HomeMy WebLinkAboutGeotechnical/GeologicalEngineeringStudy(Oct.30,2000)
I
~EN COfRoratlon
JiJI ~/ -//Jle
I
I
-Soil Engineering and Consulting Services e Engineering Geoiogy .CompaclionTesting
.lnspeclions-ConslructionMalerialsTesting. LaboraloryTesting.PercolationTesting
-Geology. Water Resource Stooies . Phasal&1I Environmental SileAssessments
ENVIRONMENTAL & GEOTECHNICAL ENGINEERING NETWORK
I
I
I
GEOTECHNICAUGEOLOGICAL ENGINEERING STUDY
Proposed Structure, Medical Building
Lots 23 and 24 of Tract 23172
Vail Ranch area of Riverside County, California
Project Number: T2183-GS
I
October 30, 2000
I
I
I
I
I
I
I
I
Prepared for:
I
."1;;"
Don Veasey Construction
27574'Commerce Center Drive, Suite 131
Temecula, California 92590
~~,.,.,.."".,
, .
.' " "
..- \- \ F
. .
, .
. ,
, .
, .
" .
I~---'- ----;--------7 "......._.~
-, - - '"" , -
:,1:,
---
II
,"
-- ,
-- ,
, ,
.' _ _. I ' __ I ,r -."_ I
';,.....1.;,' ".1 ; / ~~ - ',->", /-;;....;;:;,,';,;..--.~....I. '-'-"~;~'~""'S'-' "-, 'C/_:.-" "
;,;~jjiiii~~~~ ._ ~~~~(;Et~Jl[ E mti:1tjj;p~!rcleN! rt ;:siJiiel';'emiipl!l?rtAg.2~90' phone: (909) 296-2230' fax: (909) 296-2237
~"' . . .~~~~tJ:&fmO.@n"@ I ;_~~=~~~~ :PPC~T . ::~~~~~;:'~'c~~;~:~:~.~~:~:.::~1 . fax: (714) 546-4052
/ ,-, -
'- "-- -'
\
I
I
I
I
I
I
I
I
I
i I
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: T2183-GS
TABLE OF CONTENTS
Section Number and Title
PaQe
1.0 EXECUTIVE SUMMARy................................................................................................... 1
2.0 INTRODUCTION ..... ...... ... .......... ....... ....... ....... ............. ............. ...... ...... ............................2
2.1 Authorization .......................... .................................. ............. ......... ........ ........ ........ 2
2.2 Scope of Study....................................................................................................... 2
2.3 Previous Site Studies.............................................................................................2
3.0 PROPOSED DEVELOPMENT I PROJECT DESCRIPTION ............................................ 2
4.0 SITE DESCRIPTION ......................................................................................................... 3
4.1 Location ................ ................................... .......................... .................. ........ ..........3
4.2 Topography............................................................................................................ 3
4.3 Vegetation.............................................................................................................. 3
4.4 Structures............................................................................................................... 3
5.0 FIELD STUDY .................................................................................................................3
6.0 LABORATORY TESTING................................................................................................. 3
6.1 General .................................................................................................................3
6.2 Classification.......................................................................................................... 4
6.3 In-Situ Moisture Content and Density Test ............................................................ 4
6.4 Maximum Dry Density I Optimum Moisture Content Relationship Test................. 4
6.5 Consolidation Test ................................................................................................. 4
6.6 Direct Shear Test................................................................................................... 5
6.7 Expansion Test ...................................................................................................... 5
7.0 ENGINEERING GEOLOGY/SEISMICITY......................................................................... 5
7.1 Geologic Setting.....................................................................................................5
7.2 Faulting................................................................................................................. 5
7.3 Seismicity............................................................................................................... 6
7.4 Earth Materials....................................................................................................... 6
7.4.1 Engineered Fill......................................................................................... 6
7.4.2 Alluvium................................................................................................... 6
7.5 Groundwater.......................................................................................................... 7
7.6 Secondary Effects of Seismic Activity................................................................ ....7
8.0 CONCLUSIONS AND RECOMMENDATIONS................................................................. 7
8.1 General ................................................................................................................. 7
8.2 Earthwork Recommendations.................. ....... ... ... .......... ... ...... ....... ........... ............8
8.2.1 General.................................................................................................... 8
8.2.2 Clearing.................................................................................................... 8
8.2.3 Excavation Characteristics....................................................................... 8
8.2.4 Suitability of On-Site Materials as FilL.................................................... 8
8.2.5 Removal and Recompaction.................................................................... 8
8.2.6 Fill Placement Requirements ................................................................... 9
8.2.7 Compaction Equipment............................................................................ 9
z;
EnGEN Corporation
I
I
I
I
I
I
I
I
I
I
!I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: T2183-GS
TABLE OF CONTENTS (Continued)
Section Number and Title
Paae
8.2.8 Shrinkage and Subsidence .................................................................... 10
8.2.9 Fill Slopes ... ............................................................ ........... .......... ........... 10
8.2.10 Subdrains ... ................. .......... .................... .................. ........................... 10
8.2.11 Observation and Testing ........................................................................10
8.2.12 Soil Expansion Potential......................................................................... 11
8.3 Foundation Design Recommendations................................................................ 11
8.3.1 General.................................................................................................. 11
8.3.2 Foundation Size ..................................................................................... 11
8.3.3 Depth of EmbedmenL.......................................................................... 12
8.3.4 Bearing Capacity....................................................................................12
8.3.5 Settlement.............................................................................................. 12
8.3.6 Lateral Capacity ..................................................................................... 13
8.3.7 Soluble Sulfate Content ......................................................................... 13
8.4 Slab-on-Grade Recommendations ......................................................................13
8.4.1 Interior Slabs ........................ ....... ............. ..................................... ......... 14
8.4.2 Exterior Slabs.............................. ....... ... ... ....... ............. ...... ... ........ ......... 14
8.5 Utility Trench Recommendations .........................................................................14
8.6 Finish Lot Drainage Recommendations............................................................... 15
8.7 Planter Recommendations...................................................................................15
8.8 Temporary Construction Excavation Recommendations..................................... 16
8.9 Retaining Wall Recommendations....................................................................... 17
8.9.1 Earth Pressures ....................................................................................... 17
8.9.2 Foundation Design...................................................................................17
8.9.3 Subdrain................................................................................................... 17
8.9.4 Backfill...................................................................................................... 18
8.9.5 Pavement Design Recommendations ..................................................... 18
9.0 PLAN REVIEW ............................................................................................................... 19
10.0 PRE-BID CONFERENCE ...... ........ ....... .............. ............. ....... ................... ........... ...... ..... 20
11.0 PRE-GRADING CONFERENCE ..................................................................................... 20
12.0 CONSTRUCTION OBSERVATIONS AND TESTING..................................................... 20
13.0 CLOSURE..................................................................................................................... 21
APPENDIX: TECHNICAL REFERENCES
SUMMARY OF RECOMMENDATIONS FOR CONVENTIONAL FOUNDATIONS
AND SLABS
EXPLORATORY BORING LOG SUMMARIES
LABORATORY TEST RESULTS
DRAWINGS
EnGEN Corporation
I~ =
," ~-'. . -....." "i.. ^" . "",:,
I~EN
I
I
I
I
I
I
I
I
I
I
I
I
I
I
COf1~oration
. Soil Engineefing and Consulling Services e EngineeringGeology-Comp action Testing
-Inspections e ConstructionMalerialsTestiIljj.laboraloryTesting-Per colationTesting
. Geology. Water Resource Studies . Phase I & II Environmental Site Assessments
ENVIRONMENTAL & GEOTECHNICAL ENGINEERING NETWORK
October 30, 2000
Don Veasey Construction
27574 Commerce Center Drive, Suite 131
Temecula, California 92590
(909) 694-1957 / FAX (909) 694-1398
Attention:
Mr. Don Veasey
Regarding:
GEOTECHNICAUGEOLOGICAL ENGINEERING STUDY
Proposed Structure, Medical Building
Lots 23 and 24 ofTract 23172
Vail Ranch area of Riverside County, California
Project Number: T2183-GS
Reference:
HLC Civil Engineering, Preliminary Grading Plan, Lots 23 and 24, Tract No.
23172, plans dated August 30, 1999.
Geocon, Inc., Report of Testing and Observation Services During Remedial
Grading for Vail Ranch Commercial Site, Tentative Tract No. 23172, Temecula,
California, report dated September 2, 1994.
1.
2.
Dear Mr. Veasey:
According to your request and signed authorization, we have performed a Geotechnical/Geological
Engineering Study for the subject project. The purpose of this study was to evaluate the existing
geologic and geotechnical conditions within the subject property with respect to recommendations for
fine grading of the site and design recommendations for foundations, slabs on-grade, etc., for the
proposed development. Submitted, herewith, are the results of this firm's findings and
recommendations, along with the supporting data.
1.0
EXECUTIVE SUMMARY
A geotechnical study of the subsurface conditions of the subject site has been performed for
the proposed development. Exploratory excavations have been completed and earth
material samples subjected to laboratory testing. The data has been analyzed with respect to
the project information furnished to us for the proposed development. It is the opinion of this
firm that the proposed development is feasible from a geotechnical/geologic standpoint,
provided that the recomme~dations presented in this report are followed in the design and
construction of the project.
, .
I'
,'"-----,.
" .
, .
\ ~ ' -
'/ " '..
, , ~ ,- - - \
/ , ,,.
/ , "
. .
.' \ - - - \.r
. -
-- \ /...
, .
-- ,
" ,
,.I :...-'
~
\ \ \ '
,.. _. I / - - i
.' I ,. i _.~__ .~....f- . __.L-
~,,,,,~,-_~,,,<,___,~___, ' ,.~J,~-,:..-.":-.'_"..> ", ,....,..1."'... ". .,',,',..>',>.'.':. .:...:..-.. :,
~;;.::~;;;~~ €;.'J;!;,mIiice.4A~w E ~i,p~,j;;kcl~ N "t' Svli<i.;l;jerii~vla" CA 92g,90'-phone: (~Q9j 2.9~:2230' fax: (909) 296-2237
,~~~T:Wi:~!\~N&~i~?}JN~~~~ IJiJ~T~~~ :ir::p:~f~~~~~~:~;t~~~~;~e:~:1~c:~'c~~1 . fax: 1714) 546-4052
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
2.0
2.1
2.2
2.3
3.0
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 2
INTRODUCTION
Authorization: This report presents the results of the geotechnical engineering study
performed on the subject site for the proposed development. Authorization to perform this
study was in the form of a signed proposal.
Scooe of Study: The scope of work performed for this study was designed to determine and
evaluate the surface and subsurface conditions within the subject site with respect to
geotechnical characteristics, and to provide recommendations and criteria for use by the
design engineers and architect for the development of the site and for design and
construction of the proposed development. The scope of work included the following: 1) site
reconnaissance and surface geologic mapping; 2) subsurface exploration; 3) sampling of
on-site earth materials; 4) laboratory testing; 5) engineering analysis of field and laboratory
data; and 6) the preparation of this report.
Previous Site Studies: The site was previously graded (see the Referenced NO.2 report).
PROPOSED DEVELOPMENT / PROJECT DESCRIPTION
Precise grading and building plans were not available at the time of this report. When these
plans become available, they should be reviewed by this office in order to make additional
recommendations (if necessary).
It is understood that the proposed improvements will consist of a medical building with one
and/or two stories, slab-on-grade type structure with associated landscape and hardscape
improvements. Grading from existing elevations to proposed elevations is expected to be
minimal. It is assumed that relatively light loads will be imposed on the foundation soils. The
foundation loads are not anticipated to exceed 2,500 pounds per lineal foot (pit) for
continuous footings. The above project description and assumptions were used as the basis
for the field and laboratory exploration and testing programs and the engineering analysis for
the conclusions and recommendations presented in this report. This office should be notified
if structures, foundation loads, grading, and/or details other than those represented herein are
proposed for final development of the site so a review can be performed, supplemental
evaluation made, and revised recommendations submitted, if required.
~
EnGEN Corporation
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
4.0
4.1.
4.2
4.3
4.4
5.0
6.0
6.1
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 3
SITE DESCRIPTION
Location: The site is on the southeast side of State Highway 79 South and George
Cushman Court in the Vail Ranch area of Riverside County.
Topoaraphv: The topography of the site at the time of this study was relatively flat.
VeCletation: At the time of the field study, vegetation across the site was light to moderate
and consisted of grasses, weeds and brush.
Structures: At the time of the field study, there were no existing structures.
FIELD STUDY
Site observations and geologic mapping were conducted on October 17, 2000 by our Staff
Geologist. A study of the property's subsurface condition was performed to evaluate
underlying earth strata and the presence of groundwater. Two (2) exploratory borings were
excavated on the study site. The borings were performed by Cal-Pac Drilling, using a truck-
mounted drill rig equipped with 8.0-inch outside diameter hollow-stem augers. The maximum
depth explored was approximately 50-feet below the existing land surface at the boring
locations. Bulk and relatively undisturbed samples of the earth materials encountered were
obtained at various depths in the exploratory borings and returned to our laboratory for
verification of field classifications and testing. Bulk samples were obtained from cuttings
developed during the excavation process and represent a mixture of the soils within the depth
indicated on the logs. Relatively undisturbed samples of the earth materials encountered
were obtained by driving a thin-walled steel sampler lined with 1.0-inch high, 2.42-inch inside
diameter brass rings. The sampler was driven with successive drops of a 140-pound weight
having a free fall of approximately 30-inches. The blow counts for each successive 6.0-
inches of penetration, or fraction thereof, are shown in the Exploratory Boring Log Summaries
presented in the Appendix. The ring samples were retained in close-fitting moisture-proof
containers and returned to our laboratory for testing. The approximate locations of the
exploratory borings and pits are denoted on the Geotechnical Study Site Plan. The
exploratory borings were backfilled with cuttings.
LABORATORY TESTING
General: The results of laboratory tests performed on samples of earth material obtained
during the field study are presented in the Appendix. Following is a listing and brief
explanation of the laboratory tests which were performed. The samples obtained during the
~
EnGEN Corporation
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
6.2
6.3
6.4
6.5
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 4
field study will be discarded 30 days after the date of this report. This office should be notified
immediately if retention of samples will be needed beyond 30 days.
Classification: The field classification of soil materials encountered in the exploratory
borings and pits were verified in the laboratory in general accordance with the Unified Soils
Classification System, ASTM D2488-90, Standard Practice for Determination and
Identification of Soils (Visual-Manual Procedures). The final classification is shown in the
Exploratory Boring Log Summaries presented in the Appendix.
In-Situ Moisture Content and Density Test: The in-situ moisture content and dry density
were determined in general accordance with ASTM D2216-90 and D2937-83(1990)
procedures, respectively, for each selected undisturbed sample obtained. The dry density is
determined in pounds per cubic foot and the moisture content is determined as a percentage
of the oven dry weight of the soil. Test results are shown in the Exploratory Boring Log
Summaries presented in the Appendix.
Maximum Dry Density I Optimum Moisture Content Relationship Test: Maximum dry
density I optimum moisture content relationship determination were performed on samples of
near-surface earth material in general accordance with ASTM D1557 -91 procedures using a
4.0-inch diameter mold. Samples were prepared at various moisture contents and
compacted in five (5) layers using a 10.pound weight dropping 18-inches and with 25 blows
per layer. A plot of the compacted dry density versus the moisture content of the specimens
is constructed and the maximum dry density and optimum moisture content determined from
the plot.
Consolidation Test: Settlement predictions of the on-site soil and compacted fill behavior
under load were made, based on consolidation tests that were performed in general
accordance with ASTM D2435-90 procedures. The consolidation apparatus is designed to
receive a 1.0-inch high, 2.416-inch diameter ring sample. Porous stones are placed in
contact with the top and bottom of each specimen to permit addition and release of pore
water and pore pressure. Loads normal to the face of the specimen are applied in several
increments in a geometric progression under both field moisture and submerged conditions.
The resulting changes in sample thickness are recorded at selected time intervals. Water
was added to the test apparatus at various loads to create a submerged condition and to
measure the collapse potential (hydroconsolidation) of the sample. The resulting change in
sample thickness was recorded.
~
EnGEN Corpor.tion
I
I
I
I
I
I
I
I
I
I
I
I I
I
I
I
I
I
I
I
6.6
6.7
7.0
7.1
7.2
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 5
Direct Shear Test: Direct shear tests were performed on selected samples of near-surface
earth material in general accordance with ASTM D3080-90 procedures. The shear machine
is of the constant strain type. The shear machine is designed to receive a 1.0-inch high,
2.416-inch diameter ring sample. Specimens from the sample were sheared at various
pressures normal to the face of the specimens. The specimens were tested in a submerged
condition. The maximum shear stresses were plotted versus the normal confining stresses to
determine the shear strength (cohesion and angle of internal friction).
Expansion Test: Laboratory expansion tests were performed on samples of near-surface
earth material in general accordance with the Uniform Building Code (UBC) Standard. In this
testing procedure, a remolded sample is compacted in two (2) layers in a 4.0-inch diameter
mold to a total compacted thickness of approximately 1.0-inch by using a 5.5-pound weight
dropping 12-inches and with 15 blows per layer. The sample should be compacted at a
saturation between 49 and 51 percent. After remolding, the sample is confined under a
pressure of 144 pounds per square foot (pst) and allowed to soak for 24 hours. The resulting
volume change due to the increase in moisture content within the sample is recorded and the
Expansion Index (EI) calculated. The expansion test result is presented on the UBC
Laboratory Expansion Test Results sheet.
ENGINEERING GEOLOGY/SEISMICITY
Geoloaic Settina: The site is located in the Northern Peninsular Range on the southern
sector of the structural unit known as the Perris Block. The Perris Block is bounded on the
northeast by the San Jacinto Fault Zone, on the southwest by the Elsinore Fault Zone, and on
the north by the Cucamonga Fault Zone. The southern boundary of the Perris Block is not as
distinct, but is believed to coincide with a complex group of faults trending southeast from the
Murrieta, California, area. The Peninsular Range is characterized by large Mesozoic age
intrusive rock masses flanked by volcanic, metasedimentary, and sedimentary rocks.
Various thicknesses of colluvial/ alluvial sediments derived from the erosion of the elevated
portions of the region fill the low lying areas. Engineered fill and alluvium underlie the site.
The earth materials encountered on the subject site are described in more detail in
subsequent sections of this report.
Faultina: The site is not located within an Alquist-Priolo Earthquake Fault Zone.
Elsinore Fault Zone: The Elsinore Fault Zone (Wildomar Fault) is located approximately
12,000 feet to the southwest of the site. The Elsinore Fault Zone is a major right lateral
"\
EnGEN Corporation
I
I.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 6
strike-slip fault system, which has experienced strong earthquakes in historical times (1856,
1894, and 1910) and exhibits late Quaternary movement.
San Jacinto Fault Zone: The San Jacinto Fault Zone is located approximately 18 miles
northeast of the subject site and trends northwest-southeast. The San Jacinto Fault is a
major right lateral strike-slip fault, which has displayed surface rupture and associated
seismic ground shaking in 1899, 1918, 1923, 1934, 1937, 1942, and 1954.
San Andreas Fault Zone: The southem segment of the San Andreas Fault Zone is located
approximately 28 miles northeast of the site, and trends northwest-southeast across the
southwestern front of the San Bernardino Mountains. The San Andreas Fault is a major right
lateral strike-slip fault, which exhibited major surface rupture in 1857 during the Fort Tejon
earthquake and again in 1868 during the Dos Palmas Earthquake.
7.3 Seismicity: Based on computer software by Thomas F. Blake (EQSEARCH), the
maximum peak ground acceleration experienced at the site since 1800 was approximately
0.26g from a magnitude 6.8 earthquake in 1918. The estimated peak ground acceleration
for the site is 0.60g. The following factors apply:
Fault Type: Type B Fault
Closest Distance to Known Fault: 3.5 KM
Soil Profile Type: SD
7.4 Earth Materials: A brief description of the earth materials encountered in the exploratory
excavations is presented in the following sections. A more detailed description of the earth
materials encountered is presented on the Exploratory Boring Log Summaries presented in
the Appendix. The earth material strata as shown on the logs represent the conditions in
the actual exploratory locations and other variations may occur between the excavations.
Lines of demarcation between the earth materials on the logs represented the approximate
boundary between the material types; however, the transition may be gradual.
7.4.1 Engineered Fill: Approximately five (5) feet of engineered fill was placed on the site in
1994 (Referenced No. 2 report). Engineered fill encountered consisted of silty sand that
was found to be damp and medium dense to dense.
7.4.2 Alluvium: Alluvial materials were encountered below the engineered fill materials to the
maximum depth explored (50-feet). Alluvium consisted of sand and silty sand that was
found to be slightly moist to wet and loose to dense in-place.
'a
EnGEN Corporation
II
I
I I
I
I
I
I
I
I
I"
I
I
I
I
I
I
I
I
I
7.5
7.6
8.0
8.1
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 7
Groundwater: Groundwater was encountered at a depth of approximately 29-feet below
ground surface.
Secondarv Effects of Seismic Activitv: The secondary effects of seismic activity
normally considered as possible hazards to a site include various types of ground failure
and induced flooding. The probability of occurrence of each type of ground failure depends
on the severity of the earthquake, the distance of the site from the zone of maximum
energy release of the quake, the topography of the site, the subsurface materials at the
site, and groundwater conditions beneath the site, besides other factors. Due to the overall
favorable geologic structure and topography of the area, the potential for earthquake-
induced landslides or rockfalls is considered low. Due to the lack of active faulting on the
site, the potential for hazards associated with fault rupture is considered low.
The potential for hazards associated with liquefaction exists. However, the potential for
hazards associated with liquefaction should be mitigated if the earthwork and foundation
recommendations made in this report are adhered to.
CONCLUSIONS AND RECOMMENDATIONS
General: The conclusions and recommendations presented in this report are based on the
results of field and laboratory data obtained from the exploratory excavations located
across the property, experience gained from work conducted by this firm on projects within
the property and general vicinity, and the project description and assumptions presented in
the Proposed Development I Project Description section of this report. Based on a review
of the field and laboratory data and the engineering analysis, the proposed development is
feasible from a geotechnical I geologic standpoint. The actual conditions of the near-
surface supporting material across the site may vary. The nature and extent of variations
of the surface and subsurface conditions between the exploratory excavations may not
become evident until construction. If variations of the material become evident during
construction of the proposed development, this office should be notified so that EnGEN
Corporation can evaluate the characteristics of the material and, if needed, make revisions
to the recommendations presented herein. Recommendations for general site grading,
foundations, slab support, pavement design, slope maintenance, etc., are presented in the
subsequent paragraphs.
EnGEN Corporation
<\
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8.2
8.2.1
8.2.2
8.2.3
8.2.4
8.2.5
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 8
Earthwork Recommendations
General: The grading recommendations presented in this report are intended for: 1) the use
of a conventional shallow foundation system and concrete slabs cast on-grade; and 2) the
rework of unsuitable near-surface earth materials to create an engineered building pad and
suitable support for exterior hardscape (sidewalks, patios, etc.) and pavement. If pavement
subgrade soils are prepared at the time of rough grading of the building site and the areas are
not paved immediately, additional observations and testing of the subgrade soil will have to
be performed before placing aggregate base material or asphaltic concrete or PCC pavement
to locate areas which may have been damaged by construction traffic, construction activities,
and/or seasonal wetting and drying. The following recommendations may need to be
modified and/or supplemented during rough grading as field conditions require.
Clearinll: All debris, roots, grasses, weeds, brush and other deleterious materials should be
removed from the proposed structure, exterior hardscape and pavement areas and areas to
receive structural fill before grading is performed. No disking or mixing of organic material
into the soils should be performed. Man-made objects encountered should be overexcavated
and exported from the site. Wells (if encountered) should be abandoned in accordance with
County/City regulations.
Excavation Characteristics: Excavation and trenching within the subject property is
anticipated to be relatively easy in the near-surface earth materials.
Suitability of On-Site Materials as Fill: In general, the on-site earth materials present are
considered suitable for reuse as fill. Fill materials should be free of significant amounts of
organic materials and/or debris and should not contain rocks or clumps greater than 6-inches
in maximum dimension.
Removal and Recompaction: As mentioned above, precise grading and building plans
were not available at the time of this report. When these plans become available, they should
be reviewed by this office in order to make additional recommendations, if necessary. All
existing undocumented fills, incompetent alluvium, and/or unsuitable, loose, or disturbed
near-surface soil in areas which will support structural fills, structures, exterior hardscape
(sidewalks, patios, etc.), and pavement should be removed. The following recommendations
are based on field and laboratory results:
. To mitigate for the potential hazards associated with liquefaction, removals below the
proposed structure area should extend to a depth of ten (10) feet below proposed pad
EnGEN Corporation
\'0
I
I
I
I
I
I
I
I
I
I
I
I
I
! I
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 9
grade. Horizontal extent of removals should be a minimum of ten (10) feet beyond the
perimeter footings.
. All hardscape areas to receive fill (and shallow cuts of less than 12-inches) should be
scarified 12-inches, moisture conditioned to near optimum moisture and then
recompacted to a minimum of 90 percent relative compaction. Hardscape areas with
greater than 12-inches of proposed cut need no special remedial grading unless
otherwise specified by the Soil Engineer's Representative.
. All exposed removal bottoms should be inspected by the Soil Engineer's representative
prior to placement of any fill.
. The approved exposed bottoms of all removal areas should be scarified 12-inches,
brought to near optimum moisture content, and compacted to a minimum of 90 percent
relative compaction before placement of fill. Maximum dry density and optimum moisture
content for compacted materials should be determined according to ASTM D1557-91
procedures.
8.2.6 Fill Placement Reauirements: All fill material, whether on-site material or import, should be
approved by the Project Geotechnical Engineer and/or his representative before placement.
All fill should be free of vegetation, organic material, debris, and oversize material. Import fill
should be no more expansive than the existing on-site material. Approved fill material should
be placed in horizontal lifts not exceeding 10-inches in compacted thickness and watered or
aerated to obtain near optimum moisture content (:t2.0 percent of optimum). Each lift should
be spread evenly and should be thoroughly mixed to ensure uniformity of soil moisture.
Structural fill should meet a minimum relative compaction of 90 percent. Maximum dry
density and optimum moisture content for compacted materials should be determined in
accordance with ASTM D1557-91 procedures. Moisture content of fill materials should not
vary more than 2.0 percent from optimum, unless approved the Project Geotechnical
Engineer.
8.2.7 Comoaction Eauioment: It is anticipated that the compaction equipment to be used for the
project will include a combination of rubber-tired and sheepsfoot rollers to achieve proper
compaction. Compaction by rubber-tired or track-mounted equipment, by itself, may not be
sufficient. Adequate water trucks, water pulls, and/or other suitable equipment should be
available to provide sufficient moisture and dust control. The actual selection of equipment is
the responsibility of the contractor performing the work and should be such that uniform and
proper compaction of the fill is achieved.
EnGEN Corporation
\\
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 10
8.2.8 Shrinkaae and Subsidence: There will be a material loss due to the clearing and grubbing
operations. Shrinkage of existing alluvium that is excavated and replaced as compacted fill
should be anticipated. It is estimated that the average shrinkage of these soils will be on the
order of 10 to 15 percent, based on fill volumes when compacted to a minimum of 90 percent
relative compaction. A higher relative compaction would mean a larger shrinkage value. No
shrinkage is expected from existing engineered fill materials.
8.2.9 Fill Slopes: Finish fill slopes should not be inclined steeper than 2:1 (horizontal to vertical).
Fill slope surfaces should be compacted to 90 percent relative compaction based on a
maximum dry density for the soil as determined by ASTM D1557-78(90) procedures to the
face of the finished slope. Fill slopes should be constructed in a skillful manner so that they
are positioned at the design orientations and slope ratio. Achieving a uniform slope surface
by subsequent thin wedge filling should be avoided. Any add-on correction to a fill slope
should be conducted under the observation and recommendations of the Project
Geotechnical Engineer. The proposed add-on correction procedures should be submitted in
writing by the contractor prior to commencement of corrective grading and reviewed by the
Project Geotechnical Engineer. Compacted fill slopes should be backrolled with suitable
equipment for the type of soil being used during fill placement at intervals not exceeding 4.0
feet in vertical height. As an alternative to the backrolling of the fill slopes, over-filling of the
slopes will be considered acceptable and preferred. The fill slope should be constructed by
over-filling with compacted fill a minimum of 3.0 feet horizontally, and then trimmed back to
exposed the dense inner core of the slope surface.
8.2.10 Subdrains: Although the need for subdrains is not anticipated at this time, final
recommendations should be made during grading by the Project Geologist.
8.2.11 Observation and Testina: During grading, observation and testing should be conducted by
the Geotechnical Engineer and/or his representative to verify that the grading is being
performed according to the recommendations presented in this report. The Project
Geotechnical Engineer and/or his representative should observe the scarification and the
placement of fill and should take tests to verify the moisture content, density, uniformity and
degree of compaction obtained. Where testing demonstrates insufficient density, additional
compaction effort, with the adjustment of the moisture content where necessary, should be
applied until retesting shows that satisfactory relative compaction has been obtained. The
results of observations and testing services should be presented in a formal Finish Grading
EnGEN Corporation
\1/
I
I
I
I
I
I
I
I
I
I
I
I
, I
II
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 11
Report following completion of the grading operations. Grading operations undertaken at the
site without the Geotechnical Engineer and/or his representative present may result in
exclusions of the affected areas from the finish grading report for the project. The presence of
the Geotechnical Engineer and/or his representative will be for the purpose of providing
observations and field testing and will not include any supervision or directing of the actual
work of the contractor or the contractor's employees or agents. Neither the presence and/or
the non-presence of the Geotechnical Engineer and/or his field representative nor the field
observations and testing shall excuse the contractor in any way for defects discovered in the
contractor's work.
8.2.12 Soil Expansion Potential: Upon completion of fine grading of the building pad, near-
surface samples should be obtained for expansion potential testing to identify the
expansion potential for each pad and assign appropriate foundation and slab-on-grade
recommendations for construction. The results of recent testing indicate a very low
expansion potential (EI=O). However, expansion potential may change at the completion of
grading. Therefore, design recommendations to deal with various degrees of expansion
potential are presented in the Summary of Recommendations for Conventional Foundation
and Slabs in the Appendix of this report.
8.3 Foundation Desion Recommendations:
8.3.1 General: Foundations for the proposed structure may consist of conventional column
footings and continuous wall footings founded upon properly compacted fill. The
recommendations presented in the subsequent paragraphs for foundation design and
construction are based on geotechnical characteristics and a low expansion potential for the
supporting soils and are not intended to preclude more restrictive structural requirements.
The Structural Engineer for the project should determine the actual footing width and depth to
resist design vertical, horizontal, and uplift forces.
8.3.2 Foundation Size: Continuous footings should have a minimum width of 12-inches.
Continuous footings should be continuously reinforced with a minimum of one (1) NO.4 steel
reinforcing bar located near the top and one (1) NO.4 steel reinforcing bar located near the
bottom of the footings to minimize the effects of slight differential movements which may
occur due to minor variations in the engineering characteristics or seasonal moisture change
in the supporting soils. In the case of concrete tilt-up or masonry structures when the wall
and footing combine to form a deep beam system, the Structural Engineer may alter the
EnGEN Corporation
\~
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I I
I
I
I
I
Don Veasey Construction
Project No: 2183-G5
October 2000
Page 12
reinforcing as necessary. Final foundation size and reinforcing should be determined based
on the expansive potential of the supporting soils in accordance with the Summary of
Recommendations for Conventional Foundations and Slabs presented in the Appendix of this
report. Column footings should have a minimum width of 18-inches by 18-inches and be
suitably reinforced, based on structural requirements. A grade beam, founded at the same
depths and reinforced the same as the adjacent footings, should be provided across
doorways, garage or any other types of perimeter openings.
8.3.3 Depth of Embedment: Exterior and interior footings founded in properly compacted fill
should extend to a minimum depth of 18-inches below lowest adjacent finish grade for single
story structures and two story structures. Deeper footings may be necessary for expansive
soils purposes in accordance with the Summary of Recommendations for Conventional
Foundation and Slabs in the Appendix of this report, depending on the final determination of
each lots expansive potential.
8.3.4 Bearina Capacity: Provided the recommendations for site earthwork, minimum footing
width, and minimum depth of embedment for footings are incorporated into the project design
and construction, the allowable bearing value for design of continuous and column footings
for the total dead plus frequently-applied live loads is 2,000 psf for continuous footings and
2,000 psf for column footings in properly compacted fill. The allowable bearing value has a
factor of safety of at least 3.0 and may be increased by 33.3 percent for short durations of live
and/or dynamic loading such as wind or seismic forces. Once grading is completed, the
nature of the imported soils can be tested to determine if increases in the allowable bearing
value is justified.
8.3.5 Settlement: Footings designed according to the recommended bearing values for
continuous and column footings, respectively, and the maximum assumed wall and column
loads are not expected to exceed a maximum settlement of 0.75-inch or a differential
settlement of 0,25-inch between adjacent column loads under static load conditions in
properly compacted fill. An evaluation of settlement due to possible liquefaction has been
made based on SPT values, fines content and potential earthquake magnitude. The results
indicate a possibility of potential seismically induced settlement on the order of 7 .1-inches due
to an earthquake event of magnitude 6.8 on the Elsinore Fault. As a result, potential
differential settlement on the order of Yz of the total may be experienced across the building
length. The probability of such an occurrence is considered remote. However, the Project
EnGEN Corporation
'A
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 13
Structural Engineer should be conservative in providing tension ties at the roof connections to
promote the concept of "life safety" design and minimize the potential of roof collapse in the
event of liquefaction.
8.3.6 Lateral Capacity: Additional foundation design parameters for resistance to static lateral
forces, are as follows:
Allowable Lateral Pressure (Equivalent Fluid Pressure), Passive Case:
Compacted Fill - 250 pcf
Allowable Coefficient of Friction:
Compacted Fill - 0.35
Lateral load resistance may be developed by a combination of friction acting on the base of
foundations and slabs and passive earth pressure developed on the sides of the footings and
stem walls below grade when in contact with properly compacted fill. The above values are
allowable design values and may be used in combination without reduction in evaluating the
resistance to lateral loads. The allowable values may be increased by 33.3 percent for short
durations of live and/or dynamic loading, such as wind or seismic forces. For the calculation
of passive earth resistance, the upper 1.0-foot of material should be neglected unless
confined by a concrete slab or pavement. The maximum recommended allowable passive
pressure is 5.0 times the recommended design value.
8.3.7 Soluble Sulfate Content: Excessive amounts of soluble sulfates were not detected in the
representative sample used for chemical analysis. As a result, normal Type II cement can be
used for all concrete in contact with native soils at the site.
8.4 Slab-on-Grade Recommendations: The recommendations for concrete slabs, both interior
and exterior, excluding PCC pavement, are based upon the expansion potential for the
supporting material. Concrete slabs should be designed to minimize cracking as a result of
shrinkage. Joints (isolation, contraction, and construction) should be placed in accordance
with the American Concrete Institute (ACI) guidelines. Special precautions should be taken
during placement and curing of all concrete slabs. Excessive slump (high water / cement
ratio) of the concrete and/or improper curing procedures used during either hot or cold
weather conditions could result in excessive shrinkage, cracking, or curling in the slabs. It is
recommended that all concrete proportioning, placement, and curing be performed in
accordance with ACI recommendations and procedures.
EnGEN Corpor3tion
\"5'
I
,I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 14
8.4.1 Interior Slabs: Interior concrete slabs-on-grade should be a minimum of 4.0-inches actual in
thickness and be underlain by a 1.0 to 2.0 inches of clean coarse sand or other approved
granular material placed on properly prepared subgrade per the Earthwork
Recommendations Section of this report. Slabs subjected to crane loads for tilt-up purposes
should bea minimum of 5-inches in thickness. Minimum slab reinforcement should consist of
#3 bars @24-inches on center each way, or a suitable equivalent, as determined by the
Project Structural Engineer. Varying degrees of expansive potential require additional slab
reinforcing and thickness in accordance with the Summary of Recommendations for
Conventional Foundation and Slabs presented in the Appendix of this report. Final lot
identification and slab construction requirements will be presented in the compaction report
upon completion of grading. It is essential that the reinforcing be placed at mid-depth in the
slab. The concrete section and/or reinforcing steel should be increased appropriately for
anticipated excessive or concentrated floor loads. In areas where moisture sensitive floor
coverings are anticipated over the slab, we recommend the use of a polyethylene vapor
barrier with a minimum of 6.0 mil in thickness be placed beneath the slab. The moisture
barrier should be overlapped or sealed at splices and covered top and bottom by a 1.0-inch to
2.0-inch minimum layer of clean, moist (not saturated) sand to aid in concrete curing and to
minimize potential punctures.
8.4.2 Exterior Slabs: All exterior concrete slabs cast on finish subgrade (patios, sidewalks, etc.,
with the exception of PCC pavement) should be a minimum of 4.0-inches nominal in
thickness and should be underlain by a minimum of 12.0-inches of soil that has been
prepared in accordance with the Earthwork Recommendation section of this report.
Reinforcing in the slabs and the use of a compacted sand or gravel base beneath the slabs
should be according to the current local standards. Subgrade soils should be moisture
conditioned to at least optimum moisture content to a depth of 12.0-inches and proof
compacted to a minimum of 90 percent relative compaction based on ASTM D1557-91
procedures immediately before placing the concrete.
8.5 Utilitv Trench Recommendations: Utility trenches within the zone of influence of
foundations or under building floor slabs, exterior hardscape, and/or pavement areas should
be backfilled with properly compacted soil. All utility trenches within the building pad and
extending to a distance of 5.0-feet beyond the building exterior footings should be backfilled
with on-site or similar soil. Where interior or exterior utility trenches are proposed to pass
EnGEN Corporation
\IP
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8.6
8.7
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 15
beneath or parallel to building, retaining wall, and/or decorative concrete block perimeter wall
footings, the bottom of the trench should not be located below a 1: 1 plane projected
downward from the outside bottom edge of the adjacent footing unless the utility lines are
designed for the footing surcharge loads. It is recommended that all utility trenches
excavated to depths of 5.D-feet or deeper be cut back according to the "Temporary
Construction Cut" section of this report or be properly shored during construction. Backfill
material should be placed in a lift thickness appropriate for the type of backfill material and
compaction equipment used. Backfill material should be compacted to a minimum of 90
percent relative compaction by mechanical means. Jetting or flooding of the backfill material
will not be considered a satisfactory method for compaction unless the procedures are
reviewed and approved in writing by the Project Geotechnical Engineer. Maximum dry
density and optimum moisture content for backfill material should be determined according to
ASTM D1557-91 procedures.
Finish Lot Drainaae Recommendations: Positive drainage should be established away
from the tops of slopes, the exterior walls of structures, the back of retaining walls, and the
decorative concrete block perimeter walls. Finish lot surface gradients in unpaved areas
should be provided next to tops of slopes and buildings to guide surface water away from
foundations and slabs and from flowing over the tops of slopes. The surface water should be
directed toward suitable drainage facilities. Ponding of surface water should not be allowed
next to structures or on pavements. In unpaved areas, a minimum positive gradient of 2.0
percent away from the structures and tops of slopes for a minimum distance of 5.0-feet and a
minimum of 1.0 percent pad drainage off the property in a nonerosive manner should be
provided. Landscape trees and plants with high water needs should be planted at least 5.0-
feet away from the walls of the structures. Downspouts from roof drains should discharge to
a surface which slopes away from the structure a minimum of 5.0-feet from the exterior
building walls. In no case should downspouts from roof drains discharge into planter areas
immediately adjacent to the building unless there is positive drainage away from the structure
at a minimum gradient of 2.0 percent, directed onto a permanent all-weather surface or
subdrain system.
Planter Recommendations: Planters around the perimeter of the structures should be
designed to ensure that adequate drainage is maintained and minimal irrigation water is
allowed to percolate into the soils underlying the buildings.
EnGEN Corporation
\1.
I
I
, I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8.8
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 16
Temporarv Construction Excavation Recommendations: Temporary construction
excavations for rough grading, foundations, retaining walls, utility trenches, etc., more than
5.0-feet in depth and to a maximum depth of 15-feet should be properly shored or cut back to
the following inclinations:
Earth Material Inclination
Alluvium or Compacted Fill 1.5: 1
No surcharge loads (spoil piles, earthmoving equipment, trucks, etc.) should be allowed
within a horizontal distance measured from the top of the excavation slope equal to 1.5 times
the depth of the excavation. Excavations should be initially observed by the project
Geotechnical Engineer, Geologist and/or their representative to verify the recommendations
presented or to make additional recommendations to maintain stability and safety. Moisture
variations, differences in the cohesive or cementation characteristics, or changes in the
coarseness of the deposits may require slope flattening or, conversely, permit steepening
upon review by the project Geotechnical Engineer, Geologist, or their representative. Deep
utility trenches may experience caving which will require special considerations to stabilize
the walls and expedite trenching operations. Surface drainage should be controlled along the
top of the slope to preclude erosion of the slope face. If excavations are to be left open for
long periods, the slopes should be sprayed with a protective compound and/or covered to
minimize drying out, raveling, and/or erosion of the slopes. For excavations more than 5.0-
feet in depth which will not be cut back to the recommended slope inclination, the contractor
should submit to the owner and/or the owner's designated representative detailed drawings
showing the design of shoring, bracing, sloping, or other provisions to be made for worker
protection. If the drawings do not vary from the requirements of the OSHA Construction
Safety Orders (CAL OSHA or FED OSHA, whichever is applicable for the project at the time
of construction), a statement signed by a registered Civil or Structural Engineer in the State of
California, engaged by the contractor at his expense, should be submitted certifying that the
contractor's excavation safety drawings comply with OSHA Construction Orders. If the
drawings vary from the applicable OSHA Construction Safety Orders, the drawings should be
prepared, signed, and sealed by a Registered Civil or Structural Engineer in the State of
California. The contractor should not proceed with any excavations until the project owner or
his designated representative has received and acknowledged the properly prepared
excavation safety drawings.
EnGEN Corporation
\'t1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8.9
8.9.1
8.9.2
8.9.3
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 17
Retaining Wall Recommendations:
Earth Pressures: Retaining walls backfilled with non-expansive granular soil (EI=O) or very
low expansive potential materials (Expansion Index of 20 or less) within a zone extending
upward and away from the heel of the footing at a slope of 0.5:1 (horizontal to vertical) or
flatter can be designed to resist the following static lateral soil pressures:
Condition Level Backfill 2:1 Slope
Active 30 pet 45 pcf
At Rest 58 pcf --
The on-site materials that exhibit low expansivity may be used as backfill within the active /
at-rest pressure zone as defined above. Walls that are free to deflect 0.001 radian at the top
should be designed for the above-recommended active condition. Walls that are not capable
of this movement should be assumed rigid and designed for the at-rest condition. The above
values assume well drained backfill and no buildup of hydrostatic pressure. Surcharge loads,
dead and/or live, acting on the backfill within a horizontal distance behind the wall equal to
height of the wall, should also be considered in the design. Uniform surcharge pressures
should be applied as an additional uniform (rectangular) pressure distribution. The lateral
earth pressure coefficient for a uniform vertical surcharge load behind the wall is 0.50.
Foundation Design: Retaining wall footings should be founded to the same depths into
properly compacted fill, or firm, competent, undisturbed, natural soil as standard foundations
and may be designed for the same average allowable bearing value across the footing (as
long as the resultant force is located in the middle one-third of the footing),and with the same
allowable static lateral bearing pressure and allowable sliding resistance as previously
recommended. When using the allowable lateral pressure and allowable sliding resistance, a
factor of safety of 1.0 may be used. If ultimate values are used for design, an approximate
factor of safety of 1.5 should be achieved.
Subdrain: A subdrain system should be constructed behind and at the base of all retaining
walls to allow drainage and to prevent the buildup of excessive hydrostatic pressures. Typical
subdrains may include weep holes with a continuous gravel gallery, perforated pipe
surrounded by filter rock, or some other approved system. Gravel galleries and/or filter rock, if
not properly designed and graded for the on-site and/or import materials, should be enclosed
in a geotextile fabric such as Mirafi 140N, Supac 4NP, or a suitable substitute in order to
prevent infiltration of fines and clogging of the system. The perforated pipes should be at
least 4.0 inches in diameter. Pipe perforations should be placed downward. Gravel filters
EnGEN Corporation
\<:t..
I
I
I
II
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 18
should have volume of at least 1.0 cubic foot per lineal foot of pipe. Subdrains should
maintain a positive flow gradient and have outlets that drain in a non-erosive manner. In the
case of subdrains for basement walls, they need to empty into a sump provided with a
submersible pump activated by a change in the water level.
8.9.4 Backfill: Backfill directly behind retaining walls (if backfill width is less than 3 feet) may
consist of 0.5 - to 0.75-inch diameter, rounded to subrounded gravel enclosed in a geotextile
fabric such as Mirafi 140N, Supac 4NP, or a suitable substitute or a clean sand (Sand
Equivalent Value greater than 50) water jetted into place to obtain proper compaction. If
water jetting is used, the subdrain system should be in place. Even if water jetting is used,
the sand should be densified to a minimum of 90 percent relative compaction. If the specified
density is not obtained by water jetting, mechanical methods will be required. If other types of
soil or gravel are used for backfill, mechanical compaction methods will be required to obtain
a relative compaction of at least 90 percent of maximum dry density. Backfill directly behind
retaining walls should not be compacted by wheel, track or other rolling by heavy construction
equipment unless the wall is designed for the surcharge loading. If gravel, clean sand or
other imported backfill is used behind retaining walls, the upper 18-inches of backfill in
unpaved areas should consist of typical on-site material compacted to a minimum of 90
percent relative compaction in order to prevent the influx of surface runoff into the granular
backfill and into the subdrain system. Maximum dry density and optimum moisture content
for backfill materials should be determined in accordance with ASTM D1557-78 (90)
procedures.
8.9.5 Pavement Desian Recommendations: Preliminary pavement recommendations are
presented based on R-Value testing of soils obtained from the site and an assumed future
traffic loading expressed in terms of a Traffic Index (TI).
Pavement sections have been determined in general accordance with CAL TRANS design
procedures based on a (TI) of 5.0 for automobile areas, a (TI) of 6.0 for truck traffic areas,
and an R-Value of 63.
Tvpe of Traffic Traffic Index Pavement Section
Automobile 5.0 3 inch AC/4.0 inches AB
Truck 6.0 3 inch AC/4.0 inches AB
Automobile 5.0 Portland Cement Pavement Alternative: 5 inch
PCC/95 percent SubQrade
Truck 6.0 Portland Cement Pavement Alternative: 6 inch
PCC/95 oercent Subarade
EnGEN Corporation
1P
I
I
I
i I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
9.0
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 19
The project designer should choose the appropriate pavement section for the anticipated
traffic pattern and delineate the respective areas on the site plan. Since actual calculations
may, at times, conflict with City/County adopted standards, the AC pavement sections and
the Portland Cement pavement section, are subject to review and approval by the
City/County. Asphalt concrete pavement materials should be as specified in Section 39 of
the current CAL TRANS Standard Specifications or a suitable equivalent. Aggregate base
should conform to Class 2 material as specified in Section 26-1.02B of the current
CAL TRANS Standard Specifications or a suitable equivalent. The subgrade soil, including
utility trench backfill, should be compacted to at least 90 percent relative compaction. The
aggregate base material should be compacted to at least 95 percent relative compaction.
Maximum dry density and optimum moisture content for subgrade and aggregate base
materials should be determined according to ASTM D1557-91 procedures. In dumpster pick-
up areas, and in areas where semi-trailers are to be parked on the pavement such that a
considerable load is transferred from small wheels, it is recommended that rigid Portland
Cement concrete pavement with a minimum thickness of 7.0 inches be provided in these
areas. This will provide for the proper distribution of loads to the subgrade without causing
deformation of the pavement surface. Special consideration should also be given to areas
where truck traffic will negotiate small radius turns. Asphaltic concrete pavement in these
areas should utilize stiffer emulsions or the areas should be paved with Portland Cement
concrete. In areas where Portland Cement concrete is to be placed directly on subgrade, the
subgrade should be compacted to a minimum of 95% relative compaction. If pavement
subgrade soils are prepared at the time of rough grading of the building site and the areas are
not paved immediately, additional observations and testing will have to be performed before
placing aggregate base material, asphaltic concrete, or PCC pavement to locate areas that
may have been damaged by construction traffic, construction activities, and/or seasonal
wetting and drying. In the proposed pavement areas, soil samples should be obtained at the
time the subgrade is graded for R-Value testing according to California Test Method 301
procedures to verify the pavement design recommendations.
PLAN REVIEW
Subsequent to formulation of final plans and specifications for the project, but before bids
for construction are requested, grading plans for the proposed development should be
reviewed by EnGEN Corporation to verify compatibility with site geotechnical conditions
EnGEN Corporation
z;..
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 20
and conformance with the recommendations contained in this report. If EnGEN
Corporation is not accorded the opportunity to make the recommended review, we will
assume no responsibility for misinterpretation of the recommendations presented in this
report.
10.0 PRE-BID CONFERENCE
It may be desirable to hold a pre-bid conference with the owner or an authorized
representative, the Project Architect, the Project Civil Engineer, the Project Geotechnical
Engineer, and the proposed contractors present. This conference will provide continuity in
the bidding process and clarify questions relative to the grading and construction
requirements of the project.
11.0 PRE-GRADING CONFERENCE
Before the start of grading, a conference should be held with the owner or an authorized
representative, the contractor, the Project Architect, the Project Civil Engineer, and the
Project Geotechnical Engineer present. The purpose of this meeting should be to clarify
questions relating to the intent of the grading recommendations and to verify that the project
specifications comply with the recommendations of this geotechnical engineering report. Any
special grading procedures and/or difficulties proposed by the contractor can also be
discussed at that time.
12.0 CONSTRUCTION OBSERVATIONS AND TESTING
Rough grading of the property should be performed under engineering observation and
testing performed by EnGEN Corporation. Rough grading includes, but is not limited to,
overexcavation cuts, fill placement, and excavation of temporary and permanent cut and fill
slopes. In addition, EnGEN Corporation should observe all foundation excavations.
Observations should be made before installation of concrete forms and/or reinforcing steel to
verify and/or modify the conclusions and recommendations in this report. Observations of
overexcavation cuts, fill placement, finish grading, utility or other trench backfill, pavement
subgrade and base course, retaining wall backfill, slab presaturation, or other earthwork
completed for the subject development should be performed by EnGEN Corporation. If the
observations and testing to verify site geotechnical conditions are not performed by EnGEN
Corporation, liability for the performance of the development is limited to the actual portions
of the project observed and/or tested by EnGEN Corporation. If parties other than EnGEN
EnGEN Corporation
z$'
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No; 2183-GS
October 2000
Page 21
Corporation are engaged to perform soils and materials observations and testing, they must
be notified that they will be required to assume complete responsibility for the geotechnical
aspects of the project by concurring with the recommendations in this report or providing
alternative recommendations. Neither the presence of the Geotechnical Engineer and/or his
field representative, nor the field observations and testing, shall excuse the contractor in any
way for defects discovered in the contractor's work. The Geotechnical Engineer and/or his
representative shall not be responsible for jOb or project safety. Job or project safety shall be
the sole responsibility of the contractor.
13.0 CLOSURE
This report has been prepared for use by the parties or project named or described in this
document. It mayor may not contain sufficient information for other parties or purposes. In
the event that changes in the assumed nature, design, or location of the proposed
development as described in this report are planned, the conclusions and recommendations
contained in this report will not be considered valid unless the changes are reviewed and the
conclusions and recommendations of this report modified or verified in writing. This study
was conducted in general accordance with the applicable standards of our profession and the
accepted geotechnical engineering principles and practices at the time this report was
prepared. No other warranty, implied or expressed beyond the representations of this report,
is made. Although every effort has been made to obtain information regarding the
geotechnical and subsurface conditions of the site, limitations exist with respect to the
knowledge of unknown regional or localized off-site conditions which may have an impact at
the site. The recommendations presented in this report are valid as of the date of the report.
However, changes in the conditions of a property can occur with the passage of time,
whether they are due to natural processes or to the works of man on this and/or adjacent
properties. If conditions are observed or information becomes available during the design
and construction process which are not reflected in this report, EnGEN Corporation should
be notified so that supplemental evaluations can be performed and the conclusions and
recommendations presented in this report can be modified or verified in writing. This report is
not intended for use as a bid document. Any person or company using this report for bidding
or construction purposes should perform such independent studies and explorations as he
deems necessary to satisfy himself as to the surface and subsurface conditions to be
encountered and the procedures to be used in the performance of the work on this project.
EnGEN Corporation
z.!P
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
October 2000
Page 22
Changes in applicable or appropriate standards of care or practice occur, whether they result
from legislation or the broadening of knowledge and experience. Accordingly, the conclusions
and recommendations presented in this report may be invalidated, wholly or in part, by
changes outside the control of EnGEN Corporation which occur in the future.
Thank you for the opportunity to provide our services. If we can be of further service or you should
have questions regarding this report, please contact this office at your convenience.
Respectfully submitted,
EnGEN Corporation
Thomas Dewey, CEG 19
Senior Engineering Geol
Expires 11-30-01
TD/OB:rr
Distribution: (4) Addressee
FILE: EnGEN\Reporting\T2183-GS Don Veasey Construction, Geotechnical Report
EnGEN Corporation
zA
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
Appendix Page 1
APPENDIX
EnGEN Corporation
vr
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
Don Veasey Construction
Project No: 2183-GS
Appendix Page 2
TECHNICAL REFERENCES
1.
Allen, CR., and others, 1965, Relationship between seismicity and geologic structure in the
southern California region: Bulletin of the Seismological Society of America, v. 55, no. 4, p.
753-797.
California Division of Mines and Geology, 1954, Geology of southern California, Bulletin 170.
California Division of Mines and Geology, 1969, Geologic map of California, San Bernardino
Sheet, Scale 1:250,000.
Department of Conservation, Geology map of the Santa Ana 1:100,000 Quadrangle,
California, Division of Mines and Geology Open File Report 91-17.
Dibblee, T.W., Jr., 1970, Regional geologic map of San Andreas and related faults in eastern
San Gabriel Mountains and vicinity: U.S. Geologic Society, Open-File Map, Scale 1 :125,000.
Engel, R., 1959, Geology of the Lake Elsinore Quadrangle, California: California Division of
Mines and Geology, Bulletin 146.
Envicom Corporation, 1976, Seismic safety and safety elements, Technical report for County
of Riverside Planning Department.
Hart, E. W., 1992, Fault-rupture hazard zones in California: California Division of Mines and
Geology, Department of Conservation, Special Publication 42, 9 p.
Hileman, JA, Allen, C.R. and Nordquist, J.M., 1973, Seismicity of the southern California
region, 1 January 1932 to 31 December 1972: Seismological Laboratory, California Institute
ofTechnology.
Housner, G.w., 1969, Earthquake Engineering, Weigel, R. L. (ed.), Prentice Hall, Inc., 1970,
Chap. 4.
Jennings, C.W., 1975, Fault map of California with locations of volcanoes, thermal springs
and thermal wells, 1 :750,000: California Division of Mines and Geology, Geologic Data Map
NO.1.
Jennings, C.W., 1985, An explanatory text to accompany the 1 :750,000 scale fault and
geologic maps of Califomia: California Division of Mines and Geology, Bulletin 201, 197p., 2
plates.
Kennedy, M.P., 1977, Recency and character of faulting along the Elsinore fault zone in
southern Riverside County, California: California Division of Mines and Geology, Special
Report 131,12 p., 1 plate, scale 1:24,000.
Lamar, D.L., Merifield, P.M. and Proctor, R.J., 1973, Earthquake Recurrence Interval on
Major Faults in Southern California, in Moran, Douglas E., et. ai, 1973, Geology, Seismicity &
Environmental Impact, Association of Engineering Geology, Special Publication.
Leeds, D.J., 1973, Geology, Seismicity & Environmental Impact, Association of Engineering
Geology, Special Publication.
Mann, J.F., Jr., October 1955, Geology of a portion of the Elsinore fault zone, California:
State of California, Department of Natural Resources, Division of Mines, Special Report 43.
Riverside County Planning Department, June 1982 (Revised December 1983), Riverside
County Comprehensive General Plan - Dam Inundation Areas - 100 Year Flood Plains - Area
Drainage Plan, Scale 1 Inch = 2 Miles.
EnGEN Corporation
1f,
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
! I
!I
I
I
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
Don Veasey Construction
Project No: 2183-G8
Appendix Page 3
TECHNICAL REFERENCES IContiunedl
Riverside County Planning Department, January 1983, Riverside County Comprehensive
General Plan - County Seismic Hazards Map, Scale 1 Inch = 2 Miles.
Riverside County Planning Department, February 1983, Seismic - Geologic Maps, Murrieta -
Rancho California Area, Sheet 146, Sheet 147 (Revised 11-87), Sheet 854B (Revised 11-
87), and Sheet 854A (revised 11-87), Scale 1" = 800'.
Rogers, T.H., 1966, Geologic Map of California, Olaf P. Jenkins Edition, Santa Ana Sheet,
CDMG.
Schnabel, P.B. and Seed, H.B., 1972, Accelerations in rock for earthquakes in the western
United States: College of Engineering, University of California, Berkeley, Earthquake
Engineering Research Center, Report No. EERC 72-2.
Seed, H.B. and Idriss, I.M., 1970, A simplified procedure for evaluating soil liquefaction
potential: College of Engineering, University of California, Berkeley.
Seed, H.B. and Idriss, I.M., 1982, Ground motions and soil liquefaction during earthquakes:
Earthquake Engineering Research Institute, Volume 5 of a Series Titled Engineering
Monographs on Earthquake Criteria, Structural Design, and Strong Motion Records.
South Coast Geological Society, Geology and Mineral Wealth of the California Transverse
Ranges, 1982.
State of California, January 1, 1980, Special Studies Zones, Elsinore Quadrangle, Revised
Official Map, Scale 1" = 2 Mi.
State of California Department of Water Resources, Water Wells and Springs in the Western
Part of the Upper Santa Margarita River Watershed, Bulletin No. 91-21.
Uniform Building Code (UBC), 1997 Edition.
EnGEN Corporation
~:1
I
I
I
I
I
I
I
I I
II
II
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
Appendix Page 4
SUMMARY OF RECOMMENDATIONS FOR
CONVENTIONAL FOUNDATIONS AND SLABS
Expansion Index 0-20 21 - 50 51-90 91-130
Expansive Potential Very Low Low Medium High
Minimum Footing Depth Below Lowest 18" 18" 18" 24"
Adjacent Finish Grade
Minimum Footing Width 12" 12" 18" 18"
Minimum Continuous Footing 1-#4 Top 1-#4 Top 2-#4 Top 2-#4 Top
Reinforcement 1-#4 Bottom 1-#4 Bottom 2-#4 Bottom 2-#4 Bottom
Minimum Slab Reinforcement 6X6-10/10 #3 @ 24" OC #3@ 18"OC #4@18"OC
Welded Wire Mesh
Minimum Concrete Slab Thickness 4" Nominal 4" Nominal 4" Actual 4" Actual
Minimum Moisture Content of Subgrade No Requirement Opt. + 4% to a Opt. + 5% to a Opt. + 6% to a
Immediately Prior to Placing Moisture Depth of 18" Depth of 18" Depth of 24"
Barrier or Pouring Concrete
Visqueen Moisture Barrier 6mil 6mil 6 mil 6mil
Notes: .. Reinforcing slabs to be in both directions and tied into the foundation.
EnGEN Corporation
~
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
EXPLORATORY BORING LOG SUMMARIES
(B-1 through B-2)
Don Veasey Construction
Project No: 2183-GS
Appendix Page 5
EnGEN Corporation '2- <\.
Project: Don Veasey Construction
Surface Elev.:
Logged By: C8M
I Ii Sample I uscs I
(ll Depth
Ul
I
EnGEN Corporation
I
GEOTECHNICAL BORING LOG
!I
Project Number: T2183-GS
Boring Number: 8-1
Date: 10/17/00
Soil I
Graphic
I
I
tE!l.b.
...
...
,.
SM
,I
Description
-0
I
....
...
I
...
.......
Silty sand, light olive brown,
damp, medium dense, fine
grained sand, slightly
micaceous
ALLU~
Silty sand, light brown, damp,
medium dense. very fine to
fine grained, micaeous
SM
....
.... ...
I
'I'
, 5
~
I
,1-10
~
SM
I
I
,1-15
~
I
: Sand, light grayish tan, damp,
loose, fine grained,
~I staining
'~
:i
:1
SP
. . . .' :
20
SP I
I
: Fine to medium grained sand,
clean, medium dense
...., ]
... .
L
.....
I
25
SP
I
t" .-:::.- .,
:::'.: :1
...... .1
'.:<1
Fine to coarse grained sand
contains pebble size rock,
subrounded to round medium
dense
L
i'"
L
I
....... .,
.1
'1
Groundwater at 30 feet
Sandy silt, gray, moist,
loose fine grained sand,
micaceous
ML
I
r
,(35
~
SM
I
Interbedded with fine grained
silty sands and medium coarse
grained sand, medium dense.
: :1,:
I
Notes:
II
EnGEN Corporation
Blow
Count
3,5,7
4,5,6
2,3,4
4,8,11
5,10,11
2,4,4
2,4,10
.......,-..".,
I Dry
Density
I In-Situ I
Moisture
Content
19.3
2.2
35.9
26.4
10.4
7.7
3.0
Maximum
Density
Optimum
Moisture
Content
JP
..
I
I
I
I
I
I
I
I
I
I
I
I
I
EnGEN Corporation
GEOTECHNICAL BORING LOG
Project Number: T2183-GS Project: Don Veasey Construction
Boring Number: B-1 Surface Elev.:
Date: 10/17100 Logged By: CBM
Sol] I I ~I samp]el I Blow I Ory In-Sllu I Maximum Optimum
Graphic Description ~ Depth uses Count Density Moisture Density Moisture
U) Content Content
1 ~
..j.....
IT -
mil Moist to very moist, medium i,l40 SM 14,20,19 19.2
dense.
:':[1 '-- I
. . I' . . ...
....1'1
::1::::': I
I'll iJ I
III
:::::::1 Sand, light 9ray, moist, 45 SP 5,7,8 23.5
. .... ," medium dense, fine to medium
......... grained, micaceous. -
..,. ..
.......
.... .,"
. .... ," I
_'........c~_. Medium dense, color change to SP 9,16,12 17.1
......... light brown. I
.... .
.... - , I
~ Total Depth 50 feet -50 I I I
Groundwater at 30 feet
I I
I
I
I
I -55
I
I I I
i " I I 60 I 1
I ! r I
I
I I I I I
I I
I i I
I I I 1
I I r
I ~ 65 I I I
,
I
, i I
I I .
I I I I
70 I
I
I '1
Notes: 1
~\ I;
EnGEN Corporation
1f
I
I
I
I
I
I
I
I
EnGEN Corporation
GEOTECHNICAL BORING LOG
I
Project Number: T2183-GS
Boring Number: B-2
Date: 10/17/00
Project: Don Veasey Construction
Surface Elev.:
mT "LE!LL..
. .1. ::h Silty sand, light brown, damp,
; :: :;1:1 dense, fine grained, sand,
: :: ':i.:i....2!!.qhtIY micaceous
:: : :i:~UQIUM
'",1,1
i1:
. . . . "'1 Silty sand, light olive brown,
. . . ..!.. mOist, dense
'" ''I'I
.. "1:1
.. "I""
": ::I:l
. . . .Ii ~
. .... ::1
"::',::;
r77 /7 Interbedded Silty clay to
''i'/~ sand, light gray to dark gray,
~ :::",~ '" "^" ,,,"
. .' :;1 Silty sand, light gray, damp,
. ":'.'.-:j loose, fine grained sand.
"::',:::
.....1
I
Soil
Graphic
II
I
I
I
I
I
.........,
:,::i
. ';::.::i
. .. "I
:::"':1
I
I
I
I
.......1
.,', .."
t:.-:.::.::
'.::::::1
-.---.
: :.::: .::1
I
........
: :::: :::
I
:.-.:::.'.'1
I
r . " .. '"
tl:'::: :ii:
II
Ii
I II
i
'I
I
I
.. ..1
I
Notes:
I
Description
Logged By: CBM
I ~' I I
I~! Sample uses
I &ll Depth 1
I SM
I
~ iSM
.- '
I ~ 5 I SM
I ,
I
I 110
.-
: I
I ~
~'"
: ~ 20 I
.- 1 SP
, i
: [ I
~" I"
I I
i.s:zL
~I
130
! L
ro
SM
Sand, light gray grown, damp,
dense, fine to medium grained
sand, slightly micaceous.
SP
CL
Sand, light gray, damp,
medium dense, fine to medium
coarse grained sands.
Groundwater at 29 feet
Silty sand, gray-brown, moist,
loose, fine grained sand,
slightly micaceous.
SM
Becomes dark gray, very moist.
~'"
11
SM
EnGEN Corporation
Blow
Gount
12,30,37
11,22,27
9,16,25
9,17,18
2,2,3
4,6,8
6,11,17
4,6,9
3,13,15
I Ory
Density
119.7
118.4
123.0
108.6
65.4
93.3
105.9
88.6
104.2
I In-Situ I
Moisture
Content
14.5
43.4
11.8
31.3
23.2
5.7
10.7
12.6
3.2
Maximum
Density
I Optimum
Moisture
Content
.,
1-
~
:i
;,-z...
~
ji
I
I
EnGEN Corporation
GEOTECHNICAL BORING LOG
I
Project Number: T2183-GS
Boring Number: B-2
Date: 10/17/00
I
Soil
Graphic
I
:...
I
:.: :1
:: :1
....:.. 'j
T
I
I
I
I
I
I
I
I
I
I
I
I
Notes:
I
Description
III
~~
Sand, light gray-brown, very
moist. very dense, fine to
medium to coarse grained sand,
micaceous, contains large
specs of muscovite.
I ~
I
r 45
No recovery, sampler sand
locked for 1 hour.
Total Depth 46.5 feet
Groundwater at 29 feet
;-60
,
~
I
r
~
165
r
f"
r
~
Project: Don Veasey Construction
Surface Elev.:
Logged By: CBM
Sample I uses
Depth
SP
I
[
l
1-50
1-55
EnGEN Corporation
Blow
Count
13,34,44
23.35,32
I Dry
Density
108.2
/ln9Situ
Moisture
Content
19.2
Maximum
Density
I Optimum
Moisture
Content
;,~
31;
-~
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Don Veasey Construction
Project No: 2183-GS
Appendix Page 6
LABORATORY TEST RESULTS
EnGEN Corporation
~
I
'I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
MOISTURE - DENSITY TEST REPORT
122
-~-\- I , I
, ,
I , -
,
--~ I I
!
------- -- -.- I
. I I i I
! I ! I I
. - ,
, /' ."\ I I I i ,
I
-- L___ I -I ,
.\ , ! :
-----~ --..---.--- ,
~ , :
n. -~- -~_.~---- I I
~ , i
, I
H i
\\ I :
\\ I
I
, , I
i :
, , I I
-- j
: , I I
i \; , ,
, ! , ,
, I I
,
\\ i I I
, I ,
. \\ : i i ,
,
\ i I , ,
, ,
I I
I i I i\ \' I I I I
, :
i \ ,
, I , , I I I :
, i I
i , . I ! i : i\. , I I i I I
I , I
-- r ~\- I I
, , ! i i
-- I ------'--'------ -----~- I
I i I i I ,
- , \ ,
,
I
\ I I
, I
130
128
126
U
a.
i::'
'in
c:
OJ
u
~
0
124
120
4
ZAVfor
Sp.G. =
2.58
16
6
8
10
Water content, %
12
14
Test specification: ASTM D 1557-91 Procedure A Modified
Elevl
De pth
Classification
uses AASHTO
Nat.
Moist.
%>
NO.4
%<
NO.200
Sp.G.
LL
PI
SM
3.1
TEST RESULTS
MATERIAL DESCRIPTION
SILTY SAND,GREY
Maximum dry density = 128.1 pcf
Optimum moisture = 9.4 %
Project No. T2183-GS Client: DON VEASEY
Project: MEDICAL PLAZA
Remarks:
SAMPL BI @0-5
CaLL BY CBM
COLL ON 10-17-00
. Location: HIGHWAY 79 S.
... Environmental and Geotechnical
. .._ ...._._. . Engineering Nehuork Corporation
Plate
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
UBC Laboratory Expansion Test Results
Job Number: T2183-GS
Job Name: DON VEASEY
Location: HIGHWAY 79 SOUTH
Sample Source: 81 @ 0-5
Sampled by: C8M (10-17-00)
Lab Technician: RW
Sample Descr: SIL TV SAND,GREY
::.:'::::::::.:'::
Wet Compacted WI.: 607.2
RingWt.: 195.3
Net Wet WI.: 411.9
Wet Density: 124.4
Wet Soil: 227.3
Dry Soil: 210.2
Initial Moisture (%): 8.1%
Initial Dry Density: 115.0
% Saturation: 47.3%
Final WI. & Ring WI.: 627.4
Net Final WI.: 432.1
DryWl.: 380.9
Loss: 51.2
Net Dry WI.: 378.4
Final Density: 114,3
Saturated Moisture: 13.5%
Dial
Change Time
Reading 1: 0.100 N/A 8:45
Reading 2: 0.100 0.000 9:00
Reading 3: 0.100 0.000 9:15
Reading 4: 0.100 0.000 20-0ct
Expansion Index:
o
Adjusted Index:
(ASTM D482910.1.2)
-1.0
EnGEN Corporation
41607 Enterprise Circle North
Temecula, CA 92590
(909) 676-3095
Fax: (909) 676-3294
....
>'Il<
7'" ~
jj;
~
1<7
..
..
I
I.
.3000
RESULTS
C, pst
q" deg
TAN ~
271
.35.2
0.70
o
I
I
~
Ul
Q. 2000
(f1
(f1
w
'"
f-
(f1
w
'" 1000
::>
--'
H
<(
LL
I
I
'I
5000
6000
I
I
2 .3
10.5 10.5 10.5
115.2 115.2 115.2
67.7 67.7 67.7
0..398 0..398 0..398
2.42 2.42 2.42
1.00 1.00 1.00
0.0 0,0 0.0
115.2 115.2 115.2
0.0 0.0 0.0
0..398 0..398 0..398
2.42 2.42 2.42
1,00 1.00 1,00
1000 2000 .3000
929 1770 2338
0.10 0.10 0.08
I
I
I
I
I
I
0.2000 0.2000 Q.2000
I
SAMPLE TYPE:
DESCRIPTION: SILTY SAND, GREY
CLIENT: DON VEASEY CONSTRUCTION
PROJECT:
I
SPECIFIC GRAVITY= 2.58
REMARKS: SAMPLE Bl@ 0-5
COLLECTED BY C.M. (10/17/00)
SAMPLE LOCATION: HWY. 79 SOUTH
I
PROJ. NO.: T218.3-GS
DIRECT SHEAR
DATE: 10/24/00
TEST REPORT
~."
1
Fig _ No.:
EnGEN Corporation
I
;':;;,,4~~"':c:'H"'
^=
4
!IIi
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
80
60
<JJ
::J
o
>
I
0::
40
20
R-VALUE TEST REPORT
100
0
0 100 200 300 400 500 600 700
Exuda t ion Pressure - psi
Resistance R-Value and Expansion Pressure - ASTM D 2844
Compoc t . Expansion Horizontal Sample Exud. R
Density Mo i st. R
No. Pressure Pressure Press. psi Height Pressure Value
pcf % Value
psi psi @ 160 psi in. psi Carr.
1 350 126.2" 9.7 3.33 38 2.55 387 68 69
2 250 127.8 10.3 2.12 45 2.53 286 62 62
3 150 128.3 10.6 0.00 93 2.51 91 28 28
TEST RESULTS
MATERIAL DESCRIPTION
R-Valwe @ 300 psi exudation pressure
63
SILTY SAND, GREY
Project No.: T2183-GS
Project: DON VEASEY CONSTRUCTION
Location: HWY. 79 SOUTH
Tested by: J.H.
Checked by: J.T.O.
Remarks:
SAMPLE B2@ 0-5
COLLECTED BY C.M.
COLLECTED ON (10/17/00)
Date: 10-24-1900
R-VALUE TEST REPORT
Environmental and Geotechnical
Engineering Network Corporation
Fig. No.
~
jj
I
I
I
I
I
'-I
I
I
I
I
I
I
I
I
I
I
I
I
I
19
CONSOLIDATION TEST REPORT
I
i
20
I I
I '
I
I
,
I
I
I
I I
I
i
21 WATER ADDED
I i
,
, I
I
22 ,
, I
I I
I I I
23 I ,
I I ,
I I
c I
.~
Ci5 t
c: 24 ,
<ll I I
f:!
<ll
a.
I I I
25 I I
26 I
I
I
27 I
I I
,
I I
I , I i
28 I I ,
I I
I I
I I
29 .1 .2 .5 1
Applied Pressure - ksf
Natural Dry Dens. LL Sp. Overburden Pc Cc
PI
Sat. Moist. (pc!) Gr. (ks!) (ks!)
76.9 % 10.7% 118.4 2.58 0.75 0.03
MATERIAL DESCRIPTION
FINE-SAND, BROWN
Project No. T2183-GS Client: DON VEASEY
Project: MEDICAL PLAZA
I ,
I
I I
, I
I ! I
I
I I I
I I
I I
i
! t I I I
, I
I I I I
,
i t
I I
I i
I
, I I
I i
i !
I I
2 5
Swell Press. Swell
(ks!) %
eo
Cr
0.360
USCS AASHTO
SP
Remarks:
COLLECTED BY C.M.
COLLECTED ON (10117/00)
Source: CONSOLS
Sample No.: B2 5
Environmental and Geotechnical
Engineering Network Cotporation
'"
q-
..~
3'\ ~
j
2:',d;;~. _ .., '>~~"i:""" ~,_~"'~
,,;r-; J "! ' I -,','. -
.1 '. I I ,'" -. -
-.,.""--.....,,......=---1llJ~r.mY~G..---
Plate
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
CONSOLIDATION TEST REPORT
,0
,.
-
-
I ,
,
I
2 I I
3
4
c
'm
~
1i5
c 5
(J)
e
(J)
0-
6
,
I
I I
I
I I
I I
!
7
8
9
10 .1 .2 .5 1
Applied Pressure - ksf
Natural Dry Dens. Sp. Overburden Pc Cc
LL PI
Sat. Moist. (pcf) Gr. (ksf) (ksf)
105.0 % 12.6% 123.1 2.58 0.47 0.01
2 5
Cr Swell Press. Swell eo
(ksf) %
0.309 ~
USCS AASHTO
SM
Remarks:
COLLECTED BY C.M.
COLLECTED ON (10/17/00) .it
MATERIAL DESCRIPTION
SILTY SAND, BROWN
Project No. T2183-GS
Project: MEDICAL PLAZA
Client: DON VEASEY
Source: CONSOLS
Sample No.: B2 7.5
Environmental and Geotechnical
Engineering Network Corporation
Plate
A,o
~,_ '<:.:.'::./'_~~_~..w.;:
J~~< ~- r.L~rr.L~L~~~:-~:- .~
I
I
I
II
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~I
o
2
3
4
c
.~
Ci5
C 5
Q)
e
Q)
0-
6
7
8
9
I I
CONSOLIDATION TEST REPORT
I I I
I I
I
I
I I
I I
I I
I
. i I .
.:-t-+-l-" "
. I I
, : ii'
I ,.
I
I
I
,
I
I
,
I
I I
II
I
I
I
i
,
I
I .; I I I I
I,.~:I
WATER A~~)
I I
I
I
I
I
, I
I
, i
, I
I I
,
i
I
I
I
I
I
I
I
,
I
,
, I
I
I
I
I
I '
I
I
I
I
I I
I
I I
I I
I
I , . t
! I
, ,
.2
I I
, ,
,
I
t
! I
10 .1
Natural
Sat. Moist.
77.4 % 14.5 %
.5 1
Applied Pressure. ksf
Sp. Overburden Pc Cc
Gr. (ks!) (ks!)
2.58 0.48 0.02
MATERIAL DESCRIPTION
,
2 5
Cr Swell Press. Swell eo
(ks!) %
0.482
USCS AASHTO
SM
Remarks:
COLLECTED BY C.M.
COLLECTED ON (10/17/00)
Dry Dens.
(pc!)
108.7
LL
PI
Project No. T2183.GS
Project: MEDICAL PLAZA
SILTY SAND, BROWN
Client: DON VEASEY
Source: CONSOLS
Sample No.: B2 10
Environmental and Geotechnical
Engineering Network Corporation
~..f:.._ ... ,,-?:r..~ _~:.~~~...:i
-I : I i -I -,- -
.L 1. I 1-,' .
-~~~-'lr.l:z!,"""~r.~~
Plate
~
...... HI" ,~.
#
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-1
CONSOLIDATION TEST REPORT
I' I
o
, ,
2
3
c
.~
1i5
.- 4
c
<1>
l:!
<1>
0-
5
! I
I I !
I
I
6
,
,
I i
I I
7
8
9 .1 .2 .5 1 2 5
Applied Pressure - ksf
Natural Dry Dens. LL PI Sp. Overburden Pc Cc Cr Swell Press. Swell eo
Sat. Moist. (pel) Gr. (ksl) (ksl) (ksl) %
2.58 0.59
MATERIAL DESCRIPTION
USCS
ML
AASHTO
Project No. T2183-GS
Project: MEDICAL PLAZA
SANDY SILT, DARK-BROWN
Client: DON VEASEY
Remarks: :i
WATER ADDED AT START OF ~
TEST ';'
COLLECTED BY C.M.
COLLECTED ON (10117/00)"
~:~
Source: CONSOLS
Sample No.: B2@ 15
~ Environmental and GeotechniCfJI
Engineering Network Corporation
Plate
~-
~_ ",-,"!,-::~"''>u:. _~~_~:'':1~'j'"
- jY~~-, I .; '-I ---,-
. '1- - ~,I i ' ~ --, ~ ) '- "
-"""~""""'=-ll?Il~~~
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
4
c:
'm
~
Ci5
'E 5
Q)
(J
~
Q)
a.
6
o
CONSOLIDATION TEST REPORT
2
3
7
6
9
10 .1
.2
~ 1
Applied Pressure - ksf
Overburden Pc
(ksf) (ksf)
I I I I I. I I i ! I I I I , I , I
I ! I , I I , ,
, I I , , I I
I I I , - , ,
, i
, I , I
I ! I -""""- , , i
, I
i Iii Ii i I ,
, i , ,
I : I i I , I I
,
, I , I I ,
I I I I:~ I I I
I i I i , I I !
WATER ADDED . i
I I i , I ! , , : , , I I ~. I I
, I I
I I ! i I , , - I
I I I , I , I
, I i , I I
I , ,
I
, , , , , I I ,
I , ,
I , I I , , i , I I
I I , I , , I i
, I I I
I I , , I
I , I : i , I
, , , I ,
, i I ,
, , I I I I , I I I
I I ! ! , i , , I i I
I , ,
: I , i I , I i i I I I , I I I I
! I , , I I , , I i I I I !
I i , , I i I
I , I , , i
I I I I I I I I I I ! I I
, i
I I I I , I I ! I
I , I !
I I I : I ,
, I I I I ! I I i I I I i I I I i I
, , I
I ,
I I I I , I I I , I , I i I I
I i I I I I I i I I I I I ,
I I I I ! I I I I , I
I , I I
; I I I I ,
I I I I I , I
I I I I I ! I i I i i
I I !
I I I I I I I I I , I I I , I I , I
I I i , I I I I i I
I !
I I I I I I ! ,
I I I I
I i I I I I I i , I
, I I I I . , !
, I I I I , I I I i I I
I i I I , , i I
I I , , I
i i I I I I I ! I : ,
I I : I I I , I
, , I , ,
I I I I I , , I I i I
I , ,
, : I , - , I I I I I I
I I I , I , , ,
I I , ! I
, ,
I I , ,
I I I I , , i I , I i i
I I I i I , , I I I I ,
I I I , I
I
Natural
Sat. Moist.
41.8% 11.8%
Sp.
Gr.
2.58
MATERIAL DESCRIPTION
Dry Dens.
(pcf)
93.3
LL
PI
Project No. T2183-GS
Project: MEDICAL PLAZA
FINE-SAND, GREY
Client: DON VEASEY
~Z:= -':"'~?>YA u~,,"~;iitJk~
- i ~. ~ j : l ~ ~,r-
~ '~l ! I ~'!:.
-J-.,.':"<...!.....,11.l!oil."'..ll:~..< -~
Sample No.: 82 20
Environmental and Geotechnical
Engineering Network Corporation
Source: CONSOLS
2
6
Cc
Swell Press. Swell
(ksf) %
eo
Cr
0.63
0.726 I
AASHTO
1:
0.04
USCS
SP
..
COLLECTED BY C.M. .
COLLECTED ON (10/17/00)' I
4!;
t
".m ~ i
Remarks:
I I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-1
CONSOLIDATION TEST REPORT
~'
o
2
3
c
'00
~
Ui
C 4
OJ
u
~
OJ
0-
5
5
7
8
9 .1 .2 .5 1
Applied Pressure - ksf
Natural Dry Dens. Sp. Overburden Pe Ce
LL PI
Sat. Moist. (pef) Gr. (ksf) (ksf)
98.9 % 31.3 % 88.7 2.58 0.58 0.09
2 5
Cr Swell Press. Swell eo
(ksf) %
0.816
USCS AASHTO
ML
MATERIAL DESCRIPTION
SANDY SILT, BROWN
Project No. T2183-GS
Project: MEDICAL PLAZA
Client: DON VEASEY
Remarks:
WATER ADDED AT START OF
TEST
COLLECTED BY C.M.
COLLECTED ON (10117/00)
Source: CONSOLS
Sample No.: B2@ 30
Environmental and Geotechnical
Engineering Network Corporation
Plate
APt
~
t.
~~<..,~~""~~~
, . I . I .~..~---
'1' i I: ;,,--,,-'
_:::~d:_"'_1lII:t!~-"'~
4
,d_~
ill
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Particle Size Distribution Report
5 .
0 5 5 : .~ , ,.
. n ~ - "
100
90 .";!
i
;' ..
80 ----
. i,
: ii ,
70 -- .,11,
"
,I, ] ,
a:: i
60 .
W
Z .'
u:: I
l- so -
z ,
w
u
a::
w 40 -.-------.
0-
30 - ;
. ,
I'
I , i:
20 1'1 '
I :
. .
10 'I I
.11
'1 ,
. ill; I
0 I I'
500 100
I % COBBLES I
I 0.0 I
SIEVE PERCENT
SIZE FINER
#4 100.0
#8 100,0
#16 99,9
#30 99.4
#50 80.9
#100 24.4
#200 6.9
(no specification provided)
Sample No.: BI@ IS
Location:
.
I
. I
I
,
10
% GRAVEL
0.0
SPEC:
PERCENT
~ ~ ~
: ~ ~:~i.........
- - --1~--~, u
"" '.
. .
I
I I I . I
I i
I. I
,
. -----~~- ------r. .
,
'~'
!',.; Ii
';:' :
I ! ~
! I , ~
I
1
GRAIN SIZE - mm
% SAND
93.1
% SILT
0.1
I
PASS?
(X=NO)
Soil Descriotion
FINE-SAND, BROWN
PL=
AtterberQ Limits
LL
085= 0.322
030= 0,163
Cu= 2.27
Coefficients
D60 0.230
015= 0,123
Cc= 1.13
Classification
AASHTO=
uscs= SP
Remarks
COLLECTED BY C,M,
COLLECTED ON (10/17/00)
Source of Sample: SIEVES
,I,
'Iii:
~ : i : :
I ,
I I I I ~
Ii! ~ : "
',,11
:1111
II"
IIIII I
0.01 0.001
I %CLAY I
6.9 I
PI=
050= 0.206
010= 0,102
Date: 10/24/00
Elev./Depth:
ENVIRONMENTAL AND GEOTECHNICAL
Client: DON VEASEY
Project: MEDICAL PLAZA
ENGINEERING NETWORK CORPORATION
Proiect No: T2183-GS
Plate
D6d
~l
~.
,.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Particle Size Distribution Report
.s 0 0 o.
~ 8 ~ 0
.s .5 .5 0 0 2 ~ 0 0 0
. M N - ;; ~ ~ ~ ;; . . ~ 'i1 ;; ;; ~
100 , I '\ ,
I' ;
I
90 -,- II!" I
I" I ;
I, . I I
80 , \ 1111: , I
m__~____ \ ---~
ijl: I
I!i:
I
70 -_._-~ -----~. ~, ,
- I. I I
I
IY I
W 60 -- . --- -- \ I I
Z ". ,:'1
u: .--- --\-- -- '1
f- ,
Z 50 ~
W ,I 'I , .,
u ,
IY ,
W 40
0- \ ,
,
I.' ". , i
30 " , \ ,
I ; :
i, 'II ' ,
" I
'i'l I
20 \-----
:;I! I' ! , 1,.1 ,
"I'
::il: I . . ili,':
"
10 II 1'1 I ". I I: i:
1111; ; I I . . ,I:
! :'1: 1 i
'I 'I :I!, I
, ,
0 I i::I' , I I:' II!II I I
,
500 100 10 1 0.1 0.01 0.001
GRAIN SIZE - mm
r % COBBLES ,- % GRAVEL ,- % SAND I %, SILT % CLAY I
T I 93.3 I 6.4 I
SIEVE PERCENT SPEC.' PASS? Soil Description
SIZE FINER PERCENT (X=NO) SAND, GREY
#4 99.7
#8 97.0
#16 83.2
#30 54.9 AtterberCl Limits
#50 25.0
#100 11.2 PL= LL- PI=
#200 6.4
Coefficients
DSS= 1.25 Deo- 0.669 DSO= 0.541
D30= 0.345 D1S= 0.199 DlO= 0.133
Cu= 5.04 Cc= 1.34
Classification
USCS= SP AASHTO=
Remarks
COLLECTED BY Cvl.
COLLECTED ON (10117/00)
. (no specification provided)
Sample No.: Bl@20 Source of Sample: SIEVES Date: 10/24/00
Location: Elev.lDepth:
ENVIRONMENTAL AND GEOTECHNICAL Client: DON VEASEY
Project: MEDICAL PLAZA
ENGINEERING NETWORK CORPORATION Prolect No:
T2183-GS Plate
.,..
~i
j
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Particle Size Distribution Report
c
0 c c c 0 0 0 0 0 0
, .. . .S . 0 0
~ s ~ . ~ . . ;; .
. N - . . .
100
. ':1' ---
90 . 1,,1 -
I, Iii
, "~ ""
, I I" " , , ; I I
:. . I I::: '
80 I
" " ' ,
, ' . 1;1' i
:1, '. \ 1,,11
, 11:1 I I
70 " '\ I 1:1; i ,
I
" - I II!I i I
" .' 'III
cc ." , ,
W 60
Z i , : j!il!
Ll. , I
f- 50 "11 ' ,
z . , ,1'1 i
W I ,. , , '"
u ,. , :1 I
cc "
W 40 '.: J ,.,
D- ", "1' . , ~ I i I
, I I
" , :::1
I. I".
30 i \ " i' ,
" " ,
., I'. ,
II' '. ,
i " ',1: I
20 -
" :11'1 I
":i i i
. I' '~ ' : ,
10 -'
'-...;: !: I !
, :11
:I,! I
0 , I" , 1.,11
500 100 10 1 0.1 0.01 0.001
GRAIN SIZE - mm
I % COBBLES I % GRAVEL I % SAND % SILT I 0/0 CLAY I
I I I 84.1 3.5 I
SIEVE PERCENT SPEC: PASS? Soil Description
SIZE FINER PERCENT (X=NO) GRAVELYSAND,GREY
#4 87,6
#8 73.3
#16 51.4
#30 30.7 Atterberq Limits
#50 14.5
#100 6.3 PL= LL- PI=
#200 3.5
Coefficients
085= 4,10 060- 1.53 050= 1.13
030= 0,585 015= 0.308 010= 0.222
Cu= 6.87 Cc= 1.01
Classification
uses= SP AASHTO=
Remarks
COLLECTED BY C.M.
COLLECTED ON (10/17/00)
,. (no specification provided)
Sample No.: BI@25 Source of Sample: SIEVES Date: 10/24/00
Location: Elev./Depth:
ENVIRONMENTAL AND GEOTECHNICAL Client: DON VEASEY
Project: MEDICAL PLAZA
ENGINEERING NETWORK CORPORATION Proiect No:
T2183-GS Plate
..~'.
A, 1.4
'f
-$
:I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Particle Size Distribution Report
<
c:! c: C c:.
~ c: ~ ~ ~ s ~
il
:3 0 g
;; .. ~
;; ;;
--
o 0 0
~ \Z ;{
"-
.. ..\::;
. -\ 1:1 '
, \ 1:1::
i <,~ i' ,
\: i ,
!' .
, ~:
,! j'
"
,.'
100
,
90 I;'
':! .
'I'
I:
80 I
,.1
70 . .;:, .
ill)
I!I'
cr: ".'
W 60 'I
Z
LJ..
f- 50 - ,
Z
W "11
U 'I
cr: "
W 40 - "
(l. I i
i:' I
,
30
" I
I. I
20 ! I
1'1
I'i I
10 : ! ~
, 1'1 .
, I i I
0 ! Iii: I I ,
500 100
I % COBBLES
I 0.0
SIEVE PERCENT
SIZE FINER
#4 100,0
#8 100.0
#16 99,8
#30 99.3
#50 96.2
#100 76.1
#200 55.0
"
I'll, f
i'l' I I
:!:I' '
rll:: , I,
I!: ,
I' ,
IIil:
i : ~ : . t
.,'
,'I.
i'r
;11'
, '
. ! ! ~ j ,
;'
iii, '
I" '
'"
"Ii,
,
': .
10
., I
I
1 iii' ,
" I
, , : 1"
ill: I I liii i ,
, I I ,
1 0.1 0.01 0.001
GRAIN SIZE - mm
% SAND I % SILT I % CLAY I
45.0 I 55.0 I
% GRAVEL
0.0
SPEC: PASS?
PERCENT (X=NO)
Soil Description
SANDY SILT, BROWN
AtterberQ Limits
LL-
PL=
PI=
085= 0.202
030=
Cu=
Coefficients
060- 0.0883
D15=
Cc=
Classification
AASHTO=
D50=
010=
USCS= ML
Remarks
COLLECTED BY C.M.
COLLECTED ON (10/17/00)
(no specification provided)
Sample No.: B I@ 30
Location:
Source of Sample: SIEVES
Date: 10/24/00
Elev.lDepth:
ENVIRONMENTAL AND GEOTECHNICAL
Client: DON VEASEY
Project: MEDICAL PLAZA
.:i
*'
4~:'
I
j
ENGINEERING NETWORK CORPORATION
Project No: T2183-GS
Plate
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Particle Size Distribution Report
< .5
.5 < s
< < ~ s ~ :
. N -
il
c c c
o . c
_ _ N
. . .
c
"
ceo
.. ~ .;;
100
90 ... -
"
80
70
cr: 60
W
Z
U-
f- 50
Z
W
U
cr:
W 40
Cl.
I
--- --~---~------_.
~
'I
i: '
"
II
'--
.,
!
, ,
, ! ! ! ,
I I
, I
,
: I ,
! I I : ,
! , ! I.
! , !
. I , : i
i ! ,
I ! , I
! ,
! I i I
,
I
j,
ii:
30
!
i
.il
. ,
20
1"1'
iljl
!.
, I
'---'----
i" t ,
!
! "
j',11 I . .
!
!
111-1 I
0.01 0.001
%SILT I % CLAY I
24.6 I
10
; , ~
. ,
!
"
I I . I ~
illl"
III. I
Iii
iii"
I: I
';1,
IIII! I
!II,: '
100
"
.,
!.
o
500
:'1
10
1
GRAIN SIZE - mm
% SAND
74.6
0.1
I % COBBLES
I
% GRAVEL
I
I
I
I
I
SIEVE
SIZE
#4
#8
#16
#30
#50
#100
#200
SPEC.' PASS7
PERCENT (X=NO)
Soil Description
SILTY SAND, BROWN
PERCENT
FINER
99.2
93.5
83.0
71.3
52.3
34.3
24.6
AtterberQ Limits
ll=
Pl=
PI=
085= 1.34
D30= 0.117
Cu=
Coefficients
060= 0.390
D1S=
Cc=
Classification
AASHTO=
050= 0.277
010=
uses= SM
Remarks
COLLECTED BY C.M.
COLLECTED ON (10/20/00)
* (no specification provided)
Sample No.: BI@35
Location:
Source of Sample: SIEVES
Date: 10/24/00
Elev.lDepth:
ENVIRONMENTAL AND GEOTECHNICAL
Client: DON VEASEY
Project: MEDICAL PLAZA
.;if.
ENGINEERING NETWORK CORPORATION
4p.,1
,13
,J
Proiect No: TZI83-GS
Plate
I
I
I
I
I
I
'1
I
I
I
I
I
I
I
I
I
I
I
I
Particle Size Distribution Report
c .5
M , C 0 0 0 0 8 0 0
, 5 , ;; M . ~ 0
; M " ;; ;;
. " M - c; . . . . .
-
100 -~~-- .... ---'~
90 - - _n_~____ ,
Ii.! :
:!:: :
80 1111
illl \ :11; : iil! ,
'" ,'.'
:'Ii , , J.
70 , .' ,
I I I ~ , 'I" ,
Ii'
i, I ,I: , , I,
" , I II '
0:: .' i," I
60 'III
W ,. I:!: ;
z "
u.. '. i "I
'il
f- " I ~ ' I
Z 50 ,Ii'i
W :i; , ,
I'll ,
U '!I; , I :ill'
0:: 1III I :111 .
w 40
0- .j. :;1' 'III
;;1 " : i ; I I '
., I' , ,
~ ,., I, ':!I.
I!i I " ,
30 \ I
!,l I', ,
, \ I' , , :!!I:
,
20 ---~~---- ------ ---,._~.~ ,
:1 " , :!:I:
illll t , ~ I 1 . !
10 i, --.----- ,;1'
, ~I , [,.' ,
". ii,
, 1:11 , li'.1 J'
0 'I', i :
, ,I' ,
500 100 10 1 0.1 0.01 0.001
GRAIN SIZE - mm
r- % COBBLES I' % GRAVEL I %. SAND I % SILT % CLAY I
r- 0.0 I' 0.0 T 95.9 I 4.1 I
SIEVE PERCENT SPEC: PASS7 Soil Description
SIZE FINER PERCENT (X=NO) SAND, BROWN
#4 100.0
#8 99.6
#16 96.9
#30 77.2 AtterberQ Limits
#50 32.4
#100 10.1 PL= LL- PI=
#200 4.1
Coefficients
D85= 0.711 060= 0.456 050= 0.395
030= 0.287 015= 0.192 010= 0.149
Cu= 3.06 Cc= 1.21
Classification
USCS= SP AASHTO=
Remarks
COLLECTED BY C.M.
COLLECTED ON (10/17/00)
. (no speciticD.tion provided)
Sample No.: BI@45 Source of Sample: SIEVES Date: 10/24/00
Location: Elev./Depth:
ENVIRONMENTAL AND GEOTECHNICAL Client: DON VEASEY
Project: MEDICAL PLAZA
ENGINEERING NETWORK CORPORA liON Proiect No:
T2183-GS Plate
. -'~1.
'f"
50,~:
'..
j
I
, I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Particle Size Distribution Report
.~ .s .~ e
.!E .5 .s ~ 5 ~ ~ ~ 0 ~ 0 0 il ~ ~ 8
: " " : ~
. " ~ - .
100 III1 ; :' --........- i"
, 'I -" ':
"j "Ii
90 III! : O"j'
, " Illi' Ilil
II
1'1 " I,I, ' illl'
80 II" ,
, ' 'I,; , " 'I
lilT Illi 1:11 I 1'1'
i .' I I , I, '1 I '
, , II " , Iii: ,.
70 , , 111'1 , , :I;i'
III' , , ,. ii: I
.,11 ' I,..
ill: ' , " ,
a:: I I' I ! i ! ~ : ! ~ : :
60 , ,II, j ,II. ,
W I;: ., "
Z I I ! ~ . I:, 'I' :11
u: !,I ' 'I
'11'1 " , i,1
l- so il! :11 : , . , ,
Z I' I' I. , 1:1
W ." .
III: ' I :i I111 I,;
() II, Iii
a:: 1111, I!
, , , Ii;: ':1 II : ,
w 40
a. , I IIII! ';1 I III I II'
1,'11'
I 11II I " , :!I: i
, J :11
30 11'1 , ,I'
I' , "
I " ", 1 II \ i I ~
11I1I I III II III: .' .
1111' I II, I I: ! ,I
;:1 ' I ,
20 ill:l: ! '111 , , Iii 'I" ,
I II ' I '"
I : III 'I I,
III , , 'Iii, I', I
I , '!I' : "
10 1III I ;11' I , 'I II'-! ' , II!! )
I !
I I I II I III ,
III I I Iii: : , illl I
I I' I, I
'0 , ,. II'
500 100 10 1 0.1 0.01 0.001
GRAIN SIZE - mm
% COBBLES % GRAVEL % SAND % SILT % CLAY
90.3 9.1
SIEVE
SIZE
#4
#8
#16
#30
#50
#100
#200
SPEC:
PERCENT
SAND, BROWN
PERCENT
FINER
99.4
97.6
90.0
69.8
37.7
17.1
9.1
PASS?
(X=NO)
Soil Description
AtterberQ Limits
PL= LL=
PI=
D85= 0.943
030= 0.245
Cu= 5.77
Coefficients
D60- 0.483
015= 0.132
Cc= 1.49
Classification
AASHTO=
D50= 0.393
010= 0.0837
uscs= SP
Remarks
COLLECTED BY C.M.
COLLECTED ON (10/17/00)
...r;;"
''I'
... (no specification provided)
Sample No.: Bl@48.5
Location:
Source of Sample: SIEVES
Date: 10/25/00
Elev./Depth:
~
ENVIRONMENTAL AND GEOTECHNICAL
Client: DON VEASEY
Project: MEDICAL PLAZA
ENGINEERING NETWORK CORPORATION
Pro ect No: T2183-GS
Plate
I
I
I
I
I
I
I
I
I
I
I
I
I
I:
I'
I
i
I:
I
I
10/27/2000,
NO. 039
~02
E.S.BRBCOCK & SONS, INC. ~ 2962237
12:28
Environmental LallOmlaty Col1lllcaVon 11156
6'00 Quall Vallsv Court R..._. CA 92507.0704
P.O. _ 432 _. CA!I2S/l200432
PH (9091 &53.3351 FAll (909) sss.l662
e-mail: _s@aol.ccrn
lWNI.b'''QocI(Isb9.com
~
i
I
i
i E.S. BABCOCK
6. SONS,INC.
E8'1'lriIlUaI!Dl_
Laboratory Results
2860-791
client:
Engen. Inc.
Tom Dewey
41607 Enterprise Circle N.
Temecula,CA 92590-5614
Client I.D.: B1@Q-S
Site: PRJ#T2183-GS-
Description:
1'i~Jl1?~;;&~"~;lai,';~,i"i'
'll.[..:;"..",.,~~t"'>;;:&"'ft"'~^.f'"''
. ,cUZ~":P:,..,;:.:::.~t:N~~"';';'U~:::;U~~-:::'-:-;:
Date Reported: 10/27/00
Collected By'
Date:
Time:
Submitted By: GSO
Date: 10/20/00
Time: 0935
Matrix:
soil-ag
Ccmat;!t1aOAt
Rooult
lIetllo4
RL
Date /
Analyst
00102S/lCCS
Water Extractable sulfate
220
Ion Chro1I\,
10
ppm
NO c None detected at RL (Reporting Limit). RL units eame as result.
Results reported in ppm expressed an an air-dried soil basie.
cc;
~
t>"
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-.
.
Don Veasey Construction
Project No: 2183-GS
Appendix Page 7
DRAWINGS
?~
EnGEN Corporation