14 = Commercial ai= .9 ------------------------------------------------------------------------------- k = .304 Tc = 6.24 min. I = 3.060"/hr A(total) = 0,380 ac Fp = 0.501"/hr C=.E:85 Q(subarea) = 1.03 cfs Q(tot:al) = 1.03 cfs ___________________________________ Summary -------..--------------------------- Stream 6 to node 516.3 Length= 180 ft. 2.71 cfs/acre avg. A(tot)= 0.38 acres Tc~ 6.24 min Q-. -' 1. 03 cfs ===================================================================:============ Record 39 Subarea 33 Stream 6 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Node 516.3 to node 515 Elev 42.00 to elev 38.60 delta H = 3.40' Lengt.h= 450' Slope~' .00756 Subarea: 1.66 acres Soil: C, RI= 69 Development type 14 = Commercial ai= Street template 5 Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfall = .02 '/' Tt= 4,11 min. based on Qavg= 1.36 Davg=O,31' Aavg= 1.51 s.f. Vavg= ]I.t: end of reach: D = 0.35' (0,348) Flow area = 2.21 s~~~ Flooded .9 2 sides Hike = 2.0" Lip -' .38" cfs on each side of street, 1. 83' /sec V = 2,OO'/sec. width one side = Sf = .00757 D*V = 0,70 9.58' --------------------.-----~-----~-----------------_._--------------..------------ Tc = 6,24 + 4.11 = 10.35 min. I = 2.316"/hr A(t:otal) = 2.040 ac Fp = O,476"/hr C=,B82 Q(subarea) = 3.39 cfs Q(total) = 4.42 cfs _ _ _ _ _ _ __ .... .. __ _ .. _ _ __ _ _ - -- -- - - - -- - - - - Summary .. -- .. - - -" - - -- - - - -- - - .. -- .... - .. -- -- - - -- - Stream 6 to node 515 Length= 630 ft. 2.17 cfs/acre avg. A(tot)= 2.04 acres Tc= 10.35 min Q,. ,- 4,42 cfs ====================~=============================================:~============ A.~ I I "I I I I I I I I I I I I I I I I- I File RCC07-10.DAT Runtime 10-25-2000 14:55 Job# RCC Page 18 .1 Record 40 Subarea 34 Stream 6 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Node 515 to node 516 Elev 38.60 to elev 36.50 delta H = 2.10' Length= 275' Slope" .00764 Subarea: 4.88 acres Soil: C, RI= 69 Development type 14 = Commercial ai= Street template 5 Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfall = .02 '/' Tt= 1.90 min. based on Qavg= 4.48 Davg=0.42' Aavg= 3.74 s.f. Vavg= At end of reach: D = 0.47' (0.467) Flow area = 5.22 ~~ Flooded .9 2 sides Hike = 2.0" Lip .. .3811 cfs on each side of street. 2.41'/sec V = 2.58'/sec. width one side = Sl: = .00764 D*V = 1.21 15.58' ---------------------------------------------------..--------------..------------ Tc = 10.35 + 1.90 = 12.25 min. I = 2.111"/hr A(total) = 6.920 ac Fp = 0.467"/hr C=.B80 Q(subarea) = 9.06 cfs Q(total) = 13.48 cfs _ _ _ _ __ _ __ __ _ _ _ -- -- - -- - - - -- - .. -- - - - .. - Summary -- - - - -- .. - - -.. - - -.. - -- -- - .. -- - - - -- - -- - - Stream 6 to node 516 Length= 905 ft. 1.95 cfs/acre avg. A(tot)= 6.92 acres Tc= 12.25 min Q.. .. 13.48 cfs ==================================================================::============ ******************************************************************,:* New Stream Record 41 Subarea 35 Stream 7 Process 2: User-specified info at node Remark: Part of flow to C.B. into Hyw 79 S.D: 1.70 ac @ 1.95 cfs/ac = 3.32 cfs At node 517 A(total)= 5.210 acres Tc = 12.25 minutes Q = 10,16 cfs ==================================================================::============ Record 42 Subarea 36 Stream 7 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Node 517 to node 518 Elev 36.60 to elev 34.13 delta H = 2.47' Length= 495' Slope: .00499 Subarea: 2.05 acres Soil: C, RI= 69 Development type 14 = Commercial ai= Street template 5 .Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfa11 = ,02 '/' Tt= 3.78 min. based on Qavg= 5.90 Davg=O,47' Aavg= 5.40 s,f. Vavg= At end of reach: D = 0.49' (0.495) Flow area = 6.11 s...C"-' Flooded ,9 2 sides Hike = 2.0" Lip ,. .38" cfs on each side of street. 2.18'/sec V = 2.20'/sec. width one side = Sf = .00500 D*V = 1.09 16.97' ------------------------------------------------------------------.------------- Tc = 12,25 + 3.78 = 16.03 min. I = 1.820"/hr A(total) = 7.260 ac Fp = 0.451"/hr C=.878 Q(subarea) = 3.28 cfs Q(total) = 13,44 cfs _ _ _ _ __ _ _ .. _ - -- -- - .. .. - -- - .. -- -- - - - - - - - - Summary .. -- - - .. - ... - - -- -- -- - .. - - - .- - - - .. - - - - -- -- Stream 7 to node 518 Length= 495 ft. 1.85 cfs/acre avg. A(tot)= 7.26 acres Tc= 16.03 min Q= 13.44 cfs =============================================================================== ~o I I J I I , I I I I I I I I- I I I I- I File RCC07-10.DAT Runtime 10-25-2000 14:55 Job# RCC Page 19 Record 43 Subarea 37 Stream 7 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Node 518 to node 520 Elev 34,14 to elev 30.50 delta H = 3.64' Length,. 330' Slope= .01103 Subarea: 2.66 acres Soil: C, RI= 69 Development type 14 = Commercial ai= Street template 5 Half-width = 24' n = .015 CF = 6" Batter= .25 h/v Gutter width = 24" Xfa11 = .02 'I' Tt= 1.78 min. based on Qavg= 7.72 Davg=0.46' Aavg= 5,00 s.f. Vavg= At end of reach: D = 0.48' 10.477) Flow area = 5.52 s,f. . Flooded .9 2 sides Hike ,. 2.0" Lip :; .3811 cfs on each side of street. 3.09'/sec V = 3.16'/sec. width one side = Sf = ,01103 D*V = 1.51 16.06' ------------------------------------------------------------------------------- Tc = 16,03 + 1.78 = 17.81 min. I = 1.718"/hr A(total) = 9.920 ac Fp = 0.444"/hr C=.877 Q(subarea) = 4.01 cfs Q(total) = 17,44 cfs ___________________________________ Summary ---------..------------------------- Stream 7 to node 520 Length= 825 ft. 1.76 cfs/acre avg. A(tot)= 9.92 acres Tc= 17.81 min Q= 17.44 cfs ====:;======:;=====:;========:;:;================:;==:;=====:========:;=:=========:;===:; Record 44 Subarea 38 Stream 7 Process 4: valley gutter section flow Subarea Q enters stream uniformly distributed along reach. Node 520 to node 121 Elev 30,50 to elev 28.10 delta H = 2,40' Length,. 300' Slope= .00800 Subarea: 1.71 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 valley gutter template'2 Section width = 24' ~ = .015 Gutter width = 3' Hike = 1,5" Lip = ,38" Pav't X-fall = .02 'I' Tt based on Qavg= 18.67 cfs Davg=0.47' Aavg= 5.61 sf. Vavg= 3.33 fps At end of reach: D = 0.47' (0.470) V = 3.55'/sec. D*V = 1.67 Sf = .00806 Flow area = 5.61 s.f. Flooded width = 24.00' Flow exceeds edge of pavement. Vertical curbs assumed both sides. __________________________________________________8____________________________ Tc = 17.81 + 1.50 =- 19.31 min. I = 1.643"/hr A(total) = 11.630 ac Fp = O,439"/hr C=.876 Q(subarea) = 2.46 cfs Q(total) = 19.90 cfs ___________________________________ Summary ----------------------------------- Stream 7 to node 121 Length= 1125 ft. 1.71 cfs/acre avg. A(tot)= 11.63 acres Tc= 19,31 min Q= 19.90 cfs This stream is designated for confluence with 1 other by record 37 ==:;======:;:;===========:;=========================:;==:=====:;===:;==:;==:;============ ?\ I I~- . ~ I -I I I I I I I. I I I I I I I I, I File RCC07-10.DAT Runtime 10-25-2000 14:55 Job# RCC Page 20 Record 45 Confluencing 2 streams at node 121 Process 9 Confluence Constituent streams: Stream 1: Q= 147.76* Stream 7: Q= 19.90 Tc= 17.94 Tc= 19.31 1= 1. 710 1= 1. 643 @ Tc Stream 1 + Stream 7 = Confluenced 17.94 Q= 147.76 + Ratio= 18.49 = Tcl/Tc7 166.26 cfs Qpeak = 166.26 cfs at Tc = 17.94 minutes Confluenced streams will be designated as stream # 1 to continue downstream. ___________________________________ Summary --------.--------------------------- Stream 1 at node 121 Length= 4710 ft. 1,42 cfs/acre avg. (c) A(tot)=116.69 acres Tc= 17.94 min Q- 166.26 cfs ;;============================================================================= Record 46 Subarea 39 Stream 1 Process 7: Channel flow - Improve6 All subarea Q enters stream at downstream node. Node 121 to node 122 Elev 24.00 to elev 21.48 delta H = 2.52' Len!jth= 505' Slope: .00499 Subarea: 3.15 acres Soil: BC, RI= 63 Development type 4 = O.~ dwelling /acre ai= ,1 Max d = 4' Bottom width = 5' Sideslope Z = 1,5:1 (h:v) n = .03 Q=166,26 cfs. Calc'd flow depth, D = 3.18 ft. V= :;.35' /sec, ------------------------------------------------------------------------------- Tc = 17.94 + 1.57 = 19.52 min. I = l,633"/hr A(total) = 119.840 ac A(contrib) = 119.840 ac Fp" 0.529"/hr C=.637 Q(subarea) = 3.28 cfs Q(total) = 169.54 cfs ___________________________________ Summary -------..--------------------------- Stream 1 to node 122 Length= 5215 ft. 1.41 cfs/acre avg. (c) A(tot),,119.84 acres Tc" 19.52 min Q= 169.54 cfs ==================================================================;:============ Record 47 Subarea 40 Stream 1 Process 8: Add a subarea at last node At node 122 Subarea: 3.08 acres Soil: C, RI= 69 Development type 14 = Commercial ai= .9 ----------------------------------------------------.---------------.------------ Tc = 19.52 min. I = 1.633"/hr A{total) = 122.920 ac A(contrib) = 122.920 ac Fp" O.438"/hr C=.876 Q(subarea) = 4.41 cfs Q(total) = ~73.94 cfs ___________________________________ Summary -------..--------------..------------ Stream 1 to node 122 Length= 5215 ft. 1.42 cfs/acre avg. (c) A(tot)=122.92 acres Tc= 19.52 min Q= 173.94 cfs ===================================================~==============::============ 61/ I 1 I. I I, I I I. I I I I I I I I I I- I File RCC07-10.DAT Runtime 10-25-2000 14:56 Job# RCC Page 21 now - stream soccer Improved at downstream fields. node. Record 48 Subarea 41 Stream 1 Process 7: Channel All subarea Q enters Remark: To NE cor ball fields. Not including ball & Node 122 to node 123 Elev 21.48 to elev 20.00 delta H = 1.48' Length= 290' Subarea: 5.01 acres Soil: BC, RI= 63 Development type 4 = 0.4 dwelling /acre ai= Botto~ width = 5' Sideslope Z = 1.5:1 (h:v) Q=173.94 cfs. Calc'd flow depth, D = 3,23 ft, Slope= ,00510 .1 n = .03 v= 5.47'/sec, ------------------------------------------------------------------------------- Te = 19.52 + 0.88 = 20.40 min. I = 1.594"/hr A(total) = 127.930 ac A(contrib) = 127,930 ac Fp = 0.525"/hr C=.633 Q(subarea) = 5.06 cfs Q(total) = 179.00 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 123 Length= 5505 ft. 1.40 cfs/acre avg. Ie) A(tot)=127.93 acres Tc= 20.40 min Q= 179,00 cfs ------------------------------------------------------------------------------- ------------------------------------------------------------------------------- Record 49 Subarea 42 Stream 1 Process 7: Channel flow - Improved All subarea Q enters: stream at downstream node. Node 123 to node 124 Elev 20,00 to elev 18.20 delta H = 1.80' Length. 360' Slope= .00500 Subarea: 3.15 acres Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.l Max d = 4' Bottom width = 8' Sideslope Z = 1.5:1 (h:v) n = .03 Q=179.00 cfs. Calc'd flow depth, D = 2.76 ft. V= 5.34'/sec, ---------------------------------------------------.---------------------------- Tc = 20,40 + 1.12 = 21,52 min. I = 1.547"/hr A(total) = 131.080 ac A(contrib) = 131.080 ac Fp = 0.432"/hr C=.674 Q(subarea) = 3.29 cfs Q(total) = 182.28 efs ___________________________________ Summary ------..---------------------------- Stream 1 to node 124 Length= 5865 ft. 1.39 cfs/acre avg. (c) A(tot)=131.08 acres Tc= 21.52 min Q= 182,28 cfs ;=================================================;============================= ?~ I I I I I I I I I I I I I I I I I I I Por. File RCC07-10.DAT Runtime 12-18-2001 17:24 Job# RCC ID-ur Page 22 Record 50 Subarea 43 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at downstream node. Remark: 25% park, 75% commercial. Node 124 to node 190 Elev 18.20 to elev 16.00 delta H = 2.20' r,ength= 470' Slope= .00468 Subarea: 9.07 acres Soil: C, RI= 69 Development type 15 = User's fraction / mix ai:o .7125 Max d = 4' Bottom width = 10' Sideslope Z = 1.5:1 (h:v) n = .03 Q=182.28 cfs. Calc'd flow depth, D = 2.57 ft. V= 5.12'/sec, ------------------------------------------------.------------------------------- Tc = 21.52 + 1.53 = 23.05 min. A(total) = 140.150 ac A(contrib) = Q(subarea) = 11.16 cfs I = 1.490"/hr 140.150 ac Fp = 0.427"/hr C=.826 Q(total) = 193.44 cfs ----------------------------------- Summary ----------------------------------- Stream 1 to node 190 Length=6,335 , 1.38 cfs/acre avg. (c) A(tot)=140.15 acres Tc= 23.05 min Q= 193.44 cfs ================================================:=============================== Record 51 Subarea 44 Stream 1 Process 7: Channel flow - Improved All subarea Q entcers stream at downstream node. Remark: To Jed. Smith Rd. @ Hwy 79 Node 190 to node 191 Elev 16.00 to elev 11.56 delta H = 4.44' r,ength= 370' Slope= ,01200 Subarea: .78 acre Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.1 Max d = 4' Bottom width = 10' Sideslope Z = 2:1 (h:v) n = .015 Q=193.44 cfs. Calc'd flow depth, D = 1.34 ft. V=11.38'/sec, Tc = 23,05 + 0.54 = 23.59 min. A(total) = 140.930 ac A(contrib) = Q(subarea) = 0.76 cfs I = 1.471" /hr 140.930 ac Fp = 0.426"/hr C=.666 Q(total) = 194.21 cfs - - - - - - - - - - -. - - - - - - - - - - - - - - - - - - - - - - - - Summary -" - .. - - - - - - - - - - .. - - - - - - - .. - .. - - - - - - .. - - .. Stream 1 to node 191 Length=6, 705' 1,38 cfs/acre avg. (c) A(tot)=140.93 acres Tc= 23.59 min Q= 194.21 cfs ------------------------------------------------.------------------------------- ------------------------------------------------.------------------------------- +++++++++++++++++++++++++++++++++++++++++++++++~.+++++++++++++++++++++++++++++++ Other: Stream 2 : Len= 920' Atot= 6,42 ac Tc= 7.89 min Q= 13.02 cfs Stream 3 : Len= 1390' Atot= 9.09 ac Tc= 14.86 min Q= 11.21 cfs Stream 4 : Len= 1730' Atot= 12.60 ac Tc= 22.06 min Q= 17.07 cfs Stream 5 : Len= 1838' Atot= 13 .17 ac Tc= 15.28 min Q= 24.09 cfs Stream 6 : Len= 905.' Atot= 6.92 ac Tc= 12.25 min Q= 13 .48 cfs Stream 7 : Len= 1125' Atot= 11.63 ac Tc= 19.31 min Q= 19.90 cfs ------------------------------------------------.------------------------------- -------.-----------------------------------------.------------------------------- End of RMH run for file RCC07-10.DAT -9\ I I I I I I I I I I I I I I I I I I I RMH RC ver 6.4b Nov. 2000 RATIONAL METHOD HYDROLOGY Riverside County (C) Copyright 1999 Jack P. Norris, Tel 909-676-5816, Fax 676-0016 SiN 0 Jack P. Norris, RCE, 33055 Vi no way, Temecula CA 92591 909-676-5816 File: RCCEXIST.DAT 30 records Runtime: 10-26-2000 09:47 Page 1 By JPN Work code 8 Job# RCC +----------------------------------------------..------------------------------+ Rancho Community Church site, Hwy 79S, Temecula Existing condition +----------------------------------------------..------------------------------+ Schematic diagram. Legend: Node number! Link text: record number + process name Streams: 2 3 4 5 301 llInit 302 12Chan 303 13Stre 504 18Init 505 19Chan 506 20Chan 601 25Init 602 26Chan 603 27Chan 604 28Chan 101 201 lInit 4Init 102 202 2Chan 5Chan 103 203 3Stre 6Stre 104 <----' 8Stre 105 9Stre III <___ <~_____~J 16Chan 112 17Chan 707 <--- <------ <-------' 22Chan 708 23Chan 709 24Chan 710 <--- <------ <------ <-------' 30Chan 190 51 c,,""~ q,o.cl.e,). t~(40(j\ 1'\1 ':/> ,I I -I :1 .'1 I I I I I I I I I I I I I I RMH RC ver 6.4a Sept 2000 RATIONAL METHOD HYDROLOGY (ClCopyright 1999 Jack P. Norris, Tel 909-676-5816, SiN 0 Jack P. Norris, RCE, 33055 Vino Way, Temecula Riverside County Fax 676-0016 CA 92591 909-676-5816 Runtime: 10-06-2000 10:28 Page 1 ~.. File: RCCEXIST.DAT 20 records By JPN Work code 8 Job# RCC Frequency: 100 - yr. I =12.357 TcA-.550 Min. pipe size: 18" Legend: (i)=input (c)=computed 100-yr 1-hr D= 1.3" (il, -Loglog slope of I-D cu~ve = .55 (i) Initial subarea Tc by Kirpich formula: Tc = k (DistA3 / deltaH)A.2 +---------------------------------------------------_.-------------------------+ Rancho Community Church site, Hwy 79S, Temecula Existing condition +-----------------------------------------------------------------------------+ Record 1 Subarea 1 Node 101 to node Elev 1208.50 to elev Subarea: .64 acre Development type 4 = Process 1: Initial s:ubarea Stream 1 102 1158.00 delta H = Soil: D, RI= 75 0.4 dwelling /acre 50.50' Length,= 210' Slope= .24048 ai= .1 ------------------------------------------------------------------------------- k = .487 Tc = 5.50 min. I = 4.840"/hr A(total) = 0.640 ac Fp =, 0.407"/hr C=.832 Q(subarea) = 2.58 cfs Q(total) = 2.58 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 102 Length= 210 ft. 4.03 cfs/acre avg. A(tot)= 0.64 acres Tc= 5.50 min Q= 2.58 cfs ---------------------------------------------------.---------------------------- ---------------------------------------------------.---------------------------- Record 2 Subarea 2 Stream 1 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 102 to node 103 Elev 1158.00 to elev 1119.00 delta H = 39.00' Len,rth= 320' Slope= .12188 Subarea: 2.2 acres Soil: D, RI= 75 Development type 4 = 0.4 dwelling /acre V avg = 7,90'/sec for avg Q of 6.71 cfs ai= ,1 --------------------------------------------------..---------------------------- Tc = 5.50 + 0.67 = 6.17 min. I = 4.541"/hr A(total) = 2.840 ac Fp ,,0.405"/hr C=,E28 Q(subarea) = 8.27 cfs Q(total) = 10.85 cfs ___________________________________ Summary ------..---------------------------- Stream 1 to node 103 Length= 530 ft. 3.82 cfs/acre avg. A(tot)= 2.84 acres Tc: 6.17 min Q= 10.85 cfs ;==;==;===================================;=======::============================ .g, I I ;1 o' I I I . r I I . . I I . . . I I i I -t- I File RCCEXIST.DAT Runtime 10-06-2000 10:28 Job# ~.CC Page 2 Record 3 Subarea 3 Stream 1 Process 3: Street flow Subarea Q enters stream unifornuy distributed along reach. Remark: Verde Drive Node 103 to node Elev 1119.00 to elev Subarea: 1.22 acres Development type 4 = Street template 0 CF = 6" Batter= Xfall = .02 '/' Tt= 0.97 min. based on Qavg= 6.37 Davg=0.19' Aavg= 1.85 s.f. Vavg= At end of reach: D = 0.20' (0.203) Flow area = 2,07 s.f. Flooded Flow exceeds crown. 104 1077.00 delta H = 42.00' Soil: B, RI= 56 0.4 dwelling /acre ai=.l Half-width = 10' n = .015 .25 h/v Gutter width = 0" Length= 400' Slope= .10500 ~: sides HikE' = 0, 0" Lip = .00" cfs on each sidE' of street. 6.89'/sec V = 7.05'/sec. D*V = 1.43 width = 19.85' Sf .10527 ---------------------------------------------------.---------------------------- Tc = 6.17 + 0.97 = 7.14 min. I = 4.192"/hr A(total) = 4.060 ac Fp = 0.838"/hr C=.738 Q(subarea) = 3.77 cfs Q(tota1) = 14.62 cfs ___________________________________ Summary ------..---------------------------- Stream 1 to node 104 Length= 930 ft. 3,60 cfs/acre avg. A(tot)= 4.06 acres Tc= 7.14 min Q= 14.62 cfs This stream is designated for confluence with 1 other by record 6 ==:====;==========================================::;=========================== **************************************************~r***************** New Stream Record 4 Subarea 4 Node 201 to node Elev 1201.00 to elev Subarea: 1.84 acres Development type 4 = Stream 2 Process 1: Initial Bubarea 202 1123.00 delta H = 78.00' Lenqt.h= 300' Soil: D, RI= 75 0.4 dwelling /acre ai=.l Slope" .26000 ----------------------------------------------------.--------------------------- k = .487 Tc = 6,24 min. I = 4.513"/hr A(total) = 1.840 ac Fp = 0.405"/hr C=,fi27 Q(subarea) 6.87 cfs Q(total) = 6,87 cfs _ .. _ _ __ _ _ __ .. __ _ _ __ _ _ _ _ _ - -- - - - - - -- - - - Summary -.. -- - - ... - - - - - - - - - - - - - - - - - - - - -- - - --- Stream 2 to node 202 Length= 300 ft. 3,73 cfs/acre avg. A(tot)= 1.84 acres Tc= 6.24 min Q., -- 6.87 cfs ===================================================~==============::============ 5\ ,I I I I I I I I I I I I I I I I I I I File RCCEXIST.DAT Runtime 10-06-2000 10:28 Job# RCC Page 3 Record 5 Subarea 5 Stream 2 Process 7: Channel flow - Natural Va.lley Subarea Q enters stream uniformly distributed a.long reach. Node 202 to node 203 Elev 1123.00 to elev 1079.00 delta H = 44.00' Length= 520' Slope: .08462 Subarea: 3.86 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling lacre ai=.l V avg = 7.74'/sec for avg Q of 12.72 cfs --------------------------------------------------.----------------------------- Tc = 6.24 + 1.12 = 7.36 min. I = 4.121"/hr A(total) = 5.700 ac Fp ,,0.835"/hr C=.736 Q(subarea) = 11.71 cfs Q(total) = 18.58 cfs ___________________________________ Summary ------..---------------------------- Stream 2 to node 203 Length= 820 ft. 3.26 cfs/acre avg. A(tot)= 5.70 acres Tc= 7.36 min Q= 18.58 cfs ;;================================================::============================ Record 6 Subarea 6 Stream 2 Process 3: Street flow Subarea Q enters stream unifonnly distributed along reach. Node 203 to node 104 Elev 1079.00 to elev 1077.00 delta H = 2.00' Length= 100' Slope: .02000 Subarea: .72 acre Soil: B, RI= 56 Development type 4 = 0.4 dwelling lacre Street template 4 Half-width = 22' n = CF = 4" Batter= ,5 h/v Gutter width = Xfall = ,02 'I' 8' pkwy @ .02 'I' Tt= 0.37 min. based on Qavg= 19.63 cfs on one side of street. Davg=0.41' Aavg= 4.38 s.f. Vavg= 4.48'/sec At end of reach: D = 0.42' (0.420) V = 4.47' Isec, D*V = 1.88 Sf = .02001 Flow area = 4.63 s.f. Street flooded width one side = 21.14' Flow exceeds top of curb. Parkway flow: 4.31' ,.ide x 0,09' deep, Q= 0.8 ai= .1 .015 1 side 0" Hike = 0.0" Lip = .00" ----------------------------------------------------.--------------------------- Tc = 7,36 + 0.37 = 7.74 min. I = 4.011"/hr A(total) = 6.420 ac Fp ,,0.831"/hr C=.732 Q(subarea) = 2.11 cfs Q(total) = 20.69 cfs _ __ _ _ _ _ _ _ _ _ __ _ _ _ __ - - - - __ - - __ - - - - - - - Summary - -- - - -- O' - - - - - - - - - - - - -- - -- - - - - - -- - - - Stream 2 to node 104- Length= 920 ft. 3.22 cfs/acre avg. A(tot)= 6.42 acres Tc= 7,74 min Q= 20.69 cfs This stream is designated for confluence with 1 other by record 3 ===================================================================:============ ~fb I I ~I 'I I I I I I I I I I I I I I I~ I Por. File RCCEX1ST.DAT Runtime 10-07-2000 16:40 Job# RCC Page 4 Record 7 Confluencing 2 streams at node 104 Process 9 Confluence Constituent streams: Stream 1: Q= 14.62 Stream 2: Q= 20.69* Tc= 7.14 Tc= 7.74 1= 4,192 1= 4.011 @ Tc Stream 1 + Stream 2 = Confluenced ------ -------- -------- ------------ 7.74 Q= 13.99 + 20.69 = 34.68 cfs Ratio= 12/11 Qpeak = 34.68 cfs at Tc = 7.74 minutes Confluenced streams will be designated as stream # 1 to continue downstream. ___________________________________ Summary ----------------------------------- Stream 1 at node 104 Length= 930 ft. 3.31 cfs/acre avg. (c) A(tot)= 10.48 acres Tc= 7.74 min Q= 34.68 cfs ------------------------------------------------------------------------------- ------------------------------------------------------------------------------- Record 8 Subarea 7 Stream 1 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Remark: De portola Rd Node 104 to node 105 Elev 1077.00 to elev 1075.90 delta H = 1.10' Length= 70' Slope= .01571 Subarea: 3.14 acres Soil: B, R1= 56 Development type 4 0.4 dwelling /acre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width Xfall = .02 '/' Flow designated on 1 side but crown exceeded. Street flowing full. Tt based on 39.19 cfs avg in full street, At end of reach: D = 0.42' (0.421) V = 4.87'/sec. D*V = 2.05 Sf = .01962 Flow area = 4.48 s.t. Flooded width one side" 21.28' Flow exceeds top of curb, Plane of curb face extended up, pkwy ponded. ai= .1 .015 1 side 0" Hike = 0.0" Lip = .00" ---------------------------------------------------.---------------------------- Tc = 7.74 + 0.27 = 8.00 min. I = 3.937"/hr A(total) = 13.620 ac A(contrib) = 13.620 ac Fp = 0.827"/hr C=.730 Q(subarea) = 9.02 cfs Q(total) = 43.70 cfs ___________________________________ summary ------..---------------------------- Stream 1 to node 105 Length= 1000 ft. 3,21 cfs/acre avg. (c) A(tot)= 13.62 acres Tc= 8.00 min Q= 43.70 cfs ==================================================;:============================ s:A I I I I I I I I I I I I I I I I I I I File RCCEXIST.DAT Runtime 10-07-2000 16:40 Job# RCC Page 5 Record 9 Subarea 8 Stream 1 Process 3: Street flow Subarea Q enters stream unifonnly distributed along reach. Remark: to catch basin @ Villa del Sur Node 105 to node III Elev 1075.90 to elev 1055.50 delta H = 20.40' Len~rth= 800' Slope= .02550 Subarea: 7.72 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling lacre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width = Xfall = .02 'I' 8' pkwy @ .02 'I' Flow designated on 1 side but crown exceeded. Street flowing full. Tt based on 52.94 cfs avg ill full street. At end of reach: D = 0.44' (0.438) V = 6.06'/sec. D*V = 2.66 Sf = .03515 Flow area = 5.13 s.f. Street flooded width = 44.00' Flow exceeds top of curb. parkway flow: 5.25' \~ide x 0.11' deep, Q= 3.3 ai= .1 .015 :'. side 0" Hike = 0.011 Lip = .00" --------------------------------------------------..---------------------------- Tc = 8.00 + 2.57 = 10.57 min. I = 3.379"/hr A(total) = 21.340 ac A(contrib) = 21.340 ac Fp = 0.800"/hr C=.708 Q(subarea) = 18.47 cfs Q(total) = 62.18 cfs __ _ _ _ __ _ _ __ __ __ - - -- - -- - -- - - - - - - - - - - Summary - - - - - -... - - - - - - - - - - - - -- - -- - - - -- - - - - - Stream 1 to node III Length= 1800 ft, 2.91 cfs/acre avg. (c) A(tot)= 21.34 acres Tc= 10.57 min Q= 62,18 cfs This stream is designated for confluence with 1 other by record 13 =::=::========:===================================::;=========================== Process 8: Add a subarea at last nc.de Record 10 Subarea 9 Stream 1 Remark: Flow down villa del Sur At node III Subarea: 6.7 acres Soil: D, RI= Development type 4 = 0.4 dwelling 75 lacre ai= .1 --------------------------------------------------.----------------------------- TC = 10.57 min. I = 3.379"/hr A(total) = 28.040 ac A(contrib) = 28.040 ac Fp = 0.393"/hr C=.806 Q(subarea) = 18.24 cfs Q(total) = 80.42 cfs ___________________________________ Summary -------.--------------------------- Stream 1 to node III Length= 1800 ft. 2.87 cfs/acre avg. (c) A(tot)= 28.04 acres Tc= 10.57 min Q_. -. 80.42 cfs ===================================================~===============:============ (#) I I I I I I I I I I I I I I I I I I' I File RCCEXIST.DAT Runtime 10-07-2000 16:41 Job# RCC Page 6 ******************************************************************~.* New Stream Record 11 Subarea 10 Stream 3 Process 1: Initial subarea Node 301 to node 302 Elev 1121.00 to elev 1068.00 delta H = 53.00' Length= 620' Slope" .08548 Subarea: 1.35 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre ai=.l ---------------------------------------------------..---------------.------------ k = .487 Tc = 10.43 min. I = 3.404"/hr A(total) = 1.350 ac Fp = 0.801"/hr C=,709 Q(subarea) = 3.26 cfs Q(total) = 3.26 cfs _ .. _ _ _ _ _ __ _ _ __ _ _ __.. _ _ _ _ _ - - - - - -- - - -- - Summary - - -- -- -... - - -- - -- -- -- - - .. - - - - - - - - .. - - - Stream 3 to node 302 Length= 620 ft. 2.41 cfs/acre avg. A(tot)= 1.35 acres Tc= 10.43 min Q-- .. 3.26 cfs ===================================================:;==============::============ Record 12 Subarea 11 Stream 3 Process 7: Channel flow - Natural valley Subarea Q enters stream uniformly distributed along reach. Node 302 to node 303 Elev 1068.00 to elev 1060.00 delta H = 8.00' Length= 230' Slope" .03478 Subarea: .92 acre Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre ai=.l V avg = 3.80'/sec for avg Q of 4.30 cfs ------------------------------------------------------------------.------------- TC = 10,43 + 1,01 = 11,43 min. I = 3.235"/hr F.(total) = 2.270 ac Fp = Q,791"/hr C=.702 Q(subarea) = 2,09 cfs Q(total) = 5.35 cfs _ _ _ __ _ __ _ _ _ _ _ __ __ __ _ _ __ _ -- - - - - .. - - - - Summary - - - -- - - - -. - - - - - .. - - - -- - - .- .. - - - - -- - - - -- Stream 3 to node 303 Length= 850 ft. 2.36 cfs/acre avg. A(tot)= 2.27 acres Tc= 11.43 min Q.- .- 5.35 cfs ===================================================::=============:============= ~\ - I I I I I I I I I I I - I I I I I I File RCCEXIST.DAT Runtime 10-07-2000 16:41 Job# RCC Page 7 Record 13 Subarea 12 Stream 3 Process 3: Street flow Subarea Q enters stream uniformly distributed c.long reach. Remark: along De portola to catch basin @ Villa del Sur Node 303 to node 111 Elev 1060.00 to elev 1055.50 delta H = 4.50' Length= 540' Slope., .00833 Subarea: 6.82 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width = Xfall=.02'/' Flow designated on 1 side but crown exceeded. 3.08 cfs spills to other side. Q on 1 side= 15.66 cfs for Tt of 2.77 min. Aavg=4.81 Davg=O,44' Vavg= 3.25 .U end of reach: D = 0.44' (0.437) V = 3,25'/sec. D*V = 1.42 Sf = .01179 Flow area = 4.81 s.f. Flooded width one side g 22.05' Flow exceeds top of curb. Plane of curb face extHlded up, pkwy ponded. ai= .1 ,015 1 side 0" Hike = 0.0" Lip = .00" ------------------------------------------------------------------------------- Tc = 11.43 + 2.77 = 14.20 min. I = 2.872"/hr A(total) = 9.090 ac Fp g 0.768"/hr C=.683 Q(subarea) = 13,39 cfs Q(total) = 18.73 cfs _ _ _ _ __ _ _ __ _ __ _ _ _ __ _ _ _ _ __ _ - -- - - - -- - - Summary - - - - - - .... - - - - - - - - -- - - - - - - -- -- -- -- - -- Stream 3 to node 111 Length= 1390 ft. 2.06 cfs/acre avg. A(tot)= 9.09 acres Tc= 14.20 min Q= 18.73 cfs This stream is designated for confluence with 1 other by record 9 ===================================================~===============:============ Record 14 Remark: catch basin @ De Portola & Confluencing 2 streams at node 111 Process 9 Confluence Villa del Sur Constituent streams: Stream 1: Q= 80.42* Stream 2: Q= 18.73 Tc= ID.57 Tc= 14.20 1= 3.379 1= 2.872 @ Tc Stream 1 + Stream 3 = Confluenced 10,57 Q= 80.42 + Ratio= 13,94 TC1/Tc2 94,36 cfs Qpeak = 94.36 cfs at Tc = 10.57 minutes Confluenced streams will be designated as stream # 1 to continue downstream. ___________________________________ Summary --------..-------------------------- Stream 1 at node III Length= 1800 ft. 2.54 Cfs/acre avg. (c) A(tot)= 37.13 acres Tc= 10,57 min Q= 94.36 cfs ====================================================:=========================== ~'V I II ~I I I I I I I I I I I I I I I I. .' v ~ I File RCCEXIST.DAT Runtime 10-07-2000 16:41 Job# RCC Page 8 Record 15 Subarea 13 Stream 1 Process 8: Add a subarea at last node Remark: Half of DePortola Rd itself, although some drains into 2 or 3 driveways At node 111 Subarea: .63 acre Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.l ------------------------------------------------------------------------------- Tc = 10.57 min. I = 3.379"/hr A(total) = 37.760 ac A(contrib) = 37.760 ac Fp = O.509"/hr C=.778 Q(subarea) = 1,66 cfs Q(total) = 96.02 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node III Length= 1800 ft. 2.54 cfs/acre avg. (c) A(tot)= 37.76 acres Tc= 10.57 min Q= 96.02 cfs ===================================================:============================ Record 16 Subarea 14 Stream 1 Process 7: Channel flow - Improved .0.11 subarea Q enters stream at downstream node. Remark: to NE RCC prop cor. Node III to node 112 Elev 1055.50 to elev 1049.40 delta H = 6.10' Length= 420' Subarea: 4.57 acres Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.l Max d = 2' Bottom width = 3' Sideslope Z = 1.5:1 * Channel is overfull, Tt based on V= 6,6 for Q = Slope= .01452 (h:v) n = .03 79.77 at Dn = d(full) -------------------------------------------------------------------------------- Tc = 10,57 + 1.05 = 11.62 min. I = 3.207"/hr A(total) = 42.330 ac A(contrib) = 42.330 ac Fp = O,505"/hr C=.772 Q(subarea) = 11.32 cfs Q(total) = 107.34 cfs ___________________________________ Summary ------..---------------------------- Stream 1 to node 112 Length= 2220 ft. 2.54 cfs/acre avg. (c) A(tot)= 42.33 acres Tc= 11.62 min Q= 107,34 cfs ==================================================::============================ Stream 1 Process 7: Channel flow - Natural Valley 707 48.10 delta H = 1.30' Len9th= 190' Slope.. ,00684 Record 17 Subarea 0 Node 112 to node Elev 49.40 to elev Subarea: 0 acre . V avg = 4.01'/sec for avg Q of 107,34 cfs -------------------------------------------------------------------.------------ I = 3,093"/hr 42.330 ac Q(total) = 107.34 cfs _ _ _ _ _ _ __ __ _ _ _ _ .. _ _ .. _ _ .. _ - -- .. .. - - .. .. - - .. - Summary - - - .. .. - - .. - - - .. - - .. - - - - - -- .. - - - - .. - - - - -- - Stream 1 to node 707 Length= 2410 ft. 2.54 cfs/acre avg, (c) A(tot)= 42.33 acres Tc= 12.41 min Qa 107.34 cfs This stream is designated for confluence with 1 other by record 20 TC = 11.62 + A(total) = 0.79 = 42,330 ac 12.41 min. A(contrib) = ==;;==;=;=;;========;==;==;=======;===;============~==============:============= <O~ I I I I I I I I I I I I d I v I U D o U m File RCCEXIST.DAT Runtime 10-07-2000 16:41 Job# RCC Page 9 **************************************************~~,**************i* New Stream Record 18 Subarea 15 Stream 4 Process 1: Initial subarea Node 504 to node 505 Elev 1063.00 to elev 1054.50 delta H = 8.50' Lengt.h= 700' Slope.. .01214 Subarea: 4.59 acres Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.l --------------------------------------------------.----------------~------------ k = .487 Tc = 16.17 min. I = 2.674"/hr A(total) = 4.590 ac Fp '" 0.489"/hr C=,'i52 Q(subarea) = 9.23 cfs Q(total) = 9.23 cfs ----------------------------------- Summary ------..---------------------------- Stream 4 t.o node 505 Length= 700 ft. 2.01 cfs/acre avg. A(tot)= 4.59 acres Tc= 16.17 min Q= 9.23 cfs =============================================================================== Record 19 Subarea 16 Stream 4 Process 7: Channel flow - Natural valley Subarea Q enters stream unifonnly distributed along reach. Node 505 to node 506 Elev 1054.50 to elev 1049.10 delta H = 5.40' Lengt.h= 400' Slope= .01350 Subarea: 5.56 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = 3.18'/sec for avg Q of 14.27 cfs --------------------------------------------------..---------------------------- Tc = 16,17 + 2.09 = 18.26 min, I = 2.501"/hr A(total) = 10.150 ac Fp '" 0.483"/hr C=.'i26 Q(subarea) = 10,09 cfs Q(tot.al) = 19.32 cfs _ _ _ _ _ - - - - - - -- -- - -- - -- - - - - - -- - - -- -- - Summary -- - - - - ... - - - - - - - - - - - - - - - -- - - -- - -- - -- Stream 4 to node 506 Length= 1100 ft. 1,90 cfB/acre avg. A{tot)= 10.15 acres Tc= 18.26 min Q= 19.32 cfs ==================================================:~============================ Record 20 Subarea 17 Stream 4 Process 7: Channel flow - Natural valley Subarea Q enters stream uniformly distributed a.long reach. Node 506 to node 707 Elev 49.10 to elev 48,10 delta H = 1.00' Len~Jt.h= 230' Slope= .00435 Subarea: .96 acre Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = 1.98'/sec for avg Q of 20,14 cfs --------------------------------------------------.----------------------------- Tc = 18.26 + 1.93 = 20,20 min. I = 2.366"/hr A(total) = 11.110 ac Fp '" O,478"/hr C=.'il8 Q(subarea) = 1.63 cfs Q(total) = 20.95 cfs ----------------------------------- Summary ------..---------------------------- Stream 4 to node 707 Length= 1330 ft. 1.89 cf:,/acre avg. A{tot)= 11.11 acres Tc= 20.20 min Q= 20,95 cfs This stream is designated for confluence with 1 other by record 17 ==================================================================::============ (A I I , I I I I I I I I I I I I I I I I File RCCEXIST.DAT Runtime 10-07-2000 16:41 Job# RCC Page 10 Record 21 Confluencing 2 streams at node 707 Process 9 Confluence Constituent streams: Stream 1: Q= 107.34* Stream 2: Q= 20.95 Tc= 12.41 Tc= 20.20 1= 3.093 1= 2.366 @ Tc Stream 1 + Stream 4 = Confluenced 12.41 Q= 107.34 + Ratio= 12.87 = TCl/Tc2 120.21 cfs Qpeak = 120.21 cfs at Tc = 12,41 minutes Confluenced streams will be designated as stream # ), to continue downstream, _ _ _ _ _ _ n _ .. _ n _ _ _ n _ _ n n _ n _ _ _ _ _ _ _ _ Sununary _ _ n _ _ _ .. _ _ _ _ _ _ - - - .. - - - - - - - - n - n - - - - Stream 1 at node 707 Length= 2410 ft. 2.25 cfs/a.cre avg. (c) A(tot)= 53.44 acres Tea 12.41 min Qa 120,21 cfs ===================================================~===============:============ Record 22 Subarea 18 Stream 1 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 707 to node 708 Elev 48.10 to elev 42.50 delta H = 5.60' Length= 935' Slopea .00599 Subarea: 5.32 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = 3.94'/sec for avg Q of 125.40 cfs ---------------------------------------------------..--------------------------- Tc = 12.41 + 3.95 = 16.37 min. I = 2.656"/hr A(total) = 58.760 ac A(contrib) = 58.760 ac Fp a 0.489"/hr C=.734 Q(subarea) = 10.38 cfs Q(total) = ),30,59 cfs _ __ _ n _ _ n _ _ n _.. _ _ n .. _ n _ n _ _ _ _ _ _ _ _ Sununary _ n _ n _" _ _ _ _ _ _ _ - - - - n - .. - - - n -- - - n - Stream 1 to node 708 Length= 3345 ft. 2.22 cfs/acre avg. (c) A(tot)= 58.76 acres Tc= 16.37 min Q= 130.59 cfs ==================================================================::============ <sf, I I :,1 "I I I I I I I I I , I I I I I I File RCCEXIST.DAT Runtime 10-07-2000 16:41 Job# R.CC Page 11 Record 23 Subarea 19 Stream 1 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 70S to node 709 Elev 42.50 to elev 39.90 delta H = 2.60' Length- 430' Slope= .00605 Subarea: 21.5S acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = 4.lS'/sec for avg Q of 150.31 cfs ------------------------------------------------------------------------------- Tc = 16,37 + 1.72 = lS.0S min, I = 2.514"/hr A(total) = SO,340 ac A (contrib) = SO.340 ac Fp = 0.4S4"/hr C=.727 Q(subarea) = 39.44 cfs Q(total) = 170.03 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 709 Length= 3775 ft. 2.12 cfE:/acre avg.(c) A(tot)= SO.34 acres Tc= lS.0S min Q= 170.03 cfs ==================================================;:============================ Record 24 Subarea 20 Stream 1 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 709 to node 710 Elev 39.90 to elev 2S.00 delta H = 11.90' Len9th= 9S5' Slope= .0120S Subarea: 11.6 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = 6.24'/sec for avg Q of 179.72 cfs --------------------------------------------------..---------------------------- Tc = lS.0S + 2,63 = 20.71 min, I = 2.333"/hr A(total) = 91.940 ac A(contrib) = 91.940 ac Fp = 0.477"/hr C=,716 Q(subarea) = 19,3S cfs Q(total) = lS9.41 cfs ___________________________________ Summary ------..---------------------------- Stream 1 to node 710 Length= 4760 ft. 2,06 cfs/acre avg. (c) A(tot)= 91.94 acres Tc= 20.71 min Q= lS9.41 cfs This stream is designated for confluence with 1 other by record 2S ===================================================:============================ **************************************************~fj**************** New Stream Record 25 Subarea 21 Stream 5 Process 1: Initial subarea Node 601 to node 602 Elev 56.20 to elev 54.S0 delta H = 1.40' Length= 200' Slope- .00700 Subarea: ,1 acre Soil: C, RI= 69 Development type 1.3 = Nat/Agri, Poor cover ai= 0 ----------------------------------------------------.--------------------------- k = .525 Tc = 11.79 min. I = 3.1S1"/hr A(total) = 0.100 ac Fp = O.504"/hr C=.757 Q(subarea) = 0.24 cfs Q(tota1) = 0.24 cfs _ _ _ _ _ _ _ _ __ _ _ _ _ __ _ _ _ _ _ - - - -- - -- -- -- -- Summary - -- - - - - .. -- .. - - - - - - - - - - - .. - - -- - - - - - - -- Stream 5 to node 602 Length= 200 ft. 2,41 cfs/acre avg. A(tot)= 0.10 acres Tc= 11.79 min Q-' ., 0.24 cfs --------------------------------------------------------------------------------- --------------------------------------------------------------------------------- (jo I II(e , .1 I I I , I I I I I I I I I I I-- I File RCCEXIST.DAT Runtime 10-07-2000 16:41 Job# RCC Page 12 Record 26 Subarea 22 Stream 5 Process 7: Channel flow - Natural valley Subarea Q enters stream unifom.ly distributed along reach. Node 602 to node 603 Elev 54.80 to elev 49.10 delta H = 5.70' Length= 450' Slope= .01267 Subarea: 2.34 acres Soil: C, RI= 69 Development type 1.3 = Nat/Agri, Poor cover ai= 0 V avg = 2.05'/sec for avg Q of 2.61 cfs ------------------------------------------------------------------------------- Tc = 11.79 + 3,65 = 15,45 min. I = 2,742"/hr A(total) = 2.440 ac Fp = O.492"/hr C=.739 Q(subarea) = 4.74 cfs Q(total) = 4.98 cfs ___________________________________ Summary ---------..------------------------- Scream 5 to node 603 Length= 650 ft, 2.04 cfs/acre avg, A(tot)= 2.44 acres Tc= 15.45 min Q= 4.98 cfs =============================================================================== Record 27 Subarea 23 Stream 5 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 603 to node 604 Elev 49.10 to elev 43.00 delta H = 6.10' Length= 1070' Slopem .00570 Subarea: 6.63 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = l,88'/sec for avg Q of 9.88 cfs ------------------------------------------------------------------------------- Tc = 15.45 + A(total) = Q (subarea) 9.47 = 24,91 min, 9,070 ac = 9.80 cfs I = 2,108"/hr Fp _ 0.466"/hr C=.701 Q(total) = 14,78 cfs Summary - - -- - - - - - .- - - - - - - - - - - - - - - - - - - - - - - - - - ft. 1.63 ds/acre avg. 9.07 acres Tc= 24,91 min Q- 14.78 cfs ----------------------------------- Stream 5 to node.604 Length= 1720 A(tot)= =====================================================:========================== Record 28 Subarea 24 Stream 5 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 604 to node 710 Elev 43.00 to elev 28.00 delta H = 15.00' Lensth,= 1435' Slope- .01045 Subarea: 7.71 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg - 3.04'/sec for avg Q of 19.50 cfs ------------------------------------------------------------------------------- Tc = 24.91 + 7.86 = 32.77 min. I = 1.813"/hr A(total) = 16.780 ac Fp = 0.450"/hr C=.676 Q(subarea) = 9.46 cfs Q(total) = 24.23 cfs ___________________________________ Summary ----------------------------------- Stream 5 to node 710 Length= 3155 ft. 1.44 cfEJacre avg, A(tot)= 16.78 acres Tc= 32,77 min Q= 24.23 cfs This stream is designated for confluence with 1 other by record 24 =============================================================================== <0"\ I I I I I I I I I I I I I I I I I I I Por. File RCCEXIST.DAT Runtime 12-19-2001 07 :31 .Job# RCC I~o-yr Page 13 Record 29 Confluencing 2 streams at node 710 Process 9 Confluence Constituent streams: Stream 1: Q= 189.41* Stream 5: Q= 24.23 Tc= 20.71 Tc= 32.77 1= 2.333 1= 1. 813 @ Tc Stream 1 + Stream 5 = Confluenced 20,71 Q= Ratio= 204.73 cfs' 189.41 + 15.32 = Tc1/Tc5 Qpeak = 204.73 cfs at Tc = 20.71 minutes Confluenced streams will be designated as stream # 1 to continue downstream.. - - - - -- - - - -- - - - -'- - -- - - - - - - - -- - - - --- - Surrnnary - - - - - -.. -- - -- - - - - -- -".- - - - -- - - - - - - - - -- Stream 1 at node 710 Length=4,760' 1.88 cfs/acre avg. (c) A(tot)=108.72 acres Tc= 20.71 min Q= 204.73 cfs ---------------------------------------------------------------------------.---- -------------------------------------------------------------------------------- Record 30 Subarea 25 Stream 1 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 710 to node 190 Elev 28.00 to el.ev 17.80 delta H = 10.20' Length= 1570' Slope=. 00650 Subarea: 33.75 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 Vavg = 4.93'/sec for avg Q of 228.94 cfs Tc = 20.71 + 5,31 = 26.02 min. A(total) = 142.470 ac A(contrib) = Q(subarea) = 48.43 cfs I = 2,058"/hr 142.470 ac 1"9 = 0.464"/hr C=,697 Q(total) = 253.15 cfs - - -. - - - - - - -. - - - - - - - - - .. - - - - - - - - - - - - - - - Surrnnary - - - - - - .. - - - - - - - - - - - -- .. - - - - - - - - " - - - - - Stream 1 to node 190 Length=6,330' 1.78 cfs/acre avg. (c) A(tot)=142,47 acres Tc= 26.02 min Q= 253.15 cfs ------------------------------------------------.----------------.---------------- -------------------------------------------------------------------------------- Record 31 Subarea 26 Stream 1 Process 7: Subarea Q enters stream Remark: To exist, RCB @ Jed. Smith Rd & Hwy Node 190 to node 191 Elev 17.80 to elev 17.00 delta H = 0,80' Subarea: .78 acre Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre Vavg = 2,94'/sec for avg Q of 253.70 cfs Channe1 flow - Natural Valley uniformly distributed along reach. 79 Length= 370' Slope= .00216 ai= .1 Tc = 26.02 + 2.10 = 28.12 min. A(total) = 143.250 ac A(contrib) = Q(subarea) = 1.09 cfs I = 1.972"/hr 143.250 ac Fp = 0.459"/hr C=.711 Q(total) = 254.25 cfs --------------------------,,-------- Surrnnary ------,,----------------------------- Stream 1 to node 191 Length=6, 700' 1. 77 cfs/acre avg. (c) A(tot)=143.25 acres Tc= 28.12 min Q= 254.25 cfs -------------------------------------------------------------------------------- -------------------------------------------------,------------------------------- "~l;;:V...~ ___ ~1:> I ,I I I I I I I I I I i II I I I I I I I I I 14 1C\'>'jr +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Other: Stream 2: Len= 920' Atot= 6.42 ac Tc= 7.74 min Q= 20.69 cfs Stream 3: Len= 1390' Atot= 9.09 ac Tc= 14.20 min Q= 18.73 cfs Stream 4: Len= 1330' Atot= 11.11 ac Tc= 20.20 min Q= 20.95 cfs Stream 5: Len= 3155' Atot= 16.78 ac Tc= 32.77 min Q= 24.23 cfs ----------------------------------------------------------------.--------------- ----------------------------------------------------------------.--------------- End of RMH run for file RCCEXIST.DAT to~ I I . li~' 'il' ~I I I I I I I I I ,1----' " I I I I I. '- il RMH RC ver 6.4b Nov. 2000 RATIONAL METHOD HYDROLOGY (C) Copyright 1999 Jack P. Norris, Tel 909-676-5816, SIN 0 Jack P. Norris, RCE, 33055 Vi no Way, Temecula Riverside County Fax 676-0016 CA 92591 909-676-5816 Runtime: 10-26-2000 09:47 Page 1 File: RCCEXIST.DAT 30 records By JPN Work code 8 Job# RCC +--------------------------------------------------_..-------------------------+ Rancho Community Church site, Hwy 79S, Temecula Existing condition +--------------------------------------------------_..-------------------------+ Schematic diagram. Legend: Node number/ . Link text: 345 record number + process name Streams: 2 301 11Init 302 12Chan 303 13Stre 504 18Init 505 19Chan 506 20Chan 601 25Init 602 26Chan 603 27Chan 604 28Chan 101 201 lInit 4Init 102 202 2Chan 5Chan 103 203 3Stre 6Stre 104 <----' 8Stre 105 9Stre 111 <--- <-------' 16Chan 112 17Chan 707 <--- <------ <-------' 22Chan 708 23Chan 709 24Chan 710 <--- <------ <------ <-------' 30Chan 190 :;t LLtt.\n t(i I ,,~<i. ,j.\ [,: (~l ,\0 Tc = 5.50 + 0.75 = 6.25 min. I = 3.058"/hr ~total) = 2.840 ac Fp ,,0.388"/hr C=.797 II Q(subarea) = 5.36 cfs Q(total) = 7.05 cfs _. _ __ __ __ _ _ _ _ _ __ _ _ _ _ - - -- - - -- -- - - - - - -- surmnary - - -- - - .. - -- - - - - - - - - - - - -- - -- - - -- - - -- - Stream 1 to node 1D3 Length= 530 ft, 2.48 cfs/acre avg. A (tot) = 2.84 'acres T1:=< 6.25 min . I /-, I I I I . I . . . I I I I I I .. RMH RC ver 6.4b Nov. 2000 RATIONAL METHOD HYDROLOGY (C) Copyright 1999 Jack P. Norris, Tel 909-676-5816, SiN 0 Jack P. Norris, RCE, 33055 Vi no Way, Temecula, Riverside County Fax 676-0016 CA 92591 909-676-5816 Runtime: 10-26-2000 09:41 Page 1 ., File: RCCEXIST .DAT 30 records By JPN Work code 8 Job# RCC +-------------------------------------------------.---------------------------+ Rancho Cormnunity Church site, Hwy 79S, Temecula Existing condition +--------------------------------------------------.---------------------------+ Frequency: 10 - yr. I = 8.385 TC^-.551 Min. pipe size: 18" Legend: (i)=input (c)=computed 10-yr 1-hr 1= .88 (i), 10-yr 10-min 1= 2.36 (i) 10-yr 1-hr depth= 0,880" (c) -Loglog slope of I-I> curve = 0,5506 (c) Initial subarea Tc by Kirpich formula: Tc = k (Dist^3 / deltaH)^.2 **************************************************i"**************************** Record 1 Subarea 1 Node 101 to node Elev 1208.50 to elev Subarea: .64 acre Development type 4 = Process 1: Initial subarea Stream 1 102 1158.00 delta H = Soil: D, RI= 75 0.4 dwelling /acre 50.50' Lenc;rth= 210' Slope= .24048 ai= .1 ---------------------------------------------------.---------------------------- k = .487 Tc = 5.50 min. I = 3.281"/hr A(total) = 0.640 ac Fp ,,0.391"/hr C".803 Q(subarea) = 1.69 cfs Q(total) = 1.69 cfs ___________________________________ Surmnary -------.---------------------------- Stream 1 to node 102 Length= 210 ft. 2.64 cfs/acre avg, A(tot)= 0.64 acres Tc= 5.50 min Q= 1. 69 cis ===================~==============================::============================ Record 2 Subarea 2 Stream 1 Process 7: Channel j:low - Natural valley Subarea Q enters stream uniforrnly distributed along reach. Node 102 to node 103 Elev 1158.00 to elev 1119.00 delta H = 39.00' Len~lth= 320' Slope= ,12188 Subarea: 2.2 acres Soil: D, RI= 75 Development type 4 = 0,4 dwelling /acre V avg = 7.14'/sec for avg Q of 4.37 cfs ai= .1 --------------------------------------------------.----------------------------- Q- _. 7.05 cfs ==================================================~;===============;============ ,,\\ I '1 .~ J"! 'I I I I I I I I I I I I I I I' '- I Por. File RCCEXIST.DAT Runtime 10-26-2000 09:42 ~rob# RCC Page 2 Record 3 Subarea 3 Stream 1 Process 3: Street fl.ow Subarea Q enters stream uniformly distributed along reach. Remark: Verde Drive Node 103 to node Elev 1119.00 to elev Subarea: 1.22 acres Development type 4 = Street template 0 CF = 6" Batter= Xfall = .02 '/' Tt= 1.04 min. based on Qavg= 4.11 Davg=0.16' Aavg= 1.29 s.f. Vavg= At end of reach: D = 0,17' (0.173) Flow area = 1.51 s.f. Flooded 104 1077.00 delta H = 42.00' Soil: B, RI= 56 0.4 dwelling /acre ai=.l Half-width = 10' n = .015 .25 h/v Gutter width = 0" Len"th= 400' Slope= .10500 2 sides Hike = 0.0" Lip = .00" cfs on each side of street. 6.40'/sec V = 6.22' /sec, width one side " Sf = .10516 D*V = 1.08 8.70' --------------------------------------------------..---------------------------- Tc = 6.25 + 1.04 = 7.29 min. I = 2.809"/hr A(total) = 4.060 ac Fp" 0.763"/hr C=.680 Q(subarea) = 2.33 cfs Q(total) = 9.38 cfs ___________________________________ Summary ------..---------------------------- Stream 1 to node 104 Length= 930 ft. 2.31 cfs/acre avg. A(tot)= 4.06 acres Tc= 7.29 min Q= 9.38 cfs This stream is designated for confluence with 1 other by record 6 ==================================================:============================= ****************************************************-**************** New Stream Record 4 Subarea 4 Node 201 to node Elev 1201.00 to elev Subarea: 1.84 acres Development type 4 = Stream 2 Process 1: Initial '3Ubarea 202 1123.00 delta H = 78.00' Length= 300' Soil: D, RI= 75 0.4 dwelling /acre ai=.l Slope= .26000 ----------------------------------------------------.--------------------------- k = .487 Tc = 6.24 min. I = 3.059"/hr A(total) = 1.840 ac Fp = 0.388"/hr C=.797 Q(subarea) = 4.49 cfs Q(total) = 4.49 cfs ___________________________________ Summary --------.--------------------------- Stream 2 to node 202 Length= 300 ft. 2.44 cfs/acre avg. A(tot)= 1.84 acres Tc= 6.24 min Q= 4.49 cfs ===================================================================:============ ",\'l.- I . :. . I I I I I I I I I I I I I I 11 File RCCEXIST.DAT Runtime 10-26-2000 09:42 Job# RCC Page 3 Record 5 Subarea 5 Stream 2 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 202 to node 203 Elev 1123.00 to elev 1079.00 delta H = 44.00' Length= 520' Slope= .08462 Subarea: 3.86 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling lacre ai=.l V avg = 6.90'/sec for avg Q of 8.10 cfs __________________________________________________n____________________________ Tc = 6.24 + 1.26 = 7.50 min. I = 2.765"/hr A (total) = 5.700 ac Fp " 0.760" Ihr C=. 677 Q(subarea) = 7.23 cfs Q(total) = 11.72 cfs ___________________________________ Summary ______n____________________________ Stream 2 to node 203 Length= 820 ft. 2.06 cfs/acre avg. A(tot)= 5.70 acres Tc= 7.50 min Q= 11.72 cfs ==================================================::~=========================== Record 6 Subarea 6 Stream 2 Process 3: Street flow Subarea Q enters stream uniformly distributed a.long reach. Node 203 to node 104 Elev 1079.00 to elev 1077.00 delta H = 2.00' Length= 100' Slope= .02000 Subarea: .72 acre Soil: B, RI= 56 Development type 4 = 0,4 dwelling lacre Street template 4 Half-width = 22' n = CF = 4" Batter= .5 h/v Gutter width = Xfall = ,02 'I' 8' pkwy @ ,02 'I' Tt= 0.39 min. based on Qavg= 12.37 cfs on one side of street. Davg=0.34' Aavg= 2.91 s.f. Vavg= 4.26'/sec At end of reach: D = 0.35' (0.349) V = 4.23'/sec. D*V = 1.47 Sf = .02001 Flow area = 3.08 s.f. Street flooded width one side = 17.62' Flow exceeds top of curb. Parkway flow: 0.78' wide x 0.02' deep, Q= 0.0 ai= .1 ,015 1 side 0" Hike:, O. 0" Lip = .0011 -------------------------------------------------------------------.------------ Tc = 7,50 + 0.39 = 7.89 min. I = 2.689"/hr A(total) = 6.420 ac Fp = 0.754"/hr C=.673 Q(subarea) = 1.30 cfs Q(total) = 13.02 cfs _ _ .. _ _ no _ _ _ no _ _ no _ _ _ _ _ u _ _ _ _ _ _ _ _ _ _ .. _ Summary u _ _ u _ .. _ _ .. _ _ _ _ _ _ - - - - - n - - - - - u - - no - Stream 2 to node 104 Length= 920 ft. 2.03 cfs/acre avg, A(tot)= 6.42 acres Tc= 7.89 min Q= 13.02 cfs This stream is designated for confluence with 1 other by record 3 ==================================================================::============ ~:? I I Record 7 '. \ Confluencing 2 streams at node 104 l I I I I I I I I I I I I I I I I File RCCEX1ST.DAT Runtime 10-26-2000 09:42 Job# RCC Page 4 Process 9 Confluence Constituent streams: Stream 1: Q= 9.38 Stream 2: Q= 13.02* Tc= Tc= 7.29 7.89 1= 2.809 1= 2.689 @ Tc Stream 1 + Stream 2 = Confluenced 7.89 Q= Ratio= 8.98 + 12/ Il 13.02 = 22.00 cfs Qpeak = 22.00 cfs at Tc = 7.89 minutes Confluenced streams will be designated as stream # 1 to continue downstream. ___________________________________ Summary ------..---------------------------- Stream 1 at node 104 Length= 930 ft. 2.10 cfs/acre avg. (c) A(tot)= 10.48 acres Tc= 7.89 min Q= 22.00 cfs ==================================================::============================ 1 Process 3: Street flow Q enters stream uniformly distributed along reach. Record 8 Subarea 7 Stream Subarea Remark: De Portola Rd Node 104 to node 105 Elev 1077.00 to elev 1075.90 delta H = 1.10' Len9t.h= 70' Slope= .01571 Subarea: 3.14 acres Soil: B, R1= 56 Development type 4 = 0.4 dwelling /acre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width = Xfall = .02 '/' Flow designated on 1 side but crown exceeded. 6.05 cfs spills to other side. Q on 1 side= 21.50 cfs for Tt of 0.26 min. Aavg=4,81 Davg=0.44' Vavg= 4.47 At end of reach: D = 0.44' (0.437) V = 4,47' /sec. D*V = 1.95 Sf = .02582 Flow area = 4.81 s.f. Flooded width one side = 22.05' Flow exceeds top of curb. Plane of curb face extended up, pkwy ponded. ai= .1 ,015 1 side 0" Hike"' 0,0" Lip = .00" ---------------------------------------------------~.--------------------------- Tc = 7.89 + 0.26 =. 8.15 min. I = 2.641"/hr A(total) = 13.620 ac A (contrib) = 13.620 ac Fp = 0.750"/hr C=.670 Q(subarea) = 5.56 cfs Q(total) = 27.56 cfs ___________________________________ Summary -------..--------------------------- Stream 1 to node 105 Length= 1000 ft. 2.02 cfs/acre avg. (c) A(tot)= 13.62 acres Tc= 8.15 min Q_. -. 27.56 cfs ==================================================================='============ ~l\ I I , ,,:-'- ~I ;1 ,I I I I I I' I I I I I I I I- I File RCCEXIST.DAT Runtime 10-26-2000 09:42 Job# RCC Page 5 Record 9 Subarea 8 Stream 1 Process 3: Street flow Subarea Q enters stream uniformly distributed c.long reach. Remark: to catch basin @ Villa del Sur Node 105 to node 111 Elev 1075.90 to elev 1055.50 delta H = 20.40' Length= 800' Slope= .02550 Subarea: 7.72 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre Street template 4 Half-width = 22' n = CF = 4" Batter=.5 h/v Gutter width = Xfall = .02 'I' 8' pkwy @ .02 'I' Flow designated on 1 side but crown exceeded. 12.'71 cfs spills to other side, Q on 1 side= 26.13 cfs for Tt of 2.59 min. Aavg=4.81 Davg=0.44' Vavg= 5.14 At end of reach: D = 0.44' (0.437) V = 5.14'/sec. D*V = 2.25 Sf = .05683 Flow area = 5.08 s.f. Street flooded width one side = 22.00' Flow exceeds top of curb. Parkway flow: 5.17' ,,,ide x 0.10' deep, Q= 2,0 ai= .1 .015 1 side 0" Hike = 0.0" Lip = .0011 ----------------------------------------------------.--------------------------- Tc = 8.15 + 2.59 = 10.74 min. I = 2.269"/hr A(total) = 21.340 ac A(contrib) = 21.340 ac Fp., 0.717"/hr C=.644 Q(subarea) = 11.28 cfs Q(total) = 38.84 cfs ___________________________________ Summary ------.----------------------------- Stream 1 to node 111 Length= 1800 ft. 1.82 cfs/acre avg. (c) A(tot)= 21.34 acres Tc= 10.74 min Q= 38.84 cfs This stream is designated for confluence with 1 other by record 13 =============================================================================== Process 8: Add a subarea at last node Record 10 Subarea 9 Stream 1 Remark: Flow down Villa del Sur At node 111 Subarea: 6.7 acres Soil: D, RI= Development type 4 = 0.4 dwelling 75 lacre ai= .1 ------------------------------------------------------------------------------- Tc = 10.74 min. I = 2.269"/hr A(total) = 28.040 ac A(contrib) = 28.040 ac Fp = 0.372"/hr C=.767 Q(subarea) = 11,66 cfs Q(total) = 50.50 cfs ___________________________________ Summary -------..--------------------------- Stream 1 to node 111 Length= 1800 ft. 1.80 cfs/acre avg. (c) A(tot)= 28.04 acres Tc= 10.74 min Q_. -. 50.50 cfs ===================================================================:============ "'\F{ I I ~- I I f '1'.'- .'. ~ :1 I I I I I I I I I I I I I I :1 File RCCEXIST.DAT Runtime 10-26-2000 09:42 Job# RCC Page 6 **************************************************'~***************~* New Stream Record 11 Subarea 10 Stream 3 Process 1: Initial subarea Node 301 to node 302 Elev 1121.00 to elev 1068.00 delta H = 53.00' Length= 620' Slope., .08548 Subarea: 1.35 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre ai=.l ----------------------------------------------------.--------------------------- k = .487 Tc = 10.43 min. I = 2.306"/hr A(total) = 1.350 ac Fp ,= 0.720"/hr C=.E47 Q(subarea) = 2..01 cfs Q(total) = 2.01 cfs ___________________________________ Summary ----------------------------------- Stream 3 to node 302 Length= 620 ft. 1.49 cfs/acre avg. A(tot)= 1.35 acres Tc= 10.43 min Q= 2.01 cfs ==================================================~================:============ Record 12 Subarea 11 Stream 3 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed a.long reach. Node 302 to node 303 Elev 1068,00 to elev 1060.00 delta H = 8.00' Length= 230' Slope= .03478 Subarea: .92 acre Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre ai=.l V avg = 3.41'/sec for avg Q of 2.65 cfs ----------------------------------------------------.--------------------------- Tc = 10,43 + 1.12 = 11.55 min. I = 2.180"/hr A(total) = 2.270 ac Fp ,,0.708"/hr C=.E.37 Q(subarea) = 1.28 cfs Q(total) = 3.29 cfs ___________________________________ Summary -------..--------------------------- Stream 3 to node 303 Length= 850 ft. 1.45 cfs/acre avg. A(tot)= 2.27 acres Tc= 11.55 min Q_. -. 3.29 cf.s ===================================================================:============ ",\w I I ',1 -I I I I I I I I I I I I I I "1- 'I File RCCEXIST.DAT Runtime 10-26-2000 09:42 Job# RCC Page 7 Record 13 Subarea 12 Stream 3 Process 3: Street flow Subarea Q enters stream uniformly distributed along reach. Remark: along De Portola to catch basin @ Villa del Sur Node 303 to node III Elev 1060.00 to elev 1055.50 delta H = 4.50' Lenqth<= 540' Slope= .00833 Subarea: 6.82 acres Soil: B, RI= 56 Development type 4 = 0.4 dwelling /acre Street template 4 Half-width = 22' n = CF = 4" Batter= .5 h/v Gutter width = Xfall = .02 '/' Tt= 3,31 min. based on Qavg= 7.25 cfs on one side of street. Davg=0.33' Aavg= 2.67 s.f. Vavg= 2.72' /sec At end of reach: D = 0.39' (0.385) V = 2.99' /sec. D*V = 1.15 Sf = .00834 Flow area =. 3.75 s. f, Flooded width one side = 19.45' Flow exceeds top of curb. Plane of curb face extended up, pkwy ponded. ai= .1 .015 1 side 0" Hike = 1),0" Lip = .oon ------------------------------------------------------------------------------- TC = 11.55 + 3.31 = 14.86 min. I = 1.898"/hr A(total) = 9.090 ac Fp = 0.675"/hr C=,612 Q(subarea) = 7.92 cfs Q(total) = 11.21 cfs ___________________________________ Summary ---------.-------------------------- Stream 3 to node 111 Length= 1390 ft. 1.23 cfs/acre avg. A(tot)= 9.09 acres Tc= 14,86 min Q= 11,21 cfs This stream is designated for confluence with 1 other by record 9 =====================================================:========================== Record 14 Remark: catch basin @ De portola & Confluencing 2 streams at node 111 Process 9 Co~fluence Villa del Sur Constituent streams: Stream 1: Q= 50.50* Stream 3: Q= 11.21 Tc= 10.74 Tc= 14.86 1= 2.269 1= 1. 898 @ Tc Stream 1 + Stream 3 = Confluenced 10.74 Q= 50.50 +_ Ratio= 8.11 = Tci/TC3 58.61 cfs Qpeak = 58.61 cfs at Tc = 10.74 minutes Confluenced streams will be designated as stream # 1 to continue downstream. ___________________________________ Summary ----------------------------------- Stream 1 at node 111 Length= 1800 ft. 1.58 cfs:/acre avg. (el A(tot)= 37,13 acres Tc= 10.74 min Q= 58.61 cfs ===================================================:============================ "'\"\ I 'I - . /--::', II II I I I I I I I I I I I I' I I~ ~I File RCCEXIST.DAT Runtime 10-26-2000 09:42 Job# RCC Page 8 Record 15 Subarea 13 Stream 1 Process 8: Add a subarea at last node Remark: Half of DePortola Rd itself, although some drains into 2 or 3 driveways At node 111 Subarea: .63 acre Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.l -----------------------------------------------------.-------------------------- Tc = 10.74 min. I = 2.269"/hr A(total) = 37.760 ac A (contrib) = 37.760 ac Fp = O.474"/hr C=.731 Q(subarea) = 1.04 cfs Q(total) = 59.65 cfs ___________________________________ Summary ---------..------------------------- Stream 1 to node III Length= 1800 ft. 1.58 cfs/acre avg. (c) A(tot)= 37.76 acres Tc= 10.74 min Q= 59.65 cfs =====================================================:========================== Record 16 Subarea 14 Stream 1 Process 7: Channel flow - Improved All subarea Q enters stream at downstream node. Remark: to NE RCC prop cor, Node III to node 112 Elev 1055.50 to elev 1049.40 delta H = 6.10' Lens.th,. 420' Slope= .01452 Subarea: 4.57 acres Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre ai=.l Max d = 2' Bottom width = 3' Sideslope Z = 1,5:1 (h:v) n = .03 Q= 59.65 cfs. Calc'd flow depth, D = 1,73 ft. V= 6.16'/sec, ------------------------------------------------------------------------------- Tc = 10.74 + 1.14 = 11.88 min. I = 2,146"/hr A(total) = 42.330 ac A(contrib) = 42.330 ac Fp = O,468"/hr C=.723 Q(subarea) = 7.09 cfs Q(total) = 66.75 cfs ___________________________________ Summary ----------------------------------- Scream 1 to node 112 Length= 2220 ft. 1.58 cfs:/acre avg. (c) A(tot)= 42.33 acres Tc= 11.88 min Q= 66.75 cfs ===================================================;============================ Record 17 Subarea 0 Node 112 to node Elev 49.40 to elev Subarea: 0 acre V avg = 3.48'/sec for Stream 1 Process 7: Channel flow - Natural Valley 707 48.10 delta H = 1.30' Length= 190' Slope= .00684 avg Q of 66.75 cfs ---------------------------------------------------.---------------------------- I = 2.061"/hr 42.330 ac Q(total) = 66.75 cfs ___________________________________ Summary ----------------------------------- Stream 1 to node 707 Length= 2410 ft. 1. 58 cf,;/acre avg. (c) A(tot)= 42.33 acres Tc:= 12.79 min Q= 66.75 cfs This stream is designated for confluence with 1 other by record 20 Tc = 11.88 + 0.91 = A(total) = 42.330 ac 12.79 min. A(contrib) = ===================================================;============================ 1'0 I I . File RCCEXIST.DAT Runtime 10-26-2000 09:42 Job# RCC II ******************************************************.************* New Stream ,r~Record 18 Subarea 15 Stream 4 Process 1: Initial subarea Node 504 to node 505 Elev 1063.00 to elev 1054.50 delta H = 8.50' Length= 700' Slope= .01214 Subarea: 4.59 acres Soil: C, RI= 69 Development type 4 = 0.4 dwelling /acre Page 9 I "I I I I I I I I I I I I I I I I ai= .1 ------------------------------------------------------.------------------------ k = .487 Tc = 16.17 min. I = 1.811"/hr A(total) = 4.590 ac Fp = 0,450"/hr C=.699 Q(subarea) = 5.81 cfs Q(total) = 5.81 cfs ___________________________________ Summary ----------------------------------- Stream 4 to node 505 Length= 700 ft. 1. 27 cfs/a.cre avg. A(tot)= 4.59 acres Tc~ 16.17 min Q= 5,Sl cfs ------------------------------------------------------.------------------------- ------------------------------------------------------.------------------------- Record 19 Subarea 16 Stream 4 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 505 to node 506 Elev 1054.50 to elev 1049.10 delta H = 5.40' Length= 400' Slope= .01350 Subarea: 5,56 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = 2.S2'/sec for avg Q of S.91 cfs ------------------------------------------------------------------------------- Tc = 16.17 + 2.36 = lS.53 min, I = 1.680"/hr A(total) = 10.150 ac Fp = 0.442"/hr C=.663 Q(subarea) = 6.20 cfs Q(total) = 12.01 cfs - - -- - -- - - - - - -- - -- - - - -- - -- - - - - - - - - - - Summary -- - - - - -- -- . - - - - -- - - - - - -- -- -- - -- - - - - Stream 4 to node 506 Length= 1100 ft. 1.lS cfs/acre avg. A(tot)= 10,15 acres Tc= 18.53 min Q= 12.01 cfs ======================================================:========================= Record 20 Subarea 17 Stream 4 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly <iistributed along reach. Node 506 to node 707 Elev 49.10 to elev 4S.10 delta H = 1.00' Length= 230' Slope= .00435 Subarea: .96 acre Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = l,75'/sec for avg Q of 12.50 cfs ------------------------------------------------------------------------------- TC = 18.53 + 2.19 = 20.73 min. I = 1.5S0"/hr -".(total) = 11.110 ac Fp = OA34"/hr C=.653 Q(subarea) = 0.99 cfs Q(total) = 13.00 cfs ----------------------------------- Summary ----------------------------------- Stream 4 to node 707 Length= 1330 ft. 1.17 cfs/acre avg. A(tot)= 11.11 acres Tc= 20.73 min Q= 13.00 cfs This stream is designated for confluence with 1 othE,r by record 17 ===================================================;:=========================== "\\ File RCCEXIST.DAT Runtime 10-26-2000 09:43 Job# RCC Page 10 Record 21 Confluencing 2 streams at node 707 Process 9 Confluence Constituent streams: Stream 1: Q= 66.75* Stream 4: Q= 13.00 Tc= 12.79 Tc= 20.73 1= 2.061 1= 1. 580 @ Tc Stream 1 + Stream 4 = Confluenced 12.79 Q= 66.75 + Ratio= 8.02 = TCl/TC4 74.77 cfs Qpeak = 74.77 cfs at Tc = 12.79 minutes Confluenced streams will be designated as stream # 1 to continue dOl.mstream. ----------------------------------- Summary -------..--------------------------- Stream 1 at node 707 Length= 2410 ft. 1,40 cfs/acre avg. (cl A(tot)= 53.44 acres Tc= 12.79 min Q_. -. 74.77 cfs ----------------------------------------------------.---------------.------------ --------------------------------------------------------------------.------------ Record 22 Subarea 18 Stream 1 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed cllong reach. Node 707 to node 708 Elev 48,10 to elev 42,50 delta H = 5.60' Length= 935' Slope= .00599 Subarea: 5,32 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = 3,42'/sec for avg Q of 77,87 cfs ----------------------------------------------------.--------------------------- Tc = 12.79 + 4.56 = 17.35 min. I = l,743"/hr A(total) = 58.760 ac A(contrib) = 58.760 ac Fp = O.446"/hr C=.670 Q(subareal = 6.21 cfs Q(total) = 80.97 cfs - - -- -- -- -- -- -- - - .... .. - -- -- -- - - - - - -- - - Summary -- - - --.- .. - - - - - .. -- - - - - -- - - -- - - - - -- - - - Stream 1 to node 708 Length= 3345 ft, 1,38 cfs/acre avg. (cl A(tot)= 58,76 acres Tc~ 17.35 min Q_. -. 80.97 cfs ===================================================~===============:============ Record 23 Subarea 19 Stream 1 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 708 to node 709 Elev 42.50 to elev 39.90 delta H = 2.60' Length= 430' Slope= .00605 Subarea: 21,58 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = 3.61' /sec for avg Q of 92.65 cfs ----------------------------------------------------.--------------------------- Tc = 17.35 + 1.99 = 19.34 min. I = l,642"/hr A(total) = 80,340 ac A(contrib) = 80,340 ac Fp ~ 0.439"/hr C=.659 Q(subarea) = 23.36 cfs Q(total) = 104.33 cfs __ _ __ _ __ _ _ __ _ .. _ _ __ __ _ __ _ _ _ _ __ __ _ _ _ _ Summary _ __ _ - - - .. - - - - - - - -- - - - - n - -- -- -.. - - --- Stream 1 to node 709 Length= 3775 ft. 1.30 cfs/acre avg, (c) A(tot)= 80,34 acres Tc~ 19.34 min Q= 104,33 cfs -------------------------------------------------------------------------------- ------------------------------------------------------------------.------------- ~o I I " r~ \1 '1 I I I I I I I I I I " ~I I I .1 File RCCEXIST.DAT Runtime 10-26-2000 09:43 Job# RCC Page 11 Record 24 Subarea 20 Stream 1 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed ",long reach, Node 709 to node 710 Elev 39.90 to elev 28.00 delta H = 11.90' Length= 985' Slope= .01208 Subarea: 11.6 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = 5.37'/sec for avg Q of 109.99 cfs --------------------------------------------------..---------------------------- Tc = 19.34 + 3.06 = 22.39 min. I = 1.514"/hr A(total) = 91.940 ac A(contrib) = 91.940 ac Fp" O,429"/hr C=.645 Q(subarea) = 11.33 cfs Q(total) = 115.66 cfs ___________________________________ Summary ------..---------------------------- Stream 1 to node 710 Length= 4760 ft, 1,26 cfs/acre avg. (c) A(tot)= 91.94 acres Tc= 22.39 min Q. 115,66 cfs This stream is designated for confluence with 1 other by record 28 ==================================================::~=========================== y**************************************************i**************** New Stream Record 25 Subarea 21 Stream 5 Process 1: Initial subarea Node 601 to node 602 Elev 56.20 to elev 54.80 delta H = 1.40' Length= 200' Slope. .00700 Subarea: .1 acre Soil: C, RI= 69 Development type 1.3 = Nat/Agri, Poor cover ai= 0 --------------------------------------------------..---------------------------- k = .525 Tc = 11.79 min. I = 2.155"/hr "'.(total) = 0.100 ac Fp ,,0.469"/hr C=.704 Q(subarea) = 0.15 cfs Q(total) = 0,15 cfs ----------------------------------- Summary ------..---------------------------- Stream 5 to node 602 . Length= 200 ft. 1.52 cfs/acre avg. A(tot)= 0.10 acres T(;. 11.79 min Q. 0.15 cfs ==================================================:=~=========================== Record 26 Subarea 22 Stream 5 Process 7: Channel flow - Natural valley Subarea Q enters stream uniformly distributed a.long reach. Node 602 to node 603 Elev 54.80 to elev 49.10 delta H = 5.70' Len~,th= 450' Slope. .01267 Subarea: 2.34 acres Soil: C, RI= 69 Development type 1.3 = Nat/Agri, Poor cover ai= 0 V avg = 1.85'/sec for avg Q of 1.61 cfs ------------------------------------------------------------------------------- Tc = 11.79 + 4,05 = 15.84 min. I = 1.832"/hr A(total) = 2.440 ac Fp ,. 0.451"/hr C=.E.78 Q(subarea) 2,91 cfs Q(tota1) = 3.06 cfs - - - - -- -- - -- -- -- - - - - - - - - - -- - -- - - - - - - Summary - - - - --.. - - - - - .. - - - - - - - - - - - -- .. - - -.. - - - - Stream 5 to node 603 Length= 650 ft. 1,25 cfs/acre avg. A(tot)= 2.44 acres Tc= 15.84 min Q_. -. 3.06 cfs ===================================================;===============:============ e>\ I I.. tl j I J I I I I I I I I I I I 1- _I File RCCEXIST.DAT Runtime 10-26-2000 09:43 Job# RCC Page 12 Record 27 Subarea 23 Stream 5 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed a.long reach. Node 603 to node 604 Elev 49.10 to elev 43.00 delta H = 6.10' Length= 1070' Slop€!= .00570 Subarea: 6.63 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = 1.66'/sec for avg Q of 5.93 cfs Tc = 15.84 + A(total) = Q (subarea) 10.74 = 26.57 9.070 ac = 5.73 cfs min. --------------------------------------------------.----------------------------- ----------------------------------- Stream 5 to node 604 Length= 1720 A(tot)= --------------------------------------------------.----------------------------- --------------------------------------------------.----------------------------- I = 1.378"/hr Fp ,. 0.418"/hr C=.E27 Q(total) = 8.79 cfs Summary -- - - --... - - - - - - - - - -- - - -- - - -- - - -- - -- - ft. 0.97 cfs/acre avg. 9.07 acres Tc= 26.57 min Q= 8.79 cfs Record 28 Subarea 24 Stream 5 Process 7: Channel flow - Natural Valley Subarea Q enters stream uniformly distributed along reach. Node 604 to node 710 Elev 43.00 to elev 28.00 delta H = 15.00' Lengt.h= 1435' Slope= .01045 Subarea: 7.71 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= 0 V avg = 2.65'/sec for avg Q of 11.48 cfs --------------------------------------------------.----------------------------- Tc = 26.57 + 9.03 = 35,61 min, I = 1.173"/hr A(total) = 16.780 ac Fp ,~0.397"/hr C=.596 Q(subarea) = 5.39 cfs Q(total) = 14.18 cfs ----------------------------------- Summary ------,,---------------------------- Stream 5 to node 710 Length= 3155 ft. 0.84 cfs/acre avg. A(tot)= 16.78 acres Tc= 35.61 min Q= 14.18 cfs This stream is designated for confluence with 1 other by record 24 ==================================================;~===============;============ ~ I - I I I I I I I I I I I I I I I I J Por, File RCCEXIST.DAT Runtime 12-19-2001 07:27 Job# RCC fO"ll r Page 13 Record 29 Confluencing 2 streams at node 710 Process 9 Confluence Constituent streams: Stream 1: Q= 115.66* Stream 5: Q= 14.18 Tc= 22.39 Tc= 35.61 1= 1. 514 1= 1.173 @ Tc Stream 1 + Stream 5 Confluenced 22,39 Q= 115.66 + Ratio= 124.57 cfs 8.92 :;;; Tc1/Tc5 Qpeak = 124.57 cfs at Tc = 22.39 minutes Confluenced streams will be designated as stream # 1 to continue downstream. - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Summary - - - - - - - - - - - .. - - - .. .. - -- -- .. - - - - - - - - - - - - Stream 1 at node 710 Length=4,760' 1.15 cfs/acr,= avg. (c) A(tot)=108.72 acres Tc= 22,39 min Q= 124,57 cfs ------------------------------------------------.-------------------------------- ------------------------------------------------.------------------------------- Record 30. Subarea 25 Stream 1 Process 7: Channel flow - Natural valley Subarea Q enters stream unifonnly distributed along reach. Node 710 to node 190 Elev 28.00 to elev 17.80 delta H = 10.20' Length= 1570' Slope= .00650 Subarea: 33.75 acres Soil: C, RI= 69 Development type 1 = Natural, Agriculture ai= (I v avg = 4.22'/sec for avg Q of 138.41 cfs Tc = 22.39 + 6.20 = 28.59 min. A(total) = 142.470 ac A(contrib) = Q(subarea) = 27.67 cfs I = 1.323"/hr 142.470 ac Fp = 0.412"/hr C=,620 Q(total) ; 152.25 cfs ----------------------------------- Summary ----------------------------------- Stream 1 to node 190 Length=6, 330' 1,07 cfs/acre avg, (c) A(tot)=142.47 acres Tc= 28,59 min Q= 152.25 cfs ------.------------------------------------------.-------------------------------- ------------------------------------------------..-------------------------------- Channel flow - Natural Valley unifonnly distributed along reach. 79 Record 31 Subarea 26 Stream 1 Process 7: Subarea Q enters stream Remark: To exist. RCB @ Jed. Smith Rd & Hwy Node 190 to node 191 Elev 17.80 to elev 17.00 delta H = 0.80' Subarea: .78 acre Soil: C, RI= 69 Development type 4 = 0,4 dwelling /acre Vavg = 2.51'/sec for avg Q of 152.56 cfs Length= 370' Slope= .00216 ai= .1 -------------"-----------------------------------.-------------------.------------- Tc = 28.59 + 2.46; 31.05 min. A(total) = 143,250 ac A(contrib) = Q(subarea) = 0.63 cfs I = 1.265"/hr 143.250 ac Fp = 0.406"/hr C=,640 Q(total) = 152.88 cfs - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Summary - - -.. - - - - - - - - - - - - - - - - - - - - - - - - - - - -. - -- Stream 1 to node 191 Length=6,700' 1.07 cfs/acre avg. (c) A(tot)=143.25 acres Tc= 31,05 min Q= 152,88 cfs ------------------------------------------------.------------------------------- ------------------------------------------------.------------------------------- ~ I I I I I I I I I I I I I I I I I I I , 14- E ,'0 r. IO-1f +++++++++++++++++++++++++++++++++++++++++++++++.~~.++++++++++++++++++++++++++++++ Other: Stream 2 : Len= 920' Atot= 6.42 ac Tc:o 7.89 min Q= 13.02 cfs Stream 3 : Len= 1390 ' Atot= 9.09 ac Tc:o 14.86 min Q= 11.21 cfs Stream 4 : Len= 1330 ' Atot= 11.11 ac Tc= 20.73 min Q= 13 .00 cfs Stream 5 : Len= 3155' Atot= 16.78 ac Tc;, 35.61 min Q= 14.18 cfs ------------------------------------------------------------------------------- -----------------------------------------------.-------------------------------- End of RMH run for file RCCEXIST.DAT f(J\ . ~. ~'~".' ~'. :1" ..... ... ", " ..... . ~ .- "J ---- . '\ '., .. 4':'~'"'''' - ".' . .. " , - .... ~ .~{, !. ::.\ . ~ .!,'I:~_";''':~l' . ".......,.,. \. .;." 1,: ...::. ~ f,' : _ - .,~' "l. 1 ....".,.,... . .' . ~ . ". ..,;; .. . .~. ". ....~ ..... . I. "..'" ' .;.,,:>t . .... ---...... . .. '. , . " o , 1j :> ... ~ - :> ;") l'l f) <: f) .oj l'l '" .... -;> - :) Jl :;)