HomeMy WebLinkAbout12b. Progress Meetings VANI R • •
PROGRESS MEETING MINUTES
Meeting#: 76
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: September 22, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers,City of Kevin Terry,Tovey Shultz
Temecula Temecula Construction, Inc. (TSCI)
Larry Campbell,Vanir
Construction Mgmt. (VCM)
Meeting # Item# Description Due Action
76 1.0 Approval Of Previous Meeting Minutes:
1.76 There were no additions or corrections to the N/A Info
minutes of Weekly Progress Meeting 75.
2.0 Construction Progress Update:
Painting of doors, door frames, and walls is
ongoing. Installation of casework, carpet at the
balcony, and installation of electrical and fire alarm
finishes and devices is ongoing. Installation of A/V
wiring and termination is substantially complete
with testing in progress. Installation of the stage
floor will be complete today and finishing of wood
trim and painting of repairs in the audience
chamber is in progress.
2.76 Installation of cladding at the elevator tower is N/A Info
ongoing and concrete pavers under covered
walkways were sealed yesterday afternoon.
Final inspection of the Mercantile Building was
completed and signed off on Tuesday by the Fire
Marshal and final inspection by the Building
Department is scheduled for later this afternoon.
Correction of punch list items is substantially
complete in the scene shop, production office, and
Drooerb, stora e.
3.0 Technical Concerns:
Schedule Review: Tovey Shultz' 3-week look-
ahead schedule was reviewed during the course of
3a.76 the meeting:
N/A Info
Mercantile Building:
The Mercantile Building is substantially complete.
Page 1 of 6
VAN I R PROGRESS MEETING MINUTE•
Meeting#: 76
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
76 3.0 Technical Concerns: (continued)
Schedule Review: (continued)
Main Theater Building:
Re-painting of walls, doors, and trim to repair trade
damage will continue into early next week. The Fire
Marshal has been scheduled for four hours daily
3a.76 beginning Monday to final the building for
certificate of occupancy. All outstanding work
required for certificate of occupancy is scheduled
to be complete by the end of the day Tuesday,
9/27.
Installation of landscaping will continue and will not
hold up certificate of occupancy if not complete.
Following discussion, TSCI advised that there are
no issues foreseen as problems that require
3a.64b assistance from the City of Temecula. Based upon N/A Closed
that discussion, D. McBride advised that the
requested narrative is no longer required.
07.07.05
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 154 submittals (including
3b.76 resubmittals) have been received to date. At this N/A Info
date, there are no submittals outstanding
3c Request For Information Status Review:
A review of VCM's RFI log reflects 511 RFI's
3c.76 (including revisions) have been submitted to date. N/A Info
There are no RFI's outstanding.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.76 Both of these items have been included in N/A Info
revio sly approved change orders.
3d.1 Architect's Supplemental Instructions
3d.1.76 Nineteen Architect's Supplemental Instructions N/A Info
ASI have been issued as of this date.
3d.2 Construction Bulletins
Thirty Construction Bulletins have been issued.
3d.2.75 Of the thirty, 18 are in previously approved or 09/30/05 TSCINCM
pending change orders. Three have been
superseded and 9 are pending negotiation.
Page 2 of 6 VANIR F 503
VAN I R •OGRESS MEETING MINUTE•
Meeting#: 76
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting# Item # Description Due Action
76 3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
3e.1.74 Change Order Nos. 13 and 14 have been N/A Info
approved by the City Manager.
3e.2 Proposed Change Orders
Two hundred four potential change requests
have been identified. Of those, 80 have been
incorporated into executed change orders, 19
3e.2.75 have been rejected, 44 are pending negotiation, 09/16/05 TSCl/VCNA
40 have been voided, and 21 are pending
pricing.
There was no discussion of this Item during the course
of the meeting. 09/22/05
3e.3 Disputed Items
TSCI has identified nine of the rejected change
3e.3.72 order requests and one proposed settlement as N/A Info
potential dispute items.
3f Payment Status Review:
3f.76 TSCI's draft payment request #19 has been 10/15/05 City of
forwarded to the City of Temecula for payment. Temecula
3g Notice Of Non Conformance Status:
There is one outstanding correction notice
issued by the Fire Marshal. Corrections are
3g.76 being made and will be complete by the middle 09/28/05 TSCI
of next week.
3h As Built Status Review:
3h.76 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.76 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safe issues at this time.
4.0 Testing/Inspection:
Paving was inspected by City of Temecula Public
Works Inspectors and the Building Inspector stops
4.75 by on a daily basis. The Mercantile Building was N/A Info
inspected by the Fire Marshal on Tuesday, 9/20/05
and signed off for occupancy.
Page 3 Of 6 VANIR F 503
VAN I R VROGRESS MEETING MINUTE•
Meeting#: 76
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting# Item # Description Due Action
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall.
TSCI obtained preliminary pricing for the donor plaques. The
pricing received in significantly in excess of the donations for
the plaques. B. Beers will contact the Theater Foundation and
attempt to have cast bronze plaques approved. (07/14/05)
Following discussion, it was determined that TSCI will ask its
sign contractor for recommendations on resolving this issue.
(07/21/05)
TSCI fumished information on a number of websites offering
donor plaques. B. Beers noted that there is an upcoming
5.59a meeting with the Theater Foundation to further discuss the 10/03/05 TSCI
type of plaque to be selected. (08/11/05)
A design manual containing miscellaneous samples of etched
and cast plaques was reviewed during the course of .the
meeting. It was determined that the cast plaque with raised
letters in the better application for the donor wall. A list of
contributors was provided by B. Beers. TSCI will obtain
comparison pricing between the etched and cast plaques.
Donor plaques have been ordered and will be installed
prior to the theater opening. (09/22/05)
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements. TSCI noted
that it has contacted each of its relevant
subcontractors to obtain information. L. Campbell
will follow up with FSY to obtain the required
information.
A copy of Tri Citi Electric's response was provided to D.
5.64d McBride. FSY comments remain outstanding. (06.30.05) 07/07/05 FSY
FSY and its electrical consultant were directed to work directly
with SCE to come up with changes necessary to capture
incentives and long term savings. To date, FSY and N.A.
Cohen Group appears to be uninterested in making any
changes. (Revised 07125105)
FSY advised that current electrical drawings were forwarded to
SCE yesterday by the electrical engineer, N.A. Cohen Group.
(07/28.05)
FSY forwarded an e-mail from SCE yesterday. It appears that
this issue is close to resolution. 08/18/05
Page 4 of 6 VANIR F 503
VAN I R 9ROGRESS MEETING MINUTES•
Meeting#: 76
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting# Item # Description Due Action
Area Smoke Detectors at Mercantile Building:
B. Beers questioned the status to the final
resolution of the smoke detectors at the Mercantile
Building. FSY was instructed to delete the area
smoke detectors, include the duct smoke detector
as originally designed, and submit to the City of
Temecula Building Department for approval.
76 5.67b FSY advised that the revised mechanical plans were 08/29/05 VCM
submitted to the City on Monday,07/25/05. (07/28/05)
FSY advised that required corrections were resubmitted to the
City of Temecula earlier today. (08/18/05).
VCM will follow up with the Fire Department plan reviewer as
to the status of this submittal. (08/25/05)
Revised drawings have been approved with the condition
that HVAC tests must be conducted by an Independent
third partv.
Access to area below Platform at Audience
Chamber: TSCI noted that there is no access
shown for the area below the platform seating at
the audience chamber and that this area contains a
great deal of conduit and ducting. Following a field
5.67c review, it was determined that an access panel will N/A. Info
be installed in Electrical Closet 107A and the
access will be reflected on the as-built drawings.
In response to D. McBride's question regarding the cost of this
work,TSCI advised that the cost will be minimal. 07/28/05
Veneklausen AN changes:
See previous meeting minutes for a full discussion
of this issue.
Kevin Terry advised that Tovey Shultz will be meeting daily
with the Markus lead person and Tri Citi Electric to discuss
issues and assure that Markus is not being delayed.
(08/18/05)
The additional conduit required at the Technical Director and
5.68a Theater Managers offices to accommodate intercom, speaker Daily TSCI
control, and cable TV connections are being installed at this
time. There are no other issues delaying work for Markus at
this time. (08/25/05)
TSCI is meeting with Markus on a daily basis. At this fime
there are no issues delaying Markus'progress. (09/01/05)
TSCI is meeting with Markus on a daily basis. At this time
there are no issues delaying Markus'progress. 09/08/05
Fall arrest at ladders: W. Van Vechten asked who
is providing fall protection for ladders to the grid
5.72a iron. B. Beers noted that this is not included in the N/A Info
contract for construction and will be purchased by
TCSD.
Page 5 of 6 VANIR F 503
VAN I R IROGUSS MEETING MINUTE•
Meeting#: 76
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Operations Manual for lighting control: B. Beers
noted that the operations manual for the lighting
control is still outstanding and requested that a
copy be provided in order that production
personnel can become familiar with the controls
prior to the first scheduled performance.
76 5.74a N/A Info
Wm. Van Vechten advised that he has learned that the O&M
manual is in the box with the lighting control which is presently
in the scene shop. (09/08/05)
Wm. Van Vechten advised that he now has the O&M
manual for the lighting control. This item will be deleted
from future meeting agendas. 09/22/05
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM In writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely
nature
Name: Larry E. Campbell
Title: Project Manager
Page 6 of 6 - VANIR F 503
VANIR R R
PROGRESS MEETING MINUTES
Meeting#: 75
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: September 8, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: None
Attendees: Wm.Van Vechten, City of Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
Temecula Construction, Inc. (TSCI) Construction, Inc. (TSCI)
Larry Campbell,Vanir
Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
75 1.0 Approval Of Previous Meeting Minutes:
1.75 There were no additions or corrections to the
minutes of Weekly Progress Meeting 74. N/A Info
2.0 Construction Progress Update:
Installation of cedar siding, both on the exterior of
the building and in the audience chamber is
substantially complete. Painting of doors, door
frames, and walls is ongoing. Installation of
casework, carpet at the balcony, and installation of
electrical and fire alarm finishes and devices is
ongoing. Installation of AN wiring and termination
of wires is continuing. Interior finishes at the
Mercantile Buildings are substantially complete
with remaining work at the corbels and ticket booth
to be completed tomorrow Painting of the
Mercantile improvements is ongoing. Installation of
flooring in the Mercantile will be completed today
with finishing of the floor scheduled to begin
2.75 tomorrow. Wood doors and finish hardware is N/A Info
being installed.
Installation of theater seats has resumed and is
scheduled to be complete today. Installation of
cladding at the elevator tower is in progress and
concrete pavers under covered walkways are
expected to be complete tomorrow. Paving for the
parking lot has been completed although some
areas of repair are required. The sliding door at
the dance studio has been installed and fire alarm
terminations and testing are in progress.
Punch list items are being corrected in the scene
shop, production office, and property storage.
Page 1 of 8
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 75
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
75 3.0 Technical Concerns:
Schedule Review: Tovey Shultz' 3-week look-
ahead schedule was reviewed during the course of
the meeting:
Mercantile Building:
Installation of bars and glass at the ticket windows
is scheduled to be complete tomorrow and finishing
of the wood flooring will begin tomorrow and
require four days to complete. Lighting fixtures are
scheduled to be delivered Monday, 9/12, with
installation beginning as soon as finishing of the
flooring is complete.
3a.75 Main Theater Building: N/A Info
Painting of walls, doors, and trim will continue over
the next week. Installation of lighting, plumbing,
and fire alarm devices and trim will continue as will
installation and rigging of AN cable and
equipment. Installation of stage flooring will begin
tomorrow and be completed by mid-week. The
operable partition for the classrooms is scheduled
to be delivered on Monday.
Installation of landscaping will begin tomorrow and
continue into next week. Testing of AN systems is
scheduled to begin Monday, 9/19.
Following discussion, TSCI advised that there are
no issues foreseen as problems that require
3a.64b assistance from the City of Temecula. Based upon N/A Closed
that discussion, D. McBride advised that the
requested narrative is no longer required.
07.07.05
3b Submittal Status Review:
VCM's submittal log was reviewed during the
3b.75 course of the meeting. 154 submittals (including N/A Info
resubmittals) have been received to date. At this
date, there are no submittals outstanding
3c Request For Information Status Review:
A review of VCM's RFI log reflects 504 RFI's
3c.75 (including revisions) have been submitted to date. 09/12/05 FSY
There is one RFI's outstanding (RFI 451) which
has been outstanding for fifteen days.
Page 2 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 75
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
75 3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.75 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Eighteen Architect's Supplemental Instructions
3d.1.75 (ASI) have been issued as of this date. N/A Info
3d.2 Construction Bulletins
Thirty Construction Bulletins have been issued.
Of the thirty, 18 are in previously approved or
3d.2.75 pending change orders. Three have been 09/16/05 TSCINCM
superseded and 9 are pending negotiation.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 13 and 14 have been
3e.1.74 approved by the City Manager. N/A Info
3e.2 Proposed Change Orders
Two hundred four potential change requests
have been identified. Of those, 80 have been
incorporated into executed change orders, 19
3e.2.75 have been rejected, 44 are pending negotiation, 09/16/05 TSCINCM
40 have been voided, and 21 are pending
pricing.
3e.3 Disputed Items
TSCI has identified nine of the rejected change
3e.3.72 order requests and one proposed settlement as N/A Info
potential dispute items.
3f Payment Status Review:
3f.74 TSCI's draft payment request #19 will be 09/01/05 TSCINCM
reviewed following the meeting.
3g Notice Of Non Conformance Status:
There are no outstanding correction notices at
3g.75 this date. N/A Info
Page 3 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 75
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
75 3h As Built Status Review:
Revisions are being posted on a regular basis
3h.75 and are prerequisite to inspections. N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.75 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
Paving was inspected by City of Temecula Public
4.75 Works Inspectors and the Building Inspector stops N/A Info
by on a daily basis.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
not required and a credit for the pressure treating
5.51c. should be submitted since the original plans 03/24/05 TSCI
required pressure treated material.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall.
TSCI obtained preliminary pricing for the donor plaques. The
pricing received in significantly in excess of the donations for
the plaques. B. Beers will contact the Theater Foundation and
attempt to have cast bronze plaques approved. (07/14/05)
Following discussion, it was determined that TSCI will ask its
sign contractor for recommendations on resolving this issue.
(07/21/05)
TSCI furnished information on a number of websites offering
5.59a donor plaques. B. Beers noted that there is an upcoming 09/08/05 TSCI
meeting with the Theater Foundation to further discuss the
type of plaque to be selected. (08/11/05)
A design manual containing miscellaneous samples of etched
and cast plaques was reviewed during the course of the
meeting. It was determined that the cast plaque with raised
letters in the better application for the donor wall. A list of
contributors was provided by B. Beers. TSCI will obtain
comparison pricing between the etched and cast plaques.
Page 4 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 75
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements. TSCI noted
that it has contacted each of its relevant
subcontractors to obtain information. L. Campbell
will follow up with FSY to obtain the required
information.
A copy of Tri Citi Electric's response was provided to D.
75 5.64d McBride. FSY comments remain outstanding.(06.30.05) 07/07/05 FSY
FSY and its electrical consultant were directed to work directly
with SCE to come up with changes necessary to capture
incentives and long term savings. To date, FSY and N.A.
Cohen Group appears to be uninterested in making any
changes. (Revised 07125105)
FSY advised that current electrical drawings were forwarded to
SCE yesterday by the electrical engineer, N.A. Cohen Group.
(07/28.05)
FSY forwarded an e-mail from SCE yesterday. It appears that
this issue is close to resolution. 08/18/05
Area Smoke Detectors at Mercantile Building:
B. Beers questioned the status to the final
resolution of the smoke detectors at the Mercantile
Building. FSY was instructed to delete the area
smoke detectors, include the duct smoke detector
as originally designed, and submit to the City of
Temecula Building Department for approval.
5.67b FSY advised that the revised mechanical plans were 08/29/05 VCM
submitted to the City on Monday, 07/25/05. (07/28/05)
FSY advised that required corrections were resubmitted to the
City of Temecula earlier today. (08/18/05).
VCM will follow up with the Fire Department plan reviewer as
to the status of this submittal. (08/25/05)
Revised drawings have been approved with the condition
that HVAC tests must be conducted by an independent
third party.
Access to area below Platform at Audience
Chamber: TSCI noted that there is no access
5.67c shown for the area below the platform seating at N/A Info
the audience chamber and that this area contains a
great deal of conduit and ducting.
Access to area below Platform at Audience
Chamber: (continued)
Following a field review, it was determined that an
5.67c access panel will be installed in Electrical Closet
107A and the access will be reflected on the as-
built drawings.
In response to D. McBride's question regarding the cost of this
work,TSCI advised that the cost will be minimal. 07/28/05
Page 5 of 8 VANIR F 503
VANIR PROGRESS MEETING MINUTES•
Meeting#: 75
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Veneklausen AN changes:
See previous meeting minutes for a full discussion
of this issue.
Revisions to Veneklausen's design and Markus' pricing are
ongoing. (08/04/05)
While it appears that pricing issues have been sorted out, D.
McBride noted that it is imperative that all equipment has been
ordered. Markus Audio has not returned phone calls but a
schedule submitted by Markus reflects that all system
installation will be complete by 9/2/05. TSCI will follow up with
Markus to assure that all equipment has been ordered.
(08/11105)
5.68a Kevin Terry advised that Tovey Shultz will be meeting daily Daily TSCI
with the Markus lead person and Tri Citi Electric to discuss
issues and assure that Markus is not being delayed.
(08/18/05)
The additional conduit required at the Technical Director and
Theater Managers offices to accommodate intercom, speaker
control, and cable TV connections are being installed at this
time. There are no other issues delaying work for Markus at
this time. (08/25/05)
TSCI is meeting with Markus on a daily basis. At this time
there are no issues delaying Markus' progress. (09101105)
TSCI is meeting with Markus on a daily basis. At this time
there are no issues delaying Markus' progress. 09/08/05
Occupancy of Scene Shop and Mercantile
Building: It was explained to W. Van Vechten and
B. Beers (TCSD) again that occupancy of the
scene shop and Mercantile Building is dependent
on a completed certificate of occupancy by the
Building Department. Further, it was explained that
the project will be substantially complete by the
middle/end of August and TCSD may be able to
utilize, but not occupy, the space when the
5.68b buildings are substantially complete. This will be N/A Info
impacted by delays in construction and may not be
allowed by the rules and regulations of the City's
Building Department. The certificate of occupancy
is anticipated in early to mid September 2005.
Bruce Beers noted that ticket sales are slated to begin on
September 15 and noted that occupancy of the Mercantile
Building would be an asset. D. McBride noted that a formal
Certificate of Occupancy must be obtained prior to allowing
access to the public. 09/01/05
Sound panels at cross-over balcony: Concern has
previously been expressed regarding space for
5.68d seating at the cross-over balcony. There was N/A Info
discussion regarding whether or not the sound
panels at the rear wall should be reduced in size.
Page 6 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 75
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Sound panels at cross-over balcony: (continued)
Following field measurements performed by W.
75 5.68d Van Vechten and B. Beers after the meeting, N/A Info
construction management staff was instructed by
TSCD not to change the size of the sound panels.
Framing of side balconies: The response to RFI
427 as provided by FSY Architects indicated that
balconies are not framed in accordance with the
design intent. Following extensive discussion, it
was determined that the balconies will remain as
5.68e constructed and the back wall of the lower balcony N/A Info
will be painted black.
The back wall of the lower balcony shall be painted gray to
match the other walls in the audience chamber rather than
black as previously stated. (07/28/05)
Cap at removable handrail: W. Van Vechten asked
if the cap at the removable rail has been revised as
the revised Veneklausen drawings reflect a clip to
hold speakers. TSCI to review and advise.
Markus Audio has requested a sample of the wood
5.69a hand rail in order to design the added hanger clips. Complete Info
A sample of the cap at the removable handrail was
provided to Markus yesterday, 9/07/05. This issue will be
deleted from future meeting discussion. (09/08105)
Fall arrest at ladders: W. Van Vechten asked who
is providing fall protection for ladders to the grid
5.72a iron. B. Beers noted that this is not included in the N/A Info
contract for construction and will be purchased by
TCSD.
Capacity of ladder to Grid Iron: W. Van Vechten
noted that he is attempting to purchase fall
protection for the ladder to the Grid Iron and noted
that the ladder must have a capacity of 3,500 Ibs.
FSY to review whether or not a cage is included in
the contract for this ladder as well as the capacity
5.73a of the ladder. N/A Info
A quick calculation based upon the %-inch diameter rung
and 36ksi yield strength of the steel reflects that the
capacity of the ladder (approx. 20.25 k) greatly exceeds
the requirement for the fall protection. This issue will be
deleted from future meeting discussion. (09/01/05)
Page 7 of 8 VANIR F 503
VAN 1 R `OGRESS MEETING MINUTES
Meeting#: 75
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Operations Manual for lighting control: B. Beers
noted that the operations manual for the lighting
control is still outstanding and requested that a
copy be provided in order that production
5.74a personnel can become familiar with the controls N/A Info
prior to the first scheduled performance.
Wm. Van Vechten advised that he has learned that the
O&M manual is in the box with the lighting control which
is presently in the scene shop. 09/08/05
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
ig ature
Name: Larry E. Campbell
Title: Project Manager
Page 8 of 8 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting#: 74
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: September 1, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File # 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Kevin Terry,Tovey Shultz
Temecula Temecula Construction, Inc. (TSCI)
Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc. (TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
74 1.0 Approval Of Previous Meeting Minutes:
1.74 There were no additions or corrections to the
minutes of Weekly Progress Meeting 73. N/A Info
2.0 Construction Progress Update:
Exposed aggregate concrete flatwork was
completed during the past week. Installation of
cedar siding, both on the exterior of the building
and in the audience chamber, has resumed and is
ongoing. Painting of doors, door frames, and walls
is ongoing. Installation of casework, carpet at the
balcony, and installation of electrical and fire alarm
finishes and devices is ongoing. Installation of AN
wiring and termination of wires is continuing.
Ceiling tile is has been installed at the control
booth, amp room, and light locks. The trellis at the
east property wall of the Mercantile Building has
been installed and the decking completed. Interior
finishes at the Mercantile Buildings are
2.74 substantially complete with installation of the N/A Info
granite counter tops and completion of the ticket
booth remaining. Painting of the Mercantile
improvements is scheduled for next week.
Installation of flooring in the Mercantile is in
progress and will be completed following the Labor
Day special event in the front of the building.
Finish hardware is being installed today making the
building totally lockable.
Theater rigging is substantially complete as is the
installation of the lighting controls. Theater seats
have been installed with seating on the variable
platform and Row F remaining. Carpet is in
progress in the balcony.
Page 1 of 9
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 74
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
74 2.0 Construction Progress Update: (continued)
The Liebert air conditioning unit for the electrical
room is in progress and inspection of the elevator
by the State of California is currently being
performed. Installation of the variable platform is
scheduled for later today.
The scene shop has been turned over for use by
2.74 the theater operations personnel although some
punch list items remain to be completed.
Installation of the reduced pressure backflow
preventer for the domestic water service has been
inspected and signed off by Rancho California
Water District allowing for water service to the
project.
3.0 Technical Concerns:
Schedule Review: Tovey Shultz' 3-week look-
ahead schedule was reviewed during the course of
the meeting:
Mercantile Building:
Installation of granite counter tops and bars at the
ticket windows will occur next week. Installation of
recycled wood flooring will be completed during the
next week. Installation of lighting fixtures is
expected to begin late next week.
Main Theater Building:
Painting of walls, doors, and trim will continue over
3a.74 the next week. Exterior wood siding will continue N/A Info
as will installation of siding at the audience
chamber. Installation of lighting, plumbing, and fire
alarm devices and trim will continue as will
installation and rigging of AN cable and
equipment. Installation of stage flooring began this
week and it was determined that some corrective
work is required for the concrete substrate. The
sliding door at the dance studio is scheduled for
installation tomorrow.
Installation of paver tiles will begin tomorrow and
continue into next week. Work on the fountain is
scheduled to begin tomorrow.
Page 2 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 74
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Following discussion, TSCI advised that there are
no issues foreseen as problems that require
assistance from the City of Temecula. Based upon
74 3a.64b that discussion, D. McBride advised that the N/A Closed
requested narrative is no longer required.
(07.07.05)
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 154 submittals (including
3b.74 resubmittais) have been received to date. At this 09/07/05 FSY
date, one submittal is outstanding and has only
been outstanding for two days.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 504 RFI's
(including revisions) have been submitted to date.
3c.74 There are two RFI's outstanding; neither of 09/06/05 FSY
which have been outstanding for ten days or
more.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.74 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Eighteen Architect's Supplemental Instructions
3d.1.74 (ASI) have been issued as of this date. N/A Info
3d.2 Construction Bulletins
Thirty Construction Bulletins have been issued.
Of the thirty, 18 are in previously approved or
3d.2.74 pending change orders. Three have been 07/28/05 TSCINCIVI
superseded, 7 are pending negotiation, and 2
are pending pricing.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 13 and 14 have been
3e.1.74 approved by the City Manager. N/A Info
Page 3 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 74
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
74 3e.2 Proposed Change Orders
Two hundred potential change requests have
been identified. Of those, 80 have been
incorporated into executed change orders, 19
3e.2.74 have been rejected, 42 are pending negotiation, 09/09/05 TSCl/VCM
40 have been voided, and 19 are pending
pricing.
3e.3 Disputed Items
TSCI has identified nine of the rejected change
3e.3.72 order requests and one proposed settlement as N/A Info
potential dispute items.
3f Payment Status Review:
3f.74 TSCI's draft payment request #19 will be 09/01/05 TSCINCM
reviewed following the meeting.
3g Notice Of Non Conformance Status:
There are no outstanding correction notices at
3g.74 this date. N/A Info
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.74 N/A Info
and are prerequisite to inspections.
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.74 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
Sub grade and base course compaction has been
tested by Kleinfelder during the past week and
4.74 State of California inspection of the elevator is N/A Info
currently in progress.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Page 4 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 74
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Preservative for exterior siding:
See previous meeting minutes for full discussion of this
issue.
74 5.58a L. Campbell provided information derived from the N/A Info
Western Red Cedar Lumber Institute for the preservation
and protection of cedar siding to D. McBride. This issue
will be deleted from future meeting discussion. (09101/05)
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall.
TSCI obtained preliminary pricing for the donor plaques. The
pricing received in significantly in excess of the donations for
the plaques. B. Beers will contact the Theater Foundation and
attempt to have cast bronze plaques approved. (07/14/05)
Following discussion, it was determined that TSCI will ask its
sign contractor for recommendations on resolving this issue.
(07/21/05)
TSCI furnished information on a number of websites offering
5.59a donor plaques. B. Beers noted that there is an upcoming 09/08/05 TSCI
meeting with the Theater Foundation to further discuss the
type of plaque to be selected. (08/11/05)
A design manual containing miscellaneous samples of
etched and cast plaques was reviewed during the course
of the meeting. It was determined that the cast plaque
with raised letters in the better application for the donor
wall. A list of contributors was provided by B. Beers.
TSCI will obtain comparison pricing between the etched
and cast plaques.
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
expensive. Following discussion, it was
determined that the project team will work together
to determine a cost effective method to provide fall
protection affixed to the back wall.
It was determined that eye bolts will be installed at 10'-0" o.c.
at 6'-6" AFF. TSCI will submit the proposed bolt size and
5.64b. backing for approval. (07/14/05) N/A Info
TSCI provided a sketch of the proposed fall protection during
the course of the meeting. VCM will forward to the structural
engineer for review and approval. (08/11/05)
TSCI's sketch was forwarded to ENA Group and copied to
FSY via facsimile on Saturday,8/13/05.
Following discussion it was determined that this issue will
be deleted from future meeting discussion. (09/01/05)
Page 5 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 74
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements. TSCI noted
that it has contacted each of its relevant
subcontractors to obtain information. L. Campbell
will follow up with FSY to obtain the required
information.
A copy of Tri Citi Electric's response was provided to D.
McBride. FSY comments remain outstanding. (06.30.05)
74 5.64d FSY and its electrical consultant were directed to work directly 07/07/05 FSY
with SCE to come up with changes necessary to capture
incentives and long term savings. To date, FSY and N.A.
Cohen Group appears to be uninterested in making any
changes. (Revised 07125105)
FSY advised that current electrical drawings were forwarded to
SCE yesterday by the electrical engineer, N.A. Cohen Group.
(07/28.05)
FSY forwarded an e-mail from SCE yesterday. It appears that
this issue is close to resolution. (08/18/05)
Operating Chain at Roll Up Door 112/2: B. Beers
requested that the operating chain for the roll up
5.67a door at the stage be raised one bolt. N/A Info
This work has been completed and this issue will be
deleted from future meeting discussion. 09101/05
Area Smoke Detectors at Mercantile Building:
B. Beers questioned the status to the final
resolution of the smoke detectors at the Mercantile
Building. FSY was instructed to delete the area
smoke detectors, include the duct smoke detector
as originally designed, and submit to the City of
Temecula Building Department for approval.
FSY advised that the revised mechanical plans were
5.67b submitted to the City on Monday, 07/25/05. (07/28/05) 08/29/05 VCM
FSY advised that required corrections were resubmitted to the
City of Temecula earlier today. (08/18105).
VCM will follow up with the Fire Department plan reviewer as
to the status of this submittal. (08/25/05)
Revised drawings have been approved with the condition
that HVAC tests must be conducted by an independent
third party.
Access to area below Platform at Audience
Chamber: TSCI noted that there is no access
5.67c shown for the area below the platform seating at N/A Info
the audience chamber and that this area contains a
great deal of conduit and ducting.
Page 6 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 74
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Access to area below Platform at Audience
Chamber: (continued)
Following a field review, it was determined that an
5.67c access panel will be installed in Electrical Closet
107A and the access will be reflected on the as-
built drawings.
In response to D. McBride's question regarding the cost of this
work, TSCI advised that the cost will be minimal. 07/28/05
Veneklausen AN changes:
See previous meeting minutes for a full discussion
of this issue.
Revisions to Veneklausen's design and Markus' pricing are
ongoing. (08/04/05)
While it appears that pricing issues have been sorted out, D.
McBride noted that it is imperative that all equipment has been
ordered. Markus Audio has not returned phone calls but a
schedule submitted by Markus reflects that all system
installation will be complete by 9/2/05. TSCI will follow up with
Markus to assure that all equipment has been ordered.
5.68a (08/11/05) Daily TSCI
Kevin Terry advised that Tovey Shultz will be meeting daily
with the Markus lead person and Tri Citi Electric to discuss
issues and assure that Markus is not being delayed.
(08/18/05)
The additional conduit required at the Technical Director and
Theater Managers offices to accommodate intercom, speaker
control, and cable TV connections are being installed at this
time. There are no other issues delaying work for Markus at
this time. (08/25/05)
TSCI is meeting with Markus on a daily basis. At this time
there are no issues delaying Markus' progress. 09/01105
Occupancy of Scene Shop and Mercantile
Building: It was explained to W. Van Vechten and
B. Beers (TCSD) again that occupancy of the
scene shop and Mercantile Building is dependent
on a completed certificate of occupancy by the
Building Department. Further, it was explained that
the project will be substantially complete by the
middle/end of August and TCSD may be able to
utilize, but not occupy, the space when the
5.68b buildings are substantially complete. This will be N/A Info
impacted by delays in construction and may not be
allowed by the rules and regulations of the City's
Building Department. The certificate of occupancy
is anticipated in early to mid September 2005.
Bruce Beers noted that ticket sales are slated to begin on
September 15 and noted that occupancy of the Mercantile
Building would be an asset. D. McBride noted that a
formal Certificate of Occupancy must be obtained prior to
allowing access to the public. 09/01/05
Page 7 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 74
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Sound panels at cross-over balcony: Concern has
previously been expressed regarding space for
seating at the cross-over balcony. There was
discussion regarding whether or not the sound
73 5.68d panels at the rear wall should be reduced in size. N/A Info
Following field measurements performed by W.
Van Vechten and B. Beers after the meeting,
construction management staff was instructed by
TSCD not to change the size of the sound panels.
Framing of side balconies: The response to RFI
427 as provided by FSY Architects indicated that
balconies are not framed in accordance with the
design intent. Following extensive discussion, it
was determined that the balconies will remain as
5.68e constructed and the back wall of the lower balcony N/A Info
will be painted black.
The back wall of the lower balcony shall be painted gray to
match the other walls in the audience chamber rather than
black as previously stated. (07/28/05)
Cap at removable handrail: W. Van Vechten asked
if the cap at the removable rail has been revised as
the revised Veneklausen drawings reflect a clip to
5.69a hold speakers. TSCI to review and advise. 08/01/05 TSCI
Markus Audio has requested a sample of the wood
hand rail in order to design the added hanger clips.
Fall arrest at ladders: W. Van Vechten asked who
is providing fall protection for ladders to the grid
5.72a iron. B. Beers noted that this is not included in the N/A Info
contract for construction and will be purchased by
TCSD.
Capacity of ladder to Grid Iron: W. Van Vechten
noted that he is attempting to purchase fall
protection for the ladder to the Grid Iron and noted
that the ladder must have a capacity of 3,500 lbs.
FSY to review whether or not a cage is included in
5.73a the contract for this ladder as well as the capacity N/A Info
of the ladder.
A quick calculation based upon the %-inch diameter rung
and 36ksi yield strength of the steel reflects that the
capacity of the ladder (approx. 20.25 k) greatly exceeds
the requirement for the fall protection. This issue will be
deleted from future meeting discussion. 09/01/05
Page 8 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 74
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Labor Day Event: D. McBride noted that an event
has been scheduled for Saturday, 09/03/05 on
Main Street that will involve the use of a portion of
the Mercantile Bldg. VCM will provide TSCI an e-
mail detailing the steps that must to taken to
5.73b accommodate this event. N/A Info
Temporary handrails were inspected by Rich Johnston,
Sr. Building Inspector, earlier this morning. Minor
corrections were requested that will be complete by the
end of the day today. This item will be deleted from future
meeting discussion. 09/01/05
Operations Manual for lighting control: B. Beers
noted that the operations manual for the lighting
control is still outstanding and requested that a
5.74a 09I07/05 TSCI
copy be provided in order that production
personnel can become familiar with the controls
prior to the first scheduled performance.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely
S' nature
Name: Larry E. Campbell
Title: Project Manager
Page 9 of 9 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 73
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: August 25, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride,City of Bruce Beers,City of William Van Vechten, City of
Temecula Temecula Temecula
Steve Tovey,Tovey Shultz Kevin Terry,Tovey Shultz Arturo Yanez, FSY Larry Campbell,Vanir
Construction Inc. (TSCI) Construction, Inc. (TSCI) Architects(FSY) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
73 1.0 Approval Of Previous Meeting Minutes:
1.73 There were no additions or corrections to the
minutes of Weekly Progress Meeting 72. N/A Info
2.0 Construction Progress Update:
Concrete for fountain, steps at the dance studio,
planter walls, and sub slab for the paver tiles has
been placed and rebar installed for the concrete
flatwork. Painting of corridors, door frames, and
walls is ongoing. Room signage is being installed
currently. Installation of casework, carpet at the
audience chamber, and sound panels at the rear of
the audience chamber has been ongoing.
Installation of AN wiring and termination of wires is
ongoing. The glass for the control booth was
installed yesterday and ceiling tile is currently being
installed such that both the control booth and amp
rooms will be dust free by the end of the week.
2.73 Permanent power was connected last Friday and N/A Info
installation of lighting, electrical fixtures, and fire
alarm devices is in progress. Light bars and
handrails are being installed and theater seats are
currently being unloaded and layout is in progress.
Installation of finishes at the Mercantile Building is
continuing and should be complete by the middle
of next week.
The electrical and painting subcontractors are
continuing to work 10-hour days during the week
and additional electricians are scheduled to begin
Monday, 8/29.
Page 1 of 9
VAN 1 R 4PROGRESS MEETING MINUTE•
Meeting#: 73
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
73 3.0 Technical Concerns:
Schedule Review: Tovey Shultz' 3-week look-
ahead schedule was reviewed during the course of
the meeting:
Mercantile Building:
Installation of interior finishes and installation of
door hardware will continue into next week.
Flooring material has arrived and will be installed
beginning early next week and working from the
rear of the building toward the front.
Main Theater Building:
Painting of walls, doors, and trim will continue over
the next week. Installation of theater rigging is
3a.73 substantially complete. Exterior wood siding will N/A Info
continue as will installation of siding at the
audience chamber. Installation of lighting,
plumbing, and fire alarm devices and trim will
continue as will installation and rigging of AN cable
and equipment. Carpeting of the audience
chamber will continue into the middle of next week
as will the installation of theater seating.
Installation of stage flooring will begin tomorrow
and continue into next week. Installation of the
remaining sound panels at the rear of the audience
chamber should be completed by weeks end.
The sliding door at the dance studio is scheduled
for installation next week.
Following discussion, TSCI advised that there are
no issues foreseen as problems that require
assistance from the City of Temecula. Based upon
3a.64b that discussion, D. McBride advised that the N/A Closed
requested narrative is no longer required.
(07.07.05)
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 153 submittals (including
3b.72 resubmittals) have been received to date. At this 08/29/05 FSY
date, three submittals remain outstanding with
none outstanding in excess of ten days.
Page 2 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 73
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
73 3c Request For Information Status Review:
A review of VCM's RFI log reflects 503 RFI's
(including revisions) have been submitted to date.
3c.73 There are two RFI's outstanding; neither of 08/26/05 FSY
which have been outstanding for ten days or
more.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.73 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Eighteen Architect's Supplemental Instructions
3d.1.73 (ASI) have been issued as of this date. N/A Info
3d.2 Construction Bulletins
Thirty Construction Bulletins have been issued.
Of the thirty, 18 are in previously approved or
3d.2.73 pending change orders. Three have been 07/28/05 TSCINCM
superseded, 7 are pending negotiation, and 2
are pending pricing.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 13 and 14 have been
forwarded to TSCI for signature.3e.1.72 K.Terry advised that Change Order Nos. 13 and 14 were N/A Info
signed by TSCI earlier today. (08/18/05)
3e.2 Proposed Change Orders
One hundred ninety nine potential change
requests have been identified. Of those, 80
have been incorporated into executed change
3e.2.73 orders, 19 have been rejected, 40 are pending 09/02/05 TSCINCM
negotiation, 40 have been voided, and 20 are
pending pricing.
3e.3 Disputed Items
TSCI has identified nine of the rejected change
3e.3.72 order requests and one proposed settlement as
potential dispute items.
Page 3 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 73
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item# Description Due Action
73 3f Payment Status Review:
TSCI's payment request #18 was forwarded to City of
3f.70 the City of Temecula for processing on 8/3/05. 909/03/05 Temecula
3g Notice Of Non Conformance Status:
There are no outstanding correction notices at
3g.73 this date. N/A Info
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.73 and are prerequisite to inspections.
N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.73 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstandinq safety issues at this time.
4.0 Testing/Inspection:
Rough electrical and electrical panel make up
was inspected and signed off by the Building
4.73 Department this week. Fire Marshal inspection N/A Info
of fire alarm wiring is scheduled for later today.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51C. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. FSY stated that preservatives may cause
cupping but offered nothing more than that
5.58a statement. D. McBride explained that the City of 08/12/05 FSY
Temecula expects FSY to report on the
economics/aesthetics of preserving, staining (or
both) and comment on the frequency and cost of
these applications versus doing nothing at all.
Page 4 of 9 VANIR F 503
VAN 1 R IROGIIESS MEETING MINUTES•
Meeting#: 73
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Preservative for exterior siding (continued):
L. Campbell met with Mike McEachron to discuss
preservation of the wood siding. McEachron is of the
opinion that the application of a preservative at this point
results in a long term maintenance issue. McEachron
noted that a preservative would only penetrate the wood
to a depth of about 1132 inch and would need to reapplied
every two to three years. He did not think that application
of a preservative (either clear or semi-transparent) would
prevent cupping and expansion/shrinkage since the
73 5.58a material would not be applied to all four sides of the 09/01/05 VCM
material
Steve Tovey disagreed with McEachron's position and
stated that the wood should be cleaned by pressure
washing, have an application of citric acid applied to even
out the color, be again pressure washed, and have either
a clear of semi-transparent preservative applied. Tovey
suggested reviewing the recommendations posted on the
Redwood/Cedar Institute web site. VCM will review the
suggested web site for recommendations.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall.
TSCI obtained preliminary pricing for the donor plaques. The
pricing received in significantly in excess of the donations for
the plaques. B. Beers will contact the Theater Foundation and
attempt to have cast bronze plaques approved. (07/14/05)
5.59a Following discussion, it was determined that TSCI will ask its 08/17/05 TCSD
sign contractor for recommendations on resolving this issue.
(07/21/05)
TSCI furnished information on a number of websites offering
donor plaques. B. Beers noted that there is an upcoming
meeting with the Theater Foundation to further discuss the
type of plaque to be selected. 08/11/05
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
expensive. Following discussion, it was
determined that the project team will work together
to determine a cost effective method to provide fall
protection affixed to the back wall.
It was determined that eye bolts will be installed at 10'-0" o.c.
72 5.64b. at 6'-6" AFF. TSCI will submit the proposed bolt size and 08/15/05 ENA/FSY
backing for approval. (07/14105)
TSCI provided a sketch of the proposed fall protection during
the course of the meeting. VCM will forward to the structural
engineer for review and approval. (08/11/05)
TSCI's sketch was forwarded to ENA Group and copied to
FSY via facsimile on Saturday, 8/13105.
Page 5 of 9 VANIR F 503
VAN 1 R 'PROGRESS MEETING MINUTES•
Meeting#: 73
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements. TSCI noted
that it has contacted each of its relevant
subcontractors to obtain information. L. Campbell
will follow up with FSY to obtain the required
information.
A copy of Tri Citi Electric's response was provided to D.
McBride. FSY comments remain outstanding.(06.30.05)
73 5.64d FSY and its electrical consultant were directed to work directly 07/07/05 FSY
with SCE to came up with changes necessary to capture
incentives and long term savings. To date, FSY and N.A.
Cohen Group appears to be uninterested in making any
changes. (Revised 07125105)
FSY advised that current electrical drawings were forwarded to
SCE yesterday by the electrical engineer, N.A. Cohen Group.
(07/28.05)
FSY forwarded an e-mail from SCE yesterday. It appears that
this issue is close to resolution. (08/18/05)
Operating Chain at Roll Up Door 112/2: B. Beers
5.67a requested that the operating chain for the roll up 07/22/05 TSCI
door at the stage be raised one bolt.
Area Smoke Detectors at Mercantile Building:
B. Beers questioned the status to the final
resolution of the smoke detectors at the Mercantile
Building. FSY was instructed to delete the area
smoke detectors, include the duct smoke detector
as originally designed, and submit to the City of
5.67b Temecula Building Department for approval. 08/29/05 VCM
FSY advised that the revised mechanical plans were
submitted to the City on Monday,07/25/05. (07/28/05)
FSY advised that required corrections were resubmitted to the
City of Temecula earlier today. (08/18/05).
VCM will follow up with the Fire Department plan reviewer
as to the status of this submittal. 08/25/05
Access to area below Platform at Audience
Chamber: TSCI noted that there is no access
shown for the area below the platform seating at
the audience chamber and that this area contains a
great deal of conduit and ducting. Following a field
5.67c review, it was determined that an access panel will N/A Info
be installed in Electrical Closet 107A and the
access will be reflected on the as-built drawings.
In response to D. McBride's question regarding the cost of this
work,TSCI advised that the cost will be minimal.(07/28/05)
Page 6 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 73
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Veneklausen AN changes:
See previous meeting minutes for a full discussion
of this issue.
Revisions to Veneklausen's design and Markus' pricing are
ongoing. (08/04/05)
While it appears that pricing issues have been sorted out, D.
McBride noted that it is imperative that all equipment has been
ordered. Markus Audio has not returned phone calls but a
schedule submitted by Markus reflects that all system
installation will be complete by 9/2/05. TSCI will follow up with
5.68a Markus to assure that all equipment has been ordered. Daily TSCI
(08/11/05)
Kevin Terry advised that Tovey Shultz will be meeting daily
with the Markus lead person and Tri Citi Electric to discuss
issues and assure that Markus is not being delayed.
(08/18/05)
The additional conduit required at the Technical Director
and Theater Managers offices to accommodate intercom,
speaker control, and cable TV connections are being
installed at this time. There are no other issues delaying
work for Markus at this time.(08/25105)
Occupancy of Scene Shop and Mercantile
Building: It was explained to W. Van Vechten and
B. Beers (TCSD) again that occupancy of the
scene shop and Mercantile Building is dependent
on a completed certificate of occupancy by the
Building Department. Further, it was explained that
the project will be substantially complete by the
5.68b middle/end of August and TCSD may be able to N/A Info
utilize, but not occupy, the space when the
buildings are substantially complete. This will be
impacted by delays in construction and may not be
allowed by the rules and regulations of the City's
Building Department. The certificate of occupancy
is anticipated in early to mid September 2005.
Application for permanent power:
See previous meeting minutes for full discussion:
Inspection by the Fire Marshal is currently scheduled for .
Tuesday, 8/16/05.
Fire Sprinklers and site fire lines were signed off by the Fire
5.68c Marshal Wednesday, 08117/05. All required signatures from Closed Info
the City of Temecula were obtained by TSCI this morning.
Once notified by the City, SCE will turn on permanent power.
(08/18/05)
Permanent power was connected on Friday 08/19105. This
issue will be deleted from future meeting discussion.
(08/25/05)
Page 7 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 73
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Sound panels at cross-over balcony: Concern has
previously been expressed regarding space for
seating at the cross-over balcony. There was
discussion regarding whether or not the sound
73 5.68d panels at the rear wall should be reduced in size. N/A Info
Following field measurements performed by W.
Van Vechten and B. Beers after the meeting,
construction management staff was instructed by
TSCD not to change the size of the sound panels.
Framing of side balconies: The response to RFI
427 as provided by FSY Architects indicated that
balconies are not framed in accordance with the
design intent. Following extensive discussion, it
was determined that the balconies will remain as
5.68e constructed and the back wall of the lower balcony N/A Info
will be painted black.
The back wall of the lower balcony shall be painted gray to
match the other walls in the audience chamber rather than
black as previously stated. (07/28/05)
Cap at removable handrail: W. Van Vechten asked
if the cap at the removable rail has been revised as
the revised Veneklausen drawings reflect a clip to
5.69a hold speakers. TSCI to review and advise. 08/01/05 TSCI
Markus Audio has requested a sample of the wood
hand rail in order to design the added hanger clips.
Fall arrest at ladders: W. Van Vechten asked who
is providing fall protection for ladders to the grid
5.72a iron. B. Beers noted that this is not included in the N/A Info
contract for construction and will be purchased by
TCSD.
Capacity of ladder to Grid Iron: W. Van Vechten
noted that he is attempting to purchase fall
protection for the ladder to the Grid Iron and noted
5.73a that the ladder must have a capacity of 3,500 lbs. 08/29/05 FSY
FSY to review whether or not a cage is included in
the contract for this ladder as well as the capacity
of the ladder.
Labor Day Event: D. McBride noted that an event
has been scheduled for Saturday, 09/03/05 on
5.73b Main Street that will involve the use of a portion of 08/26/05 VCM
the Mercantile Bldg. VCM will provide TSCI an e-
mail detailing the steps that must to taken to
accommodate this event.
Page 8 of 9 VANIR F 503
VAN I R PROGRESS MEETING MINUTES
Meeting#: 73
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely4_�
Sig ature
Name: Larry E. ampbell
Title: Project Manager
Page 9 of 9 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting#: 72
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: August 18, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File # 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: Greg Butler, City of David McBride, City of Bruce Beers,City of
Temecula Temecula Temecula
William Van Vechten,City of Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell, Vanir
Temecula Construction, Inc. (TSCI) Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
72 1.0 Approval Of Previous Meeting Minutes:
1.72 There were no additions or corrections to the
minutes of Weekly Progress Meeting 71. N/A Info
2.0 Construction Progress Update:
Installation of exterior siding and trim has resumed
during the week and taping and sanding of drywall
has been ongoing. Painting in the audience
chamber and scene shop has been ongoing and
installation of exterior lights and electrical trim is in
progress. Installation of theater rigging and
installation of AN wiring and rigging for speakers is
continuing. Installation of siding within the
2.72 audience chamber has been curtailed pending N/A Info
receipt of additional material. The sound baffles
have been completed. Exterior doors are being
installed along with door hardware. Plumbing for
the fountain is currently being installed and grading
and forming for exterior concrete flatwork is in
progress.
The electrical and painting subcontractors are
continuing to work 10-hour days during the week.
72 3.0 Technical Concerns:
Schedule Review: Tovey Shultz' 3-week look-
ahead schedule was reviewed during the course of
the meeting:
3a.72a Mercantile Building: N/A Info
Installation of interior finishes and installation of
doors will resume Monday, 8/22/05. Flooring
material has arrived and will be installed following
work by the finish trades.
Page 1 of 8
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 72
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
72 3.0 Technical Concerns:
3a.72a Schedule Review (continued)
Main Theater Building:
Painting of audience chamber walls will continue
over the next week. Installation of theater rigging
will continue. Exterior wood siding will continue as
will installation of siding at the audience chamber
dependent upon receipt of ordered cedar siding
scheduled to be delivered Thursday, 8/25.
Installation of lighting and plumbing fixtures and
trim will continue as will installation and rigging of
AN cable and equipment. Carpeting of the steps
in the audience chamber is scheduled to begin
tomorrow, 8/19/05 and installation of theater
seating (originally scheduled to begin the week of
8/15/05) will begin Tuesday, 8/23/05. The window
for the sound booth is scheduled to be installed
next week. Installation of sound panels at the rear
of the audience chamber is scheduled for
Saturday, 8/20. The sliding door at the dance
studio is scheduled for installation next week as is
installation of metal cladding at the elevator tower.
HVAC startup is scheduled for Tuesday, 8/23/05.
Following discussion, TSCI advised that there are
no issues foreseen as problems that require
assistance from the City of Temecula. Based upon
3a.64b that discussion, D. McBride advised that the N/A Closed
requested narrative is no longer required.
(07.07.05)
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 152 submittals (including
3b.72 resubmittals) have been received to date. At this 08/22/05 FSY
date, two submittals remain outstanding with
none outstanding in excess of ten days.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 495 RFI's
(including revisions) have been submitted to date.
3c.72 There are two RFI's outstanding; neither of 08/22/05 FSY
which have been outstanding for ten days or
more.
Page 2 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 72
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
72 3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.72 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Eighteen Architect's Supplemental Instructions
3d.1.72 (ASI) have been issued as of this date. N/A Info
3d.2 Construction Bulletins
Thirty Construction Bulletins have been issued.
Of the thirty, 18 are in previously approved or
3d.2.72 pending change orders. Three have been 07/28/05 TSCINCM
superseded, 7 are pending negotiation, and 2
are pending pricing.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 13 and 14 have been
3e.1.72 forwarded to TSCI for signature. N/A Info
K.Terry advised that Change Order Nos. 13 and 14
were signed by TSCI earlier today. 08/18/05
3e.2 Proposed Change Orders
One hundred ninety four potential change
requests have been identified. Of those, 80
3e.2.72
have been incorporated into executed change
orders, 19 have been rejected, 39 are pending os/25/os TSCl/VCM
negotiation, 39 have been voided, and 17 are
pending pricing.
3e.3 Disputed Items
TSCI has identified ten of the rejected change
3e.3.72 order requests and one proposed settlement as
potential dispute items.
3f Payment Status Review:
TSCI's payment request #18 was forwarded to
3f.70 the City of Temecula for processing on 8/3/05. 909/03/05 City of
Temecula
3g Notice Of Non Conformance Status:
There are no outstanding correction notices at
3g.72 this date. N/A Info
Page 3 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 72
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
72 3h As Built Status Review:
Revisions are being posted on a regular basis
3h.72 and are prerequisite to inspections.
N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.72 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
Fire sprinkler and site fire lines were inspected
4.72 and signed off by the Fire Marshal yesterday, N/A Info
8/17/05.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. FSY stated that preservatives may cause
cupping but offered nothing more than that
5.58a statement. D. McBride explained that the City of 08/12/05 FSY
Temecula expects FSY to report on the
economics/aesthetics of preserving, staining (or
both) and comment on the frequency and cost of
these applications versus doing nothing at all.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall.
TSCI obtained preliminary pricing for the donor plaques. The
pricing received in significantly in excess of the donations for
the plaques. B. Beers will contact the Theater Foundation and
attempt to have cast bronze plaques approved. (07/14/05)
72 5.59a Following discussion, it was determined that TSCI will ask its 08/17/05 TCSD
sign contractor for recommendations on resolving this issue.
(07/21/05)
TSCI furnished information on a number of websites
offering donor plaques. B. Beers noted that there is an
upcoming meeting with the Theater Foundation to further
discuss the type of plaque to be selected. 08111/05
Page 4 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 72
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
expensive. Following discussion, it was
determined that the project team will work together
to determine a cost effective method to provide fall
72 5.64b. protection affixed to the back wall. 08/12/05 VCM
It was determined that eye bolts will be installed at 10'-0" o.c.
at 6'-6" AFF. TSCI will submit the proposed bolt size and
backing for approval. (07/14/05)
TSCI provided a sketch of the proposed fall protection
during the course of the meeting. VCM will forward to the
structural engineer for review and approval. (08/11/05)
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements. TSCI noted
that it has contacted each of its relevant
subcontractors to obtain information. L. Campbell
will follow up with FSY to obtain the required
information.
A copy of Tri Citi Electric's response was provided to D.
McBride. FSY comments remain outstanding. (06.30.05)
5.64d FSY and its electrical consultant were directed to work directly 07/07/05 FSY
with SCE to come up with changes necessary to capture
incentives and long term savings. To date, FSY and N.A.
Cohen Group appears to be uninterested in making any
changes. (Revised 07/25/05)
FSY advised that current electrical drawings were forwarded to
SCE yesterday by the electrical engineer, N.A. Cohen Group.
(07/28.05)
FSY forwarded an e-mail from SCE yesterday. It appears
that this issue is close to resolution. (08118/05)
Operating Chain at Roll Up Door 112/2: B. Beers
5.67a requested that the operating chain for the roll up 07/22/05 TSCI
door at the stage be raised one bolt.
Area Smoke Detectors at Mercantile Building:
B. Beers questioned the status to the final
resolution of the smoke detectors at the Mercantile
Building. FSY was instructed to delete the area
smoke detectors, include the duct smoke detector
5.67b as originally designed, and submit to the City of 07/21/05 FSY
Temecula Building Department for approval.
FSY advised that the revised mechanical plans were
submitted to the City on Monday, 07/25/05. (07/28/05)
FSY advised that required corrections were resubmitted
to the City of Temecula earlier today. 08/18/05 .
Page 5 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 72
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Access to area below Platform at Audience
Chamber: TSCI noted that there is no access
shown for the area below the platform seating at
the audience chamber and that this area contains a
great deal of conduit and ducting. Following a field
72 5.67c review, it was determined that an access panel will N/A Info
be installed in Electrical Closet 107A and the
access will be reflected on the as-built drawings.
In response to D. McBride's question regarding the cost
of this work, TSCI advised that the cost will be minimal.
07/28/05
Veneklausen AN changes:
See previous meeting minutes for a full discussion
of this issue.
Revisions to Veneklausen's design and Markus' pricing are
ongoing. (08/04/05)
While it appears that pricing issues have been sorted out, D.
McBride noted that it is imperative that all equipment has been
5.68a ordered. Markus Audio has not returned phone calls but a Daily TSCI
schedule submitted by Markus reflects that all system
installation will be complete by 9/2/05. TSCI will follow up with
Markus to assure that all equipment has been ordered.
(08/11/05)
Kevin Terry advised that Tovey Shultz will be meeting
daily with the Markus lead person and Tri Citi Electric to
discuss issues and assure that Markus is not being
delayed. 08/18/05
Occupancy of Scene Shop and Mercantile
Building: It was explained to W. Van Vechten and
B. Beers (TCSD) again that occupancy of the
scene shop and Mercantile Building is dependent
on a completed certificate of occupancy by the
Building Department. Further, it was explained that
5.68b the project will be substantially complete by the N/A Info
middle/end of August and TCSD may be able to
utilize, but not occupy, the space when the
buildings are substantially complete. This will be
impacted by delays in construction and may not be
allowed by the rules and regulations of the City's
Building Department. The certificate of occupancy
is anticipated in early to mid September 2005.
Application for permanent power:
See previous meeting minutes for full discussion:
Inspection by the Fire Marshal is currently scheduled for
Tuesday, 8/16105.
5.68c Fire Sprinklers and site fire lines were signed off by the N/A Info
Fire Marshal Wednesday, 08/17/05. All required
signatures from the City of Temecula were obtained by
TSCI this morning. Once notified by the City, SCE will
turn on permanent power.
08/18/05
Page 6 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 72
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action Mee
9 +
Sound panels at cross-over balcony: Concern has
previously been expressed regarding space for
seating at the cross-over balcony. There was
discussion regarding whether or not the sound
72 5.68d panels at the rear wall should be reduced in size. N/A Info
Following field measurements performed by W.
Van Vechten and B. Beers after the meeting,
construction management staff was instructed by
TSCD not to change the size of the sound panels.
Framing of side balconies: The response to RFI
427 as provided by FSY Architects indicated that
balconies are not framed in accordance with the
design intent. Following extensive discussion, it
was determined that the balconies will remain as
5.68e constructed and the back wall of the lower balcony N/A Info
will be painted black.
The back wall of the lower balcony shall be painted gray to
match the other walls in the audience chamber rather than
black as previously stated. (07/28/05)
Cap at removable handrail: W. Van Vechten asked
if the cap at the removable rail has been revised as
the revised Veneklausen drawings reflect a clip to
5.69a hold speakers. TSCI to review and advise. 08/01/05 TSCI
Markus Audio has requested a sample of the wood
hand rail in order to design the added hanger clips.
Fall arrest at ladders: W. Van Vechten asked who
is providing fall protection for ladders to the grid
5.72a iron. B. Beers noted that this is not included in the N/A Info
contract for construction and will be purchased by
TCSD.
Page 7 of 8 VANIR F 503
VAN 1 R IROGUSS MEETING MINUTE
Meeting#: 72
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
�� nature
Name: Larry E. Campbell
Title: Project Manager
Page 8 of 8 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting#: 71
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: August 11, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.6
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride,City of Bruce Beers,City of William Van Vechten, City of
Temecula Temecula Temecula
Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc. (TSCI) Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
71 1.0 Approval Of Previous Meeting Minutes:
1.71 There were no additions or corrections to the
minutes of Weekly Progress Meeting 70. N/A Info
2.0 Construction Progress Update:
Framing activities have been directed toward
construction of stairs, handrails, and the trellis at
Deck 214. It was noted that cedar siding is
becoming difficult to obtain and installation of
siding will resume once the pending order is
received. Drywall at the audience chamber walls
and sides of the sound baffles is being taped and
sanded. HVAC ducting at the audience chamber
and Mercantile Building is continuing and painting
of walls in the audience chamber and exterior
doors and frames is ongoing. Electrical rough in,
making up of panels, connections to switchgear
and installation of lighting fixtures are ongoing.
Installation of theater rigging and fire curtain and
2.71 installation of A wiring is continuing with AN N/A Info
N
rigging beginning today. Installation of finishes in
the audience chamber is continuing. Finishes at
the Mercantile Building are continuing as is the
installation of door and window casing. Fire
sprinklers have been installed at stairs and decks.
Work on the elevator is continuing and ladders and
rails are being installed. Grading of the parking lot
is substantially complete and installation of
irrigation sleeves is in progress.
At this date, the electrical and painting
subcontractors are working 10-hour days during
the week and manpower has been increased.
Page 1 of 8
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 71
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
71 3.0 Technical Concerns:
Schedule Review: Tovey Shultz' 3-week look-
ahead schedule was reviewed during the course of
the meeting:
Mercantile Building:
Installation of the store front, handrails, doors, new
windows, and interior finishes will continue through
the next week.
Main Theater Building:
Painting of audience chamber walls will continue
over the next week. Installation of theater rigging
will continue. Installation of the elevator is in
progress and will continue for the next week.
3a.71 a Exterior wood siding will continue as will installation N/A Info
of siding at the audience chamber dependent upon
receipt of ordered cedar siding. Installation of
lighting and plumbing fixtures will continue as will
installation and rigging of AN cable and
equipment. Carpeting of the steps is scheduled to
begin next week and installation of theater seating
(originally scheduled to begin the week of 8/15/05)
has been delayed until 8/23/05 to allow for the
completion of painting and siding installation. The
window for the sound booth is scheduled to be
installed next week. Fire Marshal inspection is
scheduled for Tuesday, 8/16/05, and is the primary
sign-off required for permanent power.
Following discussion, TSCI advised that there are
no issues foreseen as problems that require
assistance from the City of Temecula. Based upon
3a.64b that discussion, D. McBride advised that the N/A Closed
requested narrative is no longer required.
(07.07.05)
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 152 submittals (including
3b.71 resubmittals) have been received to date. At this 08115/05 FSY
date, two submittals remain outstanding with
none outstanding in excess of ten days.
Page 2 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 71
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
70 3c Request For Information Status Review:
A review of VCM's RFI log reflects 493 RFI's
(including revisions) have been submitted to date.
3c.71 There are two RFI's outstanding; neither of 08/15/05 FSY
which have been outstanding for ten days or
more.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.71 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
3d.1.71 Eighteen Architect's Supplemental Instructions N/A Info
ASI have been issued as of this date.
3d.2 Construction Bulletins
Thirty Construction Bulletins have been issued.
Of the thirty, 18 are in previously approved or
3d.2.71 pending change orders. Three have been 07/28/05 TSCINCM
superseded, 7 are pending negotiation, and 2
are pending pricing.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 13 and 14 have been
3e.1.71 forwarded to TSCI for signature. 08/15/05 TSCI
3e.2 Proposed Change Orders
One hundred ninety two potential change
requests have been identified. Of those, 80
have been incorporated into executed or
3e.2.71 pending change orders, 19 have been rejected, 08/18/05 TSCINCM
36 are pending negotiation, 38 have been
voided, and 19 are pending pricing.
3e.3 Disputed Items
TSCI has identified ten of the rejected change
order requests as potential dispute items.
Although the proposed settlement of one
3e.3.71 additional change order request has been noted N/A Info
as disputed by the applicable subcontractor, no
official notice has been received.
Page 3 of 8 VANIR f 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 71
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
71 3f Payment Status Review:
TSCI's payment request #18 was forwarded to
3f.70 the City of Temecula for processing on 8/3/05. 909/03/05 City of
Temecula
3g Notice Of Non Conformance Status:
There are no outstanding correction notices at
3g.71 this date. N/A Info
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.71 and are prerequisite to inspections. NIA Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.71 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
Rough electrical and water supply lines for the
4.71 fountain were inspected by Building and Safety N/A Info
on Wednesday, 8/10/05.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood .
siding. FSY stated that preservatives may cause
cupping but offered nothing more than that
5.58a statement. D. McBride explained that the City of 08/12/05 FSY
Temecula expects FSY to report on the
economics/aesthetics of preserving, staining (or
both) and comment on the frequency and cost of
these applications versus doing nothing at all.
Page 4 of 8 VANIR F 503
VAN 1 R IROGRESS MEETING MINUTES
Meeting#: 71
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall.
TSCI obtained preliminary pricing for the donor plaques. The
pricing received in significantly in excess of the donations for
the plaques. B. Beers will contact the Theater Foundation and
attempt to have cast bronze plaques approved. (07/14/05)
Following discussion, it was determined that TSCI will ask its
71 5.59a sign contractor for recommendations on resolving this issue. 08/17/05 TCSD
(07/21/05)
TSCI furnished information on a number of websites
offering donor plaques. B. Beers noted that there is an
upcoming meeting with the Theater Foundation to further
discuss the type of plaque to be selected. (08/11/05)
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
expensive. Following discussion, it was
determined that the project team will work together
to determine a cost effective method to provide fall
5.64b. protection affixed to the back wall. 08/12/05 VCM
It was determined that eye bolts will be installed at 10'-0" o.c.
at 6'-6" AFF. TSCI will submit the proposed bolt size and
backing for approval. (07/14/05)
TSCI provided a sketch of the proposed fall protection
during the course of the meeting. VCM will forward to the
structural engineer for review and approval. (08111/05)
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements. TSCI noted
that it has contacted each of its relevant
subcontractors to obtain information. L. Campbell
will follow up with FSY to obtain the required
information.
5.64d A copy of Tri Citi Electric's response was provided to D. 07/07/05 FSY
McBride. FSY comments remain outstanding. (06.30.05)
FSY and its electrical consultant were directed to work directly
with SCE to come up with changes necessary to capture
incentives and long term savings. To date, FSY and N.A.
Cohen Group appears to be uninterested in making any
changes. (Revised 07125105)
FSY advised that current electrical drawings were
forwarded to SCE yesterday by the electrical engineer,
N.A. Cohen Group. (07/28.05)
Page 5 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 71
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Operating Chain at Roll Up Door 112/2: B. Beers
5.67a requested that the operating chain for the roll up 07/22/05 TSCI
door at the stage be raised one bolt.
Area Smoke Detectors at Mercantile Building:
B. Beers questioned the status to the final
resolution of the smoke detectors at the Mercantile
Building. FSY was instructed to delete the area
5.67b smoke detectors, include the duct smoke detector 07/21/05 FSY
as originally designed, and submit to the City of
Temecula Building Department for approval.
FSY advised that the revised mechanical plans were
submitted to the City on Monday,07/25/05. 07/28/05
Access to area below Platform at Audience
Chamber: TSCI noted that there is no access
shown for the area below the platform seating at
the audience chamber and that this area contains a
great deal of conduit and ducting. Following a field
5.67c review, it was determined that an access panel will N/A Info
be installed in Electrical Closet 107A and the
access will be reflected on the as-built drawings.
In response to D. McBride's question regarding the cost
of this work, TSCI advised that the cost will be minimal.
07/28/05
Veneklausen AN changes:
See previous meeting minutes for a full discussion
of this issue.
Revisions to Veneklausen's design and Markus' pricing are
ongoing. (08/04/05)
5.68a While it appears that pricing issues have been sorted out, 08/11/05 TSCI
D. McBride noted that it is imperative that all equipment
has been ordered. Markus Audio has not returned phone
calls but a schedule submitted by Markus reflects that all
system installation will be complete by 9/2/05. TSCI will
follow up with Markus to assure that all equipment has
been ordered. 08/11/05
Occupancy of Scene Shop and Mercantile
Building: It was explained to W. Van Vechten and
B. Beers (TCSD) again that occupancy of the
scene shop and Mercantile Building is dependent
on a completed certificate of occupancy by the
Building Department. Further, it was explained that
5.68b the project will be substantially complete by the N/A Info
middle/end of August and TCSD may be able to
utilize, but not occupy, the space when the
buildings are substantially complete. This will be
impacted by delays in construction and may not be
allowed by the rules and regulations of the City's
Building Department. The certificate of occupancy
is anticipated in early to mid September 2005.
Page 6 of 8 VANIR F 503 -
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 71
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Application for permanent power: TSCI requested
information regarding the application for permanent
power. Following discussion, TSCI was advised to
discuss the particulars with Building & Safety
Inspector, Bob Henderson.
5.68c The application for permanent power was submitted last 08/16/05 TSCI
Friday, 07/29/05. Inspection for sign-off for permanent power
is scheduled with Building&Safety tomorrow. (08/04/05)
Inspection by the Fire Marshal is currently scheduled for
Tuesday,8116105.
Sound panels at cross-over balcony: Concern has
previously been expressed regarding space for
seating at the cross-over balcony. There was
discussion regarding whether or not the sound
5.68d panels at the rear wall should be reduced in size. N/A Info
Following field measurements performed by W.
Van Vechten and B. Beers after the meeting,
construction management staff was instructed by
TSCD not to change the size of the sound panels.
Framing of side balconies: The response to RFI
427 as provided by FSY Architects indicated that
balconies are not framed in accordance with the
design intent. Following extensive discussion, it
was determined that the balconies will remain as
5.68e constructed and the back wall of the lower balcony N/A Info
will be painted black.
The back wall of the lower balcony shall be painted gray
to match the other walls in the audience chamber rather
than black as previously stated. (07128105)
Cap at removable handrail: W. Van Vechten asked
if the cap at the removable rail has been revised as
the revised Veneklausen drawings reflect a clip to
5.69a hold speakers. TSCI to review and advise. 08/01/05 TSCI
Markus Audio has requested a sample of the wood
hand rail in order to design the added hanger clips.
Page 7 of 8 VANIR F 503
VAN 1 R IROGRESS MEETING MINUTES
Meeting#: 71
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely, ����
7 7 � tiia ure
Name: Larry E. Campbell
Title: Project Manager
Page 8 of 8 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting#: 70
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: August 4, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of William Van Vechten, City of
Temecula Temecula Temecula
Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Sean Park, FSY Architects Larry Campbell,Vanir
Construction, Inc. (TSCI) Construction, Inc(TSCI) (FSY) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
70 1.0 Approval Of Previous Meeting Minutes:
The Minutes of Meeting No. 69 are corrected to
read as follows:
Item 5.58a: Delete the second and third sentences and add:
FSY stated that preservatives may cause cupping but
offered nothing more than that statement. D. McBride
explained that the City of Temecula expects FSY to report
1.70 on the economics/aesthetics of preserving, staining (or
both) and comment on the frequency and cost of these N/A Info
applications versus doing nothing at all.
Item 5.68a: Paragraph 2: Revise `TSCI"to read "TCSD".
Item 5.69a: ADD: Markus Audio has requested a sample
of the wood hand rail in order to design the added hanger
clips.
2.0 Construction Progress Update:
Siding installation at the south side of the theater is
continuing. Framing for the overhangs at the
classroom windows is complete and framing for the
stair at the elevator is in progress as is framing for
the property wall fences. Drywall installation is
substantially complete and taping is continuing.
HVAC ducting at the audience chamber and
2.70 Mercantile Building is continuing and painting of N/A Info
walls in the audience chamber and ceiling of the
Mercantile Building is ongoing. Electrical rough in,
making up of panels, connections to switchgear
and installation of lighting fixtures are ongoing.
Installation of theater rigging and installation of AN
wiring is continuing. Installation of finishes in the
audience chamber is continuing as is the
installation of casework throughout.
Page 1 of 8
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 70
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
70 2.0 Construction Progress Update: (continued)
Installation of the elevator is continuing and is
approximately ninety percent complete. Installation
2.70 of the storefront, doors, and handrails is in
progress at the Mercantile Building and installation
of curbs and gutters will be complete today.
3.0 Technical Concerns:
Schedule Review: Tovey Shultz' 3-week look-
ahead schedule was reviewed during the course of
the meeting:
Mercantile Buildinq:
Installation of the store front, handrails, doors, new
windows, and interior finishes will continue through
the next week. Painting of the ceiling will be
complete today and painting of walls is scheduled
to begin tomorrow.
Main Theater Buildinq:
3a.70a Painting of audience chamber walls will continue N/A Info
over the next few weeks. Installation of theater
rigging will continue. Installation of the elevator is
in progress and will continue for the next week.
Wood flooring for the Dance Studio will continue
into next week. Exterior wood siding will continue
as will installation of siding at the audience
chamber. Installation of lighting and plumbing
fixtures will continue as will installation of AN cable
and accessories. Carpeting of the steps is
scheduled to begin the week of 8/8/05 and
installation of theater seating is scheduled to begin
the week of 8/15/05.
Following discussion, TSCI advised that there are
no issues foreseen as problems that require
3a.64b assistance from the City of Temecula. Based upon N/A Closed
that discussion, D. McBride advised that the
requested narrative is no longer required.
07.07.05
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 151 submittals (including
3b.70 resubmittals) have been received to date. At this 08/08/05 FSY
date, two submittals remain outstanding of which
one has been outstanding in excess of ten days.
Page 2 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 70
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
70 3c Request For Information Status Review:
A review of VCM's RFI log reflects 490 RFI's
3c.70 (including revisions) have been submitted to date. 08/08/05 FSY
There are three RFI's outstanding; all submitted
within the last two days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.70 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
3d.1.70 Eighteen Architect's Supplemental Instructions N/A Info
(ASh have been issued as of this date.
3d.2 Construction Bulletins
Thirty Construction Bulletins have been issued.
Of the thirty, 18 are in previously approved or
3d.2.69 pending change orders. Three have been 07/28/05 TSCINCM
superseded, 7 are pending negotiation, and 2
are pending pricing.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
The draft of Change Order No. 14 containing
3e.1.69 thirteen proposed change orders was forwarded 08/05/05 City of
to D. McBride yesterday, 7/27/05. Temecula
3e.2 Proposed Change Orders
One hundred eighty nine potential change
requests have been identified. Of those, 80
have been incorporated into executed or
3e.2.69 pending change orders, 19 have been rejected, 08/05/05 TSCINCM
33 are pending negotiation, 38 have been
voided, and 19 are pending pricing.
3e.3 Disputed Items
TSCI has identified ten of the rejected change
3e.3.70 order requests as potential dispute items. N/A Info
3f Payment Status Review:
3f.70 TSCI's payment request #18 was forwarded to 909/03/05 City of
the City of Temecula for processing on 8/3/05. Temecula
Page 3 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 70
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
70 3g Notice Of Non Conformance Status:
3 70 There are no outstanding correction notices at N/A Info
S this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.70 and are prerequisite to inspections.
N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.70 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
Inspection of the electrical system was
conducted by Building and Safety on
4.70 Wednesday, 8/3/05 for purposes of permanent 08/06/05 TSCI
power. Minor corrections are required and
reins ection is scheduled for tomorrow.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. FSY stated that preservatives may cause
cupping but offered nothing more than that
5.58a statement. D. McBride explained that the City of 08/12/05 FSY
Temecula expects FSY to report on the
economics/aesthetics of preserving, staining (or
both) and comment on the frequency and cost of
these applications versus doing nothing at all.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall.
TSCI obtained preliminary pricing for the donor plaques. The
pricing received in significantly in excess of the donations for
5.59a the plaques. B. Beers will contact the Theater Foundation and 07/28/05 TSCI
attempt to have cast bronze plaques approved. (07/14/05)
Following discussion, it was determined that TSCI will ask
its sign contractor for recommendations on resolving this
issue. 07/21/05
Page 4 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 70
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
expensive. Following discussion, it was
70 5.64b. determined that the project team will work together 07/21/05 TSCI
to determine a cost effective method to provide fall
protection affixed to the back wall.
It was determined that eye bolts will be installed at 10'-0"
o.c. at 6'-6" AFF. TSCI will submit the proposed bolt size
and backing for approval. 07/14/05
Theatrical Systems: A review of the schedule
reflects that theatrical lighting, theatrical rigging,
and AN systems will be operational by mid-August.
D. McBride requested that copies of all related
5.64c submittals be provided to Bruce Beers and that Info Closed
relevant O&M manuals be submitted by early
August.
O&M Manuals for various items including theatrical
lighting, lighting control, and theatrical rigging and
draperies were provided to TCSD this date. 08105/05
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements. TSCI noted
that it has contacted each of its relevant
subcontractors to obtain information. L. Campbell
will follow up with FSY to obtain the required
information.
5.64d A copy of Tri Citi Electric's response was provided to D. 07/07/05 FSY
McBride. FSY comments remain outstanding. (06.30.05)
FSY and its electrical consultant were directed to work directly
with SCE to come up with changes necessary to capture
incentives and long term savings. To date, FSY and N.A.
Cohen Group appears to be uninterested in making any
changes. (Revised 07125105)
FSY advised that current electrical drawings were
forwarded to SCE yesterday by the electrical engineer,
N.A. Cohen Group. 07/28.05
Installation of new Mercantile storefront:
D. McBride noted that while the new storefront is
scheduled to be installed the week of July 251", he
needs notice prior to the actual start of installation
5.66a due to the sensitivity surrounding this issue. N/A Closed
TSCI advised that the revised date for the start of the
storefront installation is Wednesday,08/03/05. (07/28/05)
Storefront installation began yesterday, 813105, and is
continuing. This item will be deleted from future meeting
discussion. 08/04/05
Page 5 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 70
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Operating Chain at Roll Up Door 112/2: B. Beers
5.67a requested that the operating chain for the roll up 07/22/05 TSCI
door at the stage be raised one bolt. TSCI
concurred.
Area Smoke Detectors at Mercantile Building:
B. Beers questioned the status to the final
resolution of the smoke detectors at the Mercantile
Building. FSY was instructed to delete the area
5.67b smoke detectors, include the duct smoke detector 07/21/05 FSY
as originally designed, and submit to the City of
Temecula Building Department for approval.
FSY advised that the revised mechanical plans were
submitted to the City on Monday,07125/05. 07/28/05
Access to area below Platform at Audience
Chamber: TSCI noted that there is no access
shown for the area below the platform seating at
the audience chamber and that this area contains a
great deal of conduit and ducting. Following a field
5.67c review, it was determined that an access panel will N/A Info
be installed in Electrical Closet 107A and the
access will be reflected on the as-built drawings.
In response to D. McBride's question regarding the cost
of this work, TSCI advised that the cost will be minimal.
07/28/05
Veneklausen AN changes: D. McBride expressed
deep concern for the project schedule because
Veneklausen is failing to complete their plan
revisions and equipment changes (of which
construction management was unaware) in a
timely manner. W. Van Vechten and B. Beers
assured the group that they will take responsibility
for the AN changes and delays. D. McBride
agreed that the AN issues are solely their
responsibility but that delays are not. D. McBride
directed Beers and Van Vechten to finalize the AN Beers/Van
5.68a changes as soon as possible and advised that 07/28/05 Vechten
Veneklausen and Markus Audio need to be
prompted to complete their work in a timely
manner.
An email received from Markus Audio reflects numerous
questions and issues resulting from the revised drawings.
TCSD advised that a conference call between Veneklausen,
Markus, and TCSD is scheduled for 4:00 p.m. today to attempt
to resolve issues. D. McBride advised that the entire
construction management team should be advised of the
outcome of the conference call. (07/28/05)
Revisions to Veneklausen's design and Markus' pricing
are ongoing. 08/04/05
Page 6 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 70
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Occupancy of Scene Shop and Mercantile
Building: It was explained to W. Van Vechten and
B. Beers (TCSD) again that occupancy of the
scene shop and Mercantile Building is dependent
on a completed certificate of occupancy by the
Building Department. Further, it was explained that
the project will be substantially complete by the
70 5.68b middle/end of August and TCSD may be able to N/A Info
utilize, but not occupy, the space when the
buildings are substantially complete. This will be
impacted by delays in construction and may not be
allowed by the rules and regulations of the City's
Building Department. The certificate of occupancy
is anticipated in early to mid September 2005.
Application for permanent power: TSCI requested
information regarding the application for permanent
power. Following discussion, TSCI was advised to
discuss the particulars with Building & Safety
Inspector, Bob Henderson.
5.68C 08/05/05 TSCI
The application for permanent power was submitted last
Friday, 07/29/05. Inspection for sign-off for permanent
power is scheduled with Building & Safety tomorrow.
(08/04105)
Sound panels at cross-over balcony: Concern has
previously been expressed regarding space for
seating at the cross-over balcony. There was
discussion regarding whether or not the sound
5.68d panels at the rear wall should be reduced in size. N/A Info
Following field measurements performed by W.
Van Vechten and B. Beers after the meeting,
construction management staff was instructed by
TSCD not to change the size of the sound panels.
Framing of side balconies: The response to RFI
427 as provided by FSY Architects indicated that
balconies are not framed in accordance with the
design intent. Following extensive discussion, it
was determined that the balconies will remain as
5.68e constructed and the back wall of the lower balcony N/A Info
will be painted black.
The back wall of the lower balcony shall be painted gray
to match the other walls in the audience chamber rather
than black as previously stated. 07128/05
Page 7 of 8 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 70
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Cap at removable handrail: W. Van Vechten asked
if the cap at the removable rail has been revised as
the revised Veneklausen drawings reflect a clip to
70 5.69a hold speakers. TSCI to review and advise. 08/01/05 TSCI
Markus Audio has requested a sample of the wood
hand rail in order to design the added hanger clips.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
i lure
Name: Larry E. Campbell
Title: Project Manager
Page 8 of 8 VANIR F 503
• Page 1 of 1
Larry Campbell
From: David McBride [David.McBride@cityoftemecula.org]
Sent: Monday, August 01, 2005 9i20 AM
To: Larry Campbell
Subject: RE: Progress Meeting Minutes -Old Town Community Theater
Good morning Larry:
Comments:
5.58a: Delete all past first sentence and add the following: FSY stated preservatives may cause cupping; but offered
nothing more than that statement. D. McBride explained that we (City) expects FSY to report on the
economics/aesthetics of preserving, staining or both and comment on frequency/cost of these applications versus doing
nothing at all.
5.68a Last bolded portion, 2nd sentence I think you mean TCSD not TSCI.
5.69a Note that Markus has requested a sample of the hand railing in order to design there clips.
David
From: Larry Campbell [mailto:Larry.Campbell@Vanir.com]
Sent: Friday, July 29, 2005 11:30 AM
To: David McBride; Bruce Beers; William Van Vechten; 'Arturo Yanez'; 'Sean Park'; 'Kevint'; Ed Deleeuw
(EdDeleeuw@toveyshultz.com); 'Dave Anderson'
Subject: Progress Meeting Minutes - Old Town Community Theater
Gentlemen:
Attached are minutes of Weekly Progress Meeting 69 held yesterday, 07.28.05. If there are comments, questions, or
corrections required, please call me.,
Project Director
Vanir Construction Management,Inc
8/1/2005
VANIR R
PROGRESS MEETING MINUTES
Meeting #: 69
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: July 28, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of William Van Vechten, City of
Temecula Temecula Temecula
Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Sean Park, FSY Architects Larry Campbell,Vanir
Construction, Inc. (TSCI) Construction, Inc(TSCI) (FSY) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
69 1.0 Approval Of Previous Meeting Minutes:
1.69 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 68.
2.0 Construction Progress Update:
Installation of decking at the Mercantile walkways
and siding installation at the south side of the
theater is continuing. Framing for the overhang at
the front of the Mercantile Building is substantially
complete with installation of corbels and
"gingerbread" remaining. Drywall is being installed
at stair #2 and on the baffles in the audience
chamber and drywall taping is in progress
throughout. HVAC ducting at the audience
chamber and Mercantile Building is continuing and
painting of walls in the audience chamber is
ongoing. The wheel chair lift has been installed
2.69 with minor pick up work remaining. Electrical N/A Info
rough in, making up of panels, connections to
switchgear, and installation of lighting fixtures is
ongoing. Installation of built up roofing at the
elevator tower, stair #1, and covered walkways is
in progress today as is installation of lightweight
concrete at the cross over deck. Grading of the
parking lot and flat areas is substantially complete.
Framing for miscellaneous railings is in progress
and installation of flashing is ongoing. Siding
installation at the audience chamber began this
week.
3.0 Technical Concerns:
Schedule Review: Tovey Shultz' 3-week look-
3a ahead schedule was reviewed during the course of
the meeting:
Page 7 of 9
VAN 1 R PROGRESS MEETING MINUTES*
Meeting#: 69
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
69 3a Schedule Review: (continued)
Mercantile Building:
Installation of the store front (originally scheduled
to begin Wednesday, 07/27/05) will begin
Wednesday, 08/03/05. Painting of the ceiling and
walls is scheduled to begin early next week.
Main Theater Building:
Painting of audience chamber walls will continue
over the next few weeks. Installation of theater
3a.69a rigging will continue. Installation of the elevator is N/A Info
In progress and will continue for the next week.
Wood flooring for the Dance Studio will continue
into next week. Exterior wood siding will continue
as will installation of siding at the audience
chamber. Installation of lighting and plumbing
fixtures will continue as will installation of AN cable
and accessories. Carpeting of the steps is
scheduled to begin the week of 8/8/05 and
installation of theater seating is scheduled to begin
the week of 8/15/05.
Following discussion, TSCI advised that there are
no issues foreseen as problems that require
3a.64b assistance from the City of Temecula. Based upon N/A Closed
that discussion, D. McBride advised that the
requested narrative is no longer required.
07.07.05
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 150 submittals (including
resubmittals) have been received to date. At this
date, only submittal 71 (fountain shop drawings)
remains outstanding and has been outstanding
in excess of ten days.
Submittal #72 (infill at guardrails) was submitted
3b.69 and reviewed during the course of the meeting. 07/22/05 FSY
The samples, as submitted have a 2"x2" frame.
The drawing prepared by the architect reflects a
V x 2" frame. Following discussion, it was
determined that the frame should be as
designed and the %" back bar shall be added as
reflected in the architect's drawing. The entire
assembly shall be galvanized following
fabrication.
Page 2 of 9 VANIR F 503
VAN 1 R `PROGRESS MEETING MINUTES•
Meeting#: 69
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
69 3c Request For Information Status Review:
A review of VCM's RFI log reflects 484 RFI's
(including revisions) have been submitted to date.
There are four RFI's outstanding; two of which
will be answered by VCM later today.
3c.69 RFI 414 (fan coil unit at the electrical room) has 08/04/05 FSY
been outstanding in excess of ten days.
Following discussion, TSCI advised that they will
make the fan coil fit in the space provided and
that RFI 414 should be voided.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.69 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
3d.1.69 Seventeen Architect's Supplemental Instructions N/A Info
ASI have been issued as of this date.
3d.2 Construction Bulletins
Thirty Construction Bulletins have been issued.
Of the thirty, 18 are in previously approved or
3d.2.69 pending change orders. Three have been 07/28/05 TSCINCM
superseded, 7 are pending negotiation, and 2
are pending pricing.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
The draft of Change Order No. 14 containing City of
3e.1.69 thirteen proposed change orders was forwarded 08/05/05 Temecula
to D. McBride yesterday, 7/27/05.
3e.2 Proposed Change Orders
One hundred eighty four potential change
requests have been identified. Of those, 80
have been incorporated into executed or
3e.2.69 pending change orders, 17 have been rejected, 08/05/05 TSCINCM
33 are pending negotiation, 38 have been
voided, and 16 are pending pricing.
Page 3 of 9 VANIR F 503
VAN 1 R •OGRESS MEETING MINUTES•
Meeting#: 69
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item# Description Due Action
69 3e.3 Disputed Items
TSCI has identified nine of the rejected change
3e.3.54 order requests as potential dispute items. N/A Info
3f Payment Status Review:
3f.69 TSCI's draft payment request #18 will be N/A Info
reviewed following the meeting.
3g Notice Of Non Conformance Status:
3 69 There are no outstanding correction notices at N/A Info
g' this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.69 and are prerequisite to inspections.
N/A Info
31 Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.69 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
There has been inspection of the fire sprinkler
4.69 system by the Fire Department during the past 08/05/05 TSCI
week. Miscellaneous corrections are required.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
5.58a preservative to one side of the siding may increase Closed Info
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Page 4 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 69
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall.
TSCI obtained preliminary pricing for the donor plaques. The
pricing received in significantly in excess of the donations for
69 5.59a the plaques. B. Beers will contact the Theater Foundation and 07/28/05 TSCI
attempt to have cast bronze plaques approved. (07/14/05)
Following discussion, it was determined that TSCI will ask
its sign contractor for recommendations on resolving this
issue. (07/21105)
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
expensive. Following discussion, it was
determined that the project team will work together
5.64b. to determine a cost effective method to provide fall 07/21/05 TSCI
protection affixed to the back wall.
It was determined that eye bolts will be installed at 10'-0"
o.c. at 6'-6" AFF. TSCI will submit the proposed bolt size
and backing for approval. (07114105)
Theatrical Systems: A review of the schedule
reflects that theatrical lighting, theatrical rigging,
and AN systems will be operational by mid-August.
5.64c D. McBride requested that copies of all related 08/01/05 TSCI
submittals be provided to Bruce Beers and that
relevant O&M manuals be submitted by early
August.
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements. TSCI noted
that it has contacted each of its relevant
subcontractors to obtain information. L. Campbell
will follow up with FSY to obtain the required
information.
A copy of Tri Citi Electric's response was provided to D.
5.64d McBride. FSY comments remain outstanding. (06.30.05) 07/07/05 FSY
FSY and its electrical consultant were directed to work directly
with SCE to come up with changes necessary to capture
incentives and long term savings. To date, FSY and N.A.
Cohen Group appears to be uninterested in making any
changes. (Revised 07125105)
FSY advised that current electrical drawings were
forwarded to SCE yesterday by the electrical engineer,
N.A. Cohen Group. (07/28.05)
Page 5 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 69
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Threshold at Property Storage (Room 114):
B. Beers requested that the threshold at Room 114
be deleted to allow easy movement of a piano into
and out of the room.
69 5.65a N/A Closed
TSCI advised that there is no threshold at this door.
Therefore, this issue is resolved and will be deleted from
future meeting discussion. (07/28/05)
Connections between outriggers @ Catwalk#3:
B. Beers noted that there is no connecting rod
between the light outriggers at Catwalk #3 and
noted that pipe connections between outriggers is
required for light placement. FSY stated that the
connections are reflected in the drawings. FSY will
review the plans and advise where this connection
5.65b is reflected. N/A Closed
FSY was advised that if it cannot show the referenced
connections, a bulletin needs to be issued and that time is of
the essence. (07/14/05)
Architect's Supplemental Instruction 17 was issued
Monday, 07/25/05. This issue will be deleted from future
meeting discussion. (07128/05)
Revised landscape drawings @ Mercantile:
See previous meeting minutes for a full discussion of
this issue.
Following discussion, D. McBride advised that he will e-mail
Mike Elliott regarding this issue. (07.07.05)
A preliminary sketch of the proposed changes was received
prior to the meeting. FSY to detail what is being removed and
5.65c what is being added. (07/14/05) 07/29/05 VCM
A preconstruction meeting was held with TCSD, Mike
Elliott, and the landscape contractor on Monday, 07/25/05.
It was agreed that as-built drawings will be submitted in
accordance with Field Report #1 issued by Mike Elliott. A
copy of the Field Report will be forwarded to FSY for
record. This item will be deleted from future meeting
discussion. (07/28105)
Installation of new Mercantile storefront:
D. McBride noted that while the new storefront is
scheduled to be installed the week of July 251", he
5.66a needs notice prior to the actual start of installation N/A Info
due to the sensitivity surrounding this issue.
TSCI advised that the revised date for the start of the
storefront installation is Wednesday,08103/05. 07/28105
Page 6 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 69
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Operating Chain at Roll Up Door 112/2: B. Beers
5.67a requested that the operating chain for the roll up 07/22/05 TSCI
door at the stage be raised one bolt. TSCI
concurred.
Area Smoke Detectors at Mercantile Building:
B. Beers questioned the status to the final
resolution of the smoke detectors at the Mercantile
Building. FSY was instructed to delete the area
5.67b smoke detectors, include the duct smoke detector 07/21/05 FSY
as originally designed, and submit to the City of
Temecula Building Department for approval.
FSY advised that the revised mechanical plans were
submitted to the City on Monday,07125105. 07/28105
Access to area below Platform at Audience
Chamber: TSCI noted that there is no access
shown for the area below the platform seating at
the audience chamber and that this area contains a
great deal of conduit and ducting. Following a field
5.67c review, it was determined that an access panel will N/A Info
be installed in Electrical Closet 107A and the
access will be reflected on the as-built drawings.
In response to D. McBride's question regarding the cost
of this work, TSCI advised that the cost will be minimal.
07128/05
Veneklausen AN changes: D. McBride expressed
deep concern for the project schedule because
Veneklausen is failing to complete their plan
revisions and equipment changes (of which
construction management was unaware) in a
timely manner. W. Van Vechten and B. Beers
assured the group that they will take responsibility
for the AN changes and delays. D. McBride
agreed that the AN issues are solely their
responsibility but that delays are not. D. McBride
5.68a directed Beers and Van Vechten to finalize the AN 07/28/05 Beers/Van
changes as soon as possible and advised that Vechten
Veneklausen and Markus Audio need to be
prompted to complete their work in a timely
manner.
An email received from Markus Audio reflects numerous
questions and issues resulting from the revised drawings.
TSCI advised that a conference call between Veneklausen,
Markus, and TSCI is scheduled for 4:00 p.m. today to
attempt to resolve issues. D. McBride advised that the
entire construction management team should be advised
of the outcome of the conference call. 07/28/05
Page 7 of 9 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 69
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Occupancy of Scene Shop and Mercantile
Building: It was explained to W. Van Vechten and
B. Beers (TCSD) again that occupancy of the
scene shop and Mercantile Building is dependent
on a completed certificate of occupancy by the
Building Department. Further, it was explained that
the project will be substantially complete by the
69 5.68b middle/end of August and TCSD may be able to N/A Info
utilize, but not occupy, the space when the
buildings are substantially complete. This will be
impacted by delays in construction and may not be
allowed by the rules and regulations of the City's
Building Department. The certificate of occupancy
is anticipated in early to mid September 2005.
Application for permanent power: TSCI requested
information regarding the application for permanent
5.68c power. Following discussion, TSCI was advised to 07/28/05 TSCI
discuss the particulars with Building & Safety
Inspector, Bob Henderson.
Sound panels at cross-over balcony: Concern has
previously been expressed regarding space for
seating at the cross-over balcony. There was
discussion regarding whether or not the sound
5.68d panels at the rear wall should be reduced in size. N/A Info
Following field measurements performed by W.
Van Vechten and B. Beers after the meeting,
construction management staff was instructed by
TSCD not to change the size of the sound panels.
Framing of side balconies: The response to RFI
427 as provided by FSY Architects indicated that
balconies are not framed in accordance with the
design intent. Following extensive discussion, it
was determined that the balconies will remain as
5.68e constructed and the back wall of the lower balcony N/A Info
will be painted black.
The back wall of the lower balcony shall be painted gray
to match the other walls in the audience chamber rather
than black as previously stated. 07/28/05
Cap at removable handrail: W. Van Vechten asked
5.69a if the cap at the removable rail has been revised as 08/01/05 TSCI
the revised Veneklausen drawings reflect a clip to
hold speakers. TSCI to review and advise.
Page 8 of 9 VANIR F 503
VAN 1 R `PROGRESS MEETING MINUTES•
Meeting#: 69
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
''�
/ S nature
Name: Larry E. Campbell
Title: Project Manager
Page 9 of 9 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting#: 68 REVISED_ __.___._.__._.___ .......
Owner: _City_of Temecula_
Project: Old Town Temecula
Community Theater
Date: July 21, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of William Van Vechten, City of
Temecula Temecula Temecula
Ed Deleeuw,Tovey Shultz Larry Campbell, Vanir
Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item# Description Due Action
68 1.0 Approval Of Previous Meeting Minutes:
1.68 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 67.
2.0 Construction Progress Update:
Framing for the overhang at cross-over gallery
C310 is complete and installation of roofing is in
progress. Plywood on the platform seating area in
the audience chamber is ongoing and installation
of siding on the south side of the building is
continuing. Stair #2 has been framed and framing
for the overhang at the front of the Mercantile
Building is in progress. Installation of tile for the
restrooms, dressing rooms and concession is
2.68 complete. Drywall installation at the audience N/A Info
chamber and taping of drywall throughout is
ongoing. Installation of the elevator is continuing
as is installation of theatrical rigging. Installation of
HVAC ducting at the audience chamber is
continuing. Painting of the walls in the audience
chamber is ongoing. Main electrical feeds are
being installed as well as wiring for the audio/visual
systems. Installation of flooring at the dance studio
began yesterday and is continuing.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Mercantile Building:
3a.68a Framing of. the canopy at the entrance to the N/A Info
building is scheduled to be complete this week.
Installation of the store front is scheduled to begin
Wednesday, 07/27/05.
Page 1 of 7
VAN 1 R IROGRESS MEETING MINUTES
Meeting#: 68 REVISED
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
68 3a Schedule Review: (continued)
Main Theater Building:
Framing and drywall installation for the audience
chamber platform will continue. Painting of
audience chamber walls, stage area, and scene
shop will continue over the next few weeks.
Installation of theater rigging will continue.
Installation of the elevator is in progress and will
3a.68a continue for the next two weeks. Excavation and N/A Info
disposal of surplus dirt from the site will continue to
be followed by grading of the parking lot. Wood
flooring for the Dance Studio will continue for the
next two weeks. Exterior wood decking,
overhangs, and siding will continue over the next
two weeks. The wheel chair lift will be installed
next week. Installation of theater seats, scheduled
to begin 08/08/05 has been delayed until 08/15/05.
Following discussion, TSCI advised that there are
no issues foreseen as problems that require
3a.64b assistance from the City of Temecula. Based upon N/A Closed
that discussion, D. McBride advised that the
requested narrative is no longer required.
07.07.05
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 149 submittals (including
3b.68 resubmittals) have been received to date. At this 07/22/05 FSY
date, only submittal 71 (fountain shop drawings)
remains outstanding. There are no submittals
outstanding in excess of ten days.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 475 RFI's
3c.68 (including revisions) have been submitted to date. 07/25/05 FSY
There are currently two RFI's outstanding; none
in excess of ten days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.68 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Sixteen Architect's Supplemental Instructions
3d.1.68 ASI have been issued as of this date. N/A Info
Page 2 of 7 VANIR F 503
VAN 1 R IROGRESS MEETING MINUTES
Meeting#: 68 REVISED
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item# Description Due Action
68 3d.2 Construction Bulletins
Thirty Construction Bulletins have been issued.
Of the thirty, 18 are in previously approved or
3d.2.68 pending change orders. Three have been 07/28/05 TSCINCM
superseded, 7 are pending negotiation, and 2
are pending pricing.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Three proposals for flashing additions have City of
3e.1.68 been forwarded to D. McBride for inclusion into 07/29/05 Temecula
CO 13.
3e.2 Proposed Change Orders
One hundred eighty four potential change
requests have been identified. Of those, 80
have been incorporated into executed or
3e.2.68 pending change orders, 16 have been rejected, 07/29/05 TSCINCM
34 are pending negotiation, 39 have been
voided, and 16 are pending pricing.
3e.3 Disputed Items
TSCI has identified nine of the rejected change
3e.3.54 order requests as potential dispute items. N/A Info
3f Payment Status Review:
3f.67 Payment request #17 was forwarded to the City 08/OS/05 City of
of Temecula for payment on 07/08/05. Temecula
3g Notice Of Non Conformance Status:
3 68 There are no outstanding correction notices at N/A Info
g this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.68 and are prerequisite to inspections.
N/A Info
31 Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.68 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
Page 3 of 7 VANIR F 503
VANIR PROGRESS MEETING MINUTES
Meeting#: 68 REVISED
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
68 4.0 Testing/Inspection:
4.68 There have been no inspections during the past N/A Info
week.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
5.58a preservative to one side of the siding may increase Closed Info
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall.
TSCI obtained preliminary pricing for the donor plaques.The
pricing received in significantly in excess of the donations for
5.59a the plaques. B. Beers will contact the Theater Foundation and 07/28/05 TSCI
attempt to have cast bronze plaques approved. (07/14/05)
Following discussion, it was determined that TSCI will ask
its sign contractor for recommendations on resolving this
issue. (07/21105)
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
expensive. Following discussion, it was
determined that the project team will work together
5.64b. to determine a cost effective method to provide fall 07/21/05 TSCI
protection affixed to the back wall.
It was determined that eye bolts will be installed at
10'-0" o.c. at 6'-6" AFF. TSCI will submit the
proposed bolt size and backing for approval.
07/14/05
Theatrical Systems: A review of the schedule
reflects that theatrical lighting, theatrical rigging,
and AN systems will be operational by mid-August.
5.64c D. McBride requested that copies of all related 08/01/05 TSCI
submittals be provided to Bruce Beers and that
relevant O&M manuals be submitted by early
August.
Page 4 of 7 VANIR F 503
VAN 1 R IROGRESS MEETING MINUTES
Meeting#: 68 REVISED
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements. TSCI noted
that it has contacted each of its relevant
subcontractors to obtain information. L. Campbell
will follow up with FSY to obtain the required
68 5.64d information. 07/07/05 FSY
A copy of Tri Citi Electric's response was provided to D.
McBride. FSY comments remain outstanding. (06.30.05)
FSY and its electrical consultant were directed to work
directly with SCE to come up with changes necessary to
capture incentives and long term savings. To date, FSY
and N.A. Cohen Group appears to be uninterested in
making any changes. Revised 07/25/05
Threshold at Property Storage (Room 114):
B. Beers requested that the threshold at Room 114
5.65a be deleted to allow easy movement of a piano into 07/07/05 TSCI
and out of the room.
Connections between outriggers @ Catwalk #3:
B. Beers noted that there is no connecting rod
between the light outriggers at Catwalk #3 and
noted that pipe connections between outriggers is
required for light placement. FSY stated that the
5.65b connections are reflected in the drawings. FSY will 07/18/05 FSY
review the plans and advise where this connection
is reflected.
FSY was advised that if it cannot show the referenced
connections,a bulletin needs to be issued and that time is
of the essence. 07/14/05
Revised landscape drawings @ Mercantile:
See previous meeting minutes for a full discussion of
this issue.
Following discussion, D. McBride advised that he will e-mail
5.65c Mike Elliott regarding this issue. (07.07.05) 07/21/05 FSY
A preliminary sketch of the proposed changes was
received prior to the meeting. FSY to detail what is being
removed and what is being added. (07114/05)
Installation of new Mercantile storefront:
D. McBride noted that while the new storefront is
5.66a scheduled to be installed the week of July 251h, he As Req'd TSCI
needs notice prior to the actual start of installation
due to the sensitivity surrounding this issue.
Page 5 of 7 VANIR F 503
i
VAN 1 R 41ROGRESS MEETING MINUTES•
Meeting#: 68 REVISED
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Operating Chain at Roll Up Door 112/2: B. Beers
requested that the operating chain for the roll up
68 5.67a door at the stage be raised one bolt. TSCI 07/22/05 TSCI
concurred.
Area Smoke Detectors at Mercantile Building:
B. Beers questioned the status to the final
resolution of the smoke detectors at the Mercantile
5.67b Building. FSY was instructed to delete the area 7/21/05 FSY
smoke detectors, include the duct smoke detector
as originally designed, and submit to the City of
Temecula Building Department for approval.
Access to area below Platform at Audience
Chamber: TSCI noted that there is no access
shown for the area below the platform seating at
5.67c the audience chamber and that this area contains a N/A Info
great deal of conduit and ducting. Following a field
review, it was determined that an access panel will
be installed in Electrical Closet 107A and the
access will be reflected on the as-built drawings.
Veneklausen AN changes: D. McBride expressed
deep concern for the project schedule because
Veneklausen is failing to complete their plan
revisions and equipment changes (of which
construction management was unaware) in a
timely manner. W Van Vechten and B. Beers
assured the group that they will take responsibility Beers/Van
5.68a for the AN changes and delays. D. McBride 7/21/05 Vechten
agreed that the AN issues are solely their
responsibility but that delays are not. D. McBride
directed Beers and Van Vechten to finalize the AN
changes as soon as possible and advised that
Veneklausen and Markus Audio need to be
prompted to complete their work in a timely
manner. Revised 07/25/05
Occupancy of Scene Shop and Mercantile
Building: It was explained to W. Van Vechten and
B. Beers (TCSD) again that occupancy of the
scene shop and Mercantile Building is dependent
on a completed certificate of occupancy by the
5.68b Building Department. Further, it was explained that N/A Info
the project will be substantially complete by the
middle%nd of August and TCSD maybe able to
utilize, but not occupy, the space when the
buildings are substantially complete.
Page 6 of 7 VANIR F 503
VANIR IROGRESS MEETING MINUTES
Meeting#: 68 REVISED
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # . Item # Description Due Action
Occupancy of Scene Shop and Mercantile
Building: (continued)
This will be impacted by delays in construction and
68 5.68b may not be allowed by the rules and regulations of
the City's Building Department. The certificate of
occupancy is anticipated in early to mid September
2005. Revised 07125105
Application for permanent power: TSCI requested
information regarding the application for permanent
5.68c power. Following discussion, TSCI was advised to 7/28/05 TSCI
discuss the particulars with Building & Safety
Inspector, Bob Henderson.
Sound panels at cross-over balcony: Concern has
previously been expressed regarding space for
seating at the cross-over balcony. There was
discussion regarding whether or not the sound
5.68d panels at the rear wall should be reduced in size. N/A Info
Following field measurements performed by W.
Van Vechten and B. Beers after the meeting,
construction management staff was instructed by
TSCD not to change the size of the sound panels.
Revised 07125105)
Framing of side balconies: The response to RFI
427 as provided by FSY Architects indicated that
balconies are not framed in accordance with the
5.68e design intent. Following extensive discussion, it N/A Info
was determined that the balconies will remain as
constructed and the back wall of the lower balcony
will be painted black.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely, �_��`
g tore
Name. Larry E. Campbell
Title: Project Manager
Page 7 of 7 VANIR F 503
Page 1 of 2
Larry Campbell
From: David McBride [David.McBride@cityoftemecula.org]
Sent: Monday, July 25, 2005 10:24 AM
To: Larry Campbell
Subject: RE: Meeting Minutes - Old Town Temecula Community Theater
Larry:
Comments/corrections:
5.64d (add) FSY and their electrical consultant were directed to work with SCE directly to come up with changes
necessary to capture incentives and long term savings. To date FSY/consultant appears to be uninterested to changing
anything.
5.65b Since time is of the essence, what can we do to move this along?
5.67c What is the cost impact of this?
5.68a (replace with): Veneklasen AN changes: D. McBride expressed deep concern for the project's schedule
because Veneklasen is failing to complete their plan revisions and equipment changes (which construction management
was unaware of) in a timely manner. Further, Markus Audio will not order the AN equipment until the revisions are
complete. WVV and BB assured the group that they will take responsibility for the AN changes and for delays. D.
McBride agreed that the AN issues are solely their responsibility but that delays are not. D. McBride directed BB and
WVV fore the need to finalize the AN changes as soon as possible and that Veneklasen and Markus need to be
prompted to complete their work in a timely manner.
5.68b and 5.68c: (combine into one) It was explained to WVV and BB (TSCD), again, that occupancy of the scene
shop and Mercantile building was dependent on a completed certificate of occupancy by the Building Department.
Further, it was explained the project would be substantially complete by the middle/end of August and that WVV and BB
may be able to utilize, but not occupy, the space in the middle when substantially complete but this will be impacted by
delays in construction and may not be allowed by the rules and regulations of the City's Building Department. Certificate
of occupancy is anticipated in early to mid September of 2005.
5.69e: (revise third sentence): Following field measurements, performed by WVV and BB, after the meeting.
Construction management staff was instructed by WVV and BB not to change the size of the sound panels.
David
From: Larry Campbell [mailto:Larry.Campbell@Vanir.com]
Sent: Friday, July 22, 2005 8:05 AM
To: David McBride; Bruce Beers; William Van Vechten; 'Dave Anderson'; Yevint'; Ed Deleeuw
(EdDeleeuw@toveyshultz.com); 'Arturo Yanez'; 'Sean Park'
Subject: Meeting Minutes - Old Town Temecula Community Theater
Gentlemen,
Please find attached minutes of Weekly Progress Meeting 68 held yesterday, 07/21/05. If there are comments, questions,
or corrections required, please call me.
&"*E.C'am p6dt
Project Director
Vanir Construction Management, Inc
7/28/2005
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 68
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: July 21, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers,City of William Van Vechten, City of
Temecula Temecula Temecula
Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc (TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
68 1.0 Approval Of Previous Meeting Minutes:
1.68 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 67.
2.0 Construction Progress Update:
Framing for the overhang at cross-over gallery
C310 is complete and installation of roofing is in
progress. Plywood on the platform seating area in
the audience chamber is ongoing and installation
of siding on the south side of the building is
continuing. Stair #2 has been framed and framing
for the overhang at the front of the Mercantile
Building is in progress. Installation of tile for the
restrooms, dressing rooms and concession is
2.68 complete. Drywall installation at the audience N/A Info
chamber and taping of drywall throughout is
ongoing. Installation of the elevator is continuing
as is installation of theatrical rigging. Installation of
HVAC ducting at the audience chamber is
continuing. Painting of the walls in the audience
chamber is ongoing. Main electrical feeds are
being installed as well as wiring for the audio/visual
systems. Installation of flooring at the dance studio
began yesterday and is continuing.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Mercantile Buildinq:
3a.68a Framing of the canopy at the entrance to the N/A Info
building is scheduled to be complete this week.
Installation of the store front is scheduled to begin
Wednesday, 07/27/05.
Page 1 of 7
VAN 1 R IROGRESS MEETING MINUTES•
Meeting#: 68
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
68 3a Schedule Review: (continued)
Main Theater Building:
Framing and drywall installation for the audience
chamber platform will continue. Painting of
audience chamber walls, stage area, and scene
shop will continue over the next few weeks.
Installation of theater rigging will continue.
Installation of the elevator is in progress and will
3a.68a continue for the next two weeks. Excavation and N/A Info
disposal of surplus dirt from the site will continue to
be followed by grading of the parking lot. Wood
flooring for the Dance Studio will continue for the
next two weeks. Exterior wood decking,
overhangs, and siding will continue over the next
two weeks. The wheel chair lift will be installed
next week. Installation of theater seats, scheduled
to begin 08/08/05 has been delayed until 08/15/05.
Following discussion, TSCI advised that there are
no issues foreseen as problems that require
3a.64b assistance from the City of Temecula. Based upon N/A Closed
that discussion, D. McBride advised that the
requested narrative is no longer required.
07.07.05
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 149 submittals (including
3b.68 resubmittals) have been received to date. At this 07/22/05 FSY
date, only submittal 71 (fountain shop drawings)
remains outstanding. There are no submittals
outstanding in excess of ten days.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 475 RFI's
3c.68 (including revisions) have been submitted to date. 07/25/05 FSY
There are currently two RFI's outstanding; none
in excess of ten days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.68 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
3d.1.68 Sixteen Architect's Supplemental Instructions N/A Info
ASI have been issued as of this date.
Page 2 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 68
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
68 3d.2 Construction Bulletins
Thirty Construction Bulletins have been issued.
Of the thirty, 18 are in previously approved or
3d.2.68 pending change orders. Three have been 07/28/05 TSCINCM
superseded, 7 are pending negotiation, and 2
are pending pricing.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Three proposals for flashing additions have
3e.1.68 been forwarded to D. McBride for inclusion into 07/29/05 City of
CO 13. Temecula
3e.2 Proposed Change Orders
One hundred eighty four potential change
requests have been identified. Of those, 80
have been incorporated into executed or
3e.2.68 pending change orders, 16 have been rejected, 07/29/05 TSCINCM
34 are pending negotiation, 39 have been
voided, and 16 are pending pricing.
3e.3 Disputed Items
TSCI has identified nine of the rejected change
3e.3.54 order requests as potential dispute items. N/A Info
3f Payment Status Review:
3f.67 Payment request #17 was forwarded to the City 08/08/05 City of
of Temecula for payment on 07/08/05. Temecula
3g Notice Of Non Conformance Status:
3 68 There are no outstanding correction notices at N/A Info
g' this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.68 and are prerequisite to inspections.
N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.68 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
Page 3 of 7 VANIR F 503
VAN 1 R VROGRESS MEETING MINUTES
Meeting#: 68
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
68 4.0 Testing/Inspection:
4.68 There have been no inspections during the past N/A Info
week.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51 c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
5.58a preservative to one side of the siding may increase Closed Info
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall.
TSCI obtained preliminary pricing for the donor plaques.The
pricing received in significantly in excess of the donations for
5.59a the plaques. B. Beers will contact the Theater Foundation and 07/28/05 TSCI
attempt to have cast bronze plaques approved. (07/14/05)
Following discussion, it was determined that TSCI will ask
its sign contractor for recommendations on resolving this
issue. (07/21/05)
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
expensive. Following discussion, it was
determined that the project team will work together
5.64b. to determine a cost effective method to provide fall 07/21/05 TSCI
protection affixed to the back wall.
It was determined that eye bolts will be installed at
10'-0" o.c. at 6'-6" AFF. TSCI will submit the
proposed bolt size and backing for approval.
07/14/05
Theatrical Systems: A review of the schedule
reflects that theatrical lighting, theatrical rigging,
and AN systems will be operational by mid-August.
5.64c D. McBride requested that copies of all related 08/01/05 TSCI
submittals be provided to Bruce Beers and that
relevant O&M manuals be submitted by early
August.
Page 4 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting #: 68
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements. TSCI noted
that it has contacted each of its relevant
68 5.64d subcontractors to obtain information. L. Campbell 07/07/05 FSY
will follow up with FSY to obtain the required
information.
A copy of Tri Citi Electric's response was provided to D.
McBride. FSY comments remain outstanding. 06.30.05
Threshold at Property Storage (Room 114):
B. Beers requested that the threshold at Room 114
5.65a be deleted to allow easy movement of a piano into 07/07/05 TSCI
and out of the room.
Connections between outriggers @ Catwalk #3:
B. Beers noted that there is no connecting rod
between the light outriggers at Catwalk #3 and
noted that pipe connections between outriggers is
required for light placement. FSY stated that the
5.65b connections are reflected in the drawings. FSY will 07/18/05 FSY
review the plans and advise where this connection
is reflected.
FSY was advised that if it cannot show the referenced
connections,a bulletin needs to be issued and that time is
of the essence. 07/14/05
Revised landscape drawings @ Mercantile:
See previous meeting minutes for a full discussion of
this issue.
Following discussion, D. McBride advised that he will e-mail
5.65c Mike Elliott regarding this issue. (07.07.05) 07/21/05 FSY
A preliminary sketch of the proposed changes was
received prior to the meeting. FSY to detail what is being
removed and what is being added. 07/14/05
Installation of new Mercantile storefront:
D. McBride noted that while the new storefront is
5.66a scheduled to be installed the week of July 251h, he As Req'd TSCI
needs notice prior to the actual start of installation
due to the sensitivity surrounding this issue.
Operating Chain at Roll Up Door 112/2: B. Beers
requested that the operating chain for the roll up
5.67a door at the stage be raised one bolt. TSCI 07/22/05 TSCI
concurred.
Page 5 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting #: 68
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Area Smoke Detectors at Mercantile Building:
B. Beers questioned the status to the final
resolution of the smoke detectors at the Mercantile
68 5.67b Building. FSY was instructed to delete the area 7/21/05 FSY
smoke detectors, include the duct smoke detector
as originally designed, and submit to the City of
Temecula Building Department for approval.
Access to area below Platform at Audience
Chamber: TSCI noted that there is no access
shown for the area below the platform seating at
the audience chamber and that this area contains a
5.67c great deal of conduit and ducting. Following a field N/A Info
review, it was determined that an access panel will
be installed in Electrical Closet 107A and the
access will be reflected on the as-built drawings.
Veneklausen AN changes: W. Van Vechten
advised that revised drawings reflecting AN
changes being prepared by Veneklausen will be
provided to TSCI today. Van Vechten and B.
Beers assured the group that these changes have Beers/Van
5.68a no cost or time impact to project completion. D. 7/21/05 Vechten
McBride asked that Beers and Van Vechten
contract Veneklausen to have the PDF file
reflecting the changes be e-mailed to him today in
order that they may be printed out and early review
begun.
Occupancy of Scene Shop: Wm. Van Vechten
asked when the City might have partial occupancy
5.68b of the Scene Shop in order to begin storing N/A Info
materials. As presently scheduled, the scene shop
will be available for material storage the week of
August 22, subject to site conditions.
Occupancy of Mercantile Building: Wm. Van
Vechten asked when the City might have partial
occupancy of the Mercantile Building. D. McBride
5.68c stated that the Mercantile Building will be available N/A Info
for use by the theater upon receipt of the
Certificate of Occupancy that is anticipated to be
issued in mid-September.
Application for permanent power: TSCI requested
information regarding the application for permanent
5.68d power. Following discussion, TSCI was advised to 7/28/05 TSCI
discuss the particulars with Building & Safety
Inspector, Bob Henderson.
Page 6 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 68
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Sound panels at cross-over balcony: Concern has
previously been expressed regarding space for
seating at the cross-over balcony. There was
discussion regarding whether or not the sound
68 5.68e panels at the rear wall should be reduced in size. N/A Info
Following field measurements after the meeting, it
was determined that the sound panels will be
installed as designed and no changes are
necessary.
Framing of side balconies: The response to RFI
427 as provided by FSY Architects indicated that
balconies are not framed in accordance with the
5.68f design intent. Following extensive discussion, it N/A Info
was determined that the balconies will remain as
constructed and the back wall of the lower balcony
will be painted black.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely%�j471iure �
Name: Larry E. Campbell
Title: Project Manager
Page 7 of 7 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: 67
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: July 14, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: Bruce Beers, City of William Van Vechten, City of Steve Tovey,Tovey Shultz
Temecula Temecula Construction, Inc. (TSCI)
Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Sean Park, FSY Architects Larry Campbell,Vanir
Construction, Inc(TSCI) Construction, Inc (TSCI) (FSY) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
67 1.0 Approval Of Previous Meeting Minutes:
1.67 There were no corrections or additions to the
Minutes of Meeting No. 66. N/A Info
2.0 Construction Progress Update:
Miscellaneous framing, framing pick up work, and
framing for the new offices in the Mercantile Bldg
has been ongoing. Electrical, plumbing and fire
sprinkler rough in the audience chamber and
electrical rough in at the Mercantile Building is
ongoing. Installation of corrugated metal roofing at
the audience chamber the dance studio and scene
shop are substantially complete. Painting at the
stage, audience chamber, and scene shop is
ongoing. Installation of tile for the restrooms,
dressing rooms and concession is in progress.
Drywall installation at the audience chamber and
framing of the platform is ongoing. Installation of
2.66 N/A Info
the elevator is ongoing and will continue for the
next two weeks. Installation of theatrical rigging is
ongoing and will continue for the next several
weeks. Installation of HVAC ducting at the
Mercantile Building and audience chamber is
continuing. Wrapping of columns at the Mercantile
Building is continuing. The wheel chair lift has
been delivered and grading to export surplus
material is in progress. Miscellaneous inspections
by the Building & Safety Department have occurred
this week.
Page 1 of 7
VAN 1 R IROGRESS MEETING MINUTES
Meeting#: 67
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
67 3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Main Theater Building:
Framing and drywall installation for the audience
chamber platform is in progress and will continue
into next week. Painting of audience chamber
walls, stage area, and scene shop will continue
over the next few weeks. Installation of theater
rigging will continue. Installation of the elevator is
in progress and will continue for the next two
weeks. Excavation and disposal of surplus dirt
from the site will continue to be followed by grading
3a.67a of the parking lot. Wood flooring for the Dance N/A Info
Studio, previously scheduled to begin Wednesday,
07/13/05, has been postponed to Monday,
07/18/05. Exterior wood decking, overhangs, and
siding will continue over the next two weeks.
Mercantile Building:
Installation of drywall for the interior improvements
will continue through next week. Wrapping of
columns will continue into next week and framing
of the canopy at the entrance to the building is
scheduled to begin tomorrow, 07/15/05.
Installation of wood frames and doors is scheduled
to begin Monday, 07/18/05.
3a Schedule Review: (continued)
Following discussion, TSCI advised that there are
no issues foreseen as problems that require
3a.64b assistance from the City of Temecula. Based upon N/A Closed
that discussion, D. McBride advised that the
requested narrative is no longer required.
07.07.05
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 149 submittals (including
resubmittals) have been received to date. At this
3b.67 date, there are two submittals outstanding. 07/22/05 FSY
Submittal 69D, Mercantile Panel LCC, was
returned during the course of the meeting.
There are no submittals outstanding in excess of
ten days.
Page 2 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 67
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
67 3c Request For Information Status Review:
A review of VCM's RFI log reflects 475 RFI's
3c.67 (including revisions) have been submitted to date. 07/18/05 FSY
There are currently two RFI's outstanding; none
in excess of ten days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.67 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Sixteen Architect's Supplemental Instructions
3d.1.67 (ASI) have been issued as of this date. All are NIA Info
in approved or pending change orders with the
exception of ASI 16 issued yesterday, 07/13/05.
3d.2 Construction Bulletins
Thirty Construction Bulletins have been issued.
Of the thirty, 18 are in previously approved or
3d.2.67 pending change orders. Three have been 07/21/05 TSCl/VCIv1
superseded, 7 are pending negotiation, and 2
are pendinq pricing.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Remaining proposals for flashing additions that
have been delaying the processing of CO 13
3e.1.66 were received immediately prior to the meeting 07/15/05 VCM/TSCI
today and are currently being evaluated for
entitlement.
3e.2 Proposed Change Orders
One hundred eighty three potential change
requests, have been identified. Of those, 78
have been incorporated into executed or
3e.2.66 pending change orders, 13 have been rejected, 07/22/05 TSCl/VCM
36 are pending negotiation, 39 have been
voided, and 17 are pending pricing.
3e.3 Disputed Items
TSCI has identified nine of the rejected change
3e.3.54 order requests as potential dispute items. N/A Info
Page 3 of 7 VANIR F 503
VAN 1 R IROGRESS MEETING MINUTES•
Meeting #: 67
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
67 3f Payment Status Review:
3f.67 Payment request #17 was forwarded to the City 08/08/05 City of
of Temecula for payment on 07/08/05. Temecula
3g Notice Of Non Conformance Status:
3 67 There are no outstanding correction notices at N/A Info
g' this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.67 and are prerequisite to inspections.
N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.67 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
Fire taping, drywall installation, and rough
4.67 electrical and plumbing have been inspected N/A Info
and signed off during the week by Bldg & Safety
Inspector Bob Henderson.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
5.58a preservative to one side of the siding may increase Closed Info
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall.
TSCI obtained preliminary pricing for the donor plaques.
5.59a The pricing received in significantly in excess of the 07/21/05 B. Beers
donations for the plaques. B. Beers will contact the
Theater Foundation and attempt to have cast bronze
plaques approved. (07/14/05)
Page 4 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 67
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item# Description Due Action
Screen Wall at Corridor 215: TSCI noted that the
wall screening mechanical equipment at Corridor
215 allows easy access to the roof of the Dance
Studio. Following discussion, it was determined
that VCM will follow up with FSY.
67 5.62a. This issue was followed up in the field following the N/A Closed
meeting. FSY to review and advise. (06.09.05)
Bulletin No. 30 was issued today to address this
issue. This item will be deleted from future meeting
discussion.
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
expensive. Following discussion, it was
determined that the project team will work together
5.64b. to determine a cost effective method to provide fall 07/21/05 TSCI
protection affixed to the back wall.
It was determined that eye bolts will be installed at
10'-0" o.c. at 6'-6" AFF. TSCI will submit the
proposed bolt size and backing for approval.
(07114/05)
Theatrical systems: A review of the schedule
reflects that theatrical lighting, theatrical rigging,
and AN systems will be operational by mid-August.
5.64c. D. McBride requested that copies of all related 08/01/05 TSCI
submittals be provided Bruce Beers and that
relevant O&M manuals be submitted in early
August.
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements. TSCI noted
that it has contacted each of its relevant
5.64d subcontractors to obtain information. L. Campbell 07/07/05 FSY
will follow up with FSY to obtain the required
information.
A copy of Tri Citi Electric's response was provided to D.
McBride. FSY comments remain outstanding. (06.30.05)
Threshold at Property Storage (Room 114):
B. Beers requested that the threshold at Room 114
5.65a be deleted to allow easy movement of a piano into 07/07/05 TSCI
and out of the room.
Page 5 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 67
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Connections between outriggers @ Catwalk #3:
B. Beers noted that there is no connecting rod
between the light outriggers at Catwalk #3 and
noted that pipe connections between outriggers is
required for light placement. FSY stated that the
67 5.65b connections are reflected in the drawings. FSY will 07/18/05 FSY
review the plans and advise where this connection
is reflected.
FSY was advised that if it cannot show the
referenced connections, a bulletin needs to be
issued and that time is of the essence. 07/14/05
Revised landscape drawings @ Mercantile:
See previous meeting minutes for a full discussion of
this issue.
5.65c Following discussion, D. McBride advised that he will e-mail 07/21/05 FSY
Mike Elliott regarding this issue. (07,07.05)
A preliminary sketch of the proposed changes was
received prior to the meeting. FSY to detail what is being
removed and what is being added. 07114/05
Installation of new Mercantile storefront:
D. McBride noted that while the new storefront is
5.66a scheduled to be installed the week of July 251h, he As Req'd TSCI
needs notice prior to the actual start of installation
due to the sensitivity surrounding this issue.
Operating Chain at Roll Up Door 112/2: B. Beers
5.67a requested that the operating chain for the roll up 07/22/05 TSCI
door at the stage be raised one bolt. TSCI
concurred.
Area Smoke Detectors at Mercantile Building:
B. Beers questioned the status to the final
resolution of the smoke detectors at the Mercantile
5.671b Building. FSY was instructed to delete the area 7/21/05 FSY
smoke detectors, include the duct smoke detector
as originally designed, and submit to the City of
Temecula Building Department for approval.
Access to area below Platform at Audience
Chamber: TSCI noted that there is no access
shown for the area below the platform seating at
5.67c the audience chamber and that this area contains a N/A Info
great deal of conduit and ducting. Following a field
review, it was determined that an access panel will
be installed in Electrical Closet 107A and the
access will be reflected on the as-built drawings.
Page 6 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 67
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely, _ ,�
i ature
Name: Larry E. Campbell
Title: Project Manager
Page 7 of 7 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting#: _66_......................
......
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: July 7, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.8
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of William Van Vechten, City of
Temecula Temecula Temecula
Kevin Terry, Tovey Shultz Ed Deleeuw, Tovey Shultz Larry Campbell,Vanir
Construction, Inc(TSCI) Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
66 1.0 Approval Of Previous Meeting Minutes:
1.66 There were no corrections or additions to the
Minutes of Meeting No. 65. N/A Info
2.0 Construction Progress Update:
Miscellaneous framing, framing pick up work, and
framing for the new offices in the Mercantile Bldg
has been ongoing. Electrical, plumbing and fire
sprinkler rough in the audience chamber is ongoing
and electrical rough in at the Mercantile Building is
in progress. Installation of corrugated metal
roofing at the audience chamber is substantially
complete and roofing of the dance studio is in
progress. Painting at the stage and audience
chamber is ongoing. Installation of tile for the
restrooms is in progress. Drywall installation at the
audience chamber is ongoing and installation of
exterior doors is in progress. Installation of the
2.66 elevator began Tuesday, 07.05.05 and will N/A Info
continue for the next two weeks. Installation of
theatrical rigging is ongoing and will continue for
the next several weeks. Installation of HVAC
ducting is in progress at the Mercantile Building
and roofing repair is being done today. Wrapping
of columns at the Mercantile Building began earlier
this week and is continuing. The new moment
frame at the Mercantile Building is complete and
U/T testing was performed on Tuesday, 07.05.05.
Miscellaneous inspections by the Building & Safety
Department have occurred this week.
Page 1 of 7
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 66
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
66 3.0 Technical Concerns:
3a Schedule Review:
3a.66a Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Main Theater Building:
Framing of the audience chamber platform is in
progress and installation of rear acoustical panels
and trim is scheduled to begin Tuesday, 7/12.
Taping of drywall at the audience chamber will
continue and painting of audience chamber walls is
scheduled to begin Monday, 7/11. Installation of
corrugated metal roofing and gutters will continue
for the next two weeks as will installation of theater
rigging. Installation of the elevator is in progress
and will continue for the next two weeks.
Installation of rollup doors is scheduled for
tomorrow, 07.08.05. Excavation and disposal of N/A Info
surplus dirt from the site is scheduled to begin
Monday, 7/11, with grading of the parking lot
scheduled to begin the following week. Wood
flooring for the Dance Studio is scheduled to begin
Wednesday, 07/13/05. Exterior wood decking,
trellis, overhangs, and siding will continue over the
next two weeks.
Mercantile Buildinq:
Installation of drywall for the interior improvements
is scheduled to begin Monday, 7/11. Wrapping of
columns will continue into next week and framing
of the canopy at the entrance to the building is
scheduled to begin next week. Installation of wood
frames and doors in scheduled to begin Thursday,
07/14/05.
TSCI's schedule update for the period ended
05.31.05 has been received and indicates a project
completion date of September 16, 2005. Following
discussion, D. McBride asked that TSCI provide a
narrative to explain the extension in the completion
date from August 22 to September 16. Bruce
3a.64b. Beers indicated that concerts are currently
scheduled for Wednesday, 9/28/05 and Saturday,
10/1/05.
TSCI provided a schedule reflecting installation of lighting
fixtures for the Mercantile Building beginning 8/30/05 and
continuing for two weeks with punch list scheduled for 9/13.
The requested narrative remains outstanding. 06.30.05
Page 2 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 66
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
66 3a Schedule Review: (continued)
Following discussion,TSCI advised that there are no
issues foreseen as problems that require assistance from
3a.64b the City of Temecula. Based upon that discussion, D. N/A Closed
McBride advised that the requested narrative is no longer
required. 07.07.05
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 147 submittals (including
3b.66 resubmittals) have been received to date. At this 07/12/05 FSY
date, there is one submittal, submitted prior to
the meeting, outstanding.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 467 RFI's
3c.66 (including revisions) have been submitted to date. 07/12/05 FSY
There are currently two RFI's outstanding; none
in excess of ten days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.66 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
i
Fifteen Architect's Supplemental Instructions
3d.1.66 (AS]) have been issued as of this date. All of N/A Info
the fifteen are in approved or pending change
orders.
3d.2 Construction Bulletins
Twenty nine Construction Bulletins have been
issued. Of the twenty nine, 18 are in previously
3d.2.66 approved or pending change orders. Three 07/14/05 TSCl/VCM
have been superseded, 7 are pending
negotiation, and 1 is pending pricing.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Remaining proposals for flashing additions that
have been delaying the processing of CO 13
3e.1.66 were received immediately prior to the meeting 07/14/05 VCM
today and are currently being evaluated for
entitlement.
Page 3 of 7 VANIR F 503
3f.65 the meeting rsui io make necessary-. vriv�aivo-- — —
corrections and submit for processing.
3g Notice Of Non Conformance Status:
There are no outstanding correction notices at N/A Info
3g.66 this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.66 N/A Info
and are prerequisite to inspections.
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.66 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding saf ty issues at this time.
4.0 Testing/Inspection:
Fire taping, drywall installation, and rough
electrical and plumbing have been inspected
and signed off during the week by Bldg & Safety
4.66 Inspector Paul Zuna. Welding of the new N/A Info
moment frame at the Mercantile Building was
U/T inspected and approved by Kleinfelder
Buring the week.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51 C. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Page 4 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 66
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
65 5.58a preservative to one side of the siding may increase Closed Info
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall. FSY will
follow up with additional details sufficient to obtain
5.59a mock-ups and pricing for the plaques. 6/30/05 TSCl/FSY
TSCI and FSY will contact various vendors to obtain
pricing for the donor plaques. (05.26.05)
Screen Wall at Corridor 215: TSCI noted that the
wall screening mechanical equipment at Corridor
215 allows easy access to the roof of the Dance
Studio. Following discussion, it was determined
5.62a. that VCM will follow up with FSY. 06/13/05 FSY
This issue was followed up in the field following the
meeting. FSY to review and advise. (06.09.05)
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
5.64b. expensive. Following discussion, it was 08/01/05 All
determined that the project team will work together
to determine a cost effective method to provide fall
protection affixed to the back wall.
Theatrical systems: A review of the schedule
reflects that theatrical lighting, theatrical rigging,
and AN systems will be operational by mid-August.
5.64c. D. McBride requested that copies of all related 08/01/05 TSCI
submittals be provided Bruce Beers and that
relevant O&M manuals be submitted in early
August.
Savings by Design: D. McBride noted that
5.64d Southern California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements.
Page 5 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 66
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Savings by Design: (continued)
TSCI noted that it has contacted each of its
relevant subcontractors to obtain information. L.
65 5.64d Campbell will follow up with FSY to obtain the 07/07/05 FSY
required information.
A copy of Tri Citi Electric's response was provided to D.
McBride. FSY comments remain outstanding. 06.30.05
Threshold at Property Storage (Room 114):
5.65a B. Beers requested that the threshold at Room 114 07/07/05 TSCI
be deleted to allow easy movement of a piano into
and out of the room.
Connections between outriggers @ Catwalk#3:
B. Beers noted that there is no connecting rod
between the light outriggers at Catwalk#3 and
5.65b noted that pipe connections between outriggers is 07/05/05 FSY
required for light placement. FSY stated that the
connections are reflected in the drawings. FSY will
review the plans and advise where this connection
is reflected.
Revised landscape drawings @ Mercantile:
K. Terry noted that revised landscape drawings for
the west side of the Mercantile Bldg have not been
received and questioned whether or not these
drawings need to be reviewed by TSCD. A. Yanez
advised that revised drawings will be forwarded
5.65c Tuesday, 07/07. D. McBride suggested that either 07/14/05 D. McBride
TSCI or FSY contact Mike Elliott (TCSD) to
determine if a formal review is required or whether
as-built drawings might be acceptable.
Following discussion, D. McBride advised that he will e-
mail Mike Elliott regarding this issue. 07.07.05
Installation of new Mercantile storefront:
D. McBride noted that while the new storefront is
5.66a scheduled to be installed the week of July 251h, he As Req'd TSCI
needs notice prior to the actual start of installation
due to the sensitivity surrounding this issue.
Page 6 of 7 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 66
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely, _f_
ig lure
Name: Larry E. Campbell
Title: Project Manager
Page 7 of 7 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting#: 65
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: June 30, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers,City of William Van Vechten, City of
Temecula Temecula Temecula
Steve Tovey, Tovey Shultz Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Arturo Yanez, FSY Architects,
Construction, Inc. (TSCI) Construction, Inc(TSCI) Construction, Inc(TSCI) (FSY)
Larry Campbell,Vanir
Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
65 1.0 Approval Of Previous Meeting Minutes:
1.65 There were no corrections or additions to the
Minutes of Meeting No. 64. NIA Info
2.0 Construction Progress Update:
Miscellaneous framing and framing pick up work
has been ongoing during the last two weeks and
framing for the new offices in the Mercantile Bldg is
in progress. Electrical, plumbing and fire sprinkler
rough in the audience chamber is ongoing.
Installation of corrugated metal roofing is in
progress at the audience chamber. Roofing for the
fly tower is complete. Painting of the restrooms
and offices at the classroom building is complete
and painting at the stage in ongoing. Installation of
tile for the restrooms began on Tuesday, 6/28/05.
Drywall installation at the audience chamber is in
2.65 progress as is installation of insulation. Framing N/A Info
for the overhang at the second floor level is in
progress and door frames are being installed
throughout. Installation of HVAC ducting is
ongoing. Installation of the new steel moment
frame at the Mercantile Bldg is substantially
complete with UT inspection of the welding
scheduled for Tuesday, 7/5. Underground conduit
and vault for the electrical feed to the project has
been completed. Installation of fire sprinklers is
substantially complete with some minor pick up
work to be completed. Installation of theatrical
rigging began Tuesday, 6/28/05.
Page 1 of 6
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 65
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
65 3.0 Technical Concerns:
3a Schedule Review:
3a.65a Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Main Theater Building:
Layout for framing of the audience chamber
platform is in progress and installation will begin
Tuesday, 7/5. Installation of baffles at the balcony
is scheduled to begin Tuesday, 7/5 as is taping of
drywall at the audience chamber. Painting of
audience chamber walls is scheduled to begin
Monday, 7/11. Installation of corrugated metal
roofing and gutters will continue for the next three
weeks as will installation of theater rigging.
Installation of the elevator will begin Tuesday, 7/5
along with installation of rollup doors. Excavation
and disposal of surplus dirt from the site is
scheduled to begin Monday, 7/11, with grading of N/A Info
the parking lot scheduled to begin the following
week. Installation of acoustical panels at the
audience chamber is currently scheduled to begin
Monday, 7/18.
Mercantile Building:
Installation of the new moment frame will be
complete early next week with U/T inspection of
the welds scheduled for Tuesday, 7/5. Framing of
walls and stairs will continue through next week
with installation of drywall scheduled to begin
Monday, 7/11. Repair of the roof is scheduled for
next week with the installation of roof top ducting
scheduled to begin Monday 7/11.
TSCI's schedule update for the period ended
05.31.05 has been received and indicates a project
completion date of September 16, 2005. Following
discussion, D. McBride asked that TSCI provide a
narrative to explain the extension in the completion
date from August 22 to September 16. Bruce
3a.64b. Beers indicated that concerts are currently 06/23/05 TSCI
scheduled for Wednesday, 9/28/05 and Saturday,
10/1/05.
TSCI provided a schedule reflecting installation of lighting
fixtures for the Mercantile Building beginning 8/30105 and
continuing for two weeks with punch list scheduled for
9/13. The requested narrative remains outstanding.
06.30.05
Page 2 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 65
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 146 submittals (including
65 3b.65 resubmittals) have been received to date. At this N/A Info
date, there are no submittals outstanding.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 461 RFI's
(including revisions) have been submitted to date.
3c.65 There are currently two RFI's outstanding that 07/01/05 FSY
were submitted late yesterday.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.65 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Fifteen Architect's Supplemental Instructions
(ASI) have been issued as of this date. All of
3d.1.65 the fifteen are in approved or pending change N/A Info
orders.
3d.2 Construction Bulletins
Twenty eight Construction Bulletins have been
issued. Of the twenty eight, 18 are in previously
3d.2.65 approved or pending change orders. Three 07/08/05 TSCINCM
have been superseded, 7 are pending
negotiation.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Orders 11 and 12 have been mailed to
TSCI for signature. Change Order No. 13 has
been drafted and is being held until it is
determined that all flashing issues have been
3e.1.63 addressed. 06/23/05 TSCI
Change Order Nos. 11 and 12 have been signed
by the City of Temecula.(06.30.05)
Page 3 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 65
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
65 3e.2 Proposed Change Orders
One hundred sixty six potential change requests
have been identified. Of those, 80 have been
3e.2.65 incorporated into executed or pending change 07/08/05 TSCINCM
orders, 12 have been rejected, 22 are pending
negotiation, 37 have been voided, and 16 are
pending pricing.
3e.3 Disputed Items
3e.3.54
TSCI has identified nine of the rejected change
order requests as potential dispute items. N/A Info
3f Payment Status Review:
Draft payment request#17 was reviewed prior to
3f.65 the meeting. TSCI to make necessary 07/05/05 TSCI
corrections and submit for processing.
3g Notice Of Non Conformance Status:
3 65 There are no outstanding correction notices at N/A Info
g' this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.65 and are prerequisite to inspections.
N/A Info
31 Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.65 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
Fire taping, drywall installation, and rough
electrical and plumbing have been inspected
4.65 and signed off during the week by Bldg & Safety N/A Info
Inspection Bob Henderson.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51 c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Page 4 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 65
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
65 5.58a preservative to one side of the siding may increase Closed Info
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall. FSY will
follow up with additional details sufficient to obtain
5.59a mock-ups and pricing for the plaques. 6/30/05 TSCl/FSY
TSCI and FSY will contact various vendors to obtain
pricing for the donor plaques. (05.26.05)
Screen Wall at Corridor 215: TSCI noted that the
wall screening mechanical equipment at Corridor
215 allows easy access to the roof of the Dance
Studio. Following discussion, it was determined
5.62a. that VCM will follow up with FSY. 06/13/05 FSY
This issue was followed up in the field following the
meeting. FSY to review and advise. (06.09.05)
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
5.64b. expensive. Following discussion, it was 06/30/05 All
determined that the project team will work together
to determine a cost effective method to provide fall
protection affixed to the back wall.
Theatrical systems: A review of the schedule
reflects that theatrical lighting, theatrical rigging,
and AN systems will be operational by mid-August.
5.64c. D. McBride requested that copies of all related 0g/01/05 TSCI
submittals be provided Bruce Beers and that
relevant O&M manuals be submitted in early
August.
Savings by Design: D. McBride noted that
5.64d Southern'California Edison Company has indicated
that significant demand savings are available with
the reduction of lighting requirements.
Page 5 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 65
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Savings by Design: (continued)
TSCI noted that it has contacted each of its
relevant subcontractors to obtain information. L.
65 5.64d Campbell will follow up with FSY to obtain the 07/07/05 FSY
required information.
A copy of Tri Citi Electric's response was provided to D.
McBride. FSY comments remain outstanding. 06.30.05
Threshold at Property Storage (Room 114):
5.65a B. Beers requested that the threshold at Room 114 07/07/05 TSCI
be deleted to allow easy movement of a piano into
and out of the room.
Connections between outriggers @ Catwalk #3:
B. Beers noted that there is no connecting rod
between the light outriggers at Catwalk #3 and
5.65b noted that pipe connections between outriggers is 07/05/05 FSY
required for light placement. FSY stated that the
connections are reflected in the drawings. FSY will
review the plans and advise where this connection
is reflected.
Revised landscape drawings @ Mercantile:
K. Terry noted that revised landscape drawings for
the west side of the Mercantile Bldg have not been
received and questioned whether or not these
5.65c drawings need to be reviewed by TSCD. A. Yanez 07/07/05 TSCl/FSY
advised that revised drawings will be forwarded
Tuesday, 07107. D. McBride suggested that either
TSCI or FSY contact Mike Elliott (TCSD) to
determine if a formal review is required or whether
as-built drawings might be acceptable.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
�gn ure
Name: Larry E. Campbell
Title: Project Manager
Page 6 of 6 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting#: 64
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: June 16, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.6
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers,City of Kevin Terry,Tovey Shultz
Temecula Temecula Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
64 1.0 Approval Of Previous Meeting Minutes:
1.64 There were no corrections or additions to the
Minutes of Meeting No. 63. N/A Info
2.0 Construction Progress Update:
Miscellaneous framing and framing pick up work
has been ongoing during the last week.
Installation of siding at the scene shop is complete
and siding installation at the east wall of the
audience chamber is in progress. Electrical,
plumbing and fire sprinkler rough in the audience
chamber is ongoing. Installation of gas piping is
ongoing as is the installation of sleeving for the gas
line at the east side of the Mercantile Building.
Metal flashing at the steel members is ongoing with
some small areas to be complete next week.
Painting of the restrooms and offices is in progress.
Drywall installation at the stage area and audience
chamber is in progress as is installation of
2.64 insulation. Installation of HVAC equipment in the N/A Info
scene shop and miscellaneous ducting is ongoing.
The extension of the planter wall at the east side of
the Mercantile Bldg. has been completed and
installation of the brick fascia at the concession
building will be complete today. Irrigation lines at
the Mercantile Building have been roughed in. The
stem wall at the south side of the Mercantile Bldg.
has been cut to allow installation of the new steel
beam and demolition of the existing floor is in
progress. Miscellaneous masonry repair to the
front of the Mercantile Building is in progress.
Smoke hatches are currently being installed and
corrugated roofing is being set on the roofs.
Page 1 of 6
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 64
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
64 3.0 Technical Concerns:
3a Schedule Review:
3a.64a Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Main Theater Building:
Miscellaneous framing and pick up work and
installation of siding will continue through month
end. Wall insulation and drywall at the audience
chamber will continue through month end.
Electrical rough in to the control booth will continue
through next week. Painting of the fly tower walls
will begin tomorrow and continue through next
week. Installation of corrugated metal roofing will
begin tomorrow and continue through the end of
next week. Removal of interior and exterior
scaffolding will begin Monday, 6/20 allowing for the
start of framing of the audience chamber platform.
Installation of theatrical rigging is scheduled to N/A Info
begin Monday, 6/27/05 as is painting of the
audience chamber walls. Baffles are being
installed and will continue through the end of the
week. Installation of mortar bed and tile is
scheduled to begin Monday, 06/20/05 and continue
through month end.
Mercantile Building:
Miscellaneous demolition will continue through next
week with electrical rough in beneath the floor
scheduled to be complete by the end of the week.
Sheathing of the floor is scheduled to begin
Monday, 6/20/05, with the start of framing and
installation of the new structural steel elements
scheduled to begin Monday, 6/27/05.
TSCI's schedule update for the period ended
05.31.05 has been received and indicates a project
completion date of September 16, 2005. Following
discussion, D. McBride asked that TSCI provide a
3a.64b. narrative to explain the extension in the completion 06/23/05 TSCI
date from August 22 to September 16. Bruce
Beers indicated that concerts are currently
scheduled for Wednesday, 9/28/05 and Saturday,
10/1/05.
Page 2 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 64
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 143 submittals (including
64 3b.64 resubmittals) have been received to date. At this 06/20/05 FSY
date, four submittals remain outstanding of
which two have been outstanding in excess of
ten days.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 450 RFI's
(including revisions) have been submitted to date.
3c.64 There are currently six RFI's outstanding; all 06/20/05 FSY
submitted earlier today.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.64 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Fifteen Architect's Supplemental Instructions
3d.1.64 (ASI) have been issued as of this date. All of 06/09/05 TSCINCM
the fifteen are in approved or pending change
orders.
3d.2 Construction Bulletins
Twenty eight Construction Bulletins have been
issued. Of the twenty eight, 18 are in previously
3d.2.64 approved or pending change orders. Three 06/23/05 TSCINCM
have been superseded, 7 are pending
negotiation.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Orders 11 and 12 have been mailed to
TSCI for signature. Change Order No. 13 has
been drafted and is being held until it is
determined that all flashing issues have been
3e.1.63 addressed. 06/13/05 TSCI
Change Order Nos. 11 and 12 have been signed
by TSCI and returned to the City for execution.
06.16.05
Page 3 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 64
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
64 3e.2 Proposed Change Orders
One hundred fifty six potential change requests
have been identified. Of those, 80 have been
3e.2.64 incorporated into executed or pending change 06/23/05 TSCINCM
orders, 12 have been rejected, 15 are pending
negotiation, 35 have been voided, and 14 are
pending pricing.
3e.3 Disputed Items
3e.3.54
TSCI has identified nine of the rejected change
order requests as potential dispute items. N/A Info
3f Payment Status Review:
Payment Request#15 was forwarded to the City City of
3f.62 of Temecula today for processing. (6/2/05) 06/30/05 Temecula
3g Notice Of Non Conformance Status:
3 64 There are no outstanding correction notices at N/A Info
g" this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.64 and are prerequisite to inspections. N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.64 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
Fire taping, drywall installation, and rough
electrical and plumbing have been inspected
4.64 and signed off during the week by Bldg & Safety N/A Info
Inspection Bob Henderson.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Page 4 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 64
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
64 5.58a preservative to one side of the siding may increase Closed Info
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall. FSY will
follow up with additional details sufficient to obtain
5.59a mock-ups and pricing for the plaques. 6/30/05 TSCl/FSY
TSCI and FSY will contact various vendors to obtain
pricing for the donor plaques. 05.26.05
Transformer rack at electrical room: TSCI asked if
the wood for the transformer rack at the electrical
room should be fire treated. VCM will follow up
with Bldg. & Safety Inspector Bob Henderson.
Still awaiting response from Mr. Henderson (05.26.05)
5.59c Closed Info
VCM will follow up this question with FSY. (06.02.05)
Based upon a smaller sized battery cabinet,
transformer TA can be floor mounted eliminating the
need for the transformer rack. This item is complete
and will be deleted from future meeting discussion.
06.16.05
Screen Wall at Corridor 215: TSCI noted that the
wall screening mechanical equipment at Corridor
215 allows easy access to the roof of the Dance
5.62a. Studio. Following discussion, it was determined 06/13/05 FSY
that VCM will follow up with FSY.
This issue was followed up in the field following the
meeting. FSY to review and advise. 06.09.05
Sound baffle conflicts: TSCI noted that conflicts
exist with the sound baffles at the catwalk and light
bar supports. Following discussion, it was
determined that the sound baffles at the catwalk
5.64a will be lowered 6-inches. At the light bar supports, N/A Info
spacing between baffles will be increased to 8-
inches and light bar supports will be extended to
18-inches.
Page 5 of 6 VANIR F 503
VAN 1 R VROGRES MEETING MINUTES•
Meeting#: 64
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Balcony Fall Protection: Following a review of the
pricing for the fall protection at the balcony, it was
determined that the system as designed in too
64 5.64b. expensive. Following discussion, it was 06/30/05 All
determined that the project team will work together
to determine a cost effective method to provide fall
protection affixed to the back wall.
Theatrical systems: A review of the schedule
reflects that theatrical lighting, theatrical rigging,
and AN systems will be operational by mid-August.
5.64c. D. McBride requested that copies of all related 08/01/05 TSCI
submittals be provided Bruce Beers and that
relevant O&M manuals be submitted in early
August.
Savings by Design: D. McBride noted that
Southern California Edison Company has indicated
that significant demand savings are available with
5.64d the reduction of lighting requirements. TSCI noted 6/23/05 VCM/TSCI
that it has contacted each of its relevant
subcontractors to obtain information. L. Campbell
will follow up with FSY to obtain the required
information.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely, /��'j`% �tur
/ / Sig ature
Name: Larry E. Campbell
Title: Project Manager
Page 6 of 6 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 63
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: June 9, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File # 15.6
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Arturo Yanez, FSY Architects
Temecula Temecula (FSY)
Steve Tovey, Tovey Shultz Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc. (TSCI) Construction, Inc (TSCI) Construction, Inc (TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
63 1.0 Approval Of Previous Meeting Minutes:
1.63 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 62.
2.0 Construction Progress Update:
Framing of the balcony, amp room, and dimmer
room is substantially complete. Installation of
siding at the fly tower and scene shop is ongoing.
Framing for the covered walkway connecting the
buildings is in progress. Electrical, plumbing and
fire sprinkler rough in the audience chamber and
stage area is ongoing. Installation of gas piping is
2.63 ongoing. Metal flashing at the steel members is N/A Info
ongoing and expected to be complete by the end of
the week. Painting of the audience chamber
ceiling is in progress. Drywall installation at the
stage area and audience chamber is in progress
and drywall taping at the first floor of the classroom
building is being done today. Concrete placement
for the footing for the planter wall at the west side
of the Mercantile Bldg. is scheduled for later today.
3.0 Technical Concerns:
3a Schedule Review:
3a.63a Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Main Theater Building:
Framing for the audience chamber will be
substantially complete by the end of the week as N/A Info
will electrical and fire sprinkler rough-in within the
audience chamber and stage area. Drywall is
essentially complete at the stage area and will
progress in the audience chamber beginning
Monday, 6/13 and continuing through month end.
Page t of 5
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 63
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
63 3a. Schedule Review (Continued)
Main Theater Building (continued)
Painting of the audience chamber ceiling will be
complete tomorrow and painting will begin in the
restrooms on Monday, 6/13. Baffles are being
finished in the shop and installation is scheduled to
begin Wednesday, 06.15.05 to be followed by the
removal of the interior scaffolding. Installation of
metal gutters and corrugated roofing is scheduled
to begin Wednesday, 06/15.
3a.63a Mercantile Building: N/A Info
Concrete placement for the footings for the new
interior walls is scheduled for tomorrow, 6/10. Saw
cutting for the concrete stem wall, new door
opening, and ticket window opening is scheduled
for Saturday, 6/11. Under floor electrical rough in
will begin tomorrow 6/10, and continue through
next week. Sheathing of the floor and installation
of the structural steel is scheduled to begin
Monday, 6/20, with wall framing to begin the
following Monday, 6/27.
TSCI's schedule update for the period ended
03.31.05 was reviewed and comments provided to
TSCI yesterday, 04.06.05. The schedule as
submitted reflects project completion September 5,
2005, 31 days beyond the contract completion
date. There was discussion regarding increasing
manpower and working of extended hours to meet
the contract completion date. It was also stated
3a.54b. that work in the Mercantile Building must be 06/09/05 TSCI
completed within the same time frame.
K. Terry advised that TSCI's schedule update reflecting work
through 04.29.05 will be submitted Tuesday, 05.03.05.
(04.28.05)
VCM review comments of the 4.29.05 schedule update are
expected Monday,05.09.05. (05.05.05)
VCM review comments were forwarded to TSCI yesterday,
05.11.05 and indicated minor corrections required.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 139 submittals (including
3b.63 resubmittals) have been received to date. At this 06/10/05 FSY
date, two submittals remain outstanding. Both
of the outstanding submittals have been
outstanding in excess of ten days.
Page 2 of 5 VANIR F 503
VAN 1 R •ROGRESS MEETING MINUTE•
Meeting#: 63
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
63 3c Request For Information Status Review:
A review of VCM's RFI log reflects 444 RFI's
(including revisions) have been submitted to date.
There are currently eight RFI's outstanding. RFI
3c.63 372, relating to the overhang at the front of the 06/13/05 FSY
building has been outstanding for 30 days and is
critical to the completion of framing in this area.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.63 Both of these items have been included in N/A Info
revio sly approved change orders.
3d.1 Architect's Supplemental Instructions
Fifteen Architect's Supplemental Instructions
3d.1.63 (ASI) have been issued as of this date. Of the 06/09/05 TSCINCNI
fifteen, 9 are in approved or pending change
orders. 6 are awaiting pricing.
3d.2 Construction Bulletins
Twenty seven Construction Bulletins have been
issued. Of the twenty seven, 18 are in
3d.2.63 previously approved or pending change orders. 06/09/05 TSCl/VCM
Three have been superseded, 3 are pending
negotiation and 3 are being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Orders 11 and 12 have been mailed to
TSCI for signature. Change Order No. 13 has
3e.1.63 been drafted and is being held until it is 06/13/05 TSCI
determined that all flashing issues have been
addressed.
3e.2 Proposed Change Orders
One hundred forty nine potential change
requests have been identified. Of those, 68
3e.2.63 have been incorporated into executed or 06/16/05 TSCINCM
pending change orders, 12 have been rejected,
22 are pending negotiation, 37 have been
voided, and 10 are pending pricing.
3e.3 Disputed Items
3e.3.54 TSCI has identified nine of the rejected change N/A Info
order requests as potential dispute items.
Page 3 of 5 VANIR F 503
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 63
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
63 3f Payment Status Review:
TSCI's draft Payment Request #15 was
reviewed following the meeting. TSCI to make
3f.62 corrections and submit for processing. os/3o/o5 City of
Temecula
Payment Request #15 was forwarded to the City of
Temecula today for processing.
3g Notice Of Non Conformance Status:
3 62 There are no outstanding correction notices at N/A Info
S this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.62 and are prerequisite to inspections.
N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.62 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
Fire taping, drywall installation, and rough
electrical and plumbing have been inspected
4.62 and signed off during the week by Bldg & Safety N/A Info
Inspection Bob Henderson.
5.0 New Business:
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51 c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
5.58a preservative to one side of the siding may increase Closed Info
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Page 4 of 5 VANIR F 503
VAN 1 R •ROGRESS MEETING MINUTE?
Meeting#: 63
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall. FSY will
follow up with additional details sufficient to obtain
63 5.59a mock-ups and pricing for the plaques. 6/30/05 TSCl/FSY
TSCI and FSY will contact various vendors to obtain
pricing for the donor plaques. 05.26.05
Transformer rack at electrical room: TSCI asked if
the wood for the transformer rack at the electrical
room should be fire treated. VCM will follow up
5.59c with Bldg. & Safety Inspector Bob Henderson. 6/03/05 VCM
Still awaiting response from Mr. Henderson(05.26.05)
VCM will follow up this question with FSY. 06.02.05
Screen Wall at Corridor 215: TSCI noted that the
wall screening mechanical equipment at Corridor
215 allows easy access to the roof of the Dance
5.62a. Studio. Following discussion, it was determined 06/13/05 FSY
that VCM will follow up with FSY.
This issue was followed up in the field following the
meeting. FSY to review and advise. 06.09.05
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. if
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely
i a ur
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting#: 62
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: June 2, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
Temecula Construction, Inc(TSCI) Construction, Inc(TSCI)
Larry Campbell, Vanir
Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
62 1.0 Approval Of Previous Meeting Minutes:
1.62 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 61.
2.0 Construction Progress Update:
Framing of the balcony, amp room, and dimmer
room has continued along with the installation of
siding at the fly tower and classroom building.
Electrical rough in the audience chamber and
stage area is ongoing. Showers have been set in
the restrooms and installation of gas piping is
2.62 ongoing. Metal flashing at the steel members is N/A Info
ongoing and expected to be complete early next
week. Installation of HVAC ducting and fire
sprinkler lines at the audience chamber and stage
area is in progress as is installation of insulation
and drywall at scene shop and stage area. Paint
preparation at the audience chamber ceiling is in
progress.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Framing for the audience chamber will continue
through next week as will electrical and fire
sprinkler rough in. Painting of the audience
3a.62a. chamber ceiling will begin tomorrow and continue N/A Info
into next week. Installation of baffles is scheduled
to begin Thursday, 06.09.05 to be followed by the
removal of the interior scaffolding. Installation of
insulation and drywall at the audience chamber is
scheduled to be in Monda , 06.13.05.
Page i of 5
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 62
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
62 3a. Schedule Review (Continued)
Flashing will continue at the fly tower into next
week to be followed by the installation of metal
gutters and corrugated metal roofing. Rough
electrical under the floor of the Mercantile Building
3a.62a is scheduled to begin Monday, 06.06.05 along with N/A Info
the forming of the interior footings. Concrete for
the interior footing is scheduled for Friday,
06.10.05 to be followed by erection of the new
columns for the moment frame on Monday,
06.20.05.
TSCI's schedule update for the period ended
03.31.05 was reviewed and comments provided to
TSCI yesterday, 04.06.05. The schedule as
submitted reflects project completion September 5,
2005, 31 days beyond the contract completion
date. There was discussion regarding increasing
manpower and working of extended hours to meet
the contract completion date. It was also stated
3a.54b. that work in the Mercantile Building must be 06/09/05 TSCI
completed within the same�time frame.
K. Terry advised that TSCI's schedule update reflecting work
through 04.29.05 will be submitted Tuesday, 05.03.05.
(04.28.05)
VCM review comments of the 4.29.05 schedule update are
expected Monday,05.09.05. (05.05.05)
VCM review comments were forwarded to TSCI yesterday,
05.11.05 and indicated minor corrections required.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 139 submittals (including
3b.62 resubmittals) have been received to date. At this 06/07/05 FSY
date, four submittals remain outstanding. None
of the outstanding submittals have been
outstanding in excess of ten days.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 435 RFI's
(including revisions) have been submitted to date.
There are currently four RFI's outstanding. RFI
3c.62 372, relating to the overhang at the front of the 06/03/05 FSY
building has been outstanding for 23 days and is
critical to the completion of framing in this area.
Page 2 of 5 VANIR F 503
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 62
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item# Description Due Action
62 3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.62 Both of these items have been included in N/A Info
revio sly approved change orders.
3d.1 Architect's Supplemental Instructions
Fifteen Architect's Supplemental Instructions
3d.1.62 (ASI) have been issued as of this date. Of the 06/09/05 TSCINCM
fifteen, 9 are in approved or pending change
orders. 6 are awaiting pricing.
3d.2 Construction Bulletins
Twenty seven Construction Bulletins have been
issued. Of the twenty seven, 18 are in
3d.2.62 previously approved or pending change orders. 06/09/05 TSCINCM
Three have been superseded, 3 are pending
negotiation and 3 are being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
CO #10 has been executed by TSCI and the
City. Change Orders 11 and 12 have been
3e.1.62 drafted and will be mailed to TSCI for signature. 06/03/05 TSCI
Change Order No. 13 has been drafted and is
being held until it is determined that all flashing
issues have been addressed.
3e.2 Proposed Change Orders
One hundred forty five potential change
requests have been identified. Of those, 68
3e.2.62 have been incorporated into executed or 06/09/05 TSCINCM
pending change orders, 12 have been rejected,
14 are pending negotiation, 33 have been
voided, and 19 are pending pricing.
3e.3 Disputed Items
3e.3.54 TSCI has identified nine of the rejected change N/A Info
order requests as potential dispute items.
3f Payment Status Review:
TSCI's draft Payment Request #15 was
reviewed following the meeting. TSCI to make
O6/30I05
3f.62
corrections and submit for processing. City of
Payment Request #15 was forwarded to the City of Temecula
Temecula today for processing.
Page 3 of 5 VANIR F 503
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 62
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
62 3g Notice Of Non Conformance Status:
3 .62 There are no outstanding correction notices at N/A Info
g this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.62 and are prerequisite to inspections.
N/A Info
31 Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.62 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
Fire taping, drywall installation, and rough
electrical and plumbing have been inspected
4.62 and signed off during the week by Bldg & Safety N/A Info
Inspection Bob Henderson.
5.0 New Business:
Decorative benches: Following discussion, it
was determined that the City of Temecula will
make a decision and provide direction.
David McBride advised that the City has selected the benches
5.51 a to be used. FSY Architects is determining the layout for the O6/03I05 VCM
selected benches. (04.21.05)
Bulletin 27A was reviewed and will be issued to TSCI for
pricing tomorrow,06.03.05. This item will be deleted from
future meeting discussion. (06.02.05)
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51 c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
5.58a preservative to one side of the siding may increase Closed Info
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 62
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall. FSY will
follow up with additional details sufficient to obtain
62 5.59a mock-ups and pricing for the plaques. 6/30/05 TSCl/FSY
TSCI and FSY will contact various vendors to obtain
pricing for the donor plaques. 05.26.05
Transformer rack at electrical room: TSCI asked if
the wood for the transformer rack at the electrical
room should be fire treated. VCM will follow up
5.59c with Bldg. & Safety Inspector Bob Henderson. 6/03/05 VCM
Still awaiting response from Mr. Henderson (05.26.05)
VCM will follow up this question with FSY. 06.02.05
Screen Wall at Corridor 215: TSCI noted that the
wall screening mechanical equipment at Corridor
5.62a. 215 allows easy access to the roof of the Dance 06/03/05 VCM
Studio. Following discussion, it was determined
that VCM will follow up with FSY.
Water Feature: TSCI noted that it has received a
quote for the water feature with a note that added
5.62b. design work is required. Following discussion, it N/A Info
was determined that the water feature will be
constructed per plan.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a hue and accurate
record of the meeting.
Sincerely,
ature
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VAN 1R 0
PROGRESS MEETING MINUTES
Meeting#: -61
-_----------------..------------ -- ---- ------------
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: May 26, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Kevin Terry,Tovey Shultz
Temecula Temecula Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Sean Park, FSY Architects Larry Campbell,Vanir
Construction, Inc(TSCI) (FSY) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
61 1.0 Approval Of Previous Meeting Minutes:
1.61 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 60.
2.0 Construction Progress Update:
Framing of the audience chamber, elevator tower,
and west overhang at the Mercantile Building has
continued. Electrical rough in the audience
chamber and stage area is ongoing. Plumbing of
gas lines to HVAC units and miscellaneous
plumbing pick up work is ongoing. Metal flashing
at the steel members is ongoing. Installation of
2.61 HVAC ducting and fire sprinkler lines at the N/A Info
audience chamber and stage area is in progress as
is installation of insulation at scene shop and stage
area. Miscellaneous door frames have been
installed. Installation and taping of drywall at the
scene shop and stage area is ongoing and
excavation of footings for the interior renovations at
the Mercantile Building is in progress.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Framing for the audience chamber will continue
through next week as will electrical and fire
3a.61a. sprinkler rough in. Painting of the audience N/A Info
chamber ceiling is tentatively scheduled to begin
Wednesday, 06.01.05 to be followed by installation
of baffles.
Page i of 5
VAN 1 R •OGRESS MEETING MINUTES•
Meeting#: 61
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
61 3a. Schedule Review (Continued)
Flashing will continue at the fly tower through next
week to be followed by the installation of vapor
3a.61a barrier and siding. Metal gutters and corrugated N/A Info
metal roofing are scheduled to begin Monday,
06.06.05
TSCI's schedule update for the period ended
03.31.05 was reviewed and comments provided to
TSCI yesterday, 04.06.05. The schedule as
submitted reflects project completion September 5,
2005, 31 days beyond the contract completion
date. There was discussion regarding increasing
manpower and working of extended hours to meet
the contract completion date. It was also stated
3a.54b. that work in the Mercantile Building must be 06/02/05 TSCI
completed within the same time frame.
K. Terry advised that TSCI's schedule update reflecting work
through 04.29.05 will be submitted Tuesday, 05.03.05.
(04.28.05)
VCM review comments of the 4.29.05 schedule update are
expected Monday, 05.09.05. (05.05.05)
VCM review comments were forwarded to TSCI yesterday,
05.11.05 and indicated minor corrections required.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 139 submittals (including
resubmittals) have been received to date. At this
3b.61 date, three submittals remain outstanding. All os/02/OS FSY
three outstanding submittals have been
submitted within the last week.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 433 RFI's
(including revisions) have been submitted to date.
There are currently eight RFI's outstanding, the
3c.61 longest outstanding of which is 17 days. RFI 05/31/05 FSY
372, relating to the overhang at the front of the
building has been outstanding for 16 days and is
critical to the completion of framing in this area.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.60 Both of these items have been included in N/A Info
previously approved change orders.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 61
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
61 3d.1 Architect's Supplemental Instructions
Fifteen Architect's Supplemental Instructions
3d.1.61 (ASI) have been issued as of this date. Of the 06/02/05 TSCINCM
fifteen, 9 are in approved or pending change
orders. 6 are awaiting pricing.
3d.2 Construction Bulletins
Twenty seven Construction Bulletins have been
issued. Of the twenty seven, 18 are in
3d.2.61 previously approved or pending change orders. 06/02/05 TSCINCM
Three have been superseded, 3 are pending
negotiation and 3 are being priced.
3e Change Order/Proposed Change Order
Status:
.3e.1 Change Orders
CO #10 has been executed by TSCI and
3e.1.61 returned to the City for processing. It was N/A Info
determined that CO #10 can be included in
TSCI's payment request#15.
3e.2 Proposed Change Orders
One hundred thirty eight potential change
requests have been identified. Of those, 68
3e.2.61 have been incorporated into executed or 06/02/05 TSCINCM
pending change orders, 12 have been rejected,
13 are pending negotiation, 33 have been
voided, and 12 are pending pricing.
3e.3 Disputed Items
3e.3.54 TSCI has identified nine of the rejected change N/A Info
order requests as potential dispute items.
3f Payment Status Review:
TSCI's draft Payment Request #15 .was
3f.61 reviewed following the meeting. TSCI to make 05/31/05 City of
corrections and submit for processing. Temecula
3g Notice Of Non Conformance Status:
3 .61 There are no outstanding correction notices at
this date. N/A Info
g
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.61 and are prerequisite to inspections. N/A Info
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 61
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item# Description Due Action
61 3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.61 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection-
Fire taping, drywall installation, and rough
4.60 electrical and plumbing have been inspected N/A Info
and signed off during the week by Bldg & Safety
Inspection Bob Henderson.
5.0 New Business:
Decorative benches: Following discussion, it
was determined that the City of Temecula will
5.51a make a decision and provide direction. 04/29/05 FSY
David McBride advised that the City has selected the
benches to be used. FSY Architects is determining the
la out for the selected b enches 1AJ.21.05
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51 c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
5.58a preservative to one side of the siding may increase Closed Info
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Plaques for Donor Wall: There was discussion
regarding the plaques for the donor wall. FSY will
follow up with additional details sufficient to obtain
5.59a mock-ups and pricing for the plaques. 6/30/05 TSCI
TSCI will contact various vendors to obtain pricing
for the donor plaques. 05.26.05
Transformer rack at electrical room: TSCI asked if
the wood for the transformer rack at the electrical
5.59c room should be fire treated. VCM will follow up 5/31/05 City of
with Bldg. & Safety Inspector Bob Henderson. Temecula
Still awaiting response from Mr. Henderson 05.26.05
Page 4 of 5 VANIR F 503
VANIR •OGRESS MEETING MINUTES•
Meeting#: 61
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely, tEampbell
gnature
Name: La
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting#: 60
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: May 19, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Steve Tovey,Tovey Shultz Ed Deleeuw,Tovey Shultz
Temecula Construction, Inc(TSCI) Construction, Inc(TSCI)
Larry Campbell,Vanir
Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
60 1.0 Approval Of Previous Meeting Minutes:
1.60 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 59.
2.0 Construction Progress Update:
Framing of the audience chamber, elevator tower,
and west overhang at the Mercantile Building has
continued. Electrical rough in the audience
chamber and stage area is ongoing. Plumbing of
gas lines to HVAC units and miscellaneous
plumbing pick up work is ongoing. Metal flashing is
2.60 ongoing. Installation of HVAC ducting and fire N/A Info
sprinkler lines at the audience chamber and stage
area is in progress as is installation of insulation at
ceilings and walls at the classroom building and
dance studio. Plaster scratch coat has been
applied at the concession building.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Framing for the audience chamber will continue
through next week while electrical rough in and fire
sprinkler installation is this area is expected to be
3a.60a. substantially complete by the end of this week. N/A Info
HVAC duct in the audience chamber is expected to
continue through the middle of next week. Painting
of the audience chamber ceiling is tentatively
scheduled to begin Monday, 05.23.05 to be
followed by installation of baffles.
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 60
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item# Description Due Action
60 3a. Schedule Review (Continued)
Flashing will continue at the fly tower through the
end of this week to be followed by the installation
3a.60a of vapor barrier and siding. Metal gutters and N/A Info
corrugated metal roofing are scheduled to begin
late next week.
TSCI's schedule update for the period ended
03.31.05 was reviewed and comments provided to
TSCI yesterday, 04.06.05. The schedule as
submitted reflects project completion September 5,
2005, 31 days beyond the contract completion
date. There was discussion regarding increasing
manpower and working of extended hours to meet
the contract completion date. It was also stated
3a.54b. that work in the Mercantile Building must be 06/02/05 TSCI
completed within the same time frame.
K. Terry advised that TSCI's schedule update reflecting work
through 04.29.05 will be submitted Tuesday, 05.03.05.
(04.28.05)
VCM review comments of the 4.29.05 schedule update are
expected Monday, 05.09.05. (05.05.05)
VCM review comments were forwarded to TSCI yesterday,
05.11.05 and indicated minor corrections required.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 137 submittals (including
resubmittals) have been received to date. At this
3b.60 date, three submittals remain outstanding. The 05/26/05 FSY
longest outstanding submittal has been
outstanding for one week.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 424 RFI's
(including revisions) have been submitted to date.
3c.60 There are currently five RFI's outstanding, the 05/26/05 FSY
longest outstanding of which is 10 days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.60 Both of these items have been included in N/A Info
previously approved change orders.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 60
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
60 3d.1 Architect's Supplemental Instructions
Fifteen Architect's Supplemental Instructions
3d.1.60 (ASI) have been issued as of this date. Of the 05/26/05 TSCINCM
fifteen, 9 are in approved or pending change
orders. 6 are awaiting pricing.
3d.2 Construction Bulletins
Twenty seven Construction Bulletins have been
issued. Of the twenty seven, 18 are in
3d.2.60 previously approved or pending change orders. 05/26/05 TSCINCM
Three have been superseded, 3 are pending
negotiation and 3 are being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
David McBride advised that Change Order No.
10 has been drafted and is ready to be mailed to
TSCI for signature.
3e.1.59 05/26/05 TSCI
TSCI acknowledged receipt of CO#10. TSCI is
waiting for K Terry to return from vacation to
review prior to signing. 05.19.05
3e.2 Proposed Change Orders
One hundred thirty six potential change requests
have been identified. Of those, 68 have been
3e.2.60
incorporated into executed or pending change
orders, 12 have been rejected, 11 are pending 05/26/05 TSCINCM
negotiation, 33 have been voided, and 12 are
pending pricing.
3e.3 Disputed Items
3e.3.54 TSCI has identified nine of the rejected change N/A Info
order requests as potential dispute items.
3f Payment Status Review:
TSCI's draft Payment Request #14 was
reviewed prior to the meeting. TSCI to make
3f.57 corrections and submit for processing. 06/06/05 City of
Payment Request No. 14 has been forwarded to the Temecula
City of Temecula for processing and payment.
05.05.05
3g Notice Of Non Conformance Status:
3 60 There are no outstanding correction notices at N/A Info
g' this date.
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 60
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
60 3h As Built Status Review:
3h.60 Revisions are being posted on a regular basis
and are prerequisite to inspections.
N/A Info
31 Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.60 that are observed between meetings are discussed NIA Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
Fire taping and drywall installation was
inspected and signed off during the week by
4.60 Bldg & Safety Inspection Bob Henderson. N/A Info
Kleinfelder was on site to inspect epoxy at the
Mercantile Building.
5.0 New Business:
Decorative benches: Following discussion, it
was determined that the City of Temecula will
5.51a make a decision and provide direction. 04/29/05 FSY
David McBride advised that the City has selected the
benches to be used. FSY Architects is determining the
layout for the selected benches. 04.21.05
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
5.58a preservative to one side of the siding may increase 05/12/05 FSY
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Plaques for Donor Wall: There was discussion
5.59a regarding the plaques for the donor wall. FSY will 5/17/05 FSY
follow up with additional details sufficient to obtain
mock-ups and pricing for the plaques.
Transformer rack at electrical room: TSCI asked if
5.59c the wood for the transformer rack at the electrical 5/13/05 VCM
room should be fire treated. VCM will follow up
with Bldg. & Safety Inspector Bob Henderson.
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 60
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely
i nature
Name: Larry E. Campbell _
Title: Project Manager
Page 5 of 5 VANIR F 503
r .
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: 59
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: May 12, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
David McBride, City of Bruce Beers,City of Ed Deleeuw,Tovey Shultz
Attendees: Temecula Temecula Construction, Inc(TSCI)
Scan Park, FSY Architects Larry Campbell,Vanir
(FSY) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
59 1.0 Approval Of Previous Meeting Minutes:
1.59 There were no corrections or additions to the
Minutes of Meeting No. 58. N/A Info
2.0 Construction Progress Update:
Framing of the audience chamber and elevator
shaft and installation of miscellaneous backing has
continued. Electrical rough in the audience
chamber, including panel installation, is ongoing.
Plumbing of gas lines to HVAC units and
miscellaneous plumbing pick up work is ongoing.
Metal flashing is ongoing. Baffle hangers are being
installed and installation of exterior plywood at the
2.59 fly tower is in progress. Installation of HVAC N/A Info
ducting at the Classroom Building is in progress as
is installation of insulation at ceilings and walls.
Lathing has been completed at the concession
building in preparation for plaster. Concrete was
placed in Fourth Street during the week and layout
and demolition has begun at the Mercantile Bldg.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Framing for the audience chamber will continue
through next week as will electrical rough in at the
3a.59a. audience chamber. Installation of audience N/A Info
chamber fire sprinkler lines will continue through
the end of this week to be followed by installation
of HVAC ductwork.
Page 1 of 5
r ,
VAN 1 R 4PROGRESS MEETING MINUTES
Meeting#: 59
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
59 3a. Schedule Review (Continued)
Painting of the audience chamber ceiling is
tentatively scheduled to begin Monday, 05.23.05 to
be followed by installation of baffles. Drywall
installation, plywood, and flashing will continue at
the fly tower. Framing of roof overhangs and
3a.59a framing for the elevator tower will continue through N/A Info
next week. Installation of the vapor barrier at the
fly tower is scheduled to begin Thursday, 05.19.05
to be followed by the installation of siding. Metal
gutters and corrugated metal roofing are scheduled
to begin Monday, 05.23.05.
TSCI's schedule update for the period ended
03.31.05 was reviewed and comments provided to
TSCI yesterday, 04.06.05. The schedule as
submitted reflects project completion September 5,
2005, 31 days beyond the contract completion
date. There was discussion regarding increasing
manpower and working of extended hours to meet
the contract completion date. It was also stated
3a.54b. that work in the Mercantile Building must be 06/02/05 TSCI
completed within the same time frame.
K. Terry advised that TSCI's schedule update reflecting work
through 04.29.05 will be submitted Tuesday, 05.03.05.
(04.28.05)
VCM review comments of the 4.29.05 schedule update are
expected Monday,05.09.05. (05.05.05)
VCM review comments were forwarded to TSCI yesterday,
05.11.05 and indicated minor corrections required.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 135 submittals (including
3b.58 resubmittals) have been received to date. At this 05/26/05 FSY
date, one submittal, submitted during the course
of the meeting is outstanding.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 419 RFI's
(including revisions) have been submitted to date.
3c.58 There are currently five RFI's outstanding, the 05/19/05 FSY
longest outstanding of which is 3 days.
Page 2 of 5 VANIR F 503
VAN 1 R 'PROGRESS MEETING MINUTES
Meeting#: 59
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
59 3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.59 Both of these items have been included in N/A Info
revio sly approved change orders.
3d.1 Architect's Supplemental Instructions
Fifteen Architect's Supplemental Instructions
3d.1.59 (ASI) have been issued as of this date. Of the 05/26/05 TSCINCM
fifteen, 9 are in approved or pending change
orders. 6 are awaiting pricing.
3d.2 Construction Bulletins
Twenty seven Construction Bulletins have been
issued. Of the twenty seven, 18 are in
3d.2.59 previously approved or pending change orders. 05/26/05 TSCINCM
Three have been superseded, 3 are pending
negotiation and 3 are being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
David McBride advised that Change Order No.
3e.1.59 10 has been drafted and is ready to be mailed to N/A Info
TSCI for signature.
3e.2 Proposed Change Orders
One hundred thirty six potential change requests
have been identified. Of those, 69 have been
3e.2.59 incorporated into executed or pending change 05/26/05 TSCINCM
orders, 9 have been rejected, 6 are pending
negotiation, 32 have been voided, and 20 are
pending pricing.
3e.3 Disputed Items
3e.3.54 TSCI has identified nine of the rejected change N/A Info
order requests as potential dispute items.
3f Payment Status Review:
TSCI's draft Payment Request #14 was
reviewed prior to the meeting. TSCI to make
3f.57 corrections and submit for processing. 06/06/05 City of
Payment Request No. 14 has been forwarded to the Temecula
City of Temecula for processing and payment.
05.05.05
3g Notice Of Non Conformance Status:
3 58 There are no outstanding correction notices at
this date. N/A Info
g
Page 3 of 5 VANIR F 503
VAN 1 R 41ROGRESS MEETING MINUTES
Meeting#: 59
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
59 3h As Built Status Review:
Revisions are being posted on a regular basis
3h.59 and are prerequisite to inspections.
N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.59 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstandinq safety issues at this time.
4.0 Testing/Inspection:
Exterior drywall and rough electrical installation
4.59 was inspected and signed off during the week by N/A Info
Bldg & Safety Inspection Bob Henderson.
5.0 New Business:
Decorative benches: Following discussion, it
was determined that the City of Temecula will
make a decision and provide direction.
5.51a 04/29/05 FSY
David McBride advised that the City has selected the
benches to be used. FSY Architects is determining the
layout for the selected benches. 04.21.05
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51 c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
5.58a preservative to one side of the siding may increase 05/12/05 FSY
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
Plaques for Donor Wall: There was discussion
5.59a regarding the plaques for the donor wall. FSY will 5/17/05 FSY
follow up with additional details sufficient to obtain
mock-ups and pricing for the plaques.
Sound insulation at restrooms: TSCI noted that no
sound insulation is shown in restroom walls.
5.59b Following discussion, it was determined at the N/A Info
walls will be constructed per plan.
Page 4 of 5 VANIR F 503
VAN 1 R 4PROGRESS MEETING MINUTES
Meeting#: 59
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Transformer rack at electrical room: TSCI asked if
59 5.59c the wood for the transformer rack at the electrical 5/13/05 VCM
room should be fire treated. VCM will follow up
with Bldg. & Safety Inspector Bob Henderson.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely l'
" --._ .. ............
nature
Name: Larry . Campbell _
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: 58
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: May 5, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File # 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Steve Tovey,Tovey Shultz
Temecula Temecula Construction, Inc. (TSCI)
Kevin Terry, Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir Arturo Yanez, FSY Architects
Construction, Inc(TSCI) Construction, Inc (TSCI) Construction Mgmt. (VCM) (FSY)
Meeting # Item # Description Due Action
58 1.0 Approval Of Previous Meeting Minutes:
1.58 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 57.
2.0 Construction Progress Update:
Framing of the audience chamber and roof
overhang has continued. Electrical rough in the
stage area, Scene Shop, and audience chamber,
including panel installation, is ongoing. Plumbing
2.57 rough in and miscellaneous plumbing pick up work N/A Info
is ongoing. Metal flashing is ongoing. The
elevator tower has been erected. Baffle hangers
are being installed and installation of exterior
drywall at the fly tower and concession building is
ongoing.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Framing for the audience chamber will continue
through next week as will the installation of
exterior drywall at the fly tower. Erection of
scaffolding at the Concession Building is in
progress and lath and plaster are scheduled for
3a.57a. 05.09.05. Installation of HVAC duct at the N/A Info
audience chamber is scheduled to begin 05.09.05
and continue for approximately two weeks.
Plywood at the exterior of the fly loft is scheduled
to begin tomorrow to be followed by installation of
siding. Rough electrical inspection is scheduled for
tomorrow.
Page 1 of 6
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 58
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
58 3a. Schedule Review (Continued)
TSCI's schedule update for the period ended
03.31.05 was reviewed and comments provided to
TSCI yesterday, 04.06.05. The schedule as
submitted reflects project completion September 5,
2005, 31 days beyond the contract completion
date. There was discussion regarding increasing
manpower and working of extended hours to meet
3a.54b. the contract completion date. It was also stated 05/09/05 VCM
that work in the Mercantile Building must be
completed within the same time frame.
K. Terry advised that TSCI's schedule update reflecting work
through 04.29.05 will be submitted Tuesday, 05.03.05.
(04.28.05)
VCM review comments of the 4.29.05 schedule update are
expected Monday, 05.09.05. (05.05.05)
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 134 submittals (including
3b.58 resubmittals) have been received to date. At this 05/11/05 FSY
date, three submittals are outstanding. None of
the three have been outstanding in excess of
two weeks.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 412 RFI's
3c.58 (including revisions) have been submitted to date. N/A Info
There are current) no RFI's outstanding.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.58 Both of these items have been included in N/A Info
revio sly approved change orders.
3d.1 Architect's Supplemental Instructions
Fourteen Architect's Supplemental Instructions
3d.1.58 (ASI) have been issued as of this date. Of the 05/11/05 TSCl/VCM
fourteen, 9 are in approved or pending change
orders. 5 are awaiting pricing.
3d.2 Construction Bulletins
Twenty six Construction Bulletins have been
issued. Of the twenty six, 13 are in previously
3d.2.58 approved or pending change orders. Three 05/11/05 TSCl/VCM
have been superseded, 6 are pending
negotiation and 4 are being priced.
Page 2 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 58
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
58 3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
David McBride advised that Change Order No.
3e.1.56 10 is being reserved exclusively for the tenant N/A Info
improvements at the Mercantile Building.
3e.2 Proposed Change Orders
One hundred thirty potential change requests
have been identified. Of those, 59 have been
3e.2.58 incorporated into executed or pending change 05/11/05 TSCl/VCM
orders, 9 have been rejected, 13 are pending
negotiation, 33 have been voided, and 16 are
pending pricing.
3e.3 Disputed Items
3e.3.54 TSCI has identified nine of the rejected change N/A Info
order requests as potential dispute items.
3f Payment Status Review:
TSCI's draft Payment Request #14 was
reviewed prior to the meeting. TSCI to make
3f.57 corrections and submit for processing. 06/06/05 City of
Payment Request No. 14 has been forwarded to the Temecula
City of Temecula for processing and payment.
05.05.05
3g Notice Of Non Conformance Status:
3 58 There are no outstanding correction notices at N/A Info
g this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.58 and are prerequisite to inspections. N/A Info
31 Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.58 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
There has been no testing or inspections
4.58 performed since the last meeting. N/A Info
Page 3 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 58
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
TSCI's pricing for the tenant improvement work has been
received. Following review of TSCI's proposal, additional
items of work have been requested. Revised pricing is due
from TSCI prior to the close of business Monday, 05.02.05.
5.25b (04.28.05) N/A Closed
Following discussion, it was determined that the flooring
material will be V-8"width, laid in the NIS direction. This
item will be deleted from future meeting discussion.
(05.05.05)
Fall prevention points at the balcony level: FSY
will review railings required to prevent falls at the
balcony level and issue a bulletin reflecting
those railings required.
Bulletin No.24 was received from FSY on 02.23.05. Following
discussion during the meeting,this bulletin requires revision
for type of protection and location. (02.24.05)
5.47b The response received to RFI 332 indicates that the response 05/06/05 VCM
also addressed Bulletin No. 24. In that questions remain,
VCM will follow up with FSY and ENA Group to clarify.
(04.28.05)
Revised Bulletin No.24 was discussed during the meeting
and accepted by the City of Temecula. Bulletin 24R will
be issued to TSCI tomorrow,05.06.05. This item is
complete and will be deleted from future meeting
agendas. (05.05.05)
Trench patches @ Fourth Street: D. McBride
noted that trench patches in Fourth Street have
deteriorated and need to be addressed.
TSCI noted that installation of the Muzak conduit was
expected to begin. TSCI will obtain trench plates in order for
5.50b this work to begin. (03.31.05) N/A Closed
TSCI advised that concrete placed for the repair of Fourth
Street is scheduled to begin 05.04.05. (04.21.05)
Concrete is scheduled for 7:00 a.m.,tomorrow,05.06.05.
This item is complete and will be deleted from future
meeting agendas. (05.05.05)
Decorative benches: Following discussion, it
was determined that the City of Temecula will
make a decision and provide direction.
5.51 a 04/29/05 FSY
David McBride advised that the City has selected the
benches to be used. FSY Architects is determining the
layout for the selected benches. 04.21.05
Page 4 of 6 VANIR F 503
VAN 1 R •PROGRESS MEETING MINUTES
Meeting#: 58
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Artesian Fountain: TSCI advised that the
fountain will not work properly as designed.
Following discussion, it was determined that
TSCI will review alternative designs that fall
within the budget.
Following brief discussion, it was determined that FSY will
follow up with the Landscape Architect. (04.07.05)
David McBride advised that Robert Morris is interested in
5.51 b. constructing the fountain. VCM will follow up with Morris to N/A Closed
determine whether the fountain can be constructed as
designed and solicit other concepts for the required fountain.
TSCI advised that it has sent RFP's to a number of local
fountain contractors and will forward the information once it is
received. (04.21.05)
Following discussion during the course of the meeting, it
was determined that the fountain will be built per plan.
This item will be deleted from future meeting agendas.
(05.05.05)
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51 c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Telephone/data conduits: Bruce Beers advised
that some revisions have been made regarding
telephone and data outlet locations. D. McBride
will review the layout and provide new sketches.
5.56a A meeting was held this morning with Bruce Beers and 05/06/05 VCM
City of Temecula IS personnel. The only additional outlet
required that has not already been indicated by bulletins,
it a telephone outlet for a wall mounted telephone at the
right side of the stage. VCM will confirm with a memo.
05.05.05
Transformer Rack Design: TSCI advised that the
required design for the rack to hold the transformer
to be wall mounted has not been received. VCM to
follow up with FSY and ENA Group.
VCM participated in a conference call with FSY and ENA
5.56b Group regarding this issue. Following conversation during the 05/05/05 FSY
course of the meeting,TSCI and VCM will determine with
Bldg. &Safety whether one of the two entrances to the
electrical room can be eliminated thereby alleviating the
requirement to stack transformers.
FSY indicated that a sketch will be issued later today.
05.05.05
Page 5 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 58
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Preservative for exterior siding: Art Yanez noted
that, after reconsideration, perhaps a clear
preservative should be applied to the exterior wood
siding. TSCI noted that application of a
58 5.58a preservative to one side of the siding may increase 05/12/05 FSY
the likelihood of cupping. FSY will follow up with
the Cedar Institute to determine the ramifications of
preservative application at this stage of
construction.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Si nature
Name: Larry E. Campbell
Title: Project Manager
Page 6 of 6 VANIR F 503
VANIR
•
PROGRESS MEETING MINUTES
Meeting #: 57
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: April 28, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File # 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
Temecula Construction, Inc(TSCI) Construction, Inc(TSCI)
Larry Campbell,Vanir
Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
57 1.0 Approval Of Previous Meeting Minutes:
1.57 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 56.
2.0 Construction Progress Update:
Framing of the fly loft, audience chamber and roof
overhang has continued. Electrical rough in the
stage area, Scene Shop, and audience chamber,
including panel installation, is ongoing and backfill
and grouting of electrical and hydraulic lines
between the buildings is complete. Plumbing
2.57 rough in and miscellaneous plumbing pick up work N/A Info
is ongoing. Metal flashing and installation of HVAC
lines at the Classroom Building are ongoing.
Drywall has been installed behind electrical panels.
Framing for the overhang and walkway on the west
side of the Mercantile Building has progressed
intermittently.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Framing for the audience chamber will continue for
the next two weeks. Installation of the elevator
tower, initially scheduled for today, is scheduled for
3a.57a. tomorrow. Exterior drywall at the Concession N/A Info
Building, Scene Shop and fly tower is scheduled to
begin Monday, 05.02.05, with lath and plaster
scheduled for 05.09.05. Installation of HVAC duct
at the audience chamber is scheduled to begin
Wednesday, 05.04.05 and rough electrical
inspection is scheduled for Friday, 05.06.05.
Page 1 of 6
VAN 1 R ?ROGRESS MEETING MINUTES*
Meeting#: 57
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
56 3a. Schedule Review (Continued)
Drywall (one side) is scheduled to begin 05.09.05
with installation of plywood at the fly tower
scheduled to begin Wednesday, 05.04.05.
Installation of wall insulation is scheduled to begin
3a.57a Monday, 05.09.05. There was discussion 05/05/05 TSCI
regarding the need to either increase crew sizes or
work extended hours in order to meet the current
contract completion date. TSCI will meet with the
framing superintendent to resolve this concern.
TSCI's schedule update for the period ended
03.31.05 was reviewed and comments provided to
TSCI yesterday, 04.06.05. The schedule as
submitted reflects project completion September 5,
2005, 31 days beyond the contract completion
date. There was discussion regarding increasing
manpower and working of extended hours to meet
3a.54b. the contract completion date. It was also stated 05/03/05 TSCI
that work in the Mercantile Building must be
completed within the same time frame.
K. Terry advised that TSCI's schedule update reflecting
work through 04.29.05 will be submitted Tuesday,
05.03.05. (04.28.05)
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 131 submittals (including
3b.57 resubmittals) have been received to date. At this 05/05/05 FSY
date, one submittal is outstanding.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 412 RFI's
3c.57 (including revisions) have been submitted to date. N/A Info
There are current) no RFI's outstanding.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.57 Both of these items have been included in N/A Info
revio sly approved change orders.
3d.1 Architect's Supplemental Instructions
Fourteen Architect's Supplemental Instructions
3d.1.57 (AS]) have been issued as of this date. Of the 05/06/05 TSCINCM
fourteen, 9 are in approved or pending change
orders. 5 are awaiting pricing.
Page 2 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 57
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
57 3d.2 Construction Bulletins
Twenty six Construction Bulletins have been
issued. Of the twenty six, 13 are in previously
3d.2.57 approved or pending change orders. Three 05/06/05 TSCINCM
have been superseded, 6 are pending
negotiation and 4 are being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
David McBride advised that Change Order No.
3e.1.56 10 is being reserved exclusively for the tenant N/A Info
improvements at the Mercantile Building.
3e.2 Proposed Change Orders
One hundred twenty two potential change
requests have been identified. Of those, 58
3e.2.57 have been incorporated into executed or 05/06/05 TSCINCM
pending change orders, 8 have been rejected, 6
are pending negotiation, 33 have been voided,
and 17 are pending pricing.
3e.3 Disputed Items
3e.3.54 TSCI has identified nine of the rejected change N/A Info
order requests as potential dispute items.
3f Payment Status Review:
TSCI's draft Payment Request #14 was
3f.57 reviewed prior to the meeting. TSCI to make 05/03/05 TSCI
corrections and submit for processing.
3g Notice Of Non Conformance Status:
3 57 There are no outstanding correction notices at N/A Info
g' this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.57 and are prerequisite to inspections. N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.57 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
Page 3 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 57
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
57 4.0 Testing/Inspection:
4.57 There has been no testing or inspections N/A Info
performed since the last meeting.
5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
Design concept and final design proposal were approved by
the City Council on 02.08.05. Design development is in
progress. (02.10.05)
S. Park advised that drawings have been sent to the various
consultants with submission of plans to the Building
Department scheduled for month end. (03.10.05)
Plans for the interior renovations were submitted to Building &
5.25b Safety Tuesday,04.05.05. 05/02/05 TSCI
Plans for the interior renovations were provided to TSCI on
Tuesday,04.12.05 with pricing to be submitted prior to the
close of business Monday, 04.25.05 (04.14.05)
TSCI's pricing for the tenant improvement work has been
received. Following review of TSCI's proposal,additional
items of work have been requested. Revised pricing is
due from TSCI prior to the close of business Monday,
05.02.05. (04.28.05)
Fall prevention points at the balcony level: FSY
will review railings required to prevent falls at the
balcony level and issue a bulletin reflecting
those railings required.
Bulletin No. 24 was received from FSY on 02.23.05. Following
5.47b discussion during the meeting,this bulletin requires revision 04/29/05 VCM
for type of protection and location. (02.24.05)
The response received to RFI 332 indicates that the
response also addressed Bulletin No.24. In that
questions remain,VCM will follow up with FSY and ENA
Group to clarify. (04.28.05)
Trench patches @ Fourth Street: D. McBride
noted that trench patches in Fourth Street have
deteriorated and need to be addressed.
TSCI noted that installation of the Muzak conduit was 5.50b expected to begin. TSCI will obtain trench plates in order for 05/06/05 TSCI
this work to begin. (03.31.05)
TSCI advised that concrete placed for the repair of Fourth
Street is scheduled to begin 05.04.05. (04.21.05)
Page 4 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 57
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Decorative benches: Following discussion, it
was determined that the City of Temecula will
make a decision and provide direction.
57 5.51a 04/29/05 FSY
David McBride advised that the City has selected the
benches to be used. FSY Architects is determining the
layout for the selected benches. 04.21.05
Artesian Fountain: TSCI advised that the
fountain will not work properly as designed.
Following discussion, it was determined that
TSCI will review alternative designs that fall
within the budget.
Following brief discussion, it was determined that FSY will
follow up with the Landscape Architect. (04.07.05)
5.51 b. 04/14/05 FSY
David McBride advised that Robert Morris is interested in
constructing the fountain. VCM will follow up with Morris
to determine whether the fountain can be constructed as
designed and solicit other concepts for the required
fountain.
TSCI advised that it has sent RFP's to a number of local
fountain contractors and will forward the information once
it is received. (04.21.05)
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51 c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Telephone/data conduits: Bruce Beers advised
that some revisions have been made regarding City of
5.56a telephone and data outlet locations. D. McBride o4/28/OS Temecula
will review the layout and provide new sketches.
Transformer Rack Design: TSCI advised that the
required design for the rack to hold the transformer
to be wall mounted has not been received. VCM to
follow up with FSY and ENA Group.
5.56b VCM participated in a conference call with FSY and ENA 04/29/05 TSCINCM
Group regarding this issue. Following conversation
during the course of the meeting,TSCI and VCM will
determine with Bldg.&Safety whether one of the two
entrances to the electrical room can be eliminated thereby
alleviating the requirement to stack transformers.
Page 5 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 57
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely, _
+ ign lure
Name: Larry E. Campbell
Title: Project Manager
Page 6 of 6 VANIR F 503
VANIR r
PROGRESS MEETING MINUTES
Meeting#: 56
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: April 21, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Kevin Terry,Tovey Shultz
Temecula Temecula Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc (TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
56 1.0 Approval Of Previous Meeting Minutes:
1.56 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 55.
2.0 Construction Progress Update:
Framing of the fly loft and layout for framing at the
audience chamber has continued as has
installation of cedar siding at the Classroom
Building and construction of Stair No. 5.
Scaffolding has been erected for the fly tower and
audience chamber. Electrical rough in stage area
Scene Shop is ongoing and rough-in of electrical
2.56 and hydraulic lines between the buildings is in N/A Info
progress. Plumbing rough in and miscellaneous
plumbing pick up work is ongoing. Metal flashing is
ongoing and installation of roofing felt at the scene
shop and fly tower is complete. The Muzak conduit
has been installed in Fourth Street and the planter
area on Front St. Construction of the overhang on
the west side of the Mercantile Building is in
progress.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Exterior siding will continue for the next four weeks
as will framing for the fly loft and audience
3a.56a. chamber. Installation of the elevator tower is N/A Info
scheduled to begin 04.25.05. Exterior drywall at the
Concession Building, Scene Shop and fly tower is
scheduled to begin Wednesday, 04.27.05, with lath
and plaster scheduled for 05.02.05.
Page 1 of 5
VAN 1 R IROGRESS MEETING MINUTES
Meeting#: 56
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
56 3a. Schedule Review (Continued)
Drywall (one side) is scheduled to begin 05.04.05
as is installation of plywood at the fly tower. Rough
3a.56a electrical inspection is scheduled for 05.06.05 with N/A Info
installation of wall insulation to between 05.09.05.
TSCI's schedule update for the period ended
03.31.05 was reviewed and comments provided to
TSCI yesterday, 04.06.05. The schedule as
submitted reflects project completion September 5,
2005, 31 days beyond the contract completion
3a.54b. date. There was discussion regarding increasing N/A Info
manpower and working of extended hours to meet
the contract completion date. It was also stated
that work in the Mercantile Building must be
completed within the same time frame.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 130 submittals (including
3b.56 resubminais) have been received to date. At this N/A Info
date, there are no submittals outstanding.
3c Request For Information Status Review:
A review of VCM's RFI log reflects 411 RFI's
3c.56 (including revisions) have been submitted to date. 4 04/25/05 FSY
RFI's are outstanding. Of the four, only RFI 332
has been outstanding in excess of two weeks.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.56 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Fourteen Architect's Supplemental Instructions
3d.1.56 (ASI) have been issued as of this date. Of the 04/28/05 TSCINCM
fourteen, 9 are in approved or pending change
orders. 5 are awaiting pricing.
55 3d.2 Construction Bulletins
Twenty six Construction Bulletins have been
issued. Of the twenty six, 13 are in previously
3d.2.55 approved or pending change orders. Three 04/21/05 TSCINCM
have been superseded, 6 are pending
negotiation and 4 are being priced.
Page 2 of 5 VANIR F 503
VAN 1 R •OGRESS MEETING MINUTE•
Meeting#: 56
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
56 3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
David McBride advised that Change Order No.
3e.1.56 10 is being reserved exclusively for the tenant N/A Info
Improvements at the Mercantile Building.
3e.2 Proposed Change Orders
One hundred twenty two potential change
requests have been identified. Of those, 58
have been incorporated into executed or
3e.2.56 pending change orders, 8 have been rejected, 3 04/29/05 TSCl/VCM
are pending negotiation, 33 have been voided,
and 20 are pending pricing.
3e.3 Disputed Items
TSCI has identified nine of the rejected change
3e.3.54 order requests as potential dispute items. N/A Info
3f Payment Status Review:
Payment Request No. 13 is being processed by City of
3f.55 the City of Temecula. 05/04/05 Temecula
3g Notice Of Non Conformance Status:
There are no outstanding correction notices at
3g.56 this date. N/A Info
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.56 and are prerequisite to inspections.
N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.56 that are observed between meetings are discussed N/A Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection:
4.55 There has been no testing or inspections N/A Info
performed this week.
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 56
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item# Description Due Action
56 5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
Design concept and final design proposal were approved by
the City Council on 02.08.05. Design development is in
progress. (02.10.05)
S. Park advised that drawings have been sent to the various
5.25b consultants with submission of plans to the Building 04/25/05 TSCI
Department scheduled for month end. (03.10.05)
Plans for the interior renovations were submitted to Building&
Safety Tuesday, 04.05.05.
Plans for the interior renovations were provided to TSCI
on Tuesday, 04.12.05 with pricing to be submitted prior to
the close of business Monday,04.25.05 04.14.05
Fall prevention points at the balcony level: FSY
will review railings required to prevent falls at the
balcony level and issue a bulletin reflecting
5.47b those railings required. 02/28/05 FSY
Bulletin No.24 was received from FSY on 02.23.05.
Following discussion during the meeting,this bulletin
requires revision for type of protection and location.
02.24.05
Trench patches @ Fourth Street: D. McBride
noted that trench patches in Fourth Street have
deteriorated and need to be addressed.
5.50b TSCI noted that installation of the Muzak conduit was OS/06/05 TSCI
expected to begin. TSCI will obtain trench plates in order for
this work to begin. (03.31.05)
TSCI advised that concrete placed for the repair of Fourth
Street is scheduled to begin 05.04.05. (04.21.05)
Decorative benches: Following discussion, it
was determined that the City of Temecula will
make a decision and provide direction.
5.51 a 04/29/05 FSY
David McBride advised that the City has selected the
benches to be used. FSY Architects is determining the
layout for the selected benches. 04.21.05
Artesian Fountain: TSCI advised that the
fountain will not work properly as designed.
Following discussion, it was determined that
5.51 b. TSCI will review alternative designs that fall 04/14/05 FSY
within the budget.
Following brief discussion, it was determined that FSY
will follow up with the Landscape Architect. (04.07.05)
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 56
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Artesian Fountain: (Continued)
David McBride advised that Robert Morris is interested in 05/06/05 VCM
constructing the fountain. VCM will follow up with Morris
to determine whether the fountain can be constructed as
56 5.51 b designed and solicit other concepts for the required
fountain.
TSCI advised that it has sent RFP's to a number of local 05/06/05 TSCI
fountain contractors and will forward the information once
it is received. 04.21.05
Decking at Mercantile Bldg: Following discussion,
it was determined that pressure treated material is
5.51 c. not required and a credit for the pressure treating 03/24/05 TSCI
should be submitted since the original plans
required pressure treated material.
Telephone/data conduits: Bruce Beers advised
5.56a that some revisions have been made regarding 04/28/05 City of
telephone and data outlet locations. D. McBride Temecula
will review the layout and provide new sketches.
Transformer Rack Design: TSCI advised that the
5.56b required design for the rack to hold the transformer 04/28/05 VCM
to be wall mounted has not been received. VCM to
follow up with FSY and ENA Group.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Isign6ture
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: 55
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: April 14, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File # 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Sean Park, FSY Architects
Temecula Temecula (FSY)
Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc(TSCI) Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
55 1.0 Approval Of Previous Meeting Minutes:
1.55 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 54.
2.0 Construction Progress Update:
Framing of the fly loft and installation of cedar
siding at the Dance Studio and Classroom Building
continued. Rough in of sub-slab power, lighting,
and AN at the Audience Chamber and electrical
rough in at the Scene Shop and Classroom
2.55 Building continued over the past week. Rough-in N/A Info
for plumbing and fire sprinklers at the Scene Shop
is complete and has been inspected by Building &
Safety. Concrete for the stage and audience
chamber has been completed and installation of
the added storm drainage at the Mercantile
Building is virtually complete.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Grading and installation of drains for the Mercantile
Building will continue through next week. Exterior
siding at the Classroom Building, Dance Studio,
and Scene Shop will continue for the next two
3a.55a. weeks as will framing for the fly loft and audience N/A Info
chamber. Scaffolding will be erected on the interior
and exterior of the fly loft and audience chamber
next week. Installation of hydraulic lines and
electrical feed between building is scheduled to
begin Monday, 04.18.05. Installation of the
elevator tower is expected to begin 04.25.05.
Page 1 of 5
VAN 1 R 'PROGRESS MEETING MINUTES•
Meeting#: 55
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
55 3a. Schedule Review (Continued)
Rough electrical inspection is tentatively scheduled
for Friday, 04.22.05 after which installation of
3a.55a drywall will begin. Installation of exterior drywall N/A Info
lath and plaster at the Concession Building is
scheduled for Monday 04.25.05.
TSCI's schedule update for the period ended
03.31.05 was reviewed and comments provided to
TSCI yesterday, 04.06.05. The schedule as
submitted reflects project completion September 5,
3a.54b. 2005, 31 days beyond the contract completion N/A Info
date. There was discussion regarding increasing
manpower and working of extended hours to meet
the contract completion date. It was also stated
that work in the Mercantile Building must be
completed within the same time frame.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 130 submittals (including
resubmittals) have been received to date. At this
3b.55 date, there are two submittals outstanding; both 04/19/05 FSY
of which have been outstanding in excess of two
weeks with Submittal 65R (Irrigation) the longest
outstanding at 35 days.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 392 RFI's (including revisions) have
been submitted to date. 11 RFI's are
3c.55 outstanding. Of the eleven, 2 have been 04/19/05 FSY
outstanding in excess of two weeks and 7 were
submitted yesterday. RFI 322 requesting carpet
colors is the longest outstanding at 42 days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.55 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Thirteen Architect's Supplemental Instructions
3d.1.55 (AS]) have been issued as of this date. Of the 04/21/05 TSCINCM
thirteen, 9 are in approved or pending change
orders. 4 are awaiting pricing.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 55
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
55 3d.2 Construction Bulletins
Twenty six Construction Bulletins have been
issued. Of the twenty six, 13 are in previously
3d.2.55 approved or pending change orders. Three 04/21/05 TSCINCnA
have been superseded, 6 are pending
negotiation and 4 are being priced.
3e Change Order/Proposed Change Order
Status:
3eA Change Orders
3e.1.55 Change Order No. 9 was signed by TSCI and N/A Info
returned to the City for processing.
3e.2 Proposed Change Orders
One hundred twelve potential change requests
have been identified. Of those, 58 have been
3e.2.54 incorporated into executed or pending change 04/15/05 TSCINCM
orders, 8 have been rejected, 2 are pending
negotiation, 32 have been voided, and 12 are
pending pricing.
3e.3 Disputed Items
3e.3.54 TSCI has identified nine of the rejected change N/A Info
order requests as potential dispute items.
3f Payment Status Review:
3f.55 Payment Request No. 13 is being processed by 05/04/05 City of
the City of Temecula. Temecula
3g Notice Of Non Conformance Status:
3 55 There are no outstanding correction notices at N/A Info
S this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.55 and are prerequisite to inspections.
N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
Foreman's Meeting held every Tuesday. Those
3i.54 that are observed between meetings are discussed N/A l Info
and immediately corrected. There are no
outstanding safety issues at this time.
4.0 Testing/Inspection-
Inspection of underground electrical and rebar at
4.55 the stage area and audience chamber was N/A Info
conducted by Bldg. & Safety this week.
Page 3 of 5 VANIR F 503
VANIR PROGRESS MEETING MINUTES•
Meeting#: 55
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
55 5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
Design concept and final design proposal were approved by
the City Council on 02.08.05. Design development is in
progress. (02.10.05)
S. Park advised that drawings have been sent to the various
5.25b consultants with submission of plans to the Building 04/25/05 TSCI
Department scheduled for month end. (03.10.05)
Plans for the interior renovations were submitted to Building&
Safety Tuesday, 04.05.05.
Plans for the interior renovations were provided to TSCI
on Tuesday,04.19.05 with pricing to be submitted prior to
the close of business Monday,04.25.05 04.14.05
Fall prevention points at the balcony level: FSY
will review railings required to prevent falls at the
balcony level and issue a bulletin reflecting
those railings required.
5.47b 02/28/05 FSY
Bulletin No.24 was received from FSY on 02.23.05.
Following discussion during the meeting,this bulletin
requires revision for type of protection and location.
02.24.05
Trench patches @ Fourth Street: D. McBride
noted that trench patches in Fourth Street have
5.50b deteriorated and need to be addressed. 04/04/05 TSCI
TSCI noted that installation of the Muzak conduit was
expected to begin. TSCI will obtain trench plates in order
for this work to begin. 03.31.05
Decorative benches: Following discussion, it
5.51a was determined that the City of Temecula will 03/24/05 City of
make a decision and provide direction. Temecula
Artesian Fountain: TSCI advised that the
fountain will not work properly as designed.
Following discussion, it was determined that
5.51b. TSCI will review alternative designs that fall 04/14/05 FSY
within the budget.
Following brief discussion, it was determined that FSY
will follow up with the Landscape Architect. (04.07.05)
Decking at Mercantile Bldg: Following
discussion, it was determined that pressure
5.51c. treated material is not required and a credit for 03/24/05 TSCI
the pressure treating should be submitted since
the original plans required pressure treated
material.
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 55
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Framing for smoke hatch: FSY noted that the
framing for the smoke hatch extends above the
peak of the roof at the fly loft. Following
55 5.54b discussion it was determined that the framing N/A Info
will be lowered. FSY will provide a revise detail.
ASI 13 was issued Tuesday,04.12.05. 04.14.05
Early Occupancy: There was discussion
regarding early occupancy of portions of the
project by theater technical staff. It was
determined that permanent equipment can not
5.54c be moved into the project prior to receipt of the N/A Info
Certificate of Occupancy but technical staff
working within the project will be accommodated
in so far as possible without interruption to the
contractors activities.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
IS
ig lure
Name: Larry E. ampt ell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting#: 54
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: March 31, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Arturo Yanez, FSY Architects
Temecula Temecula (FSY)
Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc (TSCI) Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
54 1.0 Approval Of Previous Meeting Minutes:
1.54 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 53.
2.0 Construction Progress Update:
Roof sheathing for the Scene Shop, framing of the
fly loft and installation of cedar siding at the Dance
Studio and Classroom Building continued. Rough
in of sub-slab power, lighting, and A/V at the
Audience Chamber and electrical rough in at the
Scene Shop and Classroom Building continued
over the past week. Rough-in for plumbing and fire Info
2.54 sprinklers at the Scene Shop is essentially N/A
complete. Rigid insulation has been installed at
the roof of the Scene Shop and installation of vapor
barrier at the Classroom Building and north wall of
the Scene Shop is complete. Installation of rebar
and preparation for concrete for the stage and
audience chamber has been ongoing.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Electrical underground rough in for slabs is
expected to be complete tomorrow and concrete
3a.54a. for the stage slab and ramps in the audience N/A Info
chamber will be complete tomorrow. Concrete for
the audience chamber slab is scheduled for
Tuesday, 04.12.05. Grading and installation of
drains for the Mercantile Building will continue
through next week
Page 1 of 6
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 54
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
54 3a. Schedule Review (Continued)
Framing inspection and electrical rough in
inspections are currently scheduled for next
Wednesday. Wall insulation and exterior drywall
3a.54a are scheduled to begin Monday, 04.18.05 and lath N/A Info
and plaster at the Concession Building is
scheduled for Monday 04.25.05.
TSCI's schedule update for the period ended
03.31.05 was reviewed and comments provided to
TSCI yesterday, 04.06.05. The schedule as
submitted reflects project completion September 5,
2005, 31 days beyond the contract completion
3a.54b. date. There was discussion regarding increasing N/A Info
manpower and working of extended hours to meet
the contract completion date. It was also stated
that work in the Mercantile Building must be
completed within the same time frame.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 130 submittals (including
resubmittals) have been received to date. At this
3b.54 date, there are four submittals outstanding. Of 04/12/05 FSY
the fours, two have been outstanding in excess
of two weeks with Submittal 65R (Irrigation) the
longest outstanding at 28 days.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 386 RFI's (including revisions) have
been submitted to date. 6 RFI's are outstanding.
Of the six, 4 have been outstanding in excess of
3c.54 two weeks. RFI 322 requesting carpet colors is 04/11/05 FSY
the longest outstanding at 35 days. RFI Nos.
319R (Detail relating to fire rated corridors) and
335 (Details for rigging beams) as being critical
that were identified last week as being critical by
TSCI remain outstanding.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.54 Both of these items have been included in N/A Info
previously approved change orders.
Page 2 of 6 VANIR F 503
VAN 1 R IROGRES MEETING MINUTES•
Meeting#: 54
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
54 3d.1 Architect's Supplemental Instructions
Twelve Architect's Supplemental Instructions
(ASI) have been issued as of this date. Of the
3d.1.54 twelve, 8 are in approved or pending change 04/11/05 TSCINCM
orders. 1 reflects corrective work required and 3
are awaiting pricing.
3d.2 Construction Bulletins
Twenty five Construction Bulletins have been
issued. Of the twenty five, 13 are in previously
3d.2.54 approved or pending change orders. Three 04/13/05 TSCINCM
have been superseded, 4 are pending
negotiation and 5 are being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
3e.1.54 Change Order No. 9 was mailed to TSCI for 04/11/05 TSCI
signature Tuesday, 04.05.05.
3e.2 Proposed Change Orders
One hundred twelve potential change requests
have been identified. Of those, 58 have been
3e.2.54 incorporated into executed or pending change 04/15/05 TSCINCM
orders, 8 have been rejected, 2 are pending
negotiation, 32 have been voided, and 12 are
pending pricing.
3e.3 Disputed Items
3e.3.54
TSCI has identified nine of the rejected change
order requests as potential dispute items. N/A Info
3f Payment Status Review:
TSCI's draft Payment Request No. 13 was
reviewed on Monday, 03.28.05. TSCI to make
corrections and submit for processing. City of
3f.53 05/04/05 Temecula
Payment Request No. 13 was forwarded to the City of
Temecula for processing Monday,04.04.05
3g Notice Of Non Conformance Status:
There are no outstanding correction notices at
3g.54 this date. N/A Info
Page 3 of 6 VANIR F 503
VAN 1 R VROGRESS MEETING MINUTES
Meeting#: 54
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
54 3h As Built Status Review:
Revisions are being posted on a regular basis
3h.54 and are prerequisite to inspections.
N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
3i.54 Foreman's Meeting held every Tuesday. There are NIA Info
no outstanding safely issues at this time.
4.0 Testing/Inspection:
Inspection of underground electrical at the stage
4.54 area and audience chamber was conducted by N/A Info
Bldg. & Safety this week.
5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
Design concept and final design proposal were approved by
the City Council on 02.08.05. Design development is in
progress. (02.10.05)
5.25b N/A Info
S. Park advised that drawings have been sent to the various
consultants with submission of plans to the Building
Department scheduled for month end. (03.10.05)
Plans for the interior renovations were submitted to
Building &Safety Tuesday,04.05.05.
Fall prevention points at the balcony level: FSY
will review railings required to prevent falls at the
balcony level and issue a bulletin reflecting
5.47b those railings required. 02/28/05 FSY
Bulletin No.24 was received from FSY on 02.23.05.
Following discussion during the meeting,this bulletin
requires revision for type of protection and location.
02.24.05
Counter height at Concession: See previous
meeting minutes for full discussion.
TSCI questioned FSY's response to RFI 336. Following
discussion,TSCI will follow up with Cookson Door to
determine whether or not a price increase will be incurred by
extending the door 8"following which a revised RFI response
5.50a will be provided lowering the entire counter. (03.31.05) N/A Info
Based upon the price for extending the door, it was
decided that the head of the opening will be dropped to
maintain the 5'-0" clear opening and the roll down door
will remain unchanged. (04.07.05)
Page 4 of 6 VANIR F 503
VAN 1 R IROGRESS MEETING MINUTES
Meeting#: 54
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
54 5.0 New Business: (Continued)
Trench patches @ Fourth Street: D. McBride
noted that trench patches in Fourth Street have
5.50b deteriorated and need to be addressed. 04/04/05 TSCI
TSCI noted that installation of the Muzak conduit was
expected to begin. TSCI will obtain trench plates in order
for this work to begin. 03.31.05
Decorative benches: Following discussion, it City of
5.51a was determined that the City of Temecula will 03/24/05 Temecula
make a decision and provide direction.
Artesian Fountain: TSCI advised that the
fountain will not work properly as designed.
Following discussion, it was determined that
5.51b. TSCI will review alternative designs that fall 04/14/05 FSY
within the budget.
Following brief discussion, it was determined that FSY
will follow up with the Landscape Architect. 04.07.05
Decking at Mercantile Bldg: TSCI noted that
Bldg. & Safety Inspector, Bob Henderson,
advised that framing member within 6" of soil are
to be pressure treated. In that the framing
members are above 6", TSCI asked if pressure
5.51c. treated material is necessary. Following 03/24/05 TSCI
discussion, it was determined that pressure
treated material is not required and a credit for
the pressure treating should be submitted since
the original plans required pressure treated
material.
Flashing at Gable Ends of Dance Studio: FSY
5.54a confirmed that no flashing is required at the N/A Info
gable ends of the Dance Studio where siding
changes from horizontal to vertical.
Framing for smoke hatch: FSY noted that the
framing for the smoke hatch extends above the
5.54b peak of the roof at the fly loft. Following 04/11/05 FSY
discussion it was determined that the framing
will be lowered. FSY will provide a revise detail.
Early Occupancy: There was discussion
regarding early occupancy of portions of the
project by theater technical staff. It was
determined that permanent equipment can not
5.54c be moved into the project prior to receipt of the N/A Info
Certificate of Occupancy but technical staff
working within the project will be accommodated
in so far as possible without interruption to the
contractors activities.
Page 5 of 6 VANIR F 503
VAN 1 R VROGRESS MEETING MINUTE
Meeting#: 54
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
1� i ature
Name: Larry E. Campbell
Title: Project Manager
Page 6 of 6 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 53
Owner. City of Temecula
Project: Old Town Temecula
Community Theater
Date: March 31, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers,City of Steve Tovey,Tovey Shultz
Temecula Temecula Construction, Inc (TSCI)
Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc(TSCI) Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
53 1.0 Approval Of Previous Meeting Minutes:
1.53 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 52.
2.0 Construction Progress Update:
Framing for the Scene Shop and installation of
cedar siding at the Restroom/Concession Building
continued. Rough in of sub-slab power, lighting,
and AN at the Audience Chamber and electrical
rough in at the Scene Shop and Classroom
Building continued over the past week. Rough-in
for plumbing and fire sprinklers at the Scene Shop Info
2.53 and gas piping at the Classroom, Concession, and N/A
Restroom Building is ongoing. Installation of vapor
barrier is in progress at the Classroom Building and
installation of siding for the Dance Studio and
Classroom Building is beginning today. Installation
of slab edge form and setting up for slab concrete
placement at the stage area and audience
chamber is in progress.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting. Rigid
insulation for the Scene Shop roof is scheduled for
tomorrow. Framing for the north wall of the fly
3a.53a. tower and installation of siding will continue. N/A Info
Underground electrical rough-in for interior slabs
will be essentially complete tomorrow. Rough-in of
electrical, plumbing, fire sprinkler and HVAC for the
Scene Shop will continue. Installation of exterior
vapor barrier will continue through next week.
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 53
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
53 3a. Schedule Review (Continued)
Framing and rough electrical inspections are
tentatively scheduled for mid to late next week.
3a.53a Similarly, concrete for the stage and audience N/A Info
chamber slabs is tentatively scheduled for late next
week.
TSCI's schedule update for the period ended 02.28.05 will be
submitted early next week. (03.03.05)
TSCI's schedule update for the period through March 2, 2005
was received and is being reviewed. (03.03.05)
3a.50b. Schedule review comments are expected tomorrow and will be 03/31/05 TSCI
forwarded to TSCI. (03.10.05)
VCM review comments were forwarded to TSCI yesterday,
03.23.05 with required corrections noted. (03.24.05)
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 126 submittals (including
resubmittals) have been received to date. At this
date, there are two submittals outstanding.
Submittal 65R (Irrigation) has been outstanding
for two weeks. Questions regarding two items in
3b.53 this submittal were forwarded to the City of 03/30/05 FSY
Temecula for clarification during the course of
the meeting.
Two copies of the irrigation submittal were provided to
the City of Temecula(TCSD)for review. (03.31.05)
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 382 RFI's (including revisions) have
been submitted to date. 7 RFI's are outstanding.
Of the seven, 4 have been outstanding in
3c.53 excess of two weeks. RFI 320 requesting 04/04/05 FSY
details for waterproofing the telephone closet is
the longest outstanding at 37 days. TSCI also
identified RFI Nos. 319R (Detail relating to fire
rated corridors) and 335 (Details for rigging
beams) as being critical.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.53 Both of these items have been included in N/A Info
previously approved change orders.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 53
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
53 3d.1 Architect's Supplemental Instructions
Twelve Architect's Supplemental Instructions
(ASI) have been issued as of this date. Of the
3d.1.53 twelve, 8 are in approved or pending change 04/06/05 TSCINCM
orders. 1 reflects corrective work required and 3
are awaiting pricing.
3d.2 Construction Bulletins
Twenty four Construction Bulletins have been
issued. Of the twenty four, 10 are in previously
3d.2.53 approved or pending change orders. Three 04/06/05 TSCINCM
have been superseded, 6 are pending
negotiation and five are being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 9 incorporating 12 change
order requests has been drafted and forwarded
to the City of Temecula for review and
3e.1.53 processing. 04/07/05 City Temecula
CO 9 has been reviewed by D. McBride and will be
mailed to TSCI for signature next week. 03.31.05
3e.2 Proposed Change Orders
One hundred eleven potential change requests
have been identified. Of those, 50 have been
3e.2.52 incorporated into executed or pending Change 04/08/05 TSCINCM
Orders, 7 have been rejected, 16 are pending
negotiation, 30 have been voided, and 8 are
pending pricing.
3e.3 Disputed Items
3e.3.46 TSCI has identified six of the rejected change N/A Info
order requests as potential dispute items.
3f Payment Status Review:
TSCI's draft Payment Request No. 13 was
3f.53 reviewed on Monday, 03.28.05. TSCI to make 04/01/05 TSCI
corrections and submit for processing.
3g Notice Of Non Conformance Status:
There are no outstanding correction notices at
3g.53 this date. N/A Info
Page 3 of 5 VANIR F 503
VAN 1 R •PROGRESS MEETING MINUTES•
Meeting#: 53
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
53 3h As Built Status Review:
3h.53 Revisions are being posted on a regular basis
and are prerequisite to inspections.
N/A Info
3i Safety Items:
Safety items are discussed formally at the Weekly
3i.53 Foreman's Meeting held every Tuesday. There are N/A Info
no outstanding safety issues at this time.
4.0 Testing/Inspection:
Inspection of underground electrical at the stage
4.53 area and audience chamber was conducted by N/A Info
Bldg. & Safety this week.
5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
Design concept and final design proposal were approved by
the City Council on 02.08.05. Design development is in
5.25b progress. (02.10.05) 03/31/05 FSY
S. Park advised that drawings have been sent to the various
consultants with submission of plans to the Building
Department scheduled for month end. 03.10.05
Fall prevention points at the balcony level: FSY
will review railings required to prevent falls at the
balcony level and issue a bulletin reflecting
5.47b those railings required. 02/28/05 FSY
Bulletin No. 24 was received from FSY on 02.23.05.
Following discussion during the meeting,this bulletin
requires revision for type of protection and location.
02.24.05
Counter height at Concession: TSCI questioned
whether the counter height at the Concession
Bldg (currently shown at 3'-6") should be at 2'-
10" to meet ADA requirements. Following
discussion, it was determined that this issue will
be raised with the Building Inspector.
Following discussion, Building & Safety Inspector Bob
5.50a Henderson advised that the counters should be at 2'-10"to 04/04/05 TSCI
comply with ADA requirements. (03.17.05)
TSCI questioned FSY's response to RFI 336. Following
discussion,TSCI will follow up with Cookson Door to
determine whether or not a price increase will be incurred
by extending the door 8" following which a revised RFI
response will be provided lowering the entire counter.
03.31.05
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 53
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
53 5.0 New Business: (Continued)
Trench patches @ Fourth Street: D. McBride
noted that trench patches in Fourth Street have
deteriorated and need to be addressed.
5.50b 04/04/05 TSCI
TSCI noted that installation of the Muzak conduit was
expected to begin. TSCI will obtain trench plates in order
for this work to begin. 03.31.05
Decorative benches: Following discussion, it
5.51a was determined that the City of Temecula will 03/24/05 City of
make a decision and provide direction. Temecula
Artesian Fountain: TSCI advised that the
fountain will not work properly as designed.
5.51b. Following discussion, it was determined that 03/24/05 TSCI
TSCI will review alternative designs that fall
within the budget.
Decking at Mercantile Bldg: TSCI noted that
Bldg. & Safety Inspector, Bob Henderson,
advised that framing member within 6" of soil are
to be pressure treated. In that the framing
members are above 6", TSCI asked if pressure
5.51c. treated material is necessary. Following 03/24/05 TSCI
discussion, it was determined that pressure
treated material is not required and a credit for
the pressure treating should be submitted since
the original plans required pressure treated
material.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
g ure
Name: Larry E. ampbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0 9
PROGRESS MEETING MINUTES
Meeting #: 52
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: March 24, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File # 15.6
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Temecula Temecula Martin Betz, City of Temecula
Ed Deleeuw,Tovey Shultz Kevin Terry, Tovey Shultz Sean Park, FSY Architects Larry Campbell,Vanir
Construction, Inc (TSCI) Construction, Inc(TSCI) (FSY) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
52 1.0 Approval Of Previous Meeting Minutes:
1.52 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 51.
2.0 Construction Progress Update:
Framing for the Scene Shop continued and the
installation of cedar siding at the
Restroom/Concession Building began today.
Rough in of sub-slab power, lighting, and AN at
the Audience Chamber is in progress and electrical
rough in at the Scene Shop has begun. Hollow
metal door frame installation has continued at the
Classroom Building and Scene Shop. Rough-in for Info
2.52 plumbing at the Scene Shop and gas piping at the N/A
Classroom, Concession, and Restroom Building is
in progress. CMU walls have been grouted and
some wall backfill has been accomplished. Vapor
barrier and flashing have been installed the
Concession/Restroom Building and framing for the
stage is in progress. Installation of lightweight
concrete for the Classrooms in presently in
progress.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Framing for the Scene Shop and installation of
3a.52a. siding will continue. Underground electrical rough- N/A Info
in for interior slabs will continue through the end of
next week. Rough-in of electrical and plumbing for
the Scene Shop will continue and HVAC at the
Scene Shop is scheduled to begin Monday, 03/28.
Page 1 of 5
VAN 1 R •OGRESS MEETING MINUTES•
Meeting#: 52
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
52 3a. Schedule Review (Continued)
Framing inspection is tentatively scheduled for
Wednesday, 03.30.05 and rough electrical
3a.52a inspection for 03.31.05. Drilling for the elevator N/A Info
cylinder is scheduled for Monday, 03.28.05 and
concrete for the stage area tentatively scheduled
for Friday, 04.01.05.
TSCI's schedule update for the period ended 02.28.05 will be
submitted early next week. (03.03.05)
TSCI's schedule update for the period through March 2, 2005
was received and is being reviewed. (03.03.05)
3a.50b. Schedule review comments are expected tomorrow and will be 03/31/05 TSCI
forwarded to TSCI. (03.10.05)
VCM review comments were forwarded to TSCI yesterday,
03.23.05 with required corrections noted. (03.24.05)
31b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 126 submittals (including
resubmittals) have been received to date. At this
date, there are two submittals outstanding.
3b.52 Submittal 65R (Irrigation) has been outstanding 03/30/05 FSY
for two weeks. Questions regarding two items in
this submittal were forwarded to the City of
Temecula for clarification during the course of
the meeting.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 380 RFI's (including revisions) have
been submitted to date. 9 RFI's are outstanding.
3c.52 Of the nine, 3 have been outstanding in excess 03/30/05 FSY
of two weeks. RFI 320 requesting details for
waterproofing the telephone closet is the longest
outstanding at 31 days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.52 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Twelve Architect's Supplemental Instructions
(ASI) have been issued as of this date. Of the
3d.1.52 twelve, 8 are in approved or pending change 03/31/05 TSCl/VCM
orders. 1 reflects corrective work required and 3
are awaiting pricing.
Page 2 of 5 VANIR r 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 52
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
52 3d.2 Construction Bulletins
Twenty four Construction Bulletins have been
issued. Of the twenty four, 10 are in previously
3d.2.52 approved or pending change orders. Three 03/31/05 TSCINCM
have been superseded, 1 is pending A/E
revision and nine are being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 9 incorporating 12 change
order requests has been drafted and forwarded City of
3e.1.52 to the City of Temecula for review and 03/31/05 Temecula
processing.
3e.2 Proposed Change Orders
One hundred eleven potential change requests
have been identified. Of those, pricing for 71
has been submitted. Of the 71 submitted, 53
have been incorporated into executed or
pending Change Orders, 7 have been rejected,
3e.2.52 4 have been rescinded and 7 are pending 03/31/05 TSCINCM
negotiation. 26 of the 109 have been voided
and 14 of the 109 potential changes are pending
pricing.
3e.3 Disputed Items
TSCI has identified six of the rejected change
3e.3.46 order requests as potential dispute items. N/A Info
3f Payment Status Review:
3f.50 TSCI's Payment Request No. 12 is being 04/04/05 City of
processed by the City of Temecula. Temecula
3g Notice Of Non Conformance Status:
3 51 There are no outstanding correction notices at N/A Info
g this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.51 and are prerequisite to inspections. N/A Info
Page 3 of 5 VANIR F 503
VAN 1 R •OGRESS MEETING MINUTES•
Meeting#: 52
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
52 3i Safety Items:
Safety items are discussed formally at the Weekly
3i.52 Foreman's Meeting held every Tuesday. There are N/A Info
no outstanding safety issues at this time.
4.0 Testing/Inspection:
Kleinfelder has been on site during the past
4.52 week for grout inspection. N/A Info
5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
Design concept and final design proposal were approved by
5.25b the City Council on 02.08.05. Design development is in 03/31/05 FSY
progress. (02.10.05)
S. Park advised that drawings have been sent to the various
consultants with submission of plans to the Building
Department scheduled for month end. 03.10.05
Fall prevention points at the balcony level: FSY
will review railings required to prevent falls at the
balcony level and issue a bulletin reflecting
5.47b those railings required. 02/28/05 FSY
Bulletin No.24 was received from FSY on 02.23.05.
Following discussion during the meeting,this bulletin
requires revision for type of protection and location.
02.24.05
Counter height at Concession: TSCI questioned
whether the counter height at the Concession
Bldg (currently shown at 3'-6") should be at 2'-
10" to meet ADA requirements. Following
5.50a discussion, it was determined that this issue will 03/24/05 FSY
be raised with the Building Inspector.
Following discussion, Building&Safety Inspector Bob
Henderson advised that the counters should be at T-10"
to comply with ADA requirements. 03.17.05
Trench patches @ Fourth Street: D. McBride
5.50b noted that trench patches in Fourth Street have 03/14/05 TSCI
deteriorated and need to be addressed.
Decorative benches: Following discussion, it
5.51a was determined that the City of Temecula will 03/24/05 City of
make a decision and provide direction. Temecula
Artesian Fountain: TSCI advised that the
fountain will not work properly as designed.
5.51b. Following discussion, it was determined that 03/24/05 TSCI
TSCI will review alternative designs that fall
within the budget.
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 52
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
52 5.0 New Business: (Continued)
Decking at Mercantile Bldg: TSCI noted that
Bldg. & Safety Inspector, Bob Henderson,
advised that framing member within 6" of soil are
to be pressure treated. In that the framing
members are above 6", TSCI asked if pressure
5.51c. treated material is necessary. Following 03/24/05 TSCI
discussion, it was determined that pressure
treated material is not required and a credit for
the pressure treating should be submitted since
the original plans required pressure treated
material.
Siding Joints: TSCI noted that the drawings
indicate that the cedar siding members butt
together in a straight line. Concern was
expressed regarding the potential for leaks
resulting from this installation. It was noted that
with changes in weather, the joints will open due
to shrinkage of the cedar and that the material
5.51d will have a tendency to warp and cup. TSCI N/A Info
questioned whether a t-flashing should be
installed at the butt joints. VCM will follow up
with FSY to ascertain the design intent.
Following several discussions with FSY it was determined
at siding will be butted without flashing with a 1/8 inch
gap at the butt joint. 03.24.05
Utilities to Mercantile Bldg: VCM questioned
whether or not water and gas stub-outs to the
Mercantile Building are still required given the
new use of the space. Following discussion, it
5.51e was determined that these utility stub-outs will N/A Info
be installed.
Pricing for installation of gas and water to the Mercantile
Building is included in Change Order No.9 03.24.05
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. /n the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
i/ �g ure
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting#: 51
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: March 17, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Steve Tovey,Tovey Shultz
Temecula Temecula Construction, Inc. (TSCI)
Ed Deleeuw,Tovey Shultz Kevin Terry,Tovey Shultz Larry Campbell,Vanir
Construction, Inc(TSCI) Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
51 1.0 Approval Of Previous Meeting Minutes:
1.51 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 50.
2.0 Construction Progress Update:
Framing for the Scene Shop and Corridor 113
continued as has the installation of tongue and
groove sheathing at the Restroom/Concession
Building. Rough in of sub-slab power, lighting, and
AN at the Stage Area has continued Hollow metal
door frames are being installed at the Restroom, Info
2.51 Concession, and Classroom Buildings. Installation N/A
of gas and water piping between buildings is in
progress with Building Department inspection
scheduled for later today. Backfill of walls, grading,
and removal of excess dirt are in progress and
grouting of CMU walls at the donor and dancer
walls is in progress.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Framing for the Scene Shop and Corridor 113 will
continue through the next week as will the
installation of hollow metal door frames.
3a.51 a. Underground electrical rough-in for interior slabs N/A Info
will continue through the end of next week.
Concrete for the orchestra pit slab and ramp walls
is scheduled for tomorrow. Rough-in of electrical,
plumbing, and HVAC at the Scene Shop is
scheduled to begin Monday, 03/21 and continue for
the next two weeks.
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 51
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
51 3a. Schedule Review (Continued)
Metal flashing at the roofs is scheduled to begin
Monday, 03.21.05 and continue through the week.
3a.50a Installation of exterior vapor barrier is scheduled to N/A Info
begin Monday, 03.21.05 to be followed by the
installation of wall insulation.
TSCI's schedule update for the period ended 02.28.05 will be
submitted early next week. (03.03.05)
TSCI's schedule update for the period through March 2, 2005
3a.50b. was received and is being reviewed. (03.03.05) 03/11/OS VCM
Schedule review comments are expected tomorrow and
will be forwarded to TSCI. 03.10.05
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 125 submittals (including
3b.51 resubmittals) have been received to date. As this 03/23/05 FSY
date, there are four submittals outstanding all of
which have been outstanding less than two
weeks.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 372 RFI's (including revisions) have
been submitted to date. 10 RFI's are
3c.51 outstanding. Of the ten, 4 have been 03/23/05 FSY
outstanding in excess of two weeks. RFI 296
requesting details for display cases is the
longest outstanding at 66 days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.51 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Twelve Architect's Supplemental Instructions
(ASI) have been issued as of this date. Of the
3d.1.51 twelve, 8 are in approved or pending change 03124/05 TSCINCM
orders. 1 reflects corrective work required and 3
are awaiting pricing.
3d.2 Construction Bulletins
Twenty four Construction Bulletins have been
issued. Of the twenty four, 10 are in previously
3d.2.51 approved or pending change orders. Three 3/25/05 TSCINCM
have been superseded, 1 is pending A/E
revision and nine are being priced.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE
Meeting#: 51
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
51 3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 8 reflecting payment for costs
3e.1.49 incurred by B&A Construction for channel work N/A Info
has been executed by TSCI and the City of
Temecula.
3e.2 Proposed Change Orders
One hundred nine potential change requests
have been identified. Of those, pricing for 69
has been submitted. Of the 69 submitted, 51
have been incorporated into executed or
3e.2.51 pending Change Orders, 7 have been rejected, 03/25/05 TSCINCM
4 have been rescinded and 7 are pending
negotiation. 26 of the 109 have been voided
and 14 of the 109 potential changes are pending
pricing.
3e.3 Disputed Items
TSCI has identified six of the rejected change
3e.3.46 order requests as potential dispute items. N/A Info
3f Payment Status Review:
3f.50 TSCI's Payment Request No. 12 is being 04/04/05 City of
processed by the City of Temecula. Temecula
3g Notice Of Non Conformance Status:
3 51 There are no outstanding correction notices at N/A Info
g this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.51 and are prerequisite to inspections. N/A Info
50 31 Safety Items:
Safety items are discussed formally at the Weekly
3i.50 Foreman's Meeting held every Tuesday. There are N/A Info
no outstanding safety issues at this time.
4.0 Testing/Inspection:
Kleinfelder has been on site during the past
4.50 week for masonry inspection. N/A Info
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 51
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
51 5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
Design concept and final design proposal were approved by
5.25b the City Council on 02.08.05. Design development is in 03/31/05 FSY
progress. (02.10.05)
S. Park advised that drawings have been sent to the various
consultants with submission of plans to the Building
Department scheduled for month end. 03.10.05
Fall prevention points at the balcony level: FSY
will review railings required to prevent falls at the
balcony level and issue a bulletin reflecting
5.47b those railings required. 02/28/05 FSY
Bulletin No.24 was received from FSY on 02.23.05.
Following discussion during the meeting,this bulletin
requires revision for type of protection and location.
02.24.05
Counter height at Concession: TSCI questioned
whether the counter height at the Concession
Bldg (currently shown at T-6") should be at 2'-
10" to meet ADA requirements. Following
5.50a discussion, it was determined that this issue will 03/24/05 FSY
be raised with the Building Inspector.
Following discussion, Building &Safety Inspector Bob
Henderson advised that the counters should be at T-10"
to comply with ADA requirements. 03.17.05
Trench patches @ Fourth Street: D. McBride
5.50b noted that trench patches in Fourth Street has 03/14/05 TSCI
deteriorated and need to be addressed.
Decorative benches: Following discussion, it City of
5.51a was determined that the City of Temecula will 03/24/05 Temecula
make a decision and provide direction. .
Artesian Fountain: TSCI advised that the
fountain will not work properly as designed.
5.51 b. Following discussion, it was determined that 03/24/05 TSCI
TSCI will review alternative designs that fall
within the budget.
Decking at Mercantile Bldg: TSCI noted that
Bldg. & Safety Inspector, Bob Henderson,
advised that framing member within 6" of soil are
to be pressure treated. In that the framing
members are above 6", TSCI asked if pressure
5.51c. treated material is necessary. Following 03/24/05 TSCI
discussion, it was determined that pressure
treated material is not required and a credit for
the pressure treating should be submitted since
the original plans required pressure treated
material.
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 51
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
51 5.0 New Business: (Continued)
Siding Joints: TSCI noted that the drawings
indicate that the cedar siding members butt
together in a straight line. Concern was
expressed regarding the potential for leaks
resulting from this installation. It was noted that
5.51d with changes in weather, the joints will open due 03/18/05 VCM
to shrinkage of the cedar and that the material
will have a tendency to warp and cup. TSCI
questioned whether a t-flashing should be
installed at the butt joints. VCM will follow up
with FSY to ascertain the design intent.
Utilities to Mercantile Bldg: VCM questioned
whether or not water and gas stub-outs to the
5.51e Mercantile Building are still required given the N/A Info
new use of the space. Following discussion, it
was determined that these utility stub-outs will
be installed.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
atur�
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR • R
PROGRESS MEETING MINUTES
Meeting#: 50
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: March 10, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
Temecula Construction, Inc(TSCI) Construction, Inc(TSCI)
Sean Park, FSY Architects Larry Campbell,Vanir
(FSY) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
50 1.0 Approval Of Previous Meeting Minutes:
1.50 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 49.
2.0 Construction Progress Update:
Framing for the Scene Shop has continued and
framing for Corridor 113 is in progress. Installation
of the tongue and groove sheathing at the
Restroom/Concession Building overhang is in
progress. The rough in of power, lighting, and fire
alarm at the Classroom Building has continued and
excavation for sub-slab electrical at the stage area
began today. Rigid insulation has been installed at Info
2.50 the Fly loft, plywood doubled and roofing felt is N/A
scheduled to begin tomorrow. Built-up roofing has
been installed at the Classroom, Restroom, and
Concession Buildings. Installation of the cap sheet
for the Restroom/Concession Building is scheduled
for tomorrow. Work on critical path activities
resumed today with the excavation of the sub-slab
electrical at the Stage area and the backfill of CMU
walls at the Audience Chamber and property walls.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
reviewed during the course of the meeting.
Framing for the Scene Shop and Corridor 113 will
3a.50a. continue through next. The installation of built-up N/A Info
roofing for the high roof at the Fly loft will also
continue through next Friday. Underground
electrical rough-in for interior slabs will continue
through the end of next week.
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 50
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
50 3a. Schedule Review (Continued)
Masonry walls for the donor and dancer walls will
resume on Monday, 03.14.05 and is scheduled to
continue for the next two weeks. Layout, forming,
and preparation for interior slabs is scheduled to
begin tomorrow, 03.11.05 with concrete placement
3a.50a scheduled for the week of 03.21.05. Metal flashing N/A Info
at the roofs is scheduled to begin Monday,
03.14.05 and continue through the week. Rough-in
of electrical, plumbing, and HVAC at the Scene
Shop will begin on Monday, 03.14.05 and continue
for an estimated two week period.
TSCI's schedule update for the period ended 02.28.05 will be
submitted early next week. (03.03.05)
TSCI's schedule update for the period through March 2, 2005
3a.50b. was received and is being reviewed. (03.03.05) 03/11/05 VCM
Schedule review comments are expected tomorrow and
will be forwarded to TSCI. 03.10.05
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 124 submittals (including
3b.50 resubmittals) have been received to date. As this 03/4/05 FSY
date, there are three submittals outstanding that
were forwarded to the A/E during the course of
the meeting.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 362 RFI's (including revisions) have
been submitted to date. 5 RFI's are outstanding.
3c.50 Of the five, 1 has been outstanding in excess of 03/14/05 FSY
two weeks. RFI 296 requesting details for
display cases is the longest outstanding at 59
days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.50 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Twelve Architect's Supplemental Instructions
(ASI) have been issued as of this date. Of the
3d.1.50 twelve, 8 are in approved or pending change 03/18/05 TSCl/VCM
orders. 1 reflects corrective work required and 3
are awaiting pricing.
Page 2 of 5 VANIR F 503
VAN 1 R •OGRESS MEETING MINUTES•
Meeting#: 50
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
3d.2 Construction Bulletins
Twenty four Construction Bulletins have been
issued. Of the twenty four, 10 are in previously
3d.2.50 approved or pending change orders. Three 3/18/05 TSCINCM
have been superseded, 1 is pending A/E
revision and nine are being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 8 reflecting payment for costs
incurred by B&A Construction for channel work
3e.1.49 has been executed by TSCI and the City of N/A Info
Temecula.
3e.2 Proposed Change Orders
One hundred seven potential change requests
have been identified. Of those, pricing for 82
has been submitted. Of the 82 submitted, 43
have been incorporated into executed or
3e.2.50 pending Change Orders, 9 have been rejected, 03/18/05 TSCINCM
1 has been rescinded, 13 have been voided and
6 are pending negotiation. 11 of the COR's
identified have been voided prior to submission.
14 of the 107 potential changes are pending
pricing.
3e.3 Disputed Items
TSCI has identified six of the rejected change
3e.3.46 order requests as potential dispute items. N/A Info
3f Payment Status Review:
3f.50 TSCi's Payment Request No. 12 is being 04/04/05 City of
processed by the City of Temecula. Temecula
3g Notice Of Non Conformance Status:
3 50 There are no outstanding correction notices at N/A Info
S this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.50 and are prerequisite to inspections. N/A Info
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 50
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
50 3i Safety Items:
Safety items are discussed formally at the Weekly
3i.50 Foreman's Meeting held every Tuesday. There are N/A Info
no outstanding safety issues at this time.
4.0 Testing/Inspection:
Kleinfelder has been on site during the past
4.50 week for soils inspection. N/A Info
5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
Design concept and final design proposal were approved by
the City Council on 02.08.05. Design development is in
5.25b progress. (02.10.05) 03/31/05 FSY
S. Park advised that drawings have been sent to the
various consultants with submission of plans to the
Building Department scheduled for month end. (03.10.05)
Fall prevention points at the balcony level: FSY
will review railings required to prevent falls at the
balcony level and issue a bulletin reflecting
those railings required.
5.47b 02/28/05 FSY
Bulletin No.24 was received from FSY on 02.23.05.
Following discussion during the meeting,this bulletin
requires revision for type of protection and location.
(02.24.05)
Counter height at Concession: TSCI questioned
whether the counter height at the Concession
Bldg (currently shown at 3'-6") should be at 2'-
5.50a 10" to meet ADA requirements. Following 03/17/05 TSCI
discussion, it was determined that this issue will
be raised with the Building Inspector.
Trench patches @ Fourth Street: D. McBride
5.50b noted that trench patches in Fourth Street has 03/14/05 TSCI
deteriorated and need to be addressed.
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 50
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
g ure
Name: Larry E. ampbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR + r
PROGRESS MEETING MINUTES
Meeting#: 49
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: March 3, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: None
Attendees: Bruce Beers,City of Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
Temecula Construction, Inc(TSCI) Construction, Inc (TSCI)
Arturo Yanez, FSY Larry Campbell, Vanir
Architects(FSY) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
49 1.0 Approval Of Previous Meeting Minutes:
1.49 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 48.
2.0 Construction Progress Update:
Framing for the Scene Shop has continued as has
the rough in of power, lighting, and fire alarm at the
2nd floor of the Classroom Building. Installation of
windows at the Classroom Building occurred on
Monday. CMU walls at the elevator pit have been
2.49 constructed and grouted and waterproofing is in N/A Info
progress. Rigid insulation has been installed at the
Audience Chamber, plywood doubled and roofing
felt is presently being installed. There has been no
work performed on critical path activities since the
last meeting due to rain and wet, muddy
conditions.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
presented and reviewed during the course of the
meeting. Framing will continue for the next several
weeks. Backfill of masonry walls, scheduled to
begin on 03.07.05 began today. Similarly,
installation of rigid insulation at the Audience
3a.49a Chamber began yesterday as did the doubling of N/A Info
plywood for the roof with installation of roofing felt
starting today. Installation of hollow metal frames
is scheduled to begin 03.07.05 as is underground
electrical at the stage area. Waterproofing of the
elevator pit is currently in progress. Built-up
roofing on the low roofs is scheduled for Monday.
Page 1 of 5
VAN I R OPROGRESS MEETING MINUTE•
Meeting#: 49
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
49 3a. Schedule Review (Continued)
TSCI's monthly schedule update for the period
ended 01/31/054 was received 02/02/05. The
schedule update reflects project completion July
14, 2005; approximately two weeks beyond the
current contract completion date.
3a.45b. The critical path as reflected by this schedule update is 03/09/05 TSCI
through the work in the Audience Chamber. This work has
been delayed during the week due to muddy conditions
preventing the backfill of masonry walls, and grading and sand
placement for the slab on grade. (02.17.05)
TSCI's schedule update for the period ended 02.28.05 will
be submitted early next week. (03.03.05)
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 120 submittals (including
resubmittals) have been received to date. The
3b.49 three outstanding submittals were returned N/A Info
during the course of the meeting. At this date,
there are no outstanding submittals.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 357 RFI's (including revisions) have
been Submitted to date. 3 RFI's are outstanding.
3c.49 Of the three, 2 have been outstanding in excess 03/07/05 FSv
of two weeks. RFI 296 requesting details for
display cases is the longest outstanding at 52
days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.49 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Twelve Architect's Supplemental Instructions
(ASI) have been issued as of this date. Of the
3d.1.49 twelve, 8 are in approved or pending change 03/11/05 TSCINCM
orders. 1 remains to be negotiated and 3 are
awaiting pricing.
Page 2 of 5 VANIR F 503
VAN I R PROGRESS MEETING MINUTES•
Meeting#: 49
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
49 3d.2 Construction Bulletins
Twenty three Construction Bulletins have been
issued. Of the twenty three, 8 are included in
previously approved change orders. Three of
the twenty-three are in pending Change Order
3d.2.49 No. 9 and are being revised, Four have been 3/11/05 TSCINCM
submitted for review and approval, and eight are
being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 8 reflecting payment for costs
3e.1.49 incurred by B&A Construction for channel work 03/04/05 TSCI
has been mailed to TSCI for signature.
3e.2 Proposed Change Orders
One hundred four potential change requests
have been identified. Of those, pricing for 62
has been submitted. Of the 62 submitted, 38
have been incorporated into executed or
pending Change Orders, 6 have been rejected,
3e.2.49 1 has been rescinded, and 17 are pending 03/11/05 TSCINCM
negotiation. 27 of the COR's identified have
been voided. 15 of the 104 potential changes
are pending pricing.
3e.3 Disputed Items
3e.3.46 TSCI has identified six of the rejected change N/A Info
order requests as potential dispute items.
3f Payment Status Review:
3f.49 TSCI's Payment Request No. 12 was forwarded 04/04/05 City of
to the City of Temecula for processing today. Temecula
3g Notice Of Non Conformance Status:
3 .49 There are no outstanding correction notices at N/A Info
g this date.
3h As Built Status Review:
3h.49 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
Page 3 Of 5 VANIR F 503
VAN i R PROGRESS MEETING MINUTES•
Meeting#: 49
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
49 3i Safety Items:
Safety items are discussed formally at the Weekly
3i.49 Foreman's Meeting held every Tuesday. There are N/A Info
no outstanding safety issues at this time.
4.0 Testing/Inspection:
Kleinfelder has been on site during the past
4.49 week for masonry inspection. N/A Info
5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
5.25b Design concept and final design proposal were approved by 03/10/05 FSY
the City Council on 02.08.05. Design development is in
progress. (02.10.05)
Fall prevention points at the balcony level: FSY
will review railings required to prevent falls at the
balcony level and issue a bulletin reflecting
those railings required.
5.47b 02/28/05 FSY
Bulletin No.24 was received from FSY on 02.23.05.
Following discussion during the meeting,this bulletin
requires revision for type of protection and location.
(02.24.05)
Roll up door at Concession: The contract
drawings reflect the height of the roll-up door at
the Concession Bldg. as 5-0". During the
submittal process, the height of the door was
5.49a changed to 6'-2". Following discussion N/A Info
regarding ceilings heights, it was agreed that the
door will remain at 5"-0" per the contract
drawings.
Quarry Tile: TSCI advised that the quarry tile
shown in the finish schedule is 8"xW. The
5.49b selected tile color is only available in 6"x6". N/A Info
Following discussion, FSY concurred that 6"x6"
is acceptable.
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 49
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
S' ature
Name: LarrZECampbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR R
PROGRESS MEETING MINUTES
Meeting#: 48
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: February 24, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Kevin Terry,Tovey Shultz
Temecula Temecula Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc (TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
48 1.0 Approval Of Previous Meeting Minutes:
1.48 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 47.
2.0 Construction Progress Update:
Framing for the Scene Shop and construction of
the covered walkway at the Restroom/Concession
Building resumed today as did the rough in of
power, lighting, and fire alarm at the 2ntl floor of the Info
2.48 Classroom Building. There has been no other N/A
work performed on critical path activities since the
last meeting due to rain and wet, muddy
conditions.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
presented and reviewed during the course of the
meeting. Framing will continue for the next several
weeks. Installation of masonry walls will resume
on Monday however, the backfill of masonry walls
will be delayed for approximately another week to
allow for drying. Installation of sub-slab electrical is
3a.48a scheduled to begin Monday. Installation of hollow N/A Info
metal frames is scheduled to begin 03.07.05 as is
the installation of rigid insulation at the Audience
Chamber and the installation of built up roofing at
the low roofs. Waterproofing of the elevator pit is
tentatively scheduled to begin 03.07.05 and work
on the orchestra pit and stage slabs is tentatively
scheduled to begin 03.14.05.
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 48
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
48 3a. Schedule Review (Continued)
TSCI's monthly schedule update for the period
ended 01/31/054 was received 02/02/05. The
schedule update reflects project completion July
14, 2005; approximately two weeks beyond the
current contract completion date.
3a.45b. The critical path as reflected by this schedule update is N/A Info
through the work in the Audience Chamber. This work
has been delayed during the week due to muddy
conditions preventing the backfill of masonry walls, and
grading and sand placement for the slab on grade.
(02.17.05)
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 120 submittals (including
resubmihals) have been received to date. At this
3b.48 date, 3 submittals remain outstanding. 02/28/05 FSY
Submittal No. 52B, Waterproofing Substitution,
has been outstanding for 43 days.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 356 RFI's (including revisions) have
been submitted to date. 4 RFI's are outstanding.
Of the four, 3 have been outstanding in excess
3c.48 of two weeks. RFI 296 requesting details for 02/28/05 FSY
display cases is the longest outstanding at 45
days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.48 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Twelve Architect's Supplemental Instructions
(ASI) have been issued as of this date. Of the
3d.1.48 twelve, 8 are in approved or pending change 2/25/05 TSCINCM
orders. 1 remains to be negotiated and 3 are
awaiting pricing.
Page 2 of 5 VANIR F 503
VAN 1 R •OGRESS MEETING MINUTES•
Meeting#: 48
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
48 3d.2 Construction Bulletins
Twenty three Construction Bulletins have been
issued. Of the twenty three, 8 are included in
previously approved change orders. Three of
3d.2.48 the twenty are in pending Change Order No. 9 3/04/05 TSCINCM
and are being revised, Two have been
submitted for review and approval, and eight are
being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 8 has been drafted and was
forwarded to the City of Temecula Monday,
01.10.05 for review and processing.
Change Order No. 8 was returned to TSCl/FSY for
3e.1.42 revision and repricing of some items on 01.19.05. 03/04/05 TSCI
Supplemental drawings and/or clarifications are
being prepared by FSY. (02.03.05)
Change Order No. 8 reflecting payment for costs
incurred by B&A Construction for channel work
has been mailed to TSCI for signature. 02.24.05
3e.2 Proposed Change Orders
One hundred two potential change requests
have been identified. Of those, pricing for 61
has been submitted. Of the 61 submitted, 38
have been incorporated into executed or
3e.2.48 pending Change Orders, 6 have been rejected, 03/04/05 TSCINCM
1 has been rescinded, 15 are pending
negotiation and 1 is being re-priced. 24 of the
COR's identified have been voided. 17 of the
102 potential changes are pending pricing.
3e.3 Disputed Items
TSCI has identified six of the rejected change
3e.3.46 order requests as potential dispute items. N/A Info
3f Payment Status Review:
TSCI's draft Payment Request No. 12 was
3f.48 reviewed following the meeting. TSCI to make 03/038/05 TSCI
corrections and submit for processing.
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 48
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
48 3g Notice Of Non Conformance Status:
3 48 There are no outstanding correction notices at N/A Info
g this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.48 and are prerequisite to inspections.
N/A Info
3i Safety Items:
3i.48 There are no outstanding safety issues at this time. N/A Info
4.0 Testing/Inspection:
4.48 Kleinfelder has not been on site during the past N/A Info
week due to weather conditions.
5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
Dean Lee advised that he has received the schematic design
and a fee proposal is being prepared. (01.20.05)
5.25b D. McBride advised that the design concept and final design 03/03/05 FSY
proposal is scheduled for City Council action on Tuesday,
02/08/05. (02.03.05)
Design concept and final design proposal were approved
by the City Council on 02.08.05. Design development is in
progress. 02.10.05
Waterproofing at decks: There was discussion
regarding waterproofing of decks. FSY will review
and advise the type and location of waterproofing
required.
5.47a Following discussion, it was determined that Deck-O-Tex 02/22/05 FSY
will be added to the decks to provide the waterproofing
required and the area drains will be changed accordingly.
This item will be deleted from future meeting discussion.
(02.24.05)
Fall prevention points at the balcony level: FSY
will review railings required to prevent falls at the
balcony level and issue a bulletin reflecting
those railings required.
5.47b 02/28/05 FSY
Bulletin No. 24 was received from FSY on 02.23.05.
Following discussion during the meeting,this bulletin
requires revision for type of protection and location.
(02.24.05)
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 48
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Wood cap for railings. The response to RFI 303
reversed the type of wood cap at railings in the
Audience Chamber. Following discussion, it was
48 5.48a determined that the round cap as depicted in detail 02/25/05 VCM
1/A5.10 is the preferred cap to be used throughout
the Audience Chamber. VCM will advise FSY of
this decision.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
/ re
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR i
PROGRESS MEETING MINUTES
Meeting#: 47
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: February 17, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers,City of Steve Tovey,Tovey Shultz
Temecula Temecula Construction, Inc. (TSCI)
Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Arturo Yanez, FSY Dean Lee, FSY Architects (FSY)
Construction, Inc(TSCI) Construction, Inc (TSCI) Architects(FSY)
Sean Park, FSY Architects Armineh Gharibans, ENA Larry Campbell,Vanir
(FSY) Group(ENA) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
47 1.0 Approval Of Previous Meeting Minutes:
1.47 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 46.
2.0 Construction Progress Update:
Framing for the Scene Shop and construction of
the covered walkway at the Restroom/Concession
Building has continued. Rigid insulation and roofing
felt has been installed at the Dance Studio.
Construction of masonry walls at the Audience
Chamber, property walls, and trash enclosure has Info
2.47 continued and the first lift of the walls has been N/A
grouted. Rough in of power, lighting, and fire alarm
at the 2°d floor of the Classroom Building is
continuing. Campbell Certified has installed
missing bolts and begun cold galvanizing of welds.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
presented and reviewed during the course of the
meeting. Framing will continue for the next several
weeks. Installation of masonry walls will continue
through next week. Backfill of masonry walls is
3a.47a scheduled to begin on Monday as is installation of N/A Info
built-up roofing at the flat roofs. Installation of sub-
slab electrical is scheduled to begin Monday to be
followed by grading, sand placement, rebar
installation and template installation for the stage
and orchestra pit. Installation of hollow metal
frames is scheduled to begin 02.28.05.
Page t of 5
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 47
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
47 3a. Schedule Review (Continued)
TSCI's monthly schedule update for the period
ended 01/31/054 was received 02/02/05. The
schedule update reflects project completion July
14, 2005; approximately two weeks beyond the
current contract completion date.
3a.45b. The critical path as reflected by this schedule update is N/A Info
through the work in the Audience Chamber. This work
has been delayed during the week due to muddy
conditions preventing the backfill of masonry walls, and
grading and sand placement for the slab on grade.
(02.17.05)
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 120 submittals (including
resubmittals) have been received to date. At this
date, 6 submittals remain outstanding.
3b.47 Submittal No. 52B, Waterproofing Substitution, 02/22/05 FSY
and Submittal No. 63, Dura Tex Hardboard have
all been outstanding for 36 days. Submittal Nos.
64 and 65 were returned during the course of
the meeting.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 355 RFI's (including revisions) have
been submitted to date. 7 RFI's are outstanding.
3c.47 Of the seven, 3 have been outstanding in 02/21/05 FSY
excess of two weeks. RFI 296 requesting
details for display cases is the longest
outstanding at 38 days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.47 Both of these items have been included in N/A Info
revio sly approved change orders.
3d.1 Architect's Supplemental Instructions
Twelve Architect's Supplemental Instructions
(ASI) have been issued as of this date. Of the
3d.1.47 twelve, 8 are in approved or pending change 2/25/05 TSCINCM
orders. 1 remains to be negotiated and 3 are
awaiting pricing.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 47
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
3d.2 Construction Bulletins
Twenty two Construction Bulletins have been
issued. Of the twenty two, 8 are included in
previously approved change orders. Three of
47 3d.2.47 the twenty are in pending Change Order No. 8 2/25/05 TSCINCM
and are being revised, Two have been
submitted for review and approval, and seven
are being priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 8 has been drafted and was
forwarded to the City of Temecula Monday,
01.10.05 for review and processing.
3e.1.42 02/25/05 FSY/TSCI
Change Order No. 8 was returned to TSCl/FSY for
revision and repricing of some items on 01.19.05.
Supplemental drawings and/or clarifications are
being prepared by FSY. 02.03.05
3e.2 Proposed Change Orders
One hundred potential change requests have
been identified. Of those, pricing for 59 has
been submitted. Of the 59 submitted, 38 have
been incorporated into executed or pending
3e.2.47 Change Orders, 6 have been rejected, 1 has 02/25/05 TSCINCM
been rescinded, 11 are pending negotiation and
3 are being re-priced. 24 of the COR's identified
have been voided. 17 of the 100 potential
changes are pending pricing.
3e.3 Disputed Items
3e.3.46 TSCI has identified six of the rejected change N/A Info
order requests as potential dispute items.
3f Payment Status Review:
TSCI's Payment Request No. 11 was reviewed
3f.46 and forwarded to the City of Temecula for 03/08/05 City of
payment on February 8. Temecula
3g Notice Of Non Conformance Status:
3g'47 There are no outstanding correction notices at N/A Info
this date.
Page 3 of 5 VANIR F 503
VANIR PROGRESS MEETING MINUTES•
Meeting#: 47
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
47 3h As Built Status Review:
Revisions are being posted on a regular basis
3h.47 and are prerequisite to inspections.
NIA Info
3i Safety Items:
3i.47 There are no outstanding safety issues at this time. N/A Info
4.0 Testing/Inspection:
Kleinfelder has been on site during the past
4.46 week for masonry inspection. N/A Info
5.0 New Business:
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
This work will be incorporated with pending revisions to the
Mercantile Building interior renovations. (12.02.04)
A revised schematic design for the interior renovations is being
undertaken by Bruce Beers. (01,06.05)
Dean Lee advised that he has received the schematic design
5.25b and a fee proposal is being prepared. (01.20.05) 03/03/05 FSY
D. McBride advised that the design concept and final design
proposal is scheduled for City Council action on Tuesday,
02/08/05. (02.03.05)
Design concept and final design proposal were approved
by the City Council on 02.08.05. Design development is in
progress.
Signage Revisions: Bruce Beers requested a
list of room names. FSY noted that the names
are shown both on the floor plan and finish
scheduled. Beers will review and determine
whether or not signage changes are required.
Bruce Beers will provide a list of signs to be revised and/or
deleted. This list will be reviewed by David McBride for
compliance with applicable codes. (01.27.05)
5.43a N/A Info
Bruce Beers provided a list of room name changes during the
course of the meeting. This list will be reviewed by D.
McBride, FSY, and the Building Department as required,and
direction provided. (02.03.05)
Bulletin No.23, reflecting signage changes,was
presented by FSY Architects during the course of the
meeting. This item will be deleted from future meeting
discussion. (02.17.05)
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 47
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Fall Protection for Ladder to Grid: B. Beers
questioned whether a fall cage or fall arrest
system is included for the ladder to the grid.
VCM will follow up with FSY to address this
issue.
47 5.44a N/A Info
TSCI was directed to provide pricing for a fall arrest
system. (02.03.05)
TSCI COR#100 reflecting pricing for fall protection was
received during the course of the meeting. This item will
be deleted from future meeting discussion. 02.17.05
Waterproofing at decks: There was discussion
5.47a regarding waterproofing of decks. FSY will 02/22/05 FSY
review and advise the type and location of
waterproofing required.
Fall prevention points at the balcony level: FSY
5.47b will review railings required to prevent falls at the 02/22/05 FSY
balcony level and issue a bulletin reflecting
those railings required.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
�jnature
Name: Larry E. Campbell _
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting#: 46
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: February 10, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File # 15.6
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Kevin Terry,Tovey Shultz
Temecula Temecula Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
46 1.0 Approval Of Previous Meeting Minutes:
1.46 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 45.
2.0 Construction Progress Update:
Roof framing at the Fly Loft, framing for the Scene
Shop, and construction of the covered walkway at
the Restroom/Concession Building has continued.
Plumbing rough-in has continued. Reinforcement
for ramp wall footings is complete and concrete
placement is in progress. Construction of masonry Info
2.46 walls at the Audience Chamber and property walls N/A
has continued and grouting in masonry walls is
scheduled for tomorrow, weather permitting.
Installation of windows for the Dance Studio and
Classroom Building has begun and installation of
rigid insulation is in progress at the Dance Studio.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
presented and reviewed during the course of the
meeting. Framing will continue for the next several
weeks. Installation of masonry walls will continue
through next week. Rigid insulation for the roofs
will continue for the next two weeks followed by the
3a.46a doubling up of plywood on the roofs. Grading, N/A Info
sand placement, rebar installation and template
installation for the stage and orchestra pit has
begun and will continue for the next two weeks.
Backfill of masonry walls is scheduled to begin mid
to late next week.
Page 1 of 5
VAN 1 R •OGRESS MEETING MINUTES•
Meeting#: 46
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
46 3a. Schedule Review (Continued)
TSCI's monthly schedule update for the period
ended 01/31/054 was received 02/02/05. The
schedule update reflects project completion July
3a.45b. 14, 2005; approximately two weeks beyond the 02/10/05 VCM
current contract completion date.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 119 submittals (including
resubmlttais) have been received to date. At this
3b.46 date, 5 submittals remain outstanding. 02/15/05 FSY
Submittal No. 52B, Waterproofing Substitution,
Submittal No. 63, Dura Tex Hardboard, and
Submittal No. 64, Paint Sample Brush-outs have
all been outstanding for 29 days.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 354 RFI's (including revisions) have
been submitted to date. 6 RFI's are outstanding.
3c.46 Of the six, 3 have been outstanding in excess of 02/14/05 FSY
two weeks. RFI 296 requesting details for
display cases is the longest outstanding at 31
days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.46 Both of these items have been included in N/A Info
previously approved change orders.
3d.1 Architect's Supplemental Instructions
Twelve Architect's Supplemental Instructions
(ASI) have been issued as of this date. Of the
3d.1.45 twelve, 8 are in approved or pending change 2/10/05 TSCINCM
orders. 1 remains to be negotiated and 3 are
awaiting pricing.
3d.2 Construction Bulletins
Twenty two Construction Bulletins have been
issued. Of the twenty two, 8 are included in
previously approved change orders. Three of
3d.2.46 the twenty are in pending Change Order No. 8 2/170/05 TSCINCM
and are being revised, Two have been
submitted for review and approval, and seven
are being priced.
Page 2 of 5 VANIR F 503
VANIR •OGRESS MEETING MINUTES•
Meeting#: 46
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
46 3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 8 has been drafted and was
forwarded to the City of Temecula Monday,
01.10.05 for review and processing.
3e.1.42 02/10/05 FSY/TSCI
Change Order No. 8 was returned to TSCl/FSY for
revision and repricing of some items on 01.19.05.
Supplemental drawings and/or clarifications are
being prepared by FSY. 02.03.05
3e.2 Proposed Change Orders
Ninety eight potential change requests have
been identified. Of those, pricing for 67 has
been submitted. Of those 67, 45 have been
incorporated into executed or pending Change
3e.2.46 Orders, 10 have been rejected, 1 has been 02/17/05 TSCINCM
rescinded, and 11 are pending negotiation. 18
of the COR's identified have been voided. 13 of
the 98 potential changes are pending pricing.
3e.3 Disputed Items
3e.3.46
TSCI has identified six of the rejected change
order requests as potential dispute items. N/A Info
3f Payment Status Review:
TSCI's Payment Request No. 11 was reviewed
3f.46 forwarded to the City of Temecula for payment 03/08/05 City of
on February 8. Temecula
3g Notice Of Non Conformance Status:
3 46 There are no outstanding correction notices at N/A Info
g' this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.46 and are prerequisite to inspections.
N/A Info
3i Safety Items:
3i.46 There are no outstanding safety issues at this time. N/A Info
4.0 Testing/Inspection:
Kleinfelder has been on site during the past
4.46 week for soils and mason ins ection. N/A Info
Page 3 of 5 VANIR F 503
VAN 1 R •OGRESS MEETING MINUTES•
Meeting#: 46
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
46 5.0 New Business:
See previous meeting minutes for ongoing discussion.
It has been determined that granite steps at the Dance Studio
will be replaced by lightly sandblasted concrete. TSCI is to
59.23b Provide alternate cost proposals utilizing the granite on site N/A Info
with wood integrated for seating panels per e-mail direction
from D. McBride dated 01.28.05. (02.03.05)
This item will be deleted from future meeting discussion
02.10.05
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
This work will be incorporated with pending revisions to the
Mercantile Building interior renovations. (12.02.04)
A revised schematic design for the interior renovations is being
undertaken by Bruce Beers. (01.06.05)
Dean Lee advised that he has received the schematic design
5.25b and a fee proposal is being prepared. (01.20.05) 03/03/05 FSY
D. McBride advised that the design concept and final design
proposal is scheduled for City Council action on Tuesday,
02/08/05. (02.03.05)
Design concept and final design proposal were approved
by the City Council on 02.08.05. Design development is in
progress.
Wheel Chair Lift:
5.32a See previous meeting minutes for full discussion. 02/25/05 TSCI
Bulletin No. 22 was issued 02.07.05. 02.10.05
Signage Revisions: Bruce Beers requested a
list of room names. FSY noted that the names
are shown both on the floor plan and finish
scheduled. Beers will review and determine
whether or not signage changes are required.
5.43a Bruce Beers will provide a list of signs to be revised and/or 02/17/05 FSY
deleted. This list will be reviewed by David McBride for
compliance with applicable codes. (01.27.05)
Bruce Beers provided a list of room name changes during
the course of the meeting. This list will be reviewed by D.
McBride, FSY, and the Building Department as required,
and direction provided. 02.03.05
Mezzanine Occupancy: Bruce Beers inquired
as to the maximum number of seats allowable at
the mezzanine level. FSY to review and advise.
5.43b N/A Info
A review of the Code Analysis reflects the maximum seats
at 49. This item will be deleted from future meeting
discussion. 02.10.05
Page 4 of 5 VANIR F 503
VAN 1 R •OGRESS MEETING MINUTES
Meeting#: 46
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Fall Protection for Ladder to Grid: B. Beers
questioned whether a fall cage or fall arrest
system is included for the ladder to the grid.
46 5.44a VCM will follow up with FSY to address this 02/10/05 TSCI
issue.
TSCI was directed to provide pricing for a fall arrest
system. 02.03.05
Dissolution of Turnkey Forces: D. McBride
questioned the schedule impact that may result
from the bankruptcy of the electrical
subcontractor, Turnkey Forces. TSCI advised
that it met with an alternate subcontractor this
morning and should know the impact, if any, that
may result from the loss of Turnkey within the
next two weeks.
5.44b N/A Info
TSCI advised that it is working with two firms to obtain
pricing for completing the work. It is intended that a new
electrical firm will be onsite by next Monday. (02.03.05)
TSCI advised that Tri-Citi Electric began work today.
The employees will be carried on TSCI payroll until
such time as Tri-Citi can obtain bonding and
Workers Compensation Insurance. This item will be
deleted from future meeting agendas. 02.10.05
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
ign re
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 45
Owner: itY of Temecula
Project: Old Town Temecula
Community Theater
Date: February 03, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.6
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Kevin Terry,Tovey Shultz
Temecula Temecula Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Dean Lee, FSY Architects Larry Campbell,Vanir
Construction, Inc (TSCI) (FSY) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
45 1.0 Approval Of Previous Meeting Minutes:
The Minutes of Meeting No. 44 are corrected as
follows:
Item 3e.1.42: Change Orders: The draft of Change
Order No. 8 was returned for revision and/or
revised cost proposals on 1/19105.
Item 5g.23b: City Supplied Granite: David
McBride will discuss with John Meyer and
1.45 determine the course of action. This issue was
followed up with an e-mail providing direction on N/A Info
01.28.05.
Item 5.25b: Mercantile Building Interior
Renovations: Approval of the conceptual design
and final design contract are on the 02.08.05 City
Council Agenda.
Item 5.43a: Signage Revisions: ADD:"FSY and/or
Building Department" following David McBride in
the 2nd sentence.
2.0 Construction Progress Update:
Roof framing at the Fly Loft and
Restroom/Concession Building has continued and
framing for the Scene Shop has begun. Plumbing
rough-in and testing has continued. Excavation Info
2.45 for footings for ramp walls is in progress and N/A
construction of masonry walls at the Audience
Chamber and property walls is in progress.
Construction of the new fence for the Pottery Shop
is in progress.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look-ahead schedule was
presented and reviewed during the course of the N/A Info
meeting.
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 45
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
45 3a Schedule Review: (Continued)
Framing will continue for the next several weeks.
Installation of masonry walls will continue through
next week. Rigid insulation for the roofs is
3a.45a scheduled to begin Monday, 2/7 and continue for N/A Info
the next two weeks. Concrete for ramp wall and
elevator pit footings is scheduled for Thursday,
2/10 with backfill of masonry walls scheduled to
be in the week of 2/14.
TSCI's monthly schedule update for the period
ended 01/31/054 was received yesterday,
3a.45b. 02/02/05. The schedule update reflects project 02/10/05 VCM
completion July 14, 2005; approximately two
weeks beyond the current contract completion
date.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 117 submittals (including
resubmittals) have been received to date. At this
3b.45 date, 3 submittals remain outstanding. 02/09/05 FSY
Submittal No. 52B, Waterproofing Substitution,
Submittal No. 63, Dura Tex Hardboard, and
Submittal No. 64, Paint Sample Brush-outs have
all been outstanding for 22 days.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 349 RFI's (including revisions) have
been submitted to date. 14 RFI's are
3c.45 outstanding. Of the fourteen, 10 have been 02/09/05 FSY
outstanding in excess of two weeks. RFI 266
requesting additional details for waterproofing at
the Mercantile Building is the longest
outstanding at 59 days.
3d Field Clarification Status Review:
To date, 2 Field Clarifications have been issued.
3d.45 Both of these items have been included in N/A Info
revio sly approved change orders.
3d.1 Architect's Supplemental Instructions
Twelve Architect's Supplemental Instructions
(ASI) have been issued as of this date. Of the
3d.1.45 twelve, 8 are in approved or pending change 2/10/05 TSCINCM
orders. 1 remains to be negotiated and 3 are
awaiting pricing.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 45
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
45 3d.2 Construction Bulletins
Twenty Construction Bulletins have been issued.
Of the twenty, 8 are included in previously
approved change orders. Three of the twenty
3d.2.45 are in pending Change Order No. 8 and are 2/10/05 TSCl/VCIVI
being revised, Two have been submitted for
review and approval, and seven are being
priced.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 8 has been drafted and was
forwarded to the City of Temecula Monday,
01.10.05 for review and processing.
3e.1.42 02/10/05 FSY/TSCI
Change Order No. 8 was returned to TSCIIFSY for
revision and repricing of some items on 01.19.05.
Supplemental drawings and/or clarifications are
being prepared by FSY. 02.03.05
3e.2 Proposed Change Orders
Ninety one potential change requests have been
identified. Of those, pricing for 67 has been
submitted. Of those 67, 45 have been
incorporated into executed or pending Change
3e.2.45 Orders, 10 have been rejected, 1 has been 02/10/05 TSCl/VCM
rescinded, and 11 are pending negotiation. 18
of the COR's identified have been voided. 6 of
the 91 potential changes are pending pricing.
3f Payment Status Review:
TSCI's Payment Request No. 11 was received
prior to the meeting. This payment request will
3f.45 be reviewed and forwarded to the City of 02/07/05 VCM
Temecula for payment.
3g Notice Of Non Conformance Status:
3 45 There are no outstanding correction notices at N/A Info
g' this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.45 and are prerequisite to inspections.
N/A Info
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 45
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
45 3i Safety Items:
3i.45 There are no outstanding safety issues at this time. N/A Info
4.0 Testing/Inspection:
4.45 Kleinfelder has been on site during the past N/A Info
week for soils and welding inspection.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David McBride
will follow up with John Meyer.
5g.23b See previous meeting minutes for ongoing discussion. 02/18/05 TSCI
It has been determined that granite steps at the Dance
Studio will be replaced by lightly sandblasted concrete.
TSCI is to provide alternate cost proposals utilizing the
granite on site with wood integrated for seating panels per
e-mail direction from D. McBride dated 01.28.05.
02.03.05
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
This work will be incorporated with pending revisions to the
Mercantile Building interior renovations. (12.02.04)
A revised schematic design for the interior renovations is being
undertaken by Bruce Beers. (01.06.05) City of
5.25b 02/08/05 Temecula
Dean Lee advised that he has received the schematic design
and a fee proposal is being prepared. (01.20.05)
D. McBride advised that the design concept and final
design proposal is scheduled for City Council action on
Tuesday,02108/05. 02.03.05
5.0 New Business: (continued)
Wheel Chair Lift:
See previous meeting minutes for full discussion.
5.32a Dean Lee advised that the State of California Elevator 01/12/05 FSY
Code is more restrictive than OSHA requirements and
doors for the wheel chair lift are required. A bulletin
reflecting required revisions will be issued early next
week. 01.06.05
Signage Revisions: Bruce Beers requested a
list of room names. FSY noted that the names
5.43a are shown both on the floor plan and finish
scheduled. Beers will review and determine
whether or not signage changes are required.
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 45
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Signage Revisions (Continued)
Bruce Beers will provide a list of signs to be revised and/or
deleted. This list will be reviewed by David McBride for
compliance with applicable codes. (01.27.05) FSY/City of
45 5.43a 02/10/05 Bruce Beers provided a list of room name changes during Temecula
the course of the meeting. This list will be reviewed by D.
McBride, FSY,and the Building Department as required,
and direction provided. 02.03.05
Mezzanine Occupancy: Bruce Beers inquired
5.43b as to the maximum number of seats allowable at 01/27/05 FSY
the mezzanine level. FSY to review and advise.
Fall Protection for Ladder to Grid: B. Beers
questioned whether a fall cage or fall arrest
system is included for the ladder to the grid.
5.44a VCM will follow up with FSY to address this 02/10/05 TSCI
issue.
TSCI was directed to provide pricing for a fall arrest
system. 02.03.05
Dissolution of Turnkey Forces: D. McBride
questioned the schedule impact that may result
from the bankruptcy of the electrical
subcontractor, Turnkey Forces. TSCI advised
that it met with an alternate subcontractor this
morning and should know the impact, if any, that
5.44b may result from the loss of Turnkey within the N/A Info
next two weeks.
TSCI advised that it is working with two firms to
obtain pricing for completing the work. It is
intended that a new electrical firm will be onsite by
next Monday. 02.03.05
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
�ig ure
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
Message • • Page 1 of 2
Larry Campbell
From: David McBride [David.McBride@cityoftemecuIa.org)
Sent: Friday, January 28, 2005 10:14 AM
To: Larry Campbell
Subject: RE: Meeting Minutes
Larry:
In an effort to clean up a number of items, I offer the following:
Item 3a.42b Is the January schedule really going to be submitted on the next(1/27/05) meeting?
Item 3b.44 Submittal 25A, suggest stating that the submittal (really a substitiution)was never submitted correctly
(although we attempted to work with them) and has been rejected.
Item 3c.44 RFI 226 (outstanding for 98 days) -this needs to be resolved, rejected or otherwise put out of our court.
Item 3d.44 Of the instructions, clarifications and bulletins issued - how many need require futher montoring (i.e., or in
process, part of a change order, etc.).
Item 3e.1.42 I returned the CCO on 1/19 for revision and/or new cost proposals - being revised by FSY, TSCI?
Item 3e.3.44 90 CCO's identified by TSCI. 78 formally submitted -47 in CCO's, 17 voided and 12 rejected (what is the
status if remaing 2?).
Item 5g.23b Not a Council item. Earlier e-mail describes status.
Item 5.25b Approval of conceptual design and final design contract on 218/05 agenda.
Item 5.43a To be review by me, FSY and/or Building Department.
David
-----Original Message-----
From: Larry Campbell [mailto:Larry.Campbell@Vanir.com]
Sent: Friday, January 28, 2005 7:22 AM
To: David McBride; 'Dave Anderson'; 'Dean Lee'; Bruce Beers; steve@toveyshultz.com; 'Kevint'; Ed Deleeuw
(Ed Deleeuw@toveyshu Itz.com)
Subject: Meeting Minutes
Gentlemen:
Attached is a copy of the minutes of Weekly Progress Meeting No. 44 held yesterday, 01.27.05. If there are
comments or corrections required, please call me.
Outgoing mail is certified Virus Free.
Checked by AVG anti-virus system (http://www.grisoft.com).
Version: 6.0.845/Virus Database: 574 - Release Date: 1/25/2005
Incoming mail is certified Virus Free.
Checked by AVG anti-virus system(http://www.grisoft.com).
1/28/2005
\ � City o Temecula
Community Services Department
tev'. t 43200 Business Park Drive Temecula,California 92590
3 Fo73 Ln--
o Cwr -Sa+ -'�v'O 1W i X 70 II6rLJ 3d' ? ---
441 FON '2 -t�-1�• _S� �S
Usi(I
D 1 GYP i\GrCOCtN
J
- -- ---- iaQ� - SA s I, ----------
Telephone: (909) 694-6480 Fax(909) 694-6488
VANIR
PROGRESS MEETING MINUTES
Meeting#: 44
Owner: City of Temecula
Project: Old Town Temecula_
Community Theater
Date: January 27, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.8
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Steve Tovey,Tovey Shultz
Temecula Temecula Construction, Inc (TSCI)
Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc (TSCI) Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
44 1.0 Approval Of Previous Meeting Minutes:
The Minutes of Meeting No. 43 and corrected as
1.44 follows: Item 2.43: delete the word "from"in the 1s' N/A Info
sentence.
2.0 Construction Progress Update:
Roof framing at the Audience Chamber and
plumbing rough-in has continued. Pick up work
2.44 for structural steel is ongoing. Concrete for N/A Info
footings was placed on Tuesday and concrete for
the Scene Shop slab is currently in progress.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look ahead schedule was
presented and reviewed during the course of the
meeting. Framing will continue for the next several
3a.44a weeks. Installation of masonry walls is scheduled N/A Info
to begin tomorrow and continue for the next three
weeks. Framing for the Scene Shop is scheduled
to begin Monday, 1/31.
TSCI's monthly schedule update for the period
ended 12/31/04 was received on Tuesday,
01/11/05. The schedule update reflects project
completion July 15, 2005, one month beyond the
3a.42b. current contract completion date. 02/03/05 TSCI
TSCI's schedule update for the month of January
will be submitted no later than the next progress
meeting, (01.27.05)
Pago 1 of 4
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 44
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
44 3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 117 submittals (including
3b.44 resubmittals) have been received to date. 02/02/05 FSY
Submittal No. 25A, Vapor Barrier Substitution,
outstanding for 56 days, will be rejected.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 344 RFI's (including revisions) have
been submitted to date. 20 RFI's are
3c.44 outstanding. Of the twenty, 10 have been 02/02/05 FSY
outstanding in excess of two weeks. RFI 226
requesting additional details for Stair Nos 4 and
5 has been outstanding for 98 days.
3d Field Clarification Status Review:
To date, 10 Architect's Supplemental
3d.44 Instructions, 2 Field Clarifications, and 15 N/A Info
Construction Bulletins have been issued.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 8 has been drafted and was VCM/City of
3e.1.42 forwarded to the City of Temecula Monday, 01/27/05 Temecula
01.10.05 for review and processing.
3e.2 Proposed Change Orders
Ninety potential change requests have been
identified. Of those, 78 have been submitted of
3e.2.44 which 47 have been incorporated into Change 02/03/05 TSCl/VCM
Orders and 12 have been rejected. 17 of the
COR's identified have been voided.
3f Payment Status Review:
TSCI's draft Payment Request No. 11 was
3f.44 reviewed prior to the meeting. Based upon that N/A Info
payment request, the project is 43% complete.
3g Notice Of Non Conformance Status:
3 44 There are no outstanding correction notices at N/A Info
g this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.44 and are prerequisite to inspections. N/A Info
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 44
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
44 3i Safety Items:
3i.44 There are no outstanding safety issues at this time. N/A Info
4.0 Testing/Inspection:
Kleinfelder has been on site during the past
4.44 week for soils, concrete, and rebar inspection.
N/A Info
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David McBride
will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will
be photographed beside the on-site material for
comparison purposes. (10.07.04)
Photos were forwarded to D. McBride Friday, 10/8, and
are still being reviewed. TSCI advised that it has found
5g.23b an alternate source for granite and is in the process of 02/08/05 City of
obtaining samples. (10.14.04) Temecula
A brochure with price list from Swenson Granite has
been forwarded to D. McBride for review(10.21.04)
Frahm pricing will be submitted tomorrow. (11.04.05)
D. McBride requested order of magnitude pricing for the
Swenson granite in order that an informed decision can be
made. (12.02.04)
COR 64 reflecting pricing for the Swenson Granite was
received yesterday, 12.08.04. A copy has been forwarded to
D. McBride for processing. (12.09.04)
D. McBride advised that this issue will be presented to the
City Council on Tuesday,02/08/05. (01.27.05)
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
This work will be incorporated with pending revisions to the
Mercantile Building interior renovations. (12.02.04)
A revised schematic design for the interior renovations is being
5.25b undertaken by Bruce Beers. (01.06.05) 02/08/05 City of
Temecula
Dean Lee advised that he has received the schematic design
and a fee proposal is being prepared. (01.20.05)
D. McBride advised that this issue will be presented to the
City Council on Tuesday, 02/08/05. 01.27.05
Page 3 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 44
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
44 5.0 New Business: (continued)
Wheel Chair Lift:
See previous meeting minutes for full discussion.
5.32a Dean Lee advised that the State of California Elevator 01/12/05 FSY
Code is more restrictive than OSHA requirements and
doors for the wheel chair lift are required. A bulletin
reflecting required revisions will be issued early next
week. 01.06.05
Signage Revisions: Bruce Beers requested a
list of room names. FSY noted that the names
are shown both on the floor plan and finish
scheduled. Beers will review and determine City of
5.43a whether or not signage changes are required. 02/03/05 Temecula
Bruce Beers will provide a list of signs to be revised
and/or deleted. This list will be reviewed by David
McBride for compliance with applicable codes. 01.27.05
Mezzanine Occupancy: Bruce Beers inquired
5.43b as to the maximum number of seats allowable at 01/27/05 FSY
the mezzanine level. FSY to review and advise.
Fall Protection for Ladder to Grid: B. Beers
questioned whether a fall cage or fall arrest
5.44a system is included for the ladder to the grid. 02/03/05 VCM
VCM will follow up with FSY to address this
issue.
Dissolution of Turnkey Forces: D. McBride
questioned the schedule impact that may result
from the bankruptcy of the electrical
5.44b subcontractor, Turnkey Forces. TSCI advised 02/10/05 TSCI
that it met with an alternate subcontractor this
morning and should know the impact, if any, that
may result from the loss of Turnkey within the
next two weeks.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
nature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: 43 _
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: January 20, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Bruce Beers, City of Kevin Terry,Tovey Shultz
Temecula Temecula Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Dean Lee, FSY Architects Larry Campbell,Vanir
Construction, Inc (TSCI) (FSY) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
43 1.0 Approval Of Previous Meeting Minutes:
1.43 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 42.
2.0 Construction Progress Update:
The major effort over the past week has been
drying out of from footings. Roof sheathing at the Info
2.43 Audience Chamber and plumbing rough-in has N/A
continued. Pick up work for structural steel is in
progress.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look ahead schedule was
presented and reviewed during the course of the
meeting. Framing will continue as will plumbing
rough-ins for the next several weeks. Placement of
concrete for the Scene Shop slab is tentatively
3a.43a scheduled for January 25'h in conjunction with N/A Info
perimeter wall footings. There was discussion
regarding means of drying footings to allow
concrete placement. Kleinfelder is scheduled to re-
inspect footings later this afternoon.
TSCI's monthly schedule update for the period
ended 12/31/04 was received on Tuesday,
3a.42b. 01/11/05. The schedule update reflects project N/A Info
completion July 15, 2005, one month beyond the
current contract completion date.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 117 submittals (including
3b.42 resubmittals) have been received to date. 01/24/05 FSY
Submittal No. 25A, Vapor Barrier, has been
outstanding for 49 days.
Page 1 of 4
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 43
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
43 3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 343 RFI's (including revisions) have
been submitted to date. 22 RFI's are
3c.43 outstanding. Of the twenty two, 12 have been 01/24/05 FSY
submitted within the last five days. RFI 226
requesting additional details for Stair Nos 4 and
5 has been outstanding for 91 days.
3d Field Clarification Status Review:
To date, 10 Architect's Supplemental
3d.43 Instructions, 2 Field Clarifications, and 15 N/A Info
Construction Bulletins have been issued.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 8 has been drafted and was VCM/City of
3e.1.42 forwarded to the City of Temecula Monday, 01/27/05 Temecula
01.10.05 for review and processing.
3e.2 Proposed Change Orders
Ninety potential change requests have been
identified. Of those, 78 have been submitted. 47
3e.2.43 of the change requests have been incorporated 01/27/05 TSCINCM
into Change Orders. 17 of the COR's have
been voided. 12 COR's have been rejected.
3f Payment Status Review:
TSCI's Payment Request No. 10 was approved
by D. McBride yesterday. TSCI asked the status
of Payment Request No. 9 which remains
3f.43 outstanding. D. McBride will follow-up and N/A Info
advise.
The check for Payment Request No. 9 was mailed on
Friday, 01.14.05. 01.20.05
3g Notice Of Non Conformance Status:
3 .43 There are no outstanding correction notices at N/A Info
B this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.43 and are prerequisite to inspections.
N/A Info
3i Safety Items:
3i.43 There are no outstanding safety issues at this time. N/A Info
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 43
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
43 4.0 Testing/Inspection:
Kleinfelder has been on site during the past
4.43 week for soils and welding inspection. N/A Info
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David McBride
will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will
be photographed beside the on-site material for
comparison purposes. (10.07.04)
Photos were forwarded to D. McBride Friday, 10/8, and City of
5g.23b are still being reviewed. TSCI advised that it has found 12/17/04 Temecula
an alternate source for granite and is in the process of
obtaining samples. (10.14.04)
A brochure with price list from Swenson Granite has
been forwarded to D. McBride for review(10.21.04)
Frahm pricing will be submitted tomorrow. (1 1.04.05)
D. McBride requested order of magnitude pricing for the
Swenson granite in order that an informed decision can be
made. (12.02.04)
CDR 64 reflecting pricing for the Swenson Granite was
received yesterday, 12.08.04. A copy has been forwarded
to D. McBride for processing. (12.09.04)
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
This work will be incorporated with pending revisions to the
Mercantile Building interior renovations. (12.02,04)
5.25b A revised schematic design for the interior renovations is being 01124/05 FSY
undertaken by Bruce Beers. (01.06.05)
Dean Lee advised that he has received the schematic
design and afee proposal is being prepared. (01.20.05)
Wheel Chair Lift:
See previous meeting minutes for full discussion.
Dean Lee advised that the State of California Elevator
5.32a Code is more restrictive than OSHA requirements and 01/12/05 FSY
doors for the wheel chair lift are required. A bulletin
reflecting required revisions will be issued early next
week. (01.06.05)
Page 3 of 4 VANIR F 503
VANIR •PROGRESS MEETING MINUTE•
Meeting#: 43
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
43 5.0 New Business: (continued)
Corrugated Metal Roofing: TSCI noted that a letter
was forwarded by Challenger Sheet Metal
5.42a. expressing maintenance concerns with the N/A Info
specified corrugated metal roofing. Following
discussion it was determined that there will be no
change to the specified roofing.
Storm Water: There was discussion regarding
the erosion of the west bank of Murrieta Creek
that occurred during the most recent storm
event. It was noted that there is run-off from the
theater site onto the west bank, particularly in
the area adjacent to the new 18-inch storm drain
5.42b outfall. In order that future problems related to N/A Info
site storm water are avoided, TSCI was advised
that effort is required to fortify the SWPPP
procedures.
Temecula Valley Erosion Control was on site Tuesday,
01.18.05 placing sand bags as required and plastic
sheeting on the slope of Murrieta Creek. 01.20.05
Holiday Work 01/17/05: TSCI advised that while
5.42c Martin Luther King Day is a City holiday, it is not N/A Info
a construction industry holiday. Therefore, TSCI
will be working on Monday, 01/17/05.
Signage Revisions: Bruce Beers requested a
list of room names. FSY noted that the names
5.43a are shown both on the floor plan and finish 01/27/05 City of
scheduled. Beers will review and determine Temecula
whether or not si na a changes are required.
Mezzanine Occupancy: Bruce Beers inquired
5.43b as to the maximum number of seats allowable at 01/27/05 FSY
the mezzanine level. FSY to review and advise.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely, f
/Signdture
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting #: 42
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: January 13, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.6
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, City of Steve Tovey,Tovey Shultz Kevin Terry,Tovey Shultz
Temecula Construction, Inc(TSCI) Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Larry Campbell, Vanir
Construction, Inc (TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
42 1.0 Approval Of Previous Meeting Minutes:
1.42 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 41.
2.0 Construction Progress Update:
Roof sheathing at the Audience Chamber is in
progress and electrical and plumbing rough-in has Info
2.42 continued as weather allows. The major effort over N/A
the past week has been pumping of water from
footings and storm damage repair.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look ahead schedule was
presented and reviewed during the course of the
meeting. Framing will continue as will electrical,
3a.42a plumbing HVAC, and fire sprinkler rough-ins for the N/A Info
next several weeks. Placement of concrete for the
Scene Shop slab is tentatively scheduled for the
week of January 241h in conjunction with perimeter
wall footings.
TSCI's monthly schedule update for the period
ended 12/31/04 was received on Tuesday,
3a.42b. 01/11/05. The schedule update reflects project N/A Info
completion July 15, 2005, one month beyond the
current contract completion date.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 116 submittals (including
resubmittals) have been received to date. 4
3b.42 submittals remain outstanding. Two of the fours 01/17/05 FSY
have been outstanding in excess of two weeks.
Submittal No. 25A, Vapor Barrier, has been
outstanding for 42 days.
Page 1 of 4
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 42
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
42 3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 331 RFI's (including revisions) have
been submitted to date. 15 RFI's are
3c.42 outstanding. Of the fifteen, 9 have been 01/17/05 FSY
outstanding in excess of two weeks. RFI 226
requesting additional details for Stair Nos 4 and
5 has been outstanding for 84 days.
3d Field Clarification Status Review:
To date, 10 Architect's Supplemental
3d.42 Instructions, 2 Field Clarifications, and 14 N/A Info
Construction Bulletins have been issued.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 8 has been drafted and was City of
3e.1.42 forwarded to the City of Temecula Monday, 01/17/05 Temecula
01.10.05 for review and processing.
3e.2 Proposed Change Orders
Eighty eight potential change requests have
been identified. Of those, 77 have been
3e.2.42 submitted. 47 of the change requests have been 01/20/05 TSCINCM
incorporated into Change Orders. 17 of the
COR's have been voided. 12 COR's have been
re'ected.
3f Payment Status Review:
TSCI's Payment Request No. 10 was approved
by D. McBride yesterday. TSCI asked the status City of
3f.42 of Payment Request No. 9 which remains 01/14/05 Temecula
outstanding. D. McBride will follow-up and
advise.
3g Notice Of Non Conformance Status:
3 42 There are no outstanding correction notices at N/A Info
g' this date.
3h As Built Status Review:
Revisions are being posted on a regular basis
3h.42 and are prerequisite to inspections.
NIA Info
31 Safety Items:
3i.42 There are no outstanding safety issues at this time. N/A Info
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 42
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
42 4.0 Testing/Inspection:
4.42 Kleinfelder has not been on site due lack of N/A Info
activity resulting of weather conditions.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David McBride
will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will
be photographed beside the on-site material for
comparison purposes. (10.07.04)
5g.23b Photos were forwarded to D. McBride Friday, 10/8, and 12/17/04 City of
are still being reviewed. TSCI advised that it has found Temecula
an alternate source for granite and is in the process of
obtaining samples. (10.14.04)
A brochure with price list from Swenson Granite has
been forwarded to D. McBride for review(10.21.04)
Frahm pricing will be submitted tomorrow. (11.04.05)
D. McBride requested order of magnitude pricing for the
Swenson granite in order that an informed decision can be
made. (12.02.04)
COR 64 reflecting pricing for the Swenson Granite was
received yesterday, 12.08.04. A copy has been forwarded
to D. McBride for processing. (12.09.04)
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
5.25b This work will be incorporated with pending revisions to the 01/10/05 City of
Mercantile Building interior renovations. (12.02.04) Temecula
A revised schematic design for the interior renovations is
being undertaken by Bruce Beers. 01.06.05
Wheel Chair Lift:
See previous meeting minutes for full discussion.
Dean Lee advised that the State of California Elevator
5.32a Code is more restrictive than OSHA requirements and 01/12/05 FSY
doors for the wheel chair lift are required. A bulletin
reflecting required revisions will be issued early next
week. 01.06.05
Corrugated Metal Roofing: TSCI noted that a letter
was forwarded by Challenger Sheet Metal
5.42a. expressing maintenance concerns with the N/A Info
specified corrugated metal roofing. Following
discussion it was determined that there will be no
change to the specified roofing.
Page 3 of 4 VANIR F 503
VAN 1 R R OGRESS MEETING MINUTES•
Meeting#: 42
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
42 5.0 New Business: (continued)
Storm Water: There was discussion regarding
the erosion of the west bank of Murrieta Creek
that occurred during the most recent storm
event. It was noted that there is run-off from the
5.42b theater site onto the west bank, particularly in 01/20/05 TSCI
the area adjacent to the new 18-inch storm drain
outfall. In order that future problems related to
site storm water are avoided, TSCI was advised
that effort is required to fortify the SWPPP
procedures.
Holiday Work 01/17/05: TSCI advised that while
5.42c Martin Luther King Day is a City holiday, it is not N/A Info
a construction industry holiday. Therefore, TSCI
will be working on Monday, 01/17/05.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 41
Owner: City of Temecula
Project: Old Town Temecula
----- ----------- ._._.......-...._..--
Community at
Date: January 6, 2005
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File # 15.6
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: Dean Lee, FSY Architects Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
(FSY) Construction, Inc(TSCI) Construction, Inc (TSCI)
Larry Campbell,Vanir
Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
41 1.0 Approval Of Previous Meeting Minutes:
1.41 There were no corrections or. additions to the N/A Info
Minutes of Meeting No. 40.
2.0 Construction Progress Update:
Roof sheathing at the Audience Chamber is in
progress and electrical and plumbing rough-in has
continued as weather allows. Installation of the 12-
inch water line in Fourth Street is complete and Info
2.41 slurry fill of the existing storm drain line was N/A
completed yesterday. Excavation of perimeter wall
footings is complete although no rebar has been
placed due to rain. Rebar and sand have been
laced for the Scene Shop slab on grade.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look ahead schedule was
presented and reviewed during the course of the
meeting. Framing will continue as will electrical,
3a.41a plumbing HVAC, and fire sprinkler rough-ins for the N/A Info
next several weeks. Placement of concrete for the
Scene Shop slab is tentatively scheduled for the
week of January 24`" in conjunction with perimeter
wall footings.
TSCI's monthly schedule update for the period
ended 12/31/04 remains outstanding. Submission
of the schedule update is expected prior to the next
3a.41b. meeting. VCM expressed concern that the 01/13/05 TSCI
contract time is approximately 60% gone yet
billings through December reflect the project at
only 40% complete. TSCI to address this issue in
the December schedule update.
Page 1 of 4
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 41
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
41 3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 113 submittals (including
resubmittals) have been received to date. 2
3b.41 submittals remain outstanding. Both have been 01/10/05 FSY
outstanding in excess of two weeks. Submittal
No. 25A, Vapor Barrier, has been outstanding
for 35 days.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 320 RFI's (including revisions) have
3c.41 been submitted to date. 13 RFI's are 01/10/05 FSY
outstanding. Of the thirteen, 11 have been
outstanding in excess of two weeks.
3d Field Clarification Status Review:
To date, 10 Architect's Supplemental
Instructions, 2 Field Clarifications, and 14
3d.41 Construction Bulletins have been issued. N/A Info
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 8 has been drafted and will
3e.1.41 be forwarded to the City of Temecula early next 01/11/05 VCM
week for review and processing.
3e.2 Proposed Change Orders
Eighty six potential change requests have been
identified. Of those, 75 have been submitted. 40
3e.2.41 of the change requests have been incorporated 01/13/05 TSCl/VCM
in Change Orders. 17 of the COR's have been
voided. 12 COR's have been rejected.
3f Payment Status Review:
TSCI's Payment Request No. 10 was mailed
3f.41 directly to the City of Temecula for processing 01/28/05 City of
12/28104. Temecula
3g Notice Of Non Conformance Status:
There are no outstanding correction notices at
3g.41 this date. N/A Info
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 41
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
41 3h As Built Status Review:
Revisions are being posted on a regular basis
3h.41 and are prerequisite to inspections. N/A Info
3i Safety Items:
Weekly Foreman's Toolbox Safety Meetings are
3i.41 held Tuesday mornings. At this time, there are no N/A Info
safety issues unresolved.
4.0 Testing/Inspection:
Kleinfelder has not been on site due lack of
4.41 activity resulting of weather conditions. N/A Info
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David McBride
will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will
be photographed beside the on-site material for
comparison purposes. (10.07.04)
5g.23b Photos were forwarded to D. McBride Friday, 10/8, and 12/17/04 City of
are still being reviewed. TSCI advised that it has found Temecula
an alternate source for granite and is in the process of
obtaining samples. (10.14.04)
A brochure with price list from Swenson Granite has
been forwarded to D. McBride for review(10.21.04)
Frahm pricing will be submitted tomorrow. (11.04.05)
D. McBride requested order of magnitude pricing for the
Swenson granite in order that an informed decision can be
made. (12.02.04)
COR 64 reflecting pricing for the Swenson Granite was
received yesterday, 12.08.04. A copy has been forwarded
to D. McBride for processing. (112.09.04)
Mercantile Building Interior Renovations:
See previous meeting minutes for full discussion.
5.25b This work will be incorporated with pending revisions to the 01/10/05 City of
Mercantile Building interior renovations. (12.02.04) Temecula
A revised schematic design for the interior renovations is
being undertaken by Bruce Beers. 01.06.05
Page 3 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 41
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
41 5.0 New Business: (continued)
Wheel Chair Lift: TSCI noted that the submittal for
the wheel chair lift indicates a solid door at each
landing and that the submittal was returned
annotated "Make Corrections Noted". No door is
reflected on the architectural plan or door
schedule. Following discussion, it was determined
that TSCI will submit an RFI for clarification.
RFI 210 has been submitted and responded. (10.21.04)
The lift supplier has noted that a door at the lower
opening and a 42-inch high gate at the upper opening is
required by Code. This information has been forwarded
to FSY for implementation if required. (10.28.04)
5.32a FSY advised that it can find no code requirement for a 01/12/05 FSY
door at the lower opening. Fallowing discussion, FSY
will review the State Elevator Cade. (11.04.04)
FSY advised that a detail would be provided and will be
forthcoming within the next week. (11.18.04)
RFI 210 was responded by FSY on 12.06.04. This issue will
be deleted from future meeting discussion. (12.09.04)
Dean Lee advised that a check with the City of Temecula
Building &Safety Department reflected that no door is
required. FSY to follow up directly with Cal OSHA. (12.16.04)
Dean Lee advised that the State of California Elevator
Code is more restrictive than OSHA requirements and
doors for the wheel chair lift are required. A bulletin
reflecting required revisions will be issued early next
week. 01.06.05
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
7Sig tw5 ure
7
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
I
VANIR
PROGRESS MEETING MINUTES
Meeting#: 40
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: December 16, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File # 15.B
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, DPW, City of Bruce Beers, City of Dean Lee, FSY Architects
Temecula (DPW) Temecula (City) (FSY)
Kevin Terry, Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell, Vanir
Construction, Inc(TSCI) Construction, Inc (TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
40 1.0 Approval Of Previous Meeting Minutes:
1.40 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 39.
2.0 Construction Progress Update:
Framing for the classroom building, restroom
building and dance studio, along with electrical,
plumbing, and HVAC rough-in has continued.
Welding and bolting of structural steel at the fly loft
section is continuing and installation of metal Info
2.40 decking continues. Installation of the 12-inch water N/A
line -in Fourth Street is in progress and will be
complete by week end. Installation of plywood on
metal decking is in progress. Grouting of the
existing storm drain line is scheduled for later
today.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look ahead schedule was
presented and reviewed during the course of the
meeting. Framing will continue as will electrical,
plumbing HVAC, and fire sprinkler rough-ins for the
next several weeks. Pick up work for structural
3a.40a steel will continue. Excavation of remaining N/A Info
footings is scheduled to begin tomorrow with
footing placement to begin Monday, 12/20. The
new fence at the Pottery Shop will follow wall
footing placement and is presently scheduled for
the week of January 3rtl.
Review comments for TSCI's monthly schedule
3a.38b. update for the period ended 11/30/04 were N/A Info
forwarded 12/6/04.
Page 1 of 4
VAN 1 R •PROGRESS MEETING MINUTE?
Meeting#: 40
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
40 3a Schedule Review:
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 113 submittals (including
resubmittais) have been received to date. 4
3b.40 submittals remain outstanding. Of the four, two 12/20/04 FSY
have been outstanding in excess of two weeks.
Submittal No. 23B, Woodbury Granite, has been
outstanding for 28 days.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 312 RFI's (including revisions) have
3c.40 been submitted to date. 12 RFI's are 12/20/04 FSY
outstanding. Of the twelve, 3 have been
outstanding in excess of two weeks.
3d Field Clarification Status Review:
To date, 9 Architect's Supplemental Instructions,
2 Field Clarifications, and 13 Construction
3d.39 Bulletins have been issued. ASI #9, reflecting N/A Info
the furring of siding at the Concession Building
was issued 12/07/04.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 7 was mailed to TSCI for
execution yesterday, 12/01/04.
3e.1.38 Change Order No. 7, signed by TSCI was returned during N/A Info
the course of the meeting. (12.09.04)
CO No. 7 was forwarded to the City of Temecula for
processing 12/13/04. 12.16.04
3e.2 Proposed Change Orders
Eighty four potential change requests have been
identified. Of those, 62 have been submitted. 41
3e.2.39 of the change requests have been incorporated 12/17/04 TSCl/VCM
in Change Orders. 11 of the COR's have been
voided. 12 COR's have been rejected.
3f Payment Status Review:
TSCI's Payment Request No. 9 was reviewed
3f.40 and forwarded to the City of Temecula for N/A In processing 12/13/04.
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE?
Meeting#: 40
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
40 3g Notice Of Non Conformance Status:
3g.40 There are no outstanding correction notices at N/A Info
this date.
3h As Built Status Review:
3h.40 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.40 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are no
safety issues unresolved.
4.0 Testing/Inspection:
4.40 Kleinfelder has been on site this week for steel N/A Info
observation.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David McBride
will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will
be photographed beside the on-site material for
comparison purposes. (10.07.04)
Photos were forwarded to D. McBride Friday, 10/8, and
are still being reviewed. TSCI advised that it has found City of
5g.23b an alternate source for granite and is in the process of 12/17/04 Temecula
obtaining samples. (10.14.04)
A brochure with price list from Swenson Granite has
been forwarded to D. McBride for review (10.21.04)
Frahm pricing will be submitted tomorrow. It 1.04.05)
D. McBride requested order of magnitude pricing for the
Swenson granite in order that an informed decision can be
made. (12.02.04) .
COR 64 reflecting pricing for the Swenson Granite was
received yesterday, 12.08.04. A copy has been forwarded
to D. McBride for processing. (12.09.04)
.Page 3 of 4 VANIR F 503
VAN 1 R •ROGRESS MEETING MINUTE?
Meeting #: 40
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
40 5.0 New Business: (continued)
5.25b Mercantile Building Interior Renovations: 12/15/04 FSY
See previous meeting minutes for full discussion.
This work will be incorporated with pending revisions to
the Mercantile Building interior renovations. (12.02.04)
Wheel Chair Lift: TSCI noted that the submittal for
the wheel chair lift indicates a solid door at each
landing and that the submittal was returned
annotated "Make Corrections Noted". No door is
reflected on the architectural plan or door
schedule. Following discussion, it was determined
that TSCI will submit an RFI for clarification.
RFI 210 has been submitted and responded. (10.21.04)
The lift supplier has noted that a door at the lower
opening and a 42-inch high gate at the upper opening is
required by Code. This information has been forwarded
5.32a 12/23/04 FSY
to FSY for implementation if required. (10.28.04)
FSY advised that it can find no code requirement for a
door at the lower opening: Following discussion, FSY
will review the State Elevator Code. (11.04.04)
FSY advised that a detail would be provided and will be
forthcoming within the next week. (11.18.04)
RFI 210 was responded by FSY on 12.06.04. This issue will
be deleted from future meeting discussion. (12.09.04)
Dean Lee advised that a check with the City of Temecula
Building& Safety Department reflected that no door is
required. FSY to follow up directly with Cal OSHA.
12.16.04
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely, f
Si ature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting #: 39
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: December 9, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc (TSCI) Construction, Inc(TSCI) Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
39 1.0 Approval Of Previous Meeting Minutes:
1.38 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 38.
2.0 Construction Progress Update:
Framing for the classroom building, restroom
building and dance studio, along with electrical,
plumbing, and HVAC rough-in has continued.
2.39 Welding and bolting of structural steel at the fly loft N/A Info
section is continuing and installation of metal
decking continues. Installation of the 12-inch water
line in Fourth Street is in progress and will continue
for the remainder of the week.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look ahead schedule was
presented and reviewed during the course of the
meeting. Framing will continue as will electrical,
plumbing HVAC, and fire sprinkler rough-ins for the
next several weeks. Site water will continue with
the work in Fourth Street. Pick up work for
3a.39a structural steel will continue. Excavation of N/A Info
remaining footings has been postponed until next
week due to the muddy site conditions. Footing
placement will be followed by CMU walls and slab
placement at the Scene Shop. The new fence at
the Pottery Shop will follow wall footing placement
and is presently scheduled for the week of
December 20th.
Review comments for TSCI's monthly schedule
3a.38b. update for the period ended 11/30/04 were N/A Info
forwarded 12/6/04.
Page 7 or 5
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 39
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
39 3a Schedule Review:
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 111 submittals (including
resubmittais) have been received to date. 3
3b.39 submittals remain outstanding. Of the three, two 12/13/04 FSY
have been outstanding in excess of two weeks.
Submittal No. 23B, Woodbury Granite, has been
outstanding for 21 days.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 307 RFI's (including revisions) have
3c.39 been submitted to date. 18 RFI's are 12/13/04 FSY
outstanding. Of the eighteen, 6 have been
outstandinq in excess of two weeks.
3d Field Clarification Status Review:
To date, 9 Architect's Supplemental Instructions,
2 Field Clarifications, and 13 Construction
3d.39 Bulletins have been issued. ASI #9, reflecting N/A Info
the furring of siding at the Concession Building
was issued 12/07/04.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 7 was mailed to TSCI for
3e.1.38 execution yesterday, 12/01/04. N/A Info
Change Order No.7, signed by TSCI was returned
during the course of the meeting. 12.09.04)
3e.2 Proposed Change Orders
Eighty four potential change requests have been
identified. Of those, 62 have been submitted. 41
3e.2.39 of the change requests have been incorporated 12/17/04 TSCl/VCM
in Change Orders. 11 of the COR's have been
voided. 12 COR's have been rejected.
3f Payment Status Review:
TSCI's Payment Request No. 9 was reviewed
prior to the meeting. TSCI to submit finalized
payment request with required certified payrolls
308 and releases for processing. 12/13/04 VCM
Payment Request No. 9 was submitted during the
course of the meeting. The request will be reviewed
and forwarded to the City for processing. (12.09.04)
Page 2 of 5 VANIR F 503
VAN I R PROGRESS MEETING MINUTES
Meeting#: 39
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
39 3g Notice Of Non Conformance Status:
3g.39 There are no outstanding correction notices at N/A Info
this date.
3h As Built Status Review:
3h.39 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.39 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are no
safety issues unresolved.
4.0 Testing/Inspection:
4.39 Kleinfelder has been on site this week for steel N/A Info
observation.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David McBride
will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will
be photographed beside the on-site material for
comparison purposes. (10.07.04)
Photos were forwarded to D. McBride Friday, 10/8, and
are still being reviewed. TSCI advised that it has found City of
5g.23b an alternate source for granite and is in the process of 12/17/04 Temecula
obtaining samples. (10.14,04)
A brochure with price list from Swenson Granite has
been forwarded to D. McBride for review (10.21.04)
Frahm pricing will be submitted tomorrow. (11.04.05)
D. McBride requested order of magnitude pricing for the
Swenson granite in order that an informed decision can be
made. (12.02.04)
COR 64 reflecting pricing for the Swenson Granite was
received yesterday, 12.08.04. A copy has been forwarded
to D. McBride for processing. It 2.09.04)
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting #: 39
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
39 5.0 New Business: (continued)
5.25b See previous meeting minutes for full discussion. 12/15/04 FSY
This work will be incorporated with pending revisions to
the Mercantile Building interior renovations.(12.02.04)
Wheel Chair Lift: TSCI noted that the submittal for
the wheel chair lift indicates a solid door at each
landing and that the submittal was returned
annotated "Make Corrections Noted". No door is
reflected on the architectural plan or door
schedule. Following discussion, it was determined
that TSCI will submit an RFI for clarification.
RFI 210 has been submitted and responded. (10.21.04)
5.32a The lift supplier has noted that a door at the lower N/A Complete
opening and a 42-inch high gate at the upper opening is
required by Code. This information has been forwarded
to FSY for implementation if required. (10.28.04)
FSY advised that it can find no code requirement for a
door at the lower opening. Following discussion, FSY
will review the State Elevator Code. (11.04.04)
FSY advised that a detail would be provided and will be
forthcoming within the next week. (11.18.04)
RFI 210 was responded by FSY on 12.06.04. This issue
will be deleted from future meeting discussion. 12.09.04
Waterproofing of siding in contact with steel
columns: TSCI referenced Details 1 and 2, Sht
A5.03 and noted that there do not appear to be
provisions for waterproofing and/or flashing where
the cedar siding comes into contact with the steel
5.35b. columns. Following discussion, it was determined N/A Complete
that TSCI will follow up with an RFI.
FSY advised that a detail would be provided and will be
forthcoming within the next week. (11.18.04)
RFI 236 was responded by FSY on 12.03.04. This issue
will be deleted from future meeting discussion. 12.09.04
Color Board:TSCI noted that colors are not defined
in the contract documents and questioned whether
or not a color board could be provided for site use.
5.36a. FSY advised that a color schedule is being forwarded for N/A Complete
project use. (12.02.04)
Update Sheet A9.01 was received on 12.06.04. This issue
will be deleted from future meeting discussion. 12.09.04 -
Page 4 of 5 VANIR F 503
VAN 1 R •PROGRESS MEETING MINUTE
Meeting#: 39
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
�� _ ''�' nature
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
RE: Meeting Minutes #37 • • Page 1 of 2
Larry Campbell
From: Rivera, Mark[mark.rivera@vanir.coml
Sent: Monday, November 29, 2004 8:51 AM
To: Campbell, Larry
Subject: RE: Meeting Minutes#37
Larry,
If this evolves into an "extravagant' detail, (which is probably not the case), it may become a cost item with TSCI.
Either way, based on the limited discussion and what I know about the issue, it sounds like it would be an
"omission"type change. On the surface, it sounded more like a clarification that FSY was due to provide.
Mark P. Rivera, P.E.
Project Manager
VANIR Construction Management, Inc.
San Bernardino Area Office
(909) 384-1785 Off.
(909) 381-7534 Fax
(909) 208-8250 Cell
-----Original Message-----
From: David McBride [mailto:David.McBride@cityoftemecula.org]
Sent: Monday, November 29, 2004 8:02 AM
To: Rivera, Mark
Cc: Campbell, Larry
Subject: RE: Meeting Minutes #37
Mark/Larry:
Item 5.35b-this has a potential cost impact. Suggest that we review as well.
David
-----Original Message-----
From: Rivera,Mark tmailto:mark.nvera@_vanir_com]
Sent: Thursday, November 18,2004 2:16 PM
To: David McBride; Dean Lee(E-mail); EdDeleeuvv(E-mail); Kevin Terry(E-mail)
Cc: Larry.Campbell(E-mail)
Subject: Meeting Minutes#37
Please find attached below the meeting minutes from today's meeting for your review and -
comment.
Thanks,
Mark P. Rivera, P.E.
11/29/2004
RE: Meeting Minutes 437 • • Page 2 of 2
Project Manager
VANIR Construction Management,Inc.
San Bernardino Area Office
(909) 384-1785 Off.
(909) 381-7534 Fax
(909) 208-8250 Cell
<< File: Weekly Progress Meeting No. 37.doc >>
Incoming mail is certified Virus Free.
Checked by AVG anti-virus system (hutp://www.grisoft.com).
Version: 6.0.799/Virus Database: 543 - Release Date: 11/19/2004
11/29/2004
VANIR
PROGRESS MEETING MINUTES
Meeting #: 38
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: December 2, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, Dept. Public Steve Tovey,,Tovey Shultz Kevin Terry,Tovey Shultz
Works(DPW) Construction, Inc(TSCI) Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Gary Voechting,Tovey Arturo Yanez, FSY Dean Lee, FSY Architects
Construction, Inc(TSCI) Shultz Construction, Inc Architects(FSY) (FSY)
(TSCI)
Larry Campbell,Vanir
Construction Mgmt. (VCM)
Meeting # Item # Description Due Action
38 1.0 Approval Of Previous Meeting Minutes:
1.38 There were no corrections or additions to the
Minutes of Meeting No. 37. N/A Info
2.0 Construction Progress Update:
Framing for the classroom building,, restroom
building and dance studio, along with electrical,
plumbing, HVAC, and fire sprinkler rough-in has
continued. Welding and bolting of structural steel
at the fly loft section is continuing and installation of Info
2.38 metal decking is in progress. The 8-inch A/V N/A
conduit will be complete today and the 12-inch
water tie-in was completed last night with the thrust
block to be placed tomorrow.
3.0 Technical Concerns:
3a Schedule Review:
Tovey Shultz' 3-week look ahead schedule was
presented and reviewed during the course of the
meeting. Framing will continue as will electrical,
plumbing HVAC, and fire sprinkler rough-ins for the
next several weeks. Site water will continue with
the work in Fourth Street. Pick up work for
3a.38a structural steel will continue. Excavation of N/A Info
remaining footings will begin next week to be
followed by CMU walls and slab placement at the
Scene Shop. The new fence at the Pottery Shop
will follow wall footing placement and is presently
scheduled for the week of December 16'h.
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES
Meeting #: 38
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
38 3a Schedule Review:
TSCI's monthly schedule update for the period
3a.38b. ended 11/30/04 was received 11/30 and is under 12/08/04 VCM
review.
3b Submittal Status Review:
VCM's submittal log was reviewed during the
course of the meeting. 109 submittals (including
resubminals) have been received to date. 5
submittals remain outstanding. Of the five, three
3b.38 have been outstanding in excess of two weeks. 12/O6/04 FSY
Submittal No. 58, Resilient Flooring, has been
outstanding for 116 days.
3c Request For Information Status Review:
VCM's RFI log was reviewed during the course
of the meeting. 288 RFI's (Including revisions) have
3c.38 been submitted to date. 14 RFI's are 12/06/04 FSY
outstanding. 'Of the fourteen, 7 have been
outstanding in excess of two weeks.
3d Field Clarification Status Review:
To date, 8 Architect's Supplemental Instructions,
2 Field Clarifications, and 13 Construction
3d.38 Bulletins have been issued. Bulletin No. 13, N/A Info
reflecting the addition of 2 A/V conduits was
issued 11.29.04
3e Change Order/Proposed Change Order
Status:.
3e.1 Change Orders
Change Order No. 7 was mailed to TSCI for
3e.1.38 execution yesterday, 12/01/04. 12/08/04 TSCI
3e.2 Proposed Change Orders
Eighty four potential change requests have been
identified. Of those, 59 have been submitted. 41
of the change requests have been incorporated
3e.2.38 in Change Orders. 11 of the COR's have been 12/08/04 TSCl/VCM
voided. 12 COR's have been rejected.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 38
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
38 3f Payment Status Review:
TSCI's Payment Request No. 9 was reviewed
3f.38 prior to the meeting. TSCI to submit finalized 12/07/04 TSCI
payment request with required certified payrolls
and releases for processing.
3g Notice Of Non Conformance Status:
3g.38 There are no outstanding correction notices at N/A Info
this date.
3h As Built Status Review:
3h.38 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.38 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are no
safety issues unresolved.
4.0 Testing/Inspection:
4.38 Kleinfelder has been on site this week for steel N/A Info
observation and compaction testing.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David McBride
will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will
5g.23b be photographed beside the on-site material for 12/07/04 TSCI
comparison purposes. (10.07.04)
Photos were forwarded to D. McBride Friday, 10/8, and
are still being reviewed. TSCI advised that it has found
an alternate source for granite and is in the process of
obtaining samples. (10.14.04)
A brochure with price list from Swenson Granite has
been forwarded to D. McBride for review (10.21.04)
Frahm pricing will be submitted tomorrow. (11.04.05)
D. McBride requested order of magnitude pricing for the
Swenson granite in order that an informed decision can
be made. 12.02.04
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE
Meeting#: 38
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
38 5.0 New Business: (continued)
Storefront at Mercantile Building:
TSCI expressed concern for the condition of the
existing storefront at the Mercantile Building.
Following discussion, it was determined that
McEachron Construction will be asked to
review the present condition and make
recommendations for restoration.
TSCI and VCM met with McEachron Construction on 8/30/04
to discuss restoration of the storefront and replacement of
missing .windows. McEachron will provide ideas, alternates,
5.25b and pricing to TSCI (09.02.04) 12/15/04 FSY
A "laundry list" of ideas was forwarded to D. McBride prior to
the meeting for review and direction. (09.23.04)
TSCI was asked to formally submit McEachron's proposal.
VCM noted that panic hardware is required for the Mercantile
Bldg. due to occupancy loads. (09.30.04)
TSCI advised that it has not received a price for painting the
doors and will submit by next meeting. (10.07.04)
McEachron's pricing was submitted during the course of the
meeting as COR#44 (10.21.04)
This work will be incorporated with pending revisions to
the Mercantile Building interior renovations. 12.02.04
Wheel Chair Lift: TSCI noted that the submittal for
the wheel chair lift indicates a solid door at each
landing and that the submittal was returned
annotated "Make Corrections Noted". No door is
reflected on the architectural plan or door
schedule. Following discussion, it was determined
that TSCI will submit an RA for clarification.
RFI 210 has been submitted and responded. (10.21.04)
5.32a The lift supplier has noted that a door at the lower 11/24/04 FSY
opening and a 42-inch high gate at the upper opening is
required by Code. This information has been forwarded
to FSY for implementation if required. (10.28.04)
FSY advised that it can find no code requirement for a
door at the lower opening. Following discussion, FSY
will review the State Elevator Code. (11.04.04)
FSY advised that a detail would be provided and will
be forthcoming within the next week. 11.18.04
Waterproofing of siding in contact with steel
columns: TSCI referenced Details 1 and 2, Sht
A5.03 and noted that there do not appear to be
provisions for waterproofing and/or flashing where
37 5.35b. the cedar siding comes into contact with the steel 11/24/04 FSY
columns. Following discussion, it was determined
that TSCI will follow up with an RFI.
FSY advised that a detail would be provided and will be
forthcoming within the next week. 11.18.04
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE
Meeting#: 38
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Color Board:TSCI noted that colors are not defined
in the contract documents and questioned whether
38 5.36a. or not a color board could be provided for site use. t 2/03/04 FSY
FSY advised that a color schedule is being forwarded for
Project use.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 37
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: November 18, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.6
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Mark Rivera,Vanir
Construction, Inc(TSCI) Construction, Inc (TSCI) Construction Mgmt. (VCM)
Arturo Yanez, FSY Dean Lee, FSY Architects
Architects (FSY) (FSY)
Meeting # Item # Description Due Action
37 1.0 Approval Of Previous Meeting Minutes:
1.37 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 37.
2.0 Construction Progress Update:
2.37 Framing for the classroom building, restroom N/A Info
building and dance studio, along with electrical,
plumbing, and fire sprinkler rough-in has continued.
Welding of structural steel at the fly loft section is
continuing and the catwalks were installed and a
portion of the stairs at the assembly area. Work on
the 10-inch water line within the site is in progress.
The 8-inch A/V conduit was installed and is
scheduled for slurry backfill on 11-19-04.
3.0 Technical Concerns:
3a Schedule Review:
3a.37a Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Framing will continue as will electrical,
plumbing and fire sprinkler rough-ins for the next
several weeks. Site water will continue and will be
followed by the work in Fourth Street. Structural
steel is scheduled to continue and installation of
the 8-inch AV conduit was installed as planned.
3a.34b. TSCI's monthly schedule update will be submitted 11/18/04 VCM
by the next meeting.
TSCI's monthly schedule update will be submitted by Tuesday,
11.09.04 (11.04.05)
TSCI's monthly schedule update was received on
11.09.04 and is being reviewed (11.12.04). As of
(11.18.04) schedule remains under review by VCM.
Page 1 of 5
VAN I R PROGRESS MEETING MINUTES•
Meeting#: 37
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
37 3b Submittal Status Review:
3b.37 VCM's submittal log was reviewed during the 11/24/04 FSY
course of the meeting. 107 submittals (including
resubmittals) have been received to date. 3
submittals remain outstanding. All of the three
have been outstanding in excess of two weeks.
Submittal No. 58, Resilient Flooring, has been
outstanding for 102 days.
3c Request For Information Status Review:
3c.37 VCM's RFI log was reviewed during the course 11/22/04 FSY
of the meeting. 278 RFI's (including revisions) have
been submitted to date. 26 RFI's are
outstanding. Of the twenty-six, 6 have been
outstanding in excess of two weeks.
3d Field Clarification Status Review:
3d.35 To date, 8 Architect's Supplemental Instructions,
2 Field Clarifications, and 12 Construction
Bulletins have been issued. N/A Info
Bulletin No. 12, reflecting revisions to the fencing and
gate at the Mercantile Building was issued 11.08.04(
11.12.04)
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 7 has been drafted and
3e.1.36 forwarded to D. McBride for revision and N/A Info
processing.
3e.2 Proposed Change Orders
3e.2.36 Seventy nine potential change requests have 11/30/04 TSCINCM
been identified. Of those, 51 have been
submitted. 43 of the change requests have been
incorporated in Change Orders. 11 of the
COR's have been voided. 8 COR's have been
rejected.
3f Payment Status Review:
3f.35 TSCI's Payment Request No. 8 was received 12/05/04 City Temecula
during the course of the meeting. The payment
request will be reviewed and forwarded to the
City of Temecula for processing.
Payment Request No. 8 was forwarded to the City of
Temecula for processing 11.05/04(11.12,04)
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 37
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
37 3g Notice Of Non Conformance Status:
3g.37 There are no outstanding correction notices at N/A Info
this date.
3h As Built Status Review:
3h.37 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
307 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are no
safety issues unresolved.
4.0 Testing/Inspection:
4.37 Kleinfelder has been on site this week for steel N/A Info
observation.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David McBride
will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will
5g.23b be photographed beside the on-site material for 11/05/04 TSCI
comparison purposes. (10.07.04)
Photos were forwarded to D. McBride Friday, 10/8, and
are still being reviewed. TSCI advised that it has found
an alternate source for granite and is in the process of
obtaining samples. (10.14.04)
A brochure with price list from Swenson Granite has
been forwarded to D. McBride for review(10.21.04)
Frahm pricing will be submitted tomorrow.
11.04.05
Storefront at Mercantile Building:
TSCI expressed concern for the condition of the
existing storefront at the Mercantile Building.
5.25b Following discussion, it was determined that
McEachron Construction will be asked to
review the present condition and make
recommendations for restoration.
Page 3 of 5 VANIR F 503
VANIR PROGRESS MEETING MINUTES•
Meeting#: 37
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
37 5.25b Storefront at Mercantile Building: (Continued)
TSCI and VCM met with McEachron Construction on 8/30/04
to discuss restoration of the storefront and replacement of
missing windows. MCEachron will provide ideas, alternates,
and pricing to TSCI (09.02.04)
A "laundry list' of ideas was forwarded to D. McBride prior to
the meeting for review and direction. (09.23.04) City Of
TSCI was asked to formally submit McEachron's proposal. 11/04/04
VCM noted that panic hardware is required for the Mercantile Temecula
Bldg. due to occupancy loads.(09.30.04)
TSCI advised that it has not received a price for painting the
doors and will submit by next meeting.(10.07.04)
McEachron's pricing was submitted during the course of the
meeting as COR#44 10.21.04
Wheel Chair Lift: TSCI noted that the submittal for
the wheel chair lift indicates a solid door at each
landing and that the submittal was returned
annotated "Make Corrections Noted". No door is
reflected on the architectural plan or door
schedule. Following discussion, it was determined
that TSCI will submit an RFI for clarification.
5.32a RFI 210 has been submitted and responded. (10.21.04) 11/24/04 FSY
The lift supplier has noted that a door at the lower
opening and a 42-inch high gate at the upper opening is
required by Code. This information has been forwarded
to FSY for implementation if required. (10.28.04)
FSY advised that it can find no code requirement for
a door at the lower opening. Following discussion,
FSY will review the State Elevator Code. (11.04.04)
FSY advised that a detail would be provided and will
be forthcoming within the next week. 11.18.04
Meeting # Item # Description Due Action
Waterproofing of siding in contact with steel
columns: TSCI referenced Details 1 and 2, Sht
A5.03 and noted that there do not appear to be
provisions for waterproofing and/or flashing where
37 5.35b. the cedar siding comes into contact with the steel 11/24/04 FSY
columns. Following discussion, it was determined
that TSCI will follow up with an RFI.
RFI 237 was submitted 11.05.04 and remains unanswered.
(11.12.04)
FSY advised that a detail would be provided and will be
forthcoming within the next week. 11.18.04
Color Board:TSCI noted that colors are not defined
5.36a. in the contract documents and questioned whether 11/17/04 FSY
or not a color board could be provided for site use.
. Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 37
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Mark P. Rivera
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 36
Owner: City of Temecula__
Project: Old Town Temecula
Community Theater
Date: November 12, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Mark Rivera,Vanir
Construction, Inc(TSCI) Construction, Inc (TSCI) Construction Mgmt. (VCM)
Larry Campbell,Vanir
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
36 1.0 Approval Of Previous Meeting Minutes:
1.36 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 36.
2.0 Construction Progress Update:
2.36 Framing for the classroom building, restroom N/A Info
building and dance studio, along with electrical,
plumbing, and HVAC rough-in has continued.
Steel erection at the fly loft section is continuing
and work on the 6-inch water line within the site
is in progress. VCI (as subcontractor to Verizon)
is setting a vault for relocation of the telephone
pedestal.
3.0 Technical Concerns:
3a Schedule Review:
3a.36a Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Framing will continue as will electrical,
plumbing and HVAC rough-ins for the next
several weeks. Site water will continue and will
be followed by the work in Fourth Street.
Structural steel is scheduled to continue and
installation of the 8-inch AV conduit is tentatively
scheduled to begin next week based upon the
progress of the structural steel
3a.34b TSCI's monthly schedule update will be 11/18/04 VCM
submitted by the next meeting.
TSCI's monthly schedule update will be submitted by
Tuesday, 11.09.04 (11.04.05)
TSCI's monthly schedule update was received on
11.09.04 and is being reviewed (11.12.04)
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 36
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
36 3b Submittal Status Review:
3b.36 VCM's submittal log was reviewed during the 11/17/04 FSY
course of the meeting. 107 submittals (including
resubmittals) have been received to date. 3
submittals remain outstanding. All of the three
have been outstanding in excess of two
weeks. Submittal No. 58, Resilient Flooring,
has been outstanding for 95 days.
3c Request For Information Status Review:
3c.36 VCM's RFI log was reviewed during the 11/15/04 FSY
course of the meeting. 266 RFI's (including
revisions) have been submitted to date. 14 RFI's
are outstanding. Of the fourteen, 6 have been
outstanding in excess of two weeks.
3d Field Clarification Status Review:
3d.35 To date, 8 Architect's Supplemental
Instructions, 2 Field Clarifications, and 12
Construction Bulletins have been issued. N/A Info
Bulletin No. 12, reflecting revisions to the fencing
and gate at the Mercantile Building was issued
11.08.04( 11.12.04)
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 7 has been drafted and
3e.1.36 forwarded to D. McBride for revision and N/A Info
processing.
3e.2 Proposed Change Orders
3e.2.36 Seventy nine potential change requests have 11/30/04 TSCINCM
been identified. Of those, 51 have been
submitted. 43 of the change requests have
been incorporated in Change Orders. 11 of
the COR's have been voided. 8 COR's have
been rejected.
3f Payment Status Review:
305 TSCI's Payment Request No. 8 was received 12/05/04 City of
during the course of the meeting. The Temecula
payment request will be reviewed and
forwarded to the City of Temecula for
processing.
Payment Request No. 8 was forwarded to the City of
Temecula for processing 11.05/04 11.12.04
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 36
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
36 3g Notice Of Non Conformance Status:
3g.36 There are no outstanding correction notices at N/A Info
this date.
3h As Built Status Review:
3h.36 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.36 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.36 Kleinfelder has been on site this week for steel N/A Info
observation.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David
McBride will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will
5g.23b be photographed beside the on-site material for 11/05/04 TSCI
comparison purposes. (10.07.04)
Photos were forwarded to D. McBride Friday, 10/8,
and are still being reviewed. TSCI advised that it has
found an alternate source for granite and is in the
process of obtaining samples. (10.14.04)
A brochure with price list from Swenson Granite has
been forwarded to D. McBride for review(10.21.04)
Frahm pricing will be submitted tomorrow.
11.04.05
Storefront at Mercantile Building:
TSCI expressed concern for the condition of the
existing storefront at the Mercantile Building.
5.25b Following discussion, it was determined that
McEachron Construction will be asked to
review the present condition and make
recommendations for restoration.
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 36
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
36 5.25b Storefront at Mercantile Building: (Continued)
TSCI and VCM met with McEachron Construction on
8/30/04 to discuss restoration of the storefront and
replacement of missing windows. McEachron will provide
ideas, alternates, and pricing to TSCI (09.02.04)
A"laundry list"of ideas was forwarded to D. McBride prior to
the meeting for review and direction. (09.23.04)
TSCI was asked to formally submit McEachron's proposal. 11/04/04 City Of
VCM noted that panic hardware is required for the Temecula
Mercantile Bldg. due to occupancy loads. (09.30.04)
TSCI advised that it has not received a price for painting the
doors and will submit by next meeting.(10.07.04)
McEachron's pricing was submitted during the course of the
meeting as COR#!44 (10.21.04)
Water line construction at Fourth St.: VCM
advised that the Water System Grant Deed was
approved by the City Council on October 261h.
VCM will follow up with the City to determine if
the signed documents have been forwarded to
RCWD.
5.31 a. TSCI confirmed that all documents are in place and N/A Complete
upon payment of fees, a preconstruction meeting can
be scheduled. (11.04.04)
A meeting with RCWD Inspector Charlie Nemish
was held 11.09.04. This item is complete and will
be deleted from future meeting agendas. (11.12.04)
Wheel Chair Lift: TSCI noted that the submittal
for the wheel chair lift indicates a solid door at
each landing and that the submittal was returned
annotated "Make Corrections Noted". No door is
reflected on the architectural plan or door
schedule. Following discussion, it was
determined that TSCI will submit an RFI for
clarification.
RFI 210 has been submitted and responded.
5.32a (10.21.04) 11/10/04 FSY
The lift supplier has noted that a door at the lower
opening and a 42-inch high gate at the upper opening
is required by Code. This information has been
forwarded to FSY for implementation if required.
(10.28.04)
FSY advised that it can find no code requirement
for a door at the lower opening. Following
discussion, FSY will review the State Elevator
Code. (11.04.04)
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 36
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Waterproofing of siding in contact with steel
columns: TSCI referenced Details 1 and 2, Sht
A5.03 and noted that there do not appear to be
provisions for waterproofing and/or flashing
36 5.35b. where the cedar siding comes into contact with 11/17/04 FSY
the steel columns. Following discussion, it was
determined that TSCI will follow up with an RFI.
RFI 237 was submitted 11.05.04 and remains
unanswered. 11.12.04
Color Board: TSCI noted that colors are not
5.36a. defined in the contract documents and 11/17/04 FSY
questioned whether or not a color board could be
provided for site use.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting#: 35
Owner: City of Temecula
Project: ,Old Town Temecula
Community Theater
Date: November4, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: Steve Tovey,Tovey Shultz Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
Construction, Inc. (TSCI) Construction, Inc(TSCI) Construction, Inc(TSCI)
Dean Lee, FSY Architects Armineh Gharibans, ENA Larry Campbell,Vanir
(FSY) Group(ENA) Construction Mgmt(VCM)
Meeting # Item # Description Due Action
35 1.0 Approval Of Previous Meeting Minutes:
1.35 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 34.
2.0 Construction Progress Update:
2.35 Framing for the classroom building, restroom N/A Info
building and dance studio, along with electrical,
plumbing, and HVAC rough-in has continued.
Steel erection at the fly loft section is continuing
and work on the 6-inch sewer line within the site
is substantially complete.
3.0 Technical Concerns:
3a Schedule Review:
3a.35a Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Framing will continue as will electrical,
plumbing and HVAC rough-ins for the next
several weeks. Site water will begin next week
following completion of the sewer work. This
work will be followed by the work in Fourth
Street. Structural steel is scheduled to continue
and installation of the 8-inch AV conduit is
tentatively scheduled to begin next week based
upon the progress of the structural steel
3a.34b TSCI's monthly schedule update will be 11/04/04 TSCI
submitted by the next meeting.
TSCI's monthly schedule update will be submitted by
Tuesday, 11.09.04(11.04.05)
Page 1 of 6
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 35
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
35 3b Submittal Status Review:
3b.35 VCM's submittal log was reviewed during the 11/10/04 FSY
course of the meeting. 107 submittals (including
resubmittals) have been received to date. 4
submittals remain outstanding. All of the four
have been outstanding in excess of two
weeks. Submittal No. 58, Resilient Flooring,
has been outstanding for 87 days. Submittal
No. 13B was returned during the course of the
meeting.
3c Request For Information Status Review:
3c.35 VCM's RFI log was reviewed during the 11/10/04 FSY
course of the meeting. 256 RFI's (including
revisions) have been submitted to date. 8 RFI's
are outstanding. Of the eight, 5 have been
outstanding in excess of two weeks.
3d Field Clarification Status Review:
3d.35 To date, 8 Architect's Supplemental
Instructions, 2 Field Clarifications, and 10
Construction Bulletins have been issued. N/A Info
Bulletin No. 11, reflecting revisions to the plywood
sinks,was received during the course of the
meeting. 11.04.04
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 6 was sent to TSCI
3e.1.33 Tuesday, October 19. N/A Info
Signed Change Order No. 6 was returned
during the course of the meeting. 10.28.04
3e.2 Proposed Change Orders
3e.2.35 Seventy one potential change requests have 11/10/04 TSCINCM
been identified. Of those, 45 have been
submitted. 27 of the change requests have
been incorporated in Change Orders. 8 of the
COR's have been voided. 7 COR's have
been rejected.
3f Payment Status Review:
3f.35 TSCI's Payment Request No. 8 was received 11/05/04 VCM
during the course of the meeting. The
payment request will be reviewed and
forwarded to the City of Temecula for
processing.
Page 2 of 6 VANIR F 503
VAN I R PROGRESS MEETING MINUTES
Meeting#: 35
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
35 3g Notice Of Non Conformance Status:
3g.35 There are no outstanding correction notices at N/A Info
this date.
3h As Built Status Review:
3h.35 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.35 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.34 Kleinfelder has been on site this week for steel N/A Info
observation and compaction testing.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David
McBride will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will
5g.236 be photographed beside the on-site material for 11/05/04 TSCI
comparison purposes. (10.07.04).
Photos were forwarded to D. McBride Friday, 10/8,
and are still being reviewed. TSCI advised that it has
found an alternate source for granite and is in the
process of obtaining samples. (10.14.04)
A brochure with price list from Swenson Granite has
been forwarded to D. McBride for review (10.21.04)
Frahm pricing will be submitted tomorrow.
(11.04.05)
Storefront at Mercantile Building:
5.25b TSCI expressed concern for the condition of the
existing storefront at the Mercantile Building.
Page 3 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 35
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
35 5.25b Storefront at Mercantile Building: (Continued)
Following discussion, it was determined that
McEachron Construction will be asked to
review the present condition and make
recommendations for restoration.
TSCI and VCM met with McEachron Construction on
8/30/04 to discuss restoration of the storefront and
replacement of missing windows. McEachron will provide
ideas, alternates,and pricing to TSCI (09.02.04) City Of
A"laundry list"of ideas was forwarded to D. McBride prior to 11/04/04
the meeting for review and direction. (09.23.04) Temecula
TSCI was asked to formally submit McEachron's proposal.
VCM noted that panic hardware is required for the
Mercantile Bldg.due to occupancy loads. (09.30.04)
TSCI advised that it has not received a price for painting the
doors and will submit by next meeting.(10.07.04)
McEachron's pricing was submitted during the course of the
meeting as COR#44(10.21.04)
Plywood Sinks: There was discussion regarding
the plywood sinks as designed by FSY. Paul
Donaldson is requesting certification that wood
sinks meet sanitation standards. D. McBride
advised that wood sinks are not acceptable.
VCM to discuss with FSY.
FSY was directed to find an alternative solution to the
plywood sinks still retaining design intent. (09/09/04)
Following discussion it was agreed that the bulletin to
5.26a be issued for the polished concrete countertop will N/A Complete
include necessary revisions to the sink and faucet.
(10.14.04)
D. Lee confirmed that the original lavatory and faucet
will be used. The bulletin reflecting the polished
concrete counter top will be issued early next week.
(10.21.04)
Bulletin No. 11 was presented during the course of
the meeting. (11.04.04)
Revised property wall @ Pottery Shop: TSCI
asked the status of the revised details for the
property wall between the project site and the
pottery shop. A sketch of the new wall without
light fixtures was reviewed by VCM and TSCI
5.29a earlier in the week and found to be acceptable. 10/15/04 TSCI
FSY will issue a complete package as either a
Supplemental Instruction or a Bulletin.
RFP No. 14 requesting pricing on ASI No.7 was
forwarded to TSCI on 10.01.04. (10.07.04)
Page 4 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 35
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
35 Water line construction at Fourth St.: VCM
advised that the Water System Grant Deed was
approved by the City Council on October 26tn
VCM will follow up with the City to determine if
5.31a. the signed documents have been forwarded to 11/10/04 TSCI
RCWD.
TSCI confirmed that all documents are in place
and upon payment of fees, a preconstruction
meeting can be scheduled. 11.04.04
Wheel Chair Lift: TSCI noted that the submittal
for the wheel chair lift indicates a solid door at
each landing and that the submittal was returned
annotated "Make Corrections Noted". No door is
reflected on the architectural plan or door
schedule. Following discussion, it was
determined that TSCI will submit an RFI for
clarification.
5.32a RFI 210 has been submitted and responded. 11/10/04 FSY
(10.21.04)
The lift supplier has noted that a door at the lower
opening and a 42-inch high gate at the upper opening
is required by Code. This information has been
forwarded to FSY for implementation if required.
(10.28.04)
FSY advised that it can find no code requirement
for a door at the lower opening. Following
discussion, FSY will review the State Elevator
Code. 11.04.04
Air Conditioning Unit @ Telephone Room:
TSCI expressed concern that a drawing for the
air conditioning unit to be added to the
Telephone Room has not be received. VCM to
5.34 follow up with FSY regarding the specification for 11/12/04 TSCI
the A/C unit, hangers, and revised room layout to
incorporate Muzak and other City installed
equipment.
Bulletin No. 10 was issued as RFP No. 14 to TSCI
on Monday, 11.01.04. 11.04.04
5.35a. Veteran's Day Holiday: TSCI advised that it will N/A Info
be working on Thursday, 11.11.04.
Waterproofing of siding in contact with steel
columns: TSCI referenced Details 1 and 2, Sht
A5.03 and noted that there do not appear to be
5.35b. provisions for waterproofing and/or flashing 11/05/04 TSCI
where the cedar siding comes into contact with
the steel columns. Following discussion, it was
determined that TSCI will follow up with an RFI.
Page 5 of 6 VANIR F 503
VAN I R PROGRESS MEETING MINUTES•
Meeting#: 35
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Finish of exposed beams at Dance Studio: TSCI
noted that the finish schedule does not indicate a
35 5.35c. finish for the exposed beams. Following N/A Info
discussion, FSY concurred that these beams are
to be wire brushed clean and left unfinished.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 6 of 6 VANIR F 503
VANIR , 0 0
PROGRESS MEETING MINUTES
Meeting#: 34_
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: October 28, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File # 15.6
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc(TSCI) Construction, Inc(TSCI) Construction Mgmt(VCM)
Meeting # Item # Description Due Action
34 1.0 Approval Of Previous Meeting Minutes:
1.34 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 33.
2.0 Construction Progress Update:
2.34 Framing for the classroom building and restroom N/A Info
buildings along with electrical and plumbing
rough-in has continued. Steel erection resumed
on Monday and work on the 6-inch sewer line
has been in progress. The drop intake for the
24-inch storm drain was constructed yesterday
but remains to be stripped. The majority of the
day on Monday 10/25 was spent on clean-up
from last week's storm.
3.0 Technical Concerns:
3a Schedule Review:
3a.34a Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Framing will continue as will electrical
and plumbing rough-ins for the next several
weeks. Site water will begin next week following
completion of the sewer work. This work will be
followed by the work in Fourth Street. Structural
steel is scheduled to continue and installation of
the 8-inch AV conduit is tentatively scheduled
based upon the progress of the structural steel
3a.34b TSCI's monthly schedule update will be 11/04/04 TSCI
submitted by the next meeting.
Page 1 of 5
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 34
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
34 3b Submittal Status Review:
3b.34 VCM's submittal log was reviewed during the 11/03/04 FSY
course of the meeting. 107 submittals (including
resubmittals) have been received to date. 5
submittals remain outstanding. Three of the
five have been outstanding in excess of two
weeks. Submittal No. 58, Resilient Flooring,
has been outstanding for 80 days.
3c Request For Information Status Review:
3c.34 VCM's RFI log was reviewed during the 11/03/04 FSY
course of the meeting. 252 RFI's (including
revisions)have been submitted to date. 13 RFI's
are outstanding. Of the thirteen, 2 have been
outstanding in excess of two weeks.
3d Field Clarification Status Review:
3d.34 To date, 8 Architect's Supplemental
Instructions, 2 Field Clarifications, and 9 N/A Info
Construction Bulletins have been issued.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 6 was sent to TSCI
3e.1.33 Tuesday, October 19. N/A Info
Signed Change Order No. 6 was returned
during the course of the meeting. 10.28.04
3e.2 Proposed Change Orders
3e.2.34 Seventy potential change requests have been 11/03/04 TSCINCM
identified. Of those, 43 have been submitted.
25 of the change requests have been
incorporated in Change Orders. 9 of the
COR's have been voided. 8 COR's have
been rejected.
3f Payment Status Review:
3f.34 TSCI's draft Payment Request No. 8 was 11/04/04 TSCI
reviewed following the meeting. TSCI to make
corrections as required but submit for
processing with required releases.
Page 2 of 5 VANIR F 503
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 34
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
34 3g Notice Of Non Conformance Status:
3g.34 There are no outstanding correction notices at N/A Info
this date.
3h As Built Status Review:
3h.34 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.34 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.34 Kleinfelder has not been on site this week due N/A Info
to weather conditions.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David
McBride will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will City of
5g.23b be photographed beside the on-site material for 10/28/04 Temecula
comparison purposes. (10.07.04)
Photos were forwarded to D. McBride Friday, 10/8,
and are still being reviewed. TSCI advised that it has
found an alternate source for granite and is in the
process of obtaining samples. (10.14.04)
A brochure with price list from Swenson Granite
has been forwarded to D. McBride for review
(10.21.04)
32 Storefront at Mercantile Building: TSCI
expressed concern for the condition of the
existing storefront at the Mercantile Building.
Following discussion, it was determined that
McEachron Construction will be asked to
5.25b review the present condition and make
recommendations for restoration.
TSCI and VCM met with McEachron Construction on
8/30/04 to discuss restoration of the storefront and
replacement of missing windows. McEachron will provide
ideas,alternates,and pricing to TSCI (09.02.04)
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 34
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
34 5.25b Storefront at Mercantile Building: (Continued)
A"laundry list"of ideas was forwarded to D. McBride prior to
the meeting for review and direction. (09.23.04)
TSCI was asked to formally submit McEachron's proposal.
VCM noted that panic hardware is required for the
Mercantile Bldg. due to occupancy loads. (09.30.04) City of
11/04/04
TSCI advised that it has not received a price for painting the Temecula
doors and will submit by next meeting. (10.07.04)
McEachron's pricing was submitted during the course
of the meeting as COR#44(10.21.04)
Plywood Sinks: There was discussion regarding
the plywood sinks as designed by FSY. Paul
Donaldson is requesting certification that wood
sinks meet sanitation standards. D. McBride
advised that wood sinks are not acceptable.
VCM to discuss with FSY.
FSY was directed to find an alternative solution to the
plywood sinks still retaining design intent. (09/09/04)
5.26a Following discussion it was agreed that the bulletin to 10/25/04 FSY
be issued for the polished concrete countertop will
include necessary revisions to the sink and faucet.
(10.14.04)
D. Lee confirmed that the original lavatory and
faucet will be used. The bulletin reflecting the
polished concrete counter top will be issued early
next week. (10.21.04)
Revised property wall @ Pottery Shop: TSCI
asked the status of the revised details for the
property wall between the project site and the
pottery shop. A sketch of the new wall without
light fixtures was reviewed by VCM and TSCI
5.29a earlier in the week and found to be acceptable. 10/15/04 TSCI
FSY will issue a complete package as either a
Supplemental Instruction or a Bulletin.
RFP No. 14 requesting pricing on ASI No.7 was
forwarded to TSCI on 10.01.04. (10.07.04)
Water line construction at Fourth St.: VCM
advised that the Water System Grant Deed was
approved by the City Council on October 1h.
5.31a. VCM will follow up with the City to determine if 10/28/04 VCMI
the signed documents have been forwarded to
RCW D.
Page 4 of 5 VANIR F 503
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 34
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Wheel Chair Lift: TSCI noted that the submittal
for the wheel chair lift indicates a solid door at
each landing and that the submittal was returned
annotated "Make Corrections Noted". No door is
reflected on the architectural plan or door
schedule. Following discussion, it was
determined that TSCI will submit an RFI for
5.32a clarification. 11/04/04 FSY
RFI 210 has been submitted and responded.
(10.21.04)
The lift supplier has noted that a door at the lower
opening and a 42-inch high gate at the upper
opening is required by Code. This information
has been forwarded to FSY for implementation if
required. 10.28.04
Roof Drains @ Mercantile Bldg. TSCI asked the
intent regarding the existing roof drains and
5.33a scuppers at the Mercantile Building. Following N/A Info
discussion, it was determined that roof drains will
flow onto the covered walkway and the water will
drain down into the gutter.
Air Conditioning Unit @ Telephone Room:
TSCI expressed concern that a drawing for the
air conditioning unit to be added to the
5.34 Telephone Room has not be received. VCM to 10/29/04 VCM
follow up with FSY regarding the specification for
the A/C unit, hangers, and revised room layout to
incorporate Muzak and other City installed
e ui ment.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 33
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: October 21, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.8
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: Steve Tovey,Tovey Shultz Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
Construction, Inc. (TSCI) Construction, Inc(TSCI) Construction, Inc (TSCI)
Larry Campbell,Vanir Dean Lee, FSY Architects
Construction Mgmt(VCM) (FSY)
Meeting # Item # Description Due Action
33 1.0 Approval Of Previous Meeting Minutes:
1.33 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 33.
2.0 Construction Progress Update:
2.33 While framing for the classroom building and N/A Info
restroom buildings along with electrical and
plumbing rough-in has continued, no work on
critical path activities has occurred this week due
to rain and muddy conditions. The switch over to
the permanent transformer occurred last Friday,
10/15/04.
3.0 Technical Concerns:
3a Schedule Review:
3a.33 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Framing will continue as will electrical
and plumbing rough-ins for the next several
weeks. Site water will begin next week following
completion of the sewer work. This work will be
followed by the work in Fourth Street. Structural
steel is scheduled to resume on Monday.
Installation of the 8-inch AV conduit is tentative
based upon the progress of the structural steel
erection.
3a.32. TSCI's monthly schedule update was received on 11/01/04 TSCI
Tuesday, 10/12 and has been forwarded to
Sacramento for review.
Review comments were forwarded to TSCI on
Tuesday, 10/18/04. Addition of predecessor and
successor activities should be added to the next
schedule update. (10.21.04)
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 33
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
33 3b Submittal Status Review:
3b.33 VCM's submittal log was reviewed during the 10/27/04 FSY
course of the meeting. 106 submittals (including
resubmittals) have been received to date. 4
submittals remain outstanding. Two of the four
have been outstanding in excess of two
weeks. Submittal No. 58, Resilient Flooring,
has been outstanding for 73 days. Submittal
No. 57, Theater Seating, was returned during
the course of the meeting.
3c Request For Information Status Review:
3c.33 VCM's RFI log was reviewed during the 10/27/04 FSY
course of the meeting. 243 RFI's (including
revisions) have been submitted to date. 9 RFI's
are outstanding. None of these has been
outstanding in excess of two weeks.
3d Field Clarification Status Review:
3d.31 Architect's Supplemental Instruction No. 8 has
been received but not distributed pending
clarification of attachments. N/A Info
ASI 8 was forwarded to TSCI on Friday, October
15. 10.21.04
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 5 was signed and returned
3e.1.33 during the course of the meeting. Change N/A Info
Order No. 6 was sent to TSCI Tuesday,
October 19.
3e.2 Proposed Change Orders
3e.2.33 Sixty eight potential change requests have 10/27/04 TSCINCM
been identified. Of those, 47 have been
submitted. 25 of the change requests have
been incorporated in Change Orders. 9 of the
COR's have been voided. 5 COR's have
been rejected.
3f Payment Status Review:
302 TSCI's Payment Request No. 7 was forwarded 11/08/04 City of
to the City of Temecula for processing on Temecula
October 8.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 33
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
33 3g Notice Of Non Conformance Status:
3g.33 There are no outstanding correction notices at N/A Info
this date.
3h As Built Status Review:
3h.33 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.33 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.33 Kleinfelder has not been on site this week due N/A Info
to weather conditions. The structural steel
inspector is scheduled to return to the site
Monday, 10/25.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David
McBride will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples will City of
5g.23b be photographed beside the on-site material for 10/28/04 Temecula
comparison purposes. (10.07.04)
Photos were forwarded to D. McBride Friday, 10/8,
and are still being reviewed. TSCI advised that it has
found an alternate source for granite and is in the
process of obtaining samples. (10.14.04)
A brochure with price list from Swenson Granite
has been forwarded to D. McBride for review
(10.21.04)
32 Storefront at Mercantile Building: TSCI
expressed concern for the condition of the
existing storefront at the Mercantile Building.
5.25b Following discussion, it was determined that
McEachron Construction will be asked to
review the present condition and make
recommendations for restoration.
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 33
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
33 5.25b Storefront at Mercantile Building: (Continued)
TSCI and VCM met with McEachron Construction on
8/30/04 to discuss restoration of the storefront and
replacement of missing windows. McEachron will provide
ideas, alternates, and pricing to TSCI (09.02.04)
A"laundry list"of ideas was forwarded to D. McBride prior to
the meeting for review and direction. (09.23.04) City Of
TSCI was asked to formally submit McEachron's proposal. 10/18/04 Temecula
VCM noted that panic hardware is required for the
Mercantile Bldg.due to occupancy loads. (09.30.04)
TSCI advised that it has not received a price for painfing the
doors and will submit by next meeting. (10.07.04)
McEachron's pricing was submitted during the course
of the meeting as COR#44 10.21.04
Plywood Sinks: There was discussion regarding
the plywood sinks as designed by FSY. Paul
Donaldson is requesting certification that wood
sinks meet sanitation standards. D. McBride
advised that wood sinks are not acceptable.
VCM to discuss with FSY.
FSY was directed to find an alternative solution to the
5.26a plywood sinks still retaining design intent. (09/09/04) 10/25/04 FSY
Following discussion it was agreed that the bulletin to
be issued for the polished concrete countertop will
include necessary revisions to the sink and faucet.
(10.14.04)
D. Lee confirmed that the original lavatory and
faucet will be used. The bulletin reflecting the
polished concrete counter top will be issued early
next week. 10.21.04
Revised property wall @ Pottery Shop: TSCI
asked the status of the revised details for the
property wall between the project site and the
pottery shop. A sketch of the new wall without
light fixtures was reviewed by VCM and TSCI
5.29a earlier in the week and found to be acceptable. 10/15/04 TSCI
FSY will issue a complete package as either a
Supplemental Instruction or a Bulletin.
RFP No. 14 requesting pricing on ASI No. 7 was
forwarded to TSCI on 10.01.04. (10.07.04)
Water line construction at Fourth St.: TSCI
inquired as to the status of the documentation
from the City of Temecula regarding Rancho
5.31a. Water District. VCM advised that the Water 10/14/04 TSCI
System Grant Deed requires City Council
approval and that the next meeting that this issue
can be placed on the agenda is October 261"
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 33
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Water line construction at Fourth St.: (continued)
Following discussion, it was determined that
TSCI will contact Mike Meyerpeter to determine
whether a pre-construction meeting can be held
and work can proceed prior to receipt of the
required Grant Deed and Agency Agreement.
32 5.31a. David McBride provided a copy of a letter sent to 10/25/04 TSCI
RCWD regarding council approval of the grant deed
and Agency Agreement. TSCI to follow up with
RCWD to schedule a pre-construction meeting.
(10.14.04)
TSCI to follow up with RCWD to schedule the
required re-construction meeting. 10.21.04
Wheel Chair Lift: TSCI noted that the submittal
for the wheel chair lift indicates a solid door at
each landing and that the submittal was returned
annotated "Make Corrections Noted". No door is
reflected on the architectural plan or door
5.32a N/A Info
schedule. Following discussion, it was
determined that TSCI will submit an RFI for
clarification.
RFI 210 has been submitted and responded.
10.21.04
Roof Drains @ Mercantile Bldg. TSCI asked the
intent regarding the existing roof drains and
5.33a scuppers at the Mercantile Building. Following N/A Info
discussion, it was determined that roof drains will
flow onto the covered walkway and the water will
drain down into the gutter.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 32
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: October 14, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner:
File# 15.13
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
(City of Temecula) Construction, Inc (TSCI) Construction, Inc(TSCI)
Larry Campbell,Vanir
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
32 1.0 Approval Of Previous Meeting Minutes:
1.32 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 31.
2.0 Construction Progress Update:
2.32 Tie-in of the sewer to the existing main in Main N/A Info
Street is in progress. JC Framing continued
framing for the classroom building and restroom
buildings. Floor joists for the second floor of the
Classroom Building are being installed. Electrical
and plumbing rough-in in framing is in progress.
Backfill at the stage area and audience chamber
is in progress and SCE subcontractor Henkels &
McCoy are installing cable for the switch over to
the permanent transformer scheduled for
tomorrow.
3.0 Technical Concerns:
3a Schedule Review:
3a.31 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Installation of the catch basins for the
24-inch storm drain and framing will continue into
next week. Framing will continue as will
electrical and plumbing rough-ins for the next
several weeks. Site water will begin next week to
be followed by the work in Fourth Street.
Structural steel is scheduled to resume on
Monday. Installation of the 8-inch AV conduit is
scheduled to begin on Monday.
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 32
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
32 3a Schedule Review:
3a.32. TSCI's monthly schedule update was received on 10/22/04 VCM
Tuesday, 10/12 and has been forwarded to
Sacramento for review.
3b Submittal Status Review:
3b.32 VCM's submittal log was reviewed during the 10/20/04 FSY
course of the meeting. 104 submittals (including
resubmittais) have been received to date. 4
submittals remain outstanding. Three of the
four have been outstanding in excess of two
weeks. Submittal No. 56, Theater Seating,
has been outstanding for 77 days and is
becoming critical with respect to placement of
AV boxes under seats.
3c Request For Information Status Review:
3c.32 VCM's RFI log was reviewed during the 10/20/04 FSY
course of the meeting. 229 RFI's (including
revisions) have been submitted to date. 4 RFI's
are outstanding. None of these has been
outstanding in excess of two weeks.
3d Field Clarification Status Review:
3d.31 Architect's Supplemental Instruction No. 8 has 10/15/04 VCM
been received but not distributed pending
clarification of attachments.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 5 has been forwarded to 10/20/04 TSCI
3e.1.32 TSCI for signature.
Change Order No. 6 is still being drafted. 10/22/04 City of Temecula
3e.2 Proposed Change Orders
3e.2.32 Sixty six potential change requests have been 10/20/04 TSCl/VCM
identified. Of those, 43 have been submitted.
28 of the change requests have been
incorporated in Change Orders. 7 of the
COR's have been voided. 3 COR's have
been rejected.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 32
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
32 3f Payment Status Review:
302 TSCI's Payment Request No. 7 was forwarded 11/08/04 City of
to the City of Temecula for processing on Temecula
October 8.
3g Notice Of Non Conformance Status:
3g.32 There are no outstanding correction notices at N/A Info
this date.
3h As Built Status Review:
3h.32 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.32 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.32 Kleinfelder has been on site this week to N/A Info
perform compaction testing. The structural
steel inspector is scheduled to return to the
site Monday, 10/18.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David
McBride will follow up with John Meyer.
D. McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
5g.23b Six samples have been delivered. Those samples will 10/21/04 TSCI
be photographed beside the on-site material for
comparison purposes. (10.07.04)
Photos were forwarded to D. McBride Friday, 10/8,
and are still being reviewed. TSCI advised that it
has found an alternate source for granite and is in
the process of obtaining samples. (10.14.04)
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 32
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
32 Storefront at Mercantile Building: TSCI
expressed concern for the condition of the
existing storefront at the Mercantile Building.
Following discussion, it was determined that
McEachron Construction will be asked to
review the present condition and make
recommendations for restoration.
TSCI and VCM met with McEachron Construction on
5.25b 8/30/04 to discuss restoration of the storefront and 10/14/04 TSCI
replacement of missing windows. McEachron will provide
ideas, alternates, and pricing to TSCI (09.02.04)
A"laundry list"of ideas was forwarded to D. McBride prior to
the meeting for review and direction. (09.23.04)
TSCI was asked to formally submit McEachron's proposal.
VCM noted that panic hardware is required for the
Mercantile Bldg. due to occupancy loads. (09.30.04)
TSCI advised that it has not received a price for painting
the doors and will submit by next meeting. 10.07.04
Plywood Sinks: There was discussion regarding
the plywood sinks as designed by FSY. Paul
Donaldson is requesting certification that wood
sinks meet sanitation standards. D. McBride
advised that wood sinks are not acceptable.
5.26a VCM to discuss with FSY. 09/16/04 FSY
FSY was directed to find an alternative solution to the
plywood sinks still retaining design intent. (09/09/04)
Following discussion it was agreed that the
bulletin to be issued for the polished concrete
countertop will include necessary revisions to the
sink and faucet. 10.14.04
Revised property wall @ Pottery Shop: TSCI
asked the status of the revised details for the
property wall between the project site and the
pottery shop. A sketch of the new wall without
light fixtures was reviewed by VCM and TSCI
5.29a earlier in the week and found to be acceptable. 10/15/04 TSCI
FSY will issue a complete package as either a
Supplemental Instruction or a Bulletin.
RFP No. 14 requesting pricing on ASI No. 7 was
forwarded to TSCI on 10.01.04. (10.07.04)
Water line construction at Fourth St.: TSCI
inquired as to the status of the documentation
from the City of Temecula regarding Rancho
5.31a. Water District. VCM advised that the Water 10/14/04 TSCI
System Grant Deed requires City Council
approval and that the next meeting that this issue
can be placed on the agenda is October 26`h.
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 32
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Water line construction at Fourth St.: (continued)
Following discussion, it was determined that
TSCI will contact Mike Meyerpeter to determine
whether a pre-construction meeting can be held
and work can proceed prior to receipt of the
32 5.31 a. required Grant Deed and Agency Agreement. 10/15/04 TSCI
David McBride provided a copy of a letter sent to
RCWD regarding council approval of the grant
deed and Agency Agreement. TSCI to follow up
with RCWD to schedule a pre-construction
meeting. 10.14.04
Wheel Chair Lift: TSCI noted that the submittal
for the wheel chair lift indicates a solid door at
each landing and that the submittal was returned
5.32a annotated "Make Corrections Noted". No door is 10/15/04 TSCI
reflected on the architectural plan or door
schedule. Following discussion, it was
determined that TSCI will submit an RFI for
clarification.
Property Wall @ Pottery Shop: TSCI expressed
concern for the 6-inch CMU wall supporting the
5.32b property wall behind the Pottery Shop due to the N/A Info
size of the cell in the block. Following
discussion, TSCI was directed to revise the 6-
inch CMU to 8-inch.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
------ --------
Page 5 of 5 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: 31
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: October 7, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: Dean Lee, FSY Architects Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
(FSY) Construction, Inc(TSCI) Construction, Inc(TSCI)
Larry Campbell,Vanir
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
31 1.0 Approval Of Previous Meeting Minutes:
1.31 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 30.
2.0 Construction Progress Update:
2.31 The storm drain work continued during the past N/A Info
week along with sub-surface drainage that ties
into the storm drain. Waterproofing of basement
walls is complete and concrete placed for the
footings in the Scene Shop. JC Framing
continued framing for the classroom building and
began framing at the restroom buildings. CMU at
the eastern property wall is in progress with
grouting scheduled for Friday. Electrical and
plumbing rough-in in framing is in progress.
3.0 Technical Concerns:
3a Schedule Review:
3a.31 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Installation of the catch basins for the
24-inch storm drain and framing will continued
through the next week. The 6-inch sewer
connection to Main St. is scheduled to begin on
Tuesday, 10/12. Backfill and grading behind
basement walls is scheduled to begin tomorrow
and continue through next week followed by
installation of rebar and concrete for the slab at
the Scene Shop. Edison power transfer to the
new permanent transformer is scheduled for
Thursday and Friday of next week. Installation of
the 8-inch conduit at the Audience Chamber is
scheduled to begin next week following backfill.
Page 1 of 6
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 31
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
31 3a Schedule Review:
3a.29a TSCI's monthly schedule update was received on 10/08/04 TSCI
Monday, 9/20 and has been forwarded to
Sacramento for review.
Review comments have been received and will be
forwarded on Friday, 1011. (09.30.04)
A revised schedule incorporating the review
comments will be forwarded by the next meeting.
10.07.04
3b Submittal Status Review:
3b.31 VCM's submittal log was reviewed during the 10/13/04 FSY
course of the meeting. 103 submittals (including
resubmittals) have been received to date. 5
submittals remain outstanding. Three of the
five have been outstanding in excess of two
weeks. Submittal No. 56, Theater Seating,
has been outstanding for 70 days.
3c Request For Information Status Review:
3c.31 VCM's RFI log was reviewed during the 10/13/04 FSY
course of the meeting. 225 RFI's (including
revisions) have been submitted to date. 3 RFI's
are outstanding. All 3 of these has been
outstanding in excess of two weeks with the
longest outstanding being RFI No. 186 which
has been outstanding for 45 days.
3d Field Clarification Status Review:
3d.31 Architect's Supplemental Instruction No. 14 for N/A Info
revisions to the southern property wall was
issued on Friday, 10/01.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 5 and 6 have been drafted City of
3e.1.30 and forwarded to the City of Temecula for 10/11/04 Temecula
review and approval.
3e.2 Proposed Change Orders
3e.2.29 Sixty two potential change requests have been 10/14/04 TSCINCM
identified. Of those, 43 have been submitted.
31 of the change requests have been
incorporated in Change Orders. 7 of the
COR's have been voided. 2 COR's have
been rejected.
Page 2 of 6 VANIR F 503
VAN 1 R `OGRESS MEETING MINUTES•
Meeting#: 31
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
31 3f Payment Status Review:
3f.31 TSCI's Payment Request No. 7 was received 10/08/04 VCM
prior to the meeting and will be reviewed and
forwarded to the City for processing.
3g Notice Of Non Conformance Status:
3g.31 There are two outstanding correction notice N/A Complete
related to the approval of plan revisions and
the attachment of waterproofing to walls.
(NOTE) Both correction notices were signed off
by Bldg. Inspector Bob Henderson subsequent
to the meeting.
3h As Built Status Review:
3h.31 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.31 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.31 Kleinfelder has been on site this week to N/A Info
perform masonry inspection.
5.0 New Business:
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David
McBride will follow up with John Meyer.
5g.23b D. McBride asked TSCI to explore other options for 10/11/04 VCM
providing the granite including alternate designs.
(08/26/04)
Six samples have been delivered. Those samples
will be photographed beside the on-site material
for comparison purposes. (10.07.04)
Acoustic Review of HVAC: TSCI asked
whether the HVAC system has been reviewed
5.25a by the acoustical consultant. FSY stated that 09/02/04 FSY
there are no units on the theater building but
will have air velocities reviewed.
Page 3 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 31
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
31 Storefront at Mercantile Building: TSCI
expressed concern for the condition of the
existing storefront at the Mercantile Building.
Following discussion, it was determined that
McEachron Construction will be asked to
review the present condition and make
recommendations for restoration.
TSCI and VCM met with McEachron Construction on
5.25b 8/30/04 to discuss restoration of the storefront and 10/14/04 TSCI
replacement of missing windows. McEachron will provide
ideas, alternates, and pricing to TSCI (09.02.04)
A"laundry list"of ideas was forwarded to D. McBride prior to
the meeting for review and direction. (09.23.04)
TSCI was asked to formally submit McEachron's proposal.
VCM noted that panic hardware is required for the
Mercantile Bldg. due to occupancy loads. (09.30.04)
TSCI advised that it has not received a price for painting
the doors and will submit by next meeting. (10.07.04)
Plywood Sinks: There was discussion regarding
the plywood sinks as designed by FSY. Paul
Donaldson is requesting certification that wood
sinks meet sanitation standards. D. McBride
5.26a advised that wood sinks are not acceptable. 09/16/04 FSY
VCM to discuss with FSY.
FSY was directed to find an alternative solution to
the plywood sinks still retaining design intent.
(09/09/04)
Revised property wall @ Pottery Shop: TSCI
asked the status of the revised details for the
property wall between the project site and the
pottery shop. A sketch of the new wall without
light fixtures was reviewed by VCM and TSCI
5.29a earlier in the week and found to be acceptable. 10/15/04 TSCI
FSY will issue a complete package as either a
Supplemental Instruction or a Bulletin.
RFP No. 14 requesting pricing on Bulletin No. 14 was
forwarded to TSCI on 10.01.04. (10.07.04)
Default by site utilities subcontractor: TSCI
advised that its utilities subcontract, Kahl
Construction, has refused to honor its
subcontractor and has abandoned the work.
5.29b TSCI has rebid that portion of the work and N/A Info
selected B&A Construction to complete the work
originally contracted to Kahl with an additional
cost of approximately $23,000. TSCI stated that
it is of the opinion that the City of Temecula
Page 4 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 31
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item# Description Due Action
Default by site utilities subcontractor: (Continued)
should be responsible for the added cost
attributing the default of Kahl to the addition of
the storm drain work. Following discussion, D.
McBride stated that Kahl's default is a risk of the
31 5.29b contracting business and that the City of N/A Info
Temecula has no responsibility or liability for the
added cost.
Steve Tovey noted that TSCI is still not satisfied with the
City's response and will continue to review its options.
(09.30.04)
This item will be deleted from future meeting
discussion. 10.07.04
Material transportation cost: TSCI noted that JC
Framing has asked for additional cost as a part of
Change Order Request No. 6 (24-inch Storm
Drain)for the transportation of materials from the
City-provided storage/fabrication area at
Mercedes and Main Streets, stating that storage
of materials on site was negated by the work
5.29c associated with the new storm drain. Following N/A Info
discussion, D. McBride stated that no additional
costs will be allowed for moving materials from
the City lot to the project site. Delivery and
storage of materials is a contractor coordination
issue for which the City has not liability or
responsibility.
This item will be deleted from future meeting
discussion. 10.07.04
Water line construction at Fourth St.: TSCI
inquired as to the status of the documentation
from the City of Temecula regarding Rancho
Water District. VCM advised that the Water
System Grant Deed requires City Council
5.31a. approval and that the next meeting that thisnssue 10/14/04 TSCI
can be placed on the agenda is October 26 .
Following discussion, it was determined that
TSCI will contact Mike Meyerpeter to determine
whether a pre-construction meeting can be held
and work can proceed prior to receipt of the
required Grant Deed and Agency Agreement.
Page 5 of 6 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 31
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 6 of 6 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 30
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: September 30, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.6
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: Steve Tovey,Tovey Shultz Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
Construction, Inc. Construction, Inc(TSCI) Construction, Inc(TSCI)
Larry Campbell,Vanir
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
30 1.0 Approval Of Previous Meeting Minutes:
1.30 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 29.
2.0 Construction Progress Update:
2.30 The storm drain work continued during the past N/A Info
week with the junction structures placed at the
downstream end of the pipe. Waterproofing of
basement walls is in progress and forms have
been placed for the footings in the Scene Shop.
JC Framing continued framing for the classroom
building. Installation of the 4-inch sub-surface
drainage from the orchestra pit to the storm drain
is in progress.
3.0 Technical Concerns:
3a Schedule Review:
3a.30 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Rebar for footings at the Scene Shop is
scheduled for tomorrow morning and concrete for
footings is tentatively scheduled for Monday,
10/4. Work on the storm drain will continue
through next week as will framing. Sewer tie-in
will follow the storm drain work and slab set-up
for the Scene Shop will begin Tuesday, 10/05.
Masonry steps and the property line wall at the
Antique Faire is tentatively scheduled to begin on
Tuesday, 10/5. Edison power transfer to the new
permanent transformer is scheduled for the week
of 10/11.
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 30
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
30 3a Schedule Review:
3a.29a TSCI's monthly schedule update was received on 10/01/04 VCM
Monday, 9/20 and has been forwarded to
Sacramento for review.
Review comments have been received and will be
forwarded on Friday, 10/1. (09.30.04)
3b Submittal Status Review:
3b.30 VCM's submittal log was reviewed during the 10/06/04 FSY
course of the meeting. 103 submittals (including
resubminals) have been received to date. 6
submittals remain outstanding. Four of the six
have been outstanding in excess of two
weeks. Submittal No. 56, Theater Seating,
has been outstanding for 63 days.
3c Request For Information Status Review:
3c.30 VCM's RFI log was reviewed during the 10/06/04 FSY
course of the meeting. 222 RFI's (including
revisions) have been submitted to date. 3 RFI's
are outstanding. All 3 of these has been
outstanding in excess of two weeks with the
longest outstanding being RFI No. 186 which
has been outstanding for 38 days.
3d Field Clarification Status Review:
3d.29 Architect's Bulletin No. 9 for the revised N/A Info
location of gas service point of connection was
issued on Monday, 9/27.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 5 and 6 have been drafted City of
3e.1.30 and forwarded to the City of Temecula for 10/07/04 Temecula
review and approval.
3e.2 Proposed Change Orders
3e.2.29 Sixty two potential change requests have been 10/07/04 TSCl/VCM
identified. Of those, 43 have been submitted.
31 of the change requests have been
incorporated in Change Orders. 7 of the
COR's have been voided. 2 COR's have
been rejected.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 30
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
30 3f Payment Status Review:
3f.30 TSCI's Draft Payment Request No. 7 has been 10/04/04 TSCI
reviewed and returned to TSCI for corrections.
3g Notice Of Non Conformance Status:
3g.28 There is one outstanding correction notice N/A Complete
related to the approval of plan revisions. It Is
anticipated that this issue will be resolved prior
to the next meeting.
Approved plans were received Tuesday,
9128104. This issue is complete and will be
deleted from future discussion. (09.30.04)
3h As Built Status Review:
3h.30 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
31 Safety Items:
3i.30 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.30 Kleinfelder has been on site this week to N/A Info
erform compaction inspection/testing.
5.0 New Business:
5g.19 Reconciliation of Changes to Building Dept. N/A Complete
Approved Plans: (see Item 3c.28,above).
This item is complete and will be deleted from
future discussion. (09.30.04)
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David
5g.23b McBride will follow up with John Meyer. 09/08/04 TSCI
D.McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Acoustic Review of HVAC: TSCI asked
whether the HVAC system has been reviewed
5.25a by the acoustical consultant. FSY stated that 09/02/04 FSY
there are no units on the theater building but
will have air velocities reviewed.
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 30
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
30 Storefront at Mercantile Building: TSCI
expressed concern for the condition of the
existing storefront at the Mercantile Building.
Following discussion, it was determined that
McEachron Construction will be asked to
review the present condition and make
recommendations for restoration.
TSCI and VCM met with McEachron Construction on
5.25b 8/30/04 to discuss restoration of the storefront and 10/07/04 TSCI
replacement of missing windows. McEachron will provide
ideas, alternates, and pricing to TSCI (09.02.04)
A"laundry list"of ideas was forwarded to D. McBride prior to
the meeting for review and direction. (09.23.04)
TSCI was asked to formally submit McEachron's
proposal. VCM noted that panic hardware is required
for the Mercantile Bldg. due to occupancy loads.
(09.39.04)
Plywood Sinks: There was discussion regarding
the plywood sinks as designed by FSY. Paul
Donaldson is requesting certification that wood
sinks meet sanitation standards. D. McBride
5.26a advised that wood sinks are not acceptable. 09/16/04 FSY
VCM to discuss with FSY.
FSY was directed to find an alternative solution to
the plywood sinks still retaining design intent.
(09109/04)
Revised property wall @ Pottery Shop: TSCI
asked the status of the revised details for the
property wall between the project site and the
pottery shop. A sketch of the new wall without
5.29a light fixtures was reviewed by VCM and TSCI 9/29/04 FSY
earlier in the week and found to be acceptable.
FSY will issue a complete package as either a
Supplemental Instruction or a Bulletin.
Default by site utilities subcontractor: TSCI
advised that its utilities subcontract, Kahl
Construction, has refused to honor its
subcontractor and has abandoned the work.
TSCI has rebid that portion of the work and
selected B&A Construction to complete the work N/A Info
originally contracted to Kahl with an additional
cost of approximately $23,000. TSCI stated that
it is of the opinion that the City of Temecula
should be responsible for the added cost
attributing the default of Kahl to the addition of
the storm drain work.
Page 4 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 30
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Default by site utilities subcontractor: (Continued)
Following discussion, D. McBride stated that
Kahl's default is a risk of the contracting business
30 5.29b and that the City of Temecula has no N/A Info
responsibility or liability for the added cost.
Steve Tovey noted that TSCI is still not satisfied with
the City's response and will continue to review its
options. 09.30.04
Material transportation cost: TSCI noted that JC
Framing has asked for additional cost as a part of
Change Order Request No. 6 (24-inch Storm
Drain)for the transportation of materials from the
City-provided storage/fabrication area at
Mercedes and Main Streets, stating that storage
of materials on site was negated by the work
5.29c associated with the new storm drain. Following N/A Info
discussion, D. McBride stated that no additional
costs will be allowed for moving materials from
the City lot to the project site. Delivery and
storage of materials is a contractor coordination
issue for which the City has not liability or
responsibility.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting#: 29
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: September 23, 2004
Location: City of Temecula Distribution: Attendees, Paul Donaldson, Bldg & Safety
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, City of Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
Temecula(DPW) Construction, Inc(TSCI) Construction, Inc(TSCI)
Larry Campbell,Vanir Dean Lee,FSY Architects
Construction Mgmt(VCM) (FSY)
Meeting # Item # Description Due Action'
29 1.0 Approval Of Previous Meeting Minutes:
1.29 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 28.
2.0 Construction Progress Update:
2.29 Frahm Masonry continued the construction of N/A Info
CMU walls at the arbor and orchestra pits. KAR
Construction placed concrete for slabs at the
dance studio, classroom building, restroom and
concession buildings and the poured in place
wall at line 1. JC Framing began layout on
Monday and began installing sill plates at the
classroom building today. B&A Construction
began installation of the 24-inch storm drain on
Monday and Rentex is on site today backfilling.
3.0 Technical Concerns:
3a Schedule Review:
3a.29 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Inspection of CMU walls is scheduled
for later today and grouting is scheduled to
tomorrow. Work on the storm drain will continue
through next week as will framing. Sewer tie-in
will follow the storm drain work and slab set-up
for the Scene Shop will begin Monday, 9/27.
-----Masonry steps and-the -pT9-p ty;line wall at-the
Antique Faire is tentatively scheduled to begin on
Monday, 10/4. Edison power transfer to the new
permanent transformer is scheduled for the week
-of 10/11.
Page 1 of 5
VAN I R PROGRESS MEETING MINUTES
Meeting#: 29
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
29 3a Schedule Review:
3a.29a TSCI's monthly schedule update was received on 09/27/04 VCM
Monday, 9/20 and has been forwarded to
Sacramento for review.
3b Submittal Status Review:
3b.29 VCM's submittal log was reviewed during the 09/27/04 FSY
course of the meeting. 101 submittals (including
resubmittals) have been received to date. 4
submittals remain outstanding. All of the four
have been outstanding in excess of two
weeks. Submittal No. 56, Theater Seating,
has been outstanding for 56 days.
3c Request For Information Status Review:
3c.29 VCM's RFI log was reviewed during the 09/29/04 FSY
course of the meeting. 219 RFI's (including
revisions) have been submitted to date. 7 RFI's
are outstanding. Of those 7, six (6) have been
outstanding in excess of two weeks with the
longest outstanding being RFI Nos. 183 thru
185 that have been outstanding for 38 days.
3d Field Clarification Status Review:
3d.29 Architect's Bulletin No. 9 for the revised N/A Info
location of gas service point of connection was
issued on Monday, 9/27.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 1 thru 4 have been
3e.1.22 executed by both the City of Temecula and N/A Info
TSCI.
3e.2 Proposed Change Orders
3e.2.29 Sixty two potential change requests have been 09/29/04 TSCINCM
identified. Of those, 41 have been submitted.
17 of the change requests have been
=-incorporated—in_Change_Orders:_7_--of=-the__-- - - -- - — .-- --
COR's have been voided. -22 COR's have
been negotiated and are either pending
additional information or are being included in
change orders.
Paget of —VANIR F503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 29
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
3f Payment Status Review:
3f.26 TSCI's Payment Request No. 6 has been 08/30/04 TSCI
forwarded to the City for processing.
3g Notice Of Non Conformance Status:
3g.28 There is one outstanding correction notice N/A Info
related to the approval of plan revisions. It Is
anticipated that this issue will be resolved prior
to the next meeting.
3h As Built Status Review:
3h.29 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.29 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are.
no safety issues unresolved.
4.0 Testing/Inspection:
4.28 Kleinfelder has been on site this week to N/A Info
perform masonry, rebar, concrete, and
compaction inspection/testing.
5.0 New Business:
5g.19 Reconciliation of Changes to Building Dept. 08/31/04 FSY
Approved Plans: (see item 3c.28,above).
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David
5g.23b McBride will follow up with John Meyer. 09/08/04 TSCI
A McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Acoustic Review of HVAC: TSCI asked
whether the HVAC system has been reviewed
by the acoustical consultant stating that
5.25a previous—problems—have—been—encountered= 09/02/04 FSY
with noise from HVAC units and ductwork.
FSY stated that there are no units on the
theater building but will have air velocities
-- _ reviewed. ---------
Page 3 of 5 VANIR F 503
VAN I R PROGRESS MEETING MINUTES
Meeting#: 29
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
29 Storefront at Mercantile Building: TSCI
expressed concern for the condition of the
existing storefront at the Mercantile Building.
Following discussion, it was determined that
McEachron Construction will be asked to
review the present condition and make City of
5.25b recommendations for restoration. 09/30/04 Temecula
TSCI and VCM met with McEachron Construction on
8130/04 to discuss restoration of the storefront and
replacement of missing windows. McEachron will provide
ideas,alternates,and pricing to TSCI (09.02.04)
A 'laundry list" of ideas was forwarded to D. McBride
prior to the meeting for review and direction.(09.23.04)
Plywood Sinks: There was discussion regarding
the plywood sinks as designed by FSY. Paul
Donaldson is requesting certification that wood
sinks meet sanitation standards. D. McBride
5.26a advised that wood sinks are not acceptable. 09/16/04 FSY
VCM to discuss with FSY.
FSY was directed to find an alternative solution to
the plywood sinks still retaining design intent.
09109104
Revised property wall @ Pottery Shop: TSCI
asked the status of the revised details for the
property wall between the project site and the
5.29a pottery shop. A sketch of the new wall without 9/29/04 FSY
light fixtures was reviewed by VCM and TSCI
earlier in the week and found to be acceptable.
FSY will issue a complete package as either a
Su plemental Instruction or a Bulletin.
Default by site utilities subcontractor: TSCI
advised that its utilities subcontract, Kahl
Construction, has refused to honor its
subcontractor and has abandoned the work.
TSCI has rebid that portion of the work and
selected B&A Construction to complete the work
originally contracted to Kahl with an additional
5.29b cost of approximately $23,000. TSCI stated that N/A Info
it is of the opinion that the City of Temecula
should be responsible for the added cost
attributing the default of Kahl to the addition of
the storm drain work. Following discussion, D.
-McB�ide sstated-thaftiPs—di faulfls a risk—of-the
contracting business and that the City of
Temecula has no responsibility or liability for the
added cost.
Page 4 of 5 VANIR F 503
VAN I R PROGRESS MEETING MINUTES
Meeting#: 29
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Material transportation cost: TSCI noted that JC
Framing has asked for additional cost as a part of
Change Order Request No. 6 (24-inch Storm
Drain) for the transportation of materials from the
City-provided storage/fabrication area at
Mercedes and Main Streets, stating that storage
29 5.29c of materials on site was negated by the work N/A Info
associated with the new storm drain. Following
discussion, D. McBride stated that no additional
costs will be allowed for moving materials from
the City lot to the project site. Delivery and
storage of materials is a contractor coordination
issue for which the City has not liability or
responsibility.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing,within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
a
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 28
Owner: cq of Temecula
Project: Old Town Temecula
Community Theater
Date: September 16, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, City of Paul Donaldson, City of Kevin Terry,Tovey Shultz
Temecula (DPW) Temecula Bldg/Safety Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc(TSCI) Construction Mgmt(VCM)
Meetin # Item # Description Due Action
28 1.0 Approval Of Previous Meeting Minutes:
1.28 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 27.
2.0 Construction Progress Update:
2.28 Frahm Masonry continued the construction of N/A Info
CMU walls at the arbor and orchestra pits.
Turnkey Forces and David Shaposchnick have
been installing electrical and plumbing lines
under the slab and in CMU walls. KAR
Construction set slab edge forms for the dance
studio, classroom building, restroom and
concession buildings and the poured in place
wall at line 1. Concrete placement for slabs and
the wall at line 1 is in progress and grout for CMU
walls in scheduled for later today. A pre-
construction meeting was held yesterday with
EMWD regarding the sewer tie-in that is
expected to begin in approximately 3 weeks.
3.0 Technical Concerns:
3a Schedule Review:
3a.28 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. CMU walls will continue at the
orchestra pit through next week. Work on the
storm drain is scheduled to begin Monday,
09/20/04 and framing at the restroom and
concession buildings is scheduled to begin
09/20/04 as well.
Page 1 of 4
VAN I R PROGRESS MEETING MINUTES
Meeting#: 28
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
3a Schedule Review:
28 3a.23a Monthly schedule update review comments were 09/17/04 TSCI
provided to TSCI on Tuesday, 8/31. (09.02.04)
Kevin Terry advised that actual start and finish
dates have been input into the schedule and the
updated schedule is expected to be complete
tomorrow. (09/16/04)
3b Submittal Status Review:
3b.28 100 submittals (including resubmittals) have been 09/22/04 FSY
received to date. 5 submittals remain
outstanding. Of those five, 3 have been
outstanding in excess of two weeks.
3c Request For Information Status Review:
3c.28 218 RA's (including revisions) have been submitted 09/22/04 FSY
to date. 8 RFI's are outstanding. Of those 8,
six (6) have been outstanding in excess of two
weeks.
3d Field Clarification Status Review:
3d.28 No new field clarifications or Architect's N/A Info
Supplemental Instructions have been issued.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 1 thru 4 have been
3e.1.22 executed by both the City of Temecula and N/A Info
TSCI.
3e.2 Proposed Change Orders
3e.2.28 Fifty nine potential change requests have been 09/22/04 TSCINCM
identified. Of those, 38 have been submitted.
Three of those 38 were submitted prior to
today's meeting. 17 of the change requests
have been incorporated in Change Orders. 7
of the COR's have been voided.
3f Payment Status Review:
3f.26 TSCI's Payment Request No. 6 has been 08/30/04 TSCI
forwarded to the City for processing.
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 28
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
28 3g Notice Of Non Conformance Status:
3g.28 There is one outstanding correction notice N/A Info
related to the approval of plan revisions. It Is
anticipated that this issue will be resolved prior
to the next meeting.
3h As Built Status Review:
3h.28 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.28 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.28 Kleinfelder has been on site this week to N/A Info
perform masonry, rebar, and concrete
inspection.
5.0 New Business:
5g.19 Reconciliation of Changes to Building Dept. 08/31/04 FSY
Approved Plans: (see item 3c.17,above).
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David
59.23b McBride will follow up with John Meyer. 09/08/04 TSCI
D.McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Acoustic Review of HVAC: TSCI asked
whether the HVAC system has been reviewed
by the acoustical consultant stating that
previous problems have been encountered
5.25a with noise from HVAC units and ductwork. 09/02/04 FSY
FSY stated that there are no units on the
theater building but will have air velocities
reviewed.
Page 3 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES,
Meeting#: 28
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
28 Storefront at Mercantile Building: TSCI
expressed concern for the condition of the
existing storefront at the Mercantile Building.
Following discussion, it was determined that
McEachron Construction will be asked to
5.25b review the present condition and make 09/09/04 TSCI
recommendations for restoration.
TSCI and VCM met with McEachron Construction on
8/30104 to discuss restoration of the storefront and
replacement of missing windows. McEachron will
provide ideas,alternates, and pricing to TSCI 09.02.04
Plywood Sinks: There was discussion regarding
the plywood sinks as designed by FSY. Paul
Donaldson is requesting certification that wood
sinks meet sanitation standards. D. McBride
5.26a advised that wood sinks are not acceptable. 09/16/04 FSY
VCM to discuss with FSY.
FSY was directed to find an alternative solution to
the plywood sinks still retaining design intent.
09/09/04
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting #: 27
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: September 9, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.6
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, City of Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
Temecula (DPW) Construction, Inc (TSCI) Construction, Inc (TSCI)
Dean Lee, FSY Architects(FSY) Larry Campbell,Vanir
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
27 1.0 Approval Of Previous Meeting Minutes:
1.27 There were no corrections or additions to the N/A Info
Minutes of Meeting No. 26.
2.0 Construction Progress Update:
2.27 Frahm Masonry is constructing CMU walls at the N/A Info
arbor and orchestra pits. Turnkey Forces and
David Shaposchnick are installing electrical and
plumbing lines under the slab and in CMU walls.
KAR Construction is beginning work on slabs.
Campbell Certified is off the job to concentrate on
fabrication.
3.0 Technical Concerns:
3a Schedule Review:
3a.27 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. CMU walls will continue at the
orchestra pit with inspection prior to grouting
tentatively scheduled for Tuesday, 9/14.
Electrical rough-in in CMU walls will continue
through 9/17. Slab set up and concrete
placement will continue through the end of
September and the 24-inch storm drain will begin
on September 13, to be followed by the
installation of site utilities.
3a.23a Monthly schedule update review comments were 09/15/04 TSCI
provided to TSCI on Tuesday, 8/31. (09.02.04)
Page 1 of 4
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 27
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
27 3b Submittal Status Review:
3b.27 98 submittals (including resubmittals) have been 09/13/04 FSY
received to date. 3 submittals remain
outstanding. Of those three, 2 have been
outstanding in excess of two weeks.
3c Request For Information Status Review:
3c.27 216 RFI's (including revisions) have been submitted 09/13/04 FSY
to date. 12 RFI's are outstanding. Of those
12, five (5) have been outstanding in excess of
two weeks.
3d Field Clarification Status Review:
3d.27 No new field clarifications or Architect's N/A Info
Supplemental Instructions have been issued.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 1 thru 4 have been
3e.1.22 executed by both the City of Temecula and N/A Info
TSCI.
3e.2 Proposed Change Orders
3e.2.27 Fifty six potential change requests have been 09/15/04 TSCINCNI
identified. Of those, 35 have been submitted.
17 of the change requests have been
incorporated in Change Orders. 7 of the
COR's have been voided.
3f Payment Status Review:
3f.26 TSCI's Payment Request No. 6 has been 08/30/04 TSCI
forwarded to the City for processing.
26 3g Notice Of Non Conformance Status:
3g.17 There are two outstanding correction notices. 09/09/04 DSI
The correction notice related to the approval of
plan revisions should be finalized next week.
One correction notice relating to plumbing
rough-ins was issued Friday, 9/3, and
corrections are in process. Reinspection is
scheduled for later today.
3h As Built Status Review:
3h.26 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 27
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
27 3i Safety Items:
3i.27 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.27 Kleinfelder has been on site this week to N/A Info
perform masonry inspection.
5.0 New Business:
5g.19 Reconciliation of Changes to Building Dept. 08/31/04 FSY
Approved Plans: (see Item 3c.17,above).
Restroom Fixture Count: Architect's Bulletin
No. 6 for the addition of a water closet was
issued on Monday, 08/31/04.
5g.22 Plumbing rough-in for the added water closet is in N/A Complete
progress. This item will be deleted from future meeting
agendas.(09/09/04)
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
5g.23b that shop drawings are required. David 09/08/04 TSCI
McBride will follow up with John Meyer.
D.McBride asked TSCI to explore other options for
providing the granite including alternate designs.
08/26/04
Acoustic Review of HVAC: TSCI asked
whether the HVAC system has been reviewed
by the acoustical consultant stating that
5.25a previous problems have been encountered 09/02/04 FSY
with noise from HVAC units and ductwork.
FSY stated that there are no units on the
theater building but will have air velocities
reviewed.
Storefront at Mercantile Building: TSCI
expressed concern for the condition of the
existing storefront at the Mercantile Building.
Following discussion, it was determined that
McEachron Construction will be asked to
5.25b . review the present condition and make O9/O9/04 TSCI
recommendations for restoration.
TSCI and VCM met with McEachron Construction on
8/30/04 to discuss restoration of the storefront and
replacement of missing windows. McEachron will
provide ideas,alternates,and pricing to TSCI 09.02.04
Page 3 of 4 VANIR F 503
VAN 1 R •PROGRESS MEETING MINUTE•
Meeting#: 27
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
Plywood Sinks: There was discussion regarding
the plywood sinks as designed by FSY. Paul
Donaldson is requesting certification that wood
sinks meet sanitation standards. D. McBride
5.26a advised that wood sinks are not acceptable. 09/16/04 FSY
VCM to discuss with FSY.
FSY was directed to find an alternative solution to
the plywood sinks still retaining design intent.
09/09/04
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting#: 26
_.._.__.._------_.----
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: September 2, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, City of Paul Donaldson, Building Kevin Terry,Tovey Shultz
Temecula (DPW) & Safety(B&S) Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc(TSCI) Construction Mgmt(VCM)
Meeting # Item # Description Due Action
26 1.0 Approval Of Previous Meeting Minutes:
1.26 The Minutes of Meeting No. 25 are corrected as N/A Info
follows:
Item 5g.9: The firm's name is corrected to read
Cozad& Fox.
2.0 Construction Progress Update:
2.26 Campbell Certified continued the erection of N/A Info
structural steel at the Audience Chamber and
has continued welding columns to base plates
and beams to columns. Turnkey Forces and
David Shaposchnick Inc. have worked on sub-
slab lines in preparation for slab placement for
the wood framed buildings and JC Framing has
been fabricating at the Main/Mercedes site.
3.0 Technical Concerns:
3a Schedule Review:
3a.26 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Campbell Certified will pull off the job at
the end of this work for a period of two to three
weeks to concentrate on shop fabrication.
Construction of CMU walls in the Orchestra Pit
will begin along with preparation for slab
construction on Tuesday, 9/7. Concurrently, the
new 24-inch storm drain will begin on September
7 to be followed by the installation of site utilities.
Page 1 of 4
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 26
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
26 3a Schedule Review: (continued)
3a.23a TSCI's monthly schedule update indicates a 09/15/04 TSCI
delay in project completion of 29 days. Sixteen
of those twenty nine days have been accounted
for in Change Order No. 4. The schedule will be
reviewed and comments forwarded to TSCI.
Review comments were provided to TSCI on
Tuesday, 8131. (09.02.04)
3b Submittal Status Review:
3b.26 98 submittals (including resubmittais) have been 09/08/04 FSY
received to date. 3 submittals remain
outstanding. Of those three, 2 have been
outstanding in excess of two weeks.
3c Request For Information Status Review:
3c.26 208 RFI's (including revisions) have been submitted 09/08/04 FSY
to date. 5 RFI's are outstanding. Of those 5,
all have been outstanding in excess of two
weeks.
3d Field Clarification Status Review:
3d.26 No new field clarifications have been issued. N/A Info
Architect's Supplemental Instruction No. 5 was
issued today indicating some minor relocation
of electrical elements on the stage to eliminate
conflict with other elements.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 1 thru 4 have been
3e.1.22 executed by both the City of Temecula and N/A Info
TSCI.
3e.2 Proposed Change Orders
3e.2.26 Fifty two potential change requests have been 09/10/04 TSCINCM
identified. Of those, 32 have been submitted.
17 of the change requests have been
incorporated in Change Orders. 7 of the
COR's have been voided.
3f Payment Status Review:
3f.26 TSCI's Payment Request No. 6 has been 08/30/04 TSCI
forwarded to the City for processing.
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 26
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
26 3g Notice Of Non Conformance Status:
3g.17 There is one outstanding correction notice 08/31/04 FSY
related to the approval of plan revisions. It is
anticipated that drawings will be back not later
than Monday, 07/26/04. (Dean Lee advised that all
corrections are complete with the exception of the
addition of a fan coil unit for cooling the electrical room
and telephone room)08/12/04
D. Lee advised that revised plans incorporating the new
fan coil unit should be complete by Tuesday, 08/31/04.
(08/26/04)
Corrections were forwarded to D. McBride via Fedex
last night. 09.02.04
3h As Built Status Review:
3h.26 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.26 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.26 Kleinfelder has been on site this week to N/A Info
perform welding inspection.
5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. The majority of materials in the
affected area have been removed. Mr. Green
has asked for an area for temporary storage of
the shed that was disassembled. The area can
be provided at the SW corner of the project site
against the fence. The existing fence at the north
end of the encroachment area will be removed
next week. 08112104
The existing fence was removed on Tuesday. The area has
been substantially cleared. This item is complete and will be
deleted from future meeting agendas.(09.02.04)
5g.19 Reconciliation of Changes to Building Dept. 08/31/04 FSY
Approved Plans: (see Item 3c.17,above).
Restroom Fixture Count: Architect's Bulletin
5g 22 No. 6 for the addition of a water closet was 09/10/04 TSCI
issued on Monday, 08/31/04.
Page 3 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE
Meeting#: 26
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
26 5.0 New Business: (continued)
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David
5g.23b 09/08/04 TSCI
McBride will follow up with John Meyer.
D.McBride asked TSCI to explore other options for
providing the granite including alternate designs.
08/26/04
Acoustic Review of HVAC: TSCI asked
whether the HVAC system has been reviewed
by the acoustical consultant stating that
5.25a previous problems have been encountered 09/02/04 FSY
with noise from HVAC units and ductwork.
FSY stated that there are no units on the
theater building but will have air velocities
reviewed.
Storefront at Mercantile Building: TSCI
expressed concern for the condition of the
existing storefront at the Mercantile Building.
Following discussion, it was determined that
McEachron Construction will be asked to
5.25b review the present condition and make 09/09/04 TSCI
recommendations for restoration.
TSCI and VCM met with McEachron Construction on
8/30/04 to discuss restoration of the storefront and
replacement of missing windows. McEachron will
provide ideas,alternates,and pricing to TSCI 09.02.04
Plywood Sinks: There was discussion regarding
the plywood sinks as designed by FSY. Paul
5.26a Donaldson is requesting certification that wood 09/02/04 VCM
sinks meet sanitation standards. D. McBride
advised that wood sinks are not acceptable.
VCM to discuss with FSY.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
Message • • Page 1 of 1
Larry Campbell
From: David McBride (David.McBride@cityoftemecula.org]
Sent: Monday, August 30, 2004 10:20 AM
To: Larry Campbell
Subject: RE: Minutes, Weekly Progress Meeting No. 25
Larry:
Under item 5g.9 -the firm's name is Cozad & Fox not Kevin & Fox.
David
-----Original Message-----
From: Larry Campbell [mailto:Larry.Campbell@Vanir.com]
Sent: Friday, August 27, 2004 2:26 PM
To: David McBride; 'Dave Anderson'; 'Dean Lee'; 'Kevin Terry'; Ed Deleeuw
(EdDeleeuw@toveyshultz.com); Paul Donaldson
Subject: Minutes, Weekly Progress Meeting No. 25
Gentlemen:
Please find attached a copy of the minutes of Weekly Progress Meeting No. 25 held Thursday, August 26.
If there are questions, corrections, or other comments, please call me.
Outgoing mail is certified Virus Free.
Checked by AVG anti-virus system (http://www.grisoft.com).
Version: 6.0.740/Virus Database:494 -Release Date: 8/16/2004
Incoming mail is certified Virus Free.
Checked by AVG anti-virus system(http://www.grisoft.com).
Version: 6.0.740/Virus Database: 494- Release Date: 8/16/2004
8/30/2004
VANIR
PROGRESS MEETING MINUTES
Meeting #: 25
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: August 26, 2004
Location: City of Temecula Distribution: Attendees,
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, City of Bill McAteer, City of Steve Tovey,Tovey Shultz
Temecula (DPW) Temecula (DPW) Construction, Inc(TSCI)
Paul Donaldson, Building Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Dean Lee, FSY Architects
& Safety(B&S) Construction, Inc(TSCI) Construction, Inc(TSCI) (FSY)
Larry Campbell,Vanir
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
25 1.0 Approval Of Previous Meeting Minutes:
1.25 There were no exceptions or corrections to the N/A Info
Minutes of Meeting No. 24.
2.0 Construction Progress Update:
2.25 Campbell Certified continued the erection of N/A Info
structural steel at the Audience Chamber and
has continued welding columns to base plates
and beams to columns. Frahm Masonry has
completed the re-pointing of interior brick at the
Mercantile Building. Backfill of foundation walls
was completed last Friday. SCE transferred
power to the temporary transformer to provide
service to adjacent businesses yesterday and
removed the existing power line that bisected the
site.
3.0 Technical Concerns:
3a Schedule Review:
3a.25 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Campbell Certified will continue
erection of structural steel next week and then
demobilize for approximately two weeks to
concentrate on fabrication. The first week of
September, construction of CMU walls in the
Orchestra Pit is scheduled to begin along with
preparation for slab construction. Concurrently,
the new 24-inch storm drain is scheduled to
begin on September 7 to be followed by the
installation of site utilities.
Page 1 of 5
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 25
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
25 3a Schedule Review: (continued)
3a.23a TSCI's monthly schedule update indicates a 08/30/04 VCM
delay in project completion of 29 days. Sixteen
of those twenty nine days have been accounted
for in Change Order No. 4. The schedule will be
reviewed and comments forwarded to TSCI.
3b Submittal Status Review:
3b.25 98 submittals (including resubmittals) have been 08/30/04 FSY
received to date. 3 submittals remain
outstanding. Of those three, all have been
outstanding in excess of two weeks.
3c Request For Information Status Review:
3c.25 208 RFI's (including revisions)have been submitted 08/30/04 FSY
to date. 9 RFI's are outstanding. Of those 9,
4 have been outstanding in excess of two
weeks.
3d Field Clarification Status Review:
3d.25 No new field clarifications have been issued. N/A Info
Architect's Supplemental Instruction No. 5 was
issued today indicating some minor relocation
of electrical elements on the stage to eliminate
conflict with other elements.
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 1 thru 4 have been
3e.1.22 executed by both the City of Temecula and N/A Info
TSCI.
3e.2 Proposed Change Orders
3e.2.25 Fifty two potential change requests have been 09/03/04 TSCINCM
identified. Of those, 30 have been submitted.
17 of the change requests have been
incorporated in Change Orders. 7 of the
COR's have been voided.
3f Payment Status Review:
3f.25 TSCI's draft Payment Request No. 6 was 08/30/04 TSCI
reviewed following the meeting. TSCI to
incorporate changes/corrections and submit
with all required lien releases and certified
payrolls.
Page 2 of 5 VANIR F 503
VAN 1 R •ROGRESS MEETING MINUTE•
Meeting#: 25
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
5.0 New Business: (continued)
Restroom Fixture Count: Mark Harold, Deputy
Building Official, City of Temecula, advised
that there is some doubt as to whether or not
the proper number of water closets is being
provided for the Men's restroom. This issue
was not noted on either of the plan reviews but
needs to be verified. FSY will be directed to
provide sketches for the addition of one water
5g.22 closet per our discussions and the work will be 08/30/04 FSY
completed as a change order unless FSY can
prove that the number provided meets code
requirements.
FSY has been directed to provide a bulletin for the
addition of one water closet for the men's restroom
(08/19/04)
FSY will issue Bulletin by Monday, 08/30/04.
(08126/04)
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
source of granite for benches and steps noting
that shop drawings are required. David
5g.23b McBride will follow up with John Meyer. 09/08/04 TSCI
D.McBride asked TSCI to explore other options for
providing the granite including alternate designs.
(08/26/04)
Acoustic Review of HVAC: TSCI asked
whether the HVAC system has been reviewed
by the acoustical consultant stating that
previous problems have been encountered
5.25a with noise from HVAC units and ductwork. 09/02/04 FSY
FSY stated that there are no units on the
theater building but will have air velocities
reviewed.
Storefront at Mercantile Building: TSCI
expressed concern for the condition of the
existing storefront at the Mercantile Building.
5.25b Following discussion, it was determined that 09/09/04 TSCI
McEachron Construction will be asked to
review the present condition and make
recommendations for restoration.
Page 4 of 5 VANIR F 503
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 25
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
25 3g Notice Of Non Conformance Status:
3g.17 There is one outstanding correction notice 08/31/04 FSY
related to the approval of plan revisions. It is
anticipated that drawings will be back not later
than Monday, 07/26/04. (Dean Lee advised that all
corrections are complete with the exception of the
addition of a fan coil unit for cooling the electrical room
and telephone room)08/12/04
D. Lee advised that revised plans incorporating the
new fan coil unit should be complete by Tuesday,
08/31/04. (08/26/04)
3h As Built Status Review:
3h.25 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.25 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.25 Kleinfelder has been on site this week to N/A Info
perform welding inspection.
5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. The majority of materials in the
affected area have been removed. Mr. Green
has asked for an area for temporary storage of
the shed that was disassembled. The area can
be provided at the SW corner of the project site
against the fence. The existing fence at the north
end of the encroachment area will be removed
next week. 08/12/04
5g.9 Revised Grading Plan: The civil engineer Completed Info
(Kevin & Fox) is revising the storm drain plan
to raise the invert by 5-feet and move the line
from 3 to 5 feet north of where it is presently
shown. Plans are scheduled to be complete
early next week. (08119/04)
Revised plan received 08/26/04. This item is complete
5g.19 Reconciliation of Changes to Building Dept. 08/31/04 FSY
Approved Plans: (see Item 3c.17,above).
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 25
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
25 5.0 New Business: (continued)
Use of Storage Yard for Fabrication: TSCI asked
if fabrication can be done at the City-owned area
at Mercedes and Main Streets. Following
discussion, tentative approval was given subject
5.25c to: 1) fabrication can begin no earlier than 9.00 N/A Info
a.m. 2) the area will be kept in an orderly fashion
and cuttings will be contained in the immediate
area, and 3) the first noise or nuisance complaint
will be the basis for termination of the fabrication
activity.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
. 1
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 24
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: August 19, 2004
Location: City of Temecula Distribution: Attendees, Paul Donaldson
Project Office Dean Lee
Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz Larry Campbell, Vanir
Construction, Inc (TSCI) Construction, Inc (TSCI) Construction Mgmt(VCM)
Meeting # Item # Description Due Action
24 1.0 Approval Of Previous Meeting Minutes:
1.24 Minutes of Meeting No. 23 are corrected to read N/A Info
as follows:
All references to Saddleback Insulation should read
Saddleback Waterproofing.
2.0 Construction Progress Update:
2.24 Campbell Certified erected trusses at the N/A Info
Audience Chamber on Monday and
miscellaneous beams and diagonal bracing
throughout the structure on Tuesday and
Wednesday. Fit up, breaking of bolts, and
welding will continue through the remainder of
the week. Turnkey has completed the work
required for SCE cut-over to the new temporary
transformer. Frahm has continued work on the
re-pointing of the interior brick at the Mercantile
Building and backfill of foundation walls began on
Monday and will continue throughout the week.
3.0 Technical Concerns:
3a Schedule Review:
3a.23a TSCI's monthly schedule update indicates a 08/26/04 VCM
delay in project completion of 29 days. Sixteen
of those twenty nine days have been accounted
for in Change Order No. 4. The schedule will be
reviewed and comments forwarded to TSCI.
3b Submittal Status Review:
3b.24 98 submittals (including resubmittals) have been 08/23/04 FSY
received to date. 7 submittals remain
outstanding. Of those seven, six have been
outstanding in excess of two weeks.
Page 1 of 4
VAN 1 R PROGRESS MEETING MINUTE•
Meeting#: 24
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
24 3c Request For Information Status Review:
3c.24 203 RFI's (including revisions)have been submitted 08/23/04 FSY
to date. 9 RFI's are outstanding. Of those 9,
5 have been outstanding in excess of two
weeks.
3d Field Clarification Status Review:
3d.24 No new field clarifications have been issued. N/A Info
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 1 thru 4 have been
3e.1.22 executed by both the City of Temecula and N/A Info
TSCI.
3e.2 Proposed Change Orders
3e.2.24 Fifty one potential change requests have been 08/27/04 TSCINCM
identified. Of those, 30 have been submitted.
17 of the change requests have been
incorporated in Change Orders. 1 of the 51
were submitted during the course of the
meeting. 7 of the COR's have been voided.
3f Payment Status Review:
3f.23 TSCI's Payment Request No. 5 is being 09/09/04 City of
processed by the City. Temecula
3g Notice Of Non Conformance Status:
3g.17 There is one outstanding correction notice 08/23/04 FSY
related to the approval of plan revisions. It is
anticipated that drawings will be back not later
than Monday, 07/26/04. (Dean Lee advised that all
corrections are complete with the exception of the
addition of a fan coil unit for cooling the electrical
room and telephone room)08/12/04
3h As Built Status Review:
3h.24 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.24 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 24
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
24 4.0 Testing/Inspection:
4.24 Kleinfelder has been on site this week to N/A Info
perform welding and compaction inspection.
5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. The majority of materials in the
affected area have been removed. Mr. Green
has asked for an area for temporary storage of
the shed that was disassembled. The area can
be provided at the SW corner of the project site
against the fence. The existing fence at the north
end of the encroachment area will be removed
next week. 08112104
5g.9 Revised Grading Plan: The civil engineer 08/25/04 Kevin & Fox
(Kevin & Fox) is revising the storm drain plan
to raise the invert by 5-feet and move the line
from 3 to 5 feet north of where it is presently
shown. Plans are scheduled to be complete
early next week. (08119/04)
5g.19 Reconciliation of Changes to Building Dept. 08/17/04 FSY
Approved Plans: (see Item 3c.17,above).
Restroom Fixture Count: Mark Harold, Deputy
Building Official, City of Temecula, advised
that there is some doubt as to whether or not
the proper number of water closets is being
provided for the Men's restroom. This issue
was not noted on either of the plan reviews but
needs to be verified. FSY will be directed to
5g•22 provide sketches for the addition of one water 08/26/04 FSY
closet per our discussions and the work will be
completed as a change order unless FSY can
prove that the number provided meets code
requirements.
FSY has been directed to provide a bulletin for the
addition of one water closet for the men's
restroom 08/19/04
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
5g.23b source of granite for benches and steps noting 08/19/04 City of
that shop drawings are required. David Temecula
McBride will follow up with John Meyer.
Page 3 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 24
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
Larry Campbell
From: Ed Deleeuw[Ed Deleeuw@toveyshultz.com]
Sent: Monday, August 16, 2004 8:30 AM
To: Larry Campbell
Subject: RE: Meeting Minutes
Larry,
All I see is on 2.23 Saddleback waterproofing instead of Saddleback Insulation.
-----Original Message-----
From: Larry Campbell [mailto:Larry.campbellovanir.com]
Sent: Fri 8/13/2004 10 :45 AM
To: 'David McBride' ; 'Dave Anderson' ; 'Dean Lee' ; 'Paul Donaldson' ; Kevin Terry; Ed
Deleeuw
Cc:
Subject: Meeting Minutes
Gentlemen:
Please find attached a copy of the minutes of Weekly Progress Meeting #23 held
yesterday, 8/12 . If there are comments or corrections, please call me.
1
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 23
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: August 12, 2004
Location: City of Temecula Distribution: Attendees, Paul Donaldson
Project Office Owner: David McBride
File# 15.6
Time: 09:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride Steve Tovey,Tovey Shultz Kevin Terry,Tovey Shultz
City of Temecula Construction, Inc(TSCI) Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Dean Lee, FSY Architects Larry Campbell,Vanir
Construction, Inc (TSCI) (FSY) Construction Mgmt(VCM)
Meeting # Item # Description Due Action
23 1.0 Approval Of Previous Meeting Minutes:
1.23 Minutes of Meeting No. 22 are corrected to read 08/19/04 FSY
as follows:
Item 5.22:
Restroom Fixture Count: Mark Harold, Deputy
Building Official, City of Temecula, advised that there
is some doubt as to whether or not the proper number
of water closets is being provided for the Men's
restroom. This issue was not noted on either of the
plan reviews but needs to be verified. Following
discussion, it was determined that FSY will be
directed to provide sketches for the addition of
one water closet per our discussions and the work
will be completed as a chance order unless FSY
can prove that the number provided meets code
re ufrements.
2.0 Construction Progress Update:
2.23 Campbell Certified erected structural steel N/A Info
Monday and Tuesday and demobilized the crane
to allow for construction of the SCE conduit from
the transformer on 4`h Street to the new pull box
in the ramp. Fit-up and welding of beams to
columns and columns to base plates continued
throughout the week. Turnkey has installed the
SCE conduit and pull box from the existing
transformer to the new temporary transformer
location and backfill is in progress. Frahm has
continued work on the re-pointing of the interior
brick at the Mercantile Building and Saddleback
Insulation has completed waterproofing of
foundation walls. Waterproofing was inspected
during the course of the meeting by Paul
Donaldson, Senior Building Inspector.
Page 1 of 5
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 23
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
23 3.0 Technical Concerns:
3a Schedule Review:
3a.23 Tovey Shultz' 3-week look-ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Campbell Certified will continue the
erection of structural steel beginning tomorrow.
Backfill of foundation walls is scheduled to begin
on Monday (8/16) and SCE cut-over to temporary
power for the existing buildings is scheduled for
the week of 8/23. Following the electrical cut-
over (tentatively scheduled for early morning,
Wednesday, 8/25) the existing lines will be
removed allowing the start of the storm drain
work.
3a.23a TSCI's forwarded a monthly schedule update 08/19/04 VCM
which indicates a delay in project completion of
29 days. Sixteen of those twenty nine days have
been accounted for in Change Order No. 4. The
schedule will be reviewed and comments
forwarded to TSCI.
3b Submittal Status Review:
3b.23 98 submittals (including resubmittals) have been 08/16/04 FSY
received to date. 9 submittals remain
outstanding. Of those nine, five have been
outstanding in excess of two weeks.
3c Request For Information Status Review:
3c.23 200 RFI's (Including revisions) have been submitted 08/18/04 FSY
to date. 11 RFI's are outstanding. Of those
11, 4 have been outstanding in excess of two
weeks.
3d Field Clarification Status Review:
3d.23 No new field clarifications have been issued. N/A Info
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order Nos. 1 thru 3 have been
executed by both the City of Temecula and
3e.1.22 TSCI. Change Order No. 4 has been signed N/A Info
by TSCI and returned to the City for
processing.
Page 2 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTE
Meeting#: 23
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
23 3e.2 Proposed Change Orders
3e.2.23 Forty two potential change requests have 08/27/04 TSCINCM
been identified. Of those, 31 have been
submitted. 20 of the change requests have
been incorporated in Change Orders. 2 of the
31 were submitted during the course of the
meeting. 7 of the COR's have been voided.
3f Payment Status Review:
3f.23 TSCI's Payment Request No. 5 is being 09/09/04 City of
processed by the ity. Temecula
3g Notice Of Non Conformance Status:
3g.17 There is one outstanding correction notice 08/17/04 FSY
related to the approval of plan revisions. It is
anticipated that drawings will be back not later
than Monday, 07/26/04. (Dean Lee advised that all
corrections are complete with the exception of the
addition of a fan coil unit for cooling the electrical
room and telephone room)08/12/04
3h As Built Status Review:
3h.23 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.23 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.23 Kleinfelder has been on site this week to N/A Info
perform welding and masonry inspection.
5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. The majority of materials in the
affected area have been removed. Mr. Green
has asked for an area for temporary storage of
the shed that was disassembled. The area can
be provided at the SW corner of the project site
against the fence. The existing fence at the north
end of the encroachment area will be removed
next week. 08/12/04
Page 3 of 5 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 23
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
23 5g.9 Revised Grading Plan: The new SCE feed N/A Info
and temporary transformer pad have been set
and cut-over of electrical service to existing
businesses in scheduled for the week of
August 23. Following removal of existing
electrical lines, excavation of the new storm
drain is scheduled to begin. The firm of °
Houston Harris is on site today to video the
existing storm drain and that information will
be utilized to determine if the new line can be
relocated approximately 3 feet to the north and
the invert raised by 5 feet. (08/12/04).
5g.19 Reconciliation of Changes to Building Dept. 08/17/04 FSY
Approved Plans: (see Item 3G.17,above).
Realignment of Storm Drain: The question N/A Info
was asked as to whether or not the new storm
5g.20 drain can be moved approximately 3-feet to
the north to avoid interference with the
Children's Museum. (see Item 59.9,above)08/12/04
Restroom Fixture Count: Mark Harold, Deputy
Building Official, City of Temecula, advised
that there is some doubt as to whether or not
the proper number of water closets is being
provided for the Men's restroom. This issue
5g 22 was not noted on either of the plan reviews but 08/19/04 FSY
needs to be verified. FSY will be directed to
provide sketches for the addition of one water
closet per our discussions and the work will be
completed as a change order unless FSY can
prove that the number provided meets code
require ents.
Off Site Storage: TSCI asked if off site
storage for lumber and trusses is available. D.
McBride advised that the area at 3`d Street and
5g.23a Mercedes (behind the Musician's Workshop) is N/A Info
a likely area but will require fencing by TSCI.
(Subsequent to the meeting, McBride
advised that the site owned by the City at
Main and Mercedes is also available).
City Supplied Granite: TSCI asked whether a
final decision has been reached regarding the
5g.23b source of granite for benches and steps noting 08/19/04 City of
that shop drawings are required. David Temecula
McBride will follow up with John Meyer.
Page 4 of 5 VANIR F 503
VAN 1 R IROGRESS MEETING MINUTES
Meeting#: 23
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
Message • ® Page 1 of 1
Larry Campbell
From: David McBride [David.McBride@cityoftemecula.org]
Sent: Monday, August 09, 2004 9:35 AM
To: Larry Campbell
Subject: RE: Meeting Minutes
Larry:
My two cents.
Item 5.22 -the action is to direct FSY to provide sketches for the addition of one water closet per our discussions
and complete the work as a change order unless FSY can prove that the number provided meets code.
David
-----Original Message-----
From: Larry Campbell [mailto:Larry.Campbell@Vanir.com]
Sent: Monday, August 09, 2004 8:25 AM
To: David McBride; 'Dave Anderson'; Paul Donaldson; 'Kevin Terry'; Ed Deleeuw
(EdDeleeuw@toveyshultz.com); 'Dean Lee'
Subject: Meeting Minutes
Gentlemen:
Please find attached minutes of Weekly Progress Meeting #22 held on Thursday, 08/05/04. If there are
comments or corrections, please call me.
8/9/2004
VANIR
PROGRESS MEETING MINUTES
Meeting#: 22
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: August 5, 2004
Location: City of Temecula Distribution: Attendees, Paul Donaldson
Project Office Owner: David McBride
File# 15.B
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
City of Temecula Construction, Inc(TSCI) Construction, Inc(TSCI)
Larry Campbell,Vanir
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
22 1.0 Approval Of Previous Meeting Minutes:
1.22 There are no exceptions to the minutes of N/A Info
Meeting No. 21.
2.0 Construction Progress Update:
2.22 Campbell Certified resumed erection of structural N/A Info
steel on Tuesday and will continue into mid next
week. Welding will be ongoing for most of the
month of August. CMU walls were grouted
yesterday. Installation of the SCE conduit began
on Monday and inspection prior to backfill is
scheduled for later today. Repointing of the
interior brick at the Mercantile Bldg. is ongoing
and will continue next week.
3.0 Technical Concerns:
3a Schedule Review:
3a.22 Tovey Shultz' 3-week look-ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3a.21a TSCI's monthly schedule update is due in 08/12/04 TSCI
conjunction with the July payment request. (TSCI
advised that issues related to the storm drain and SCE
temporary power will be input into the schedule update
which will be provided no later than the next meeting.)
08.05.04
3b Submittal Status Review:
315.22 97 submittals (including resubmittals) have been 08/09/04 FSY
received to date. 12 submittals remain
outstanding. Of those twelve, nine have been
outstanding in excess of two weeks.
Page 1 of 4
VAN 1 R PROGRESS MEETING MINUTES®
Meeting#: 22
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
22 3c Request For Information Status Review:
3c.22 193 RFI's (including revisions) have been submitted 08/09/04 FSY
to date. 9 RFI's are outstanding. Of those 9,
3 have been outstanding in excess of two
weeks and 1 has been outstanding for 92
da s.
3d Field Clarification Status Review:
3d.22 No new field clarifications have been issued. N/A Info
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 1, (incorporating COR Nos. 17
and 19) Change Order No. 2, (incorporating COR
Nos.5 and 8) and Change Order No. 3 City of
3e.1.22 (incorporating COR Nos.9, 10, 10A,24, and 25) have 08/05/04 Temecula
been executed by the City. Change Order No.
4 (incorporating COR Nos. 11, 12,14,15,16,26, 27, and
30) has been drafted and forwarded to the City.
3e.2 Proposed Change Orders
3e.2.22 Forty potential change requests have been 08/18/04 TSCINCM
identified. Of those, 27 have been submitted.
20 of the change requests have been
incorporated in Change Orders. 4 of the 27
were submitted during the course of the
meeting. 7 of the COR's have been voided.
3f Payment Status Review:
3f.22 TSCI's Payment Request No. 5 has been 08/09/04 VCM
received and reviewed and will forwarded to
the City for processing and payment.
3g Notice Of Non Conformance Status:
3g.17 There is one outstanding correction notice 08/09/04 FSY
related to the approval of plan revisions. It is
anticipated that drawings will be back not later
than Monday, 07/26/04. (A list of required
corrections was received following the meeting and
forwarded to FSY for action)07129/04
3h As Built Status Review:
3h.21 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES®
Meeting#: 22
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
22 3i Safety Items:
3i.22 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.22 Kleinfelder has been on site this week to N/A Info
perform welding and masonry inspection.
5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. Removal of materials began
yesterday, 8/4 and is continuing. Removal of
trees is scheduled for tomorrow and removal of
the existing fence will occur early next week.
(08/05/04)
5g.9 Revised Grading Plan: The revised grading plan was N/A Info
received Tuesday, 05/25/04, and is being priced. (05/27/04). A
meeting held with SCE, Turnkey, and TSCI following the
meeting resulted in SCE to prepare new work order with an
expected date of receipt of 07/08/04. 06/17/04
5g.19 Reconciliation of Changes to Building Dept. 08/09/04 FSY
Approved Plans: Dean Lee turned in 4 sets of
stamped plans and narrative following the
meeting. This issue should be resolved. Per
conversation between Ed Deleeuw and Leslie of the
Building Dept., plans are expected back tomorrow or
Monday, 07/26104. (07/22/04)
List of corrections received following the meeting and
forwarded to FSY for action. 07129/04
Realignment of Storm Drain: The question 08/06/04 TSCI
was asked as to whether or not the new storm
drain can be moved approximately 3-feet to
the north to avoid interference with the
5g.20 Children's Museum. (Quality Plumbing has been
engaged to video tape the existing storm drain. The
line was full of debris limiting camera access and
has now been flushed. Video taping is expected to
be complete this week. (08105/04)
Water-proofing of walls: TSCI noted that the
plans do not indicate waterproofing for the
property wall abutting the Pottery Shop and
5g.21 the Children's Museum. Following discussion, N/A Info
it was determined that water-proofing is not
required for the starter walls at this location.
Page 3 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 22
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
22 5.0 New Business: (continued)
Restroom Fixture Count: Mark Harold, Deputy
Building Official, City of Temecula, advised
that there is some doubt as to whether or not
the proper number of water closets is being
5.22 provided for the Men's restroom. This issue 08/12/04 FSY
was not noted on either of the plan reviews but
needs to be verified. Following discussion, it
was determined that the matter will be referred
to FSY Architects for review.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting#: 21
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: July 29, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: Paul Donaldson
File# 15.B
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride Steve Tovey,Tovey Shultz Kevin Terry,Tovey Shultz
City of Temecula Construction, Inc(TSCI) Construction, Inc(TSCI)
Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction, Inc (TSCI) Construction Mgmt(VCM)
Meeting # Item # Description Due Action
21 1.0 Approval Of Previous Meeting Minutes:
1.21 There are no exceptions to the minutes of N/A Info
Meeting No. 20.
2.0 Construction Progress Update:
2.21 During the past week, welding of beams and N/A Info
braces to columns and the construction of CMU
walls has been the major focus. Campbell
Certified is scheduled to continue the erection of
steel beginning next Tuesday. Grouting of the
CMU walls is tentatively scheduled for Monday
afternoon pending City of Temecula inspection
on Monday morning.
3.0 Technical Concerns:
3a Schedule Review:
3a.21 Tovey Shultz' 3-week look-ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3a.21a TSCI's monthly schedule update is due in 08/05/04 TSCI
conjunction with the July payment request.
3b Submittal Status Review:
3b.21 93 submittals (including resubmittals) have been 08/02/04 FSY
received to date. 16 submittals remain
outstanding. Of those sixteen, fifteen have
been outstanding in excess of two weeks.
3c Request For Information Status Review:
3c.21 185 RFI's (including revisions) have been submitted 08/02/04 FSY
to date. 9 RFI's are outstanding. Of those 9,
3 have been outstanding in excess of two
weeks and 1 has been outstanding for 85
days.
Page i of 4
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 21
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
21 3d Field Clarification Status Review:
3d.21 No new field clarifications have been issued. N/A Info
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 1, (incorporating COR Nos. 17
and 19) Change Order No. 2, (incorporating COR
Nos. 5 and 8) and Change Order No. 3 City of
3e.1.21 (incorporating COR Nos.9, 10, 10A,24, and 25) have 08/05/04 Temecula
been executed by the City. Change Order No.
4 (incorporating COR Nos. 11, 12,14,15,16,26,27, and
3o) has been drafted and forwarded to the City.
3e.2 Proposed Change Orders
3e.2.21 Thirty nine potential change requests have 08/15/04 TSCI
been identified. Of those, 23 have been
submitted. 17 of the change requests have
been incorporated in Change Orders. 2 of the
23 were submitted during the course of the
meeting. 7 of the COR's have been voided.
3f Payment Status Review:
3f.21 A draft of TSCI's Payment Request No. 5 was 08/07/04 TSCI
reviewed following the meeting. TSCI to make
corrections and submit.
3g Notice Of Non Conformance Status:
3g.17 There is one outstanding correction notice 08/05/04 FSY
related to the approval of plan revisions. It is
anticipated that drawings will be back not later
than Monday, 07/26/04. (A list of required
corrections was received following the meeting and
forwarded to FSY for action)07/29/04
3h As Built Status Review:
3h.21 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.21 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.21 Kleinfelder has been on site this week to N/A Info
erform welding and masonry inspection.
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 21
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
21 5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. L. Campbell has been visiting Mr.
Green on a daily basis. Issues that Green had with
the City of Temecula letter have been resolved.
Campbell showed Greene the approximate new
property line yesterday and Green's concerns appear
to have been satisfied.
Green advised yesterday (07/28/04) that his son
would meet with Campbell today to schedule
removal of the materials. Green also stated that
the majority of the materials would be saved.
(07/29/04)
5g.9 Revised Grading Plan: The revised grading plan was N/A Info
received Tuesday, 05125/04, and is being priced. (05/27/04). A
meeting held with SCE, Turnkey, and TSCI following the
meeting resulted in SCE to prepare new work order with an
expected date of receipt of 07108104. 06117104
5g.19 Reconciliation of Changes to Building Dept. 08/05/04 FSY
Approved Plans: Dean Lee turned in 4 sets of
stamped plans and narrative following the
meeting. This issue should be resolved. per
conversation between Ed Deleeuw and Leslie of the
Building Dept., plans are expected back tomorrow or
Monday,07/26/04. (07/22/04)
List of corrections received following the meeting and
forwarded to FSY for action. 07/29/04
Realignment of Storm Drain: The question 08/07/04 TSCI
was asked as to whether or not the new storm
drain can be moved approximately 3-feet to
the north to avoid interference with the
Children's Museum. Following discussion, it
5g.20 was determined that VCM will follow-up with
Cozad.
L. Campbell talked with Troy Molaug(Cozad) regarding
relocation and raising of the invert for the new storm
drain. Cozad needs information to be obtained by video
inspection to determine what is flowing into the existing
CB., 07/29/04
Water-proofing of walls: TSCI noted that the
plans do not indicate waterproofing for the
property wall abutting the Pottery Shop and
5g.21 the Children's Museum. Following discussion, N/A Info
it was determined that water-proofing is not
required for the starter walls at this location.
Page 3 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 21
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting#: 22 _
Owner: City of Temecula
Project: Old Town Temecula _
Community Theater
Date: August 5, 2004
Location: City of Temecula Distribution: Attendees, Paul Donaldson
Project Office Owner: David McBride
File# 15.6
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride Kevin Terry,Tovey Shultz Ed Deleeuw,Tovey Shultz
City of Temecula Construction, Inc (TSCI) Construction, Inc(TSCI)
Larry Campbell,Vanir
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
22 1.0 Approval Of Previous Meeting Minutes:
1.22 There are no exceptions to the minutes of N/A Info
Meeting No. 21.
2.0 Construction Progress Update:
2.22 Campbell Certified resumed erection of structural N/A Info
steel on Tuesday and will continue into mid next
week. Welding will be ongoing for most of the
month of August. CMU walls were grouted
yesterday. Installation of the SCE conduit began
on Monday and inspection prior to backfill is
scheduled for later today. Repointing of the
interior brick at the Mercantile Bldg. is ongoing
and will continue next week.
3.0 Technical Concerns:
3a Schedule Review:
3a.22 Tovey Shultz' 3-week look-ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3a.21a TSCI's monthly schedule update is due in 08/12/04 TSCI
conjunction with the July payment request. (TSCI
advised that issues related to the storm drain and SCE
temporary power will be input into the schedule update
which will be provided no later than the next meeting.)
08.05.04
3b Submittal Status Review:
3b.22 97 submittals (including resubmittals) have been 08/09/04 FSY
received to date. 12 submittals remain
outstanding. Of those twelve, nine have been
outstanding in excess of two weeks.
Page 1 of 4
VAN 1 R PROGRESS MEETING MINUTES,
Meeting#: 22
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
22 3c Request For Information Status Review:
3c.22 193 RFI's (Including revisions) have been submitted 08/09/04 FSY
to date. 9 RFI's are outstanding. Of those 9,
3 have been outstanding in excess of two
weeks and 1 has been outstanding for 92
da s.
3d Field Clarification Status Review:
3d.22 No new field clarifications have been issued. N/A Info
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 1, (incorporating COR Nos. 17
and 19) Change Order No. 2, (incorporating COR
Nos.5 and 8) and Change Order No. 3 City of
3e.1.22 (incorporating COR Nos.9, 10, 10A,24, and 25) have 08/05/04 Temecula
been executed by the City. Change Order No.
4 (incorporating COR Nos. 11, 12,14,15,16,26, 27, and
30) as been drafted and forwarded to the City.
3e.2 Proposed Change Orders
3e.2.22 Forty potential change requests have been 08/18/04 TSCl/VCM
identified. Of those, 27 have been submitted.
20 of the change requests have been
incorporated in Change Orders. 4 of the 27
were submitted during the course of the
meeting. 7 of the COR's have been voided.
3f Payment Status Review:
3f.22 TSCI's Payment Request No. 5 has been 08/09/04 VCM
received and reviewed and will forwarded to
the City for processing and payment.
3g Notice Of Non Conformance Status:
3g.17 There is one outstanding correction notice 08/09/04 FSY
related to the approval of plan revisions. It is
anticipated that drawings will be back not later
than Monday, 07/26/04. (A list of required
corrections was received following the meeting and
forwarded to FSY for action)07/29/04
3h As Built Status Review:
3h.21 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
Page 2 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 22
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
22 3i Safety Items:
3i.22 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.22 Kleinfelder has been on site this week to N/A Info
perform welding and masonry inspection.
5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. Removal of materials began
yesterday, 8/4 and is continuing. Removal of
trees is scheduled for tomorrow and removal of
the existing fence will occur early next week.
(08/05/04)
5g.9 Revised Grading Plan: The revised grading plan was N/A Info
received Tuesday, 05125/04, and is being priced. (05127/04). A
meeting held with SCE, Turnkey, and TSCI following the
meeting resulted in SCE to prepare new work order with an
expected date of receipt of 07/08/04. 06117104
5g.19 Reconciliation of Changes to Building Dept. 08/09/04 FSY
Approved Plans: Dean Lee turned in 4 sets of
stamped plans and narrative following the
meeting. This issue should be resolved. Per
conversation between Ed Deleeuw and Leslie of the
Building Dept., plans are expected back tomorrow or
Monday,07/26/04. (07/22/04)
List of corrections received following the meeting and
forwarded to FSY for action. 07/29/04
Realignment of Storm Drain: The question 08/06/04 TSCI
was asked as to whether or not the new storm
drain can be moved approximately 3-feet to
the north to avoid interference with the
5g.20 Children's Museum. (Quality Plumbing has been
engaged to video tape the existing storm drain. The
line was full of debris limiting camera access and
has now been flushed. Video taping is expected to
be complete this week. (08/05/04)
Water-proofing of walls: TSCI noted that the
plans do not indicate waterproofing for the
property wall abutting the Pottery Shop and
5g.21 the Children's Museum. Following discussion, N/A Info
it was determined that water-proofing is not
required for the starter walls at this location.
Page 3 of 4 VANIR F 503
VAN 1 R •PROGRESS MEETING MINUTE
Meeting#: 22
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
22 5.0 New Business: (continued)
Restroom Fixture Count: Mark Harold, Deputy
Building Official, City of Temecula, advised
that there is some doubt as to whether or not
the proper number of water closets is being
5.22 provided for the Men's restroom. This issue 08/12/04 FSY
was not noted on either of the plan reviews but
needs to be verified. Following discussion, it
was determined that the matter will be referred
to FSY Architects for review.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR R
PROGRESS MEETING MINUTES
Meeting#: 20
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: July 22, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride, Paul Donaldson
File# 15.13
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
City of Temecula Construction (TSCI) Construction Mgmt(VCM)
Meeting # Item # Description Due Action
20 1.0 Approval Of Previous Meeting Minutes:
1.20 There are no exceptions to the minutes of N/A Info
Meeting No. 19.
2.0 Construction Progress Update:
2.20 Concentration of work this work has been toward N/A Info
the erection of structural steel and construction of
CMU walls. Work will continue throughout the
remainder of the week welding and fitting up of
structural steel. Work on CMU walls will continue
with grouting of walls scheduled for next
Wednesday pending approval of revised plans
which are expected to be returned tomorrow or
Monday.
3.0 Technical Concerns:
3a Schedule Review:
3a.20 Tovey Shultz' 3-week look-ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3a.17a TSCI's regular monthly schedule update is due 07/30/04 TSCI
next week in conjunction with the July payment
request.
3b Submittal Status Review:
3b.20 93 submittals (including resubmittals) have been 07/28/04 FSY
received to date. 16 submittals remain
outstanding. Of those sixteen, eleven have
been outstanding in excess of two weeks.
3c Request For Information Status Review:
3c.20 175 RFI's (Including revisions) have been submitted 07/26/04 FSY
to date. 10 RFI's are outstanding. Of those
10, 7 have been outstanding in excess of two
weeks and 1 has been outstanding for 78
days.
Page 1 of 3
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 20
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
20 3d Field Clarification Status Review:
3d.20 No new field clarifications have been issued. N/A Info
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 1, incorporating COR Nos. 07/28/04 TSCI
17 and 19 and Change Order No. 2,
3e.1.20 incorporating COR Nos. 5 and 8 have been
executed by the City. Change Order No. 3
incorporating COR Nos. 9, 10, 10A, 24, and 25
has been forwarded to TSCI for signature.
3e.2 Proposed Change Orders
3e.2.17 Thirty seven potential change requests have 07/30/04 VCM
been identified. Of those, 19 have been
submitted. 9 of the change requests have
been incorporated in Change Orders. 6 of the
19 have been negotiated with Campbell
Certified and were resubmitted via facsimile
this morning. 4 of the COR's have been
voided.
3f Payment Status Review:
3f.19 TSCI Payment Request No. 4 has been 08/08/04 City of
forwarded to the City of Temecula for Temecula
processing and payment.
3g Notice Of Non Conformance Status:
3g.17 There is one outstanding Correction notice N/A Info
related to the approval of plan revisions. It is
anticipated that drawings will be back not later
than Monday, 07/26/04.
3h As Built Status Review:
3h.20 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
31 Safety Items:
3i.20 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.20 Kleinfelder has been on site this week to N/A Info
perform welding and masonry inspection.
Page 2 of 3 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES
Meeting#: 20
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
20 5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. L. Campbell has been visiting Mr.
Green on a daily basis. Issues that Green had with
the City of Temecula letter have been resolved.
Campbell showed Greene the approximate new
property line yesterday and Green's concerns appear
to have been satisfied. Green to advise when he
wants assistance in moving materials. (7/15/04)
5g.9 Revised Grading Plan: The revised grading plan was N/A Info
received Tuesday,05/25/04, and is being priced. (05/27/04). A
meeting held with SCE, Turnkey, and TSCI following the
meeting resulted in SCE to prepare new work order with an
expected date of receipt of 07108104. 06117104
5g.19 Reconciliation of Changes to Building Dept. N/A Info
Approved Plans: Dean Lee turned in 4 sets of
stamped plans and narrative following the
meeting. This issue should be resolved. Per
conversation between Ed Deleeuw and Leslie of the
Building Dept., plans are expected back tomorrow or
Monday,07126104. (07122/04)
Realignment of Storm Drain: The question 07/23/04 VCM
was asked as to whether or not the new storm
drain can be moved approximately 3-feet to
5g.20 the north to avoid interference with the
Children's Museum. Following discussion, it
was determined that VCM will follow-up with
Cozad.
Removal of Existing Trees: It was noted that N/A Info
several mature trees are in the path of either
5h.20 the new storm drain or the new SCE conduits.
Following discussion, it was determined that
the trees will be cut.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 3 of 3 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting#: 19
Owner: City of Temecula
. ........_
Project: Old Town Temecula
Community Theater
Date: July 15, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride, Paul Donaldson
File# 15.13
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: Steve Tovey,Tovey Shultz Kevin Terry,Tovey Ed Deleeuw,Tovey Shultz
Construction (TSCI) Shultz Construction (TSCI) Construction (TSCI)
Larry Campbell,Vanir Dean Lee, FSY Architects
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
19 1.0 Approval Of Previous Meeting Minutes:
1.19 There are no exceptions to the minutes of N/A Info
Meeting No. 18.
2.0 Construction Progress Update:
2.19 Work resumed on the cutting and welding of N/A Info
columns on Monday of this week and alignment
and plumbing of steel is continuing. Layout and
construction of corners for CMU walls occurred
on Monday and Tuesday and installation of CMU
walls is in progress. Electrical stub-ups within
the CMU walls were installed on Monday and
Tuesday and removal of mortar in preparation for
re-pointing of the interior brick at the Mercantile
Building is on-going.
3.0 Technical Concerns:
3a Schedule Review:
3a.19 Tovey Shultz' 3-week look-ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3a.17a TSCI has made some preliminary revisions to its 07/16/04 TSCI
schedule to reflect the re-sequencing of work and
still has to incorporate the work related to the
new storm drain to arrive at a revised project
completion date. Revised SCE drawings related
to the storm drain work are scheduled to be
complete by next Friday, 07/09/04.
SCE revised drawings were received on 7/9 and added
work is being priced. (07115104)
Page 1 of 3
VAN 1 R IROGRESS MEETING MINUTES
Meeting#: 19
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
19 3b Submittal Status Review:
3b.19 90 submittals (including resubmittals) have been 07/21/04 FSY
received to date. 21 submittals remain
outstanding. Of those twenty one, fourteen
have been outstanding in excess of two
weeks.
3c Request For Information Status Review:
3c.19 172 RFI's (including revisions) have been submitted 07/19/04 FSY
to date. 13 RFI's are outstanding. Of those
13, 9 have been outstanding in excess of two
weeks and 1 has been outstanding for 71
da s.
3d Field Clarification Status Review:
3d.19 No new field clarifications have been issued. N/A Info
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 1, incorporating COR Nos. N/A Info
3e.1.17 17 and 19 and Change Order No. 2,
incorporating COR Nos. 5 and 8 have been
executed by the City.
3e.2 Proposed Change Orders
3e.2.17 Thirty seven potential change requests have 07/14/04 VCM
been identified. Of those, 19 have been
submitted. 4 of the change requests have
been incorporated in Change Orders. 6 of the
16 have been negotiated with Campbell
Certified and will be resubmitted. 3 have been
negotiated with Turnkey and will be
incorporated into a change order. 4 of the
COR's have been voided.
3f Payment Status Review:
3f.19 TSCI Payment Request No. 4 has been 08/08/04 City of
forwarded to the City of Temecula for Temecula
processing and payment.
3g Notice Of Non Conformance Status:
3g.17 There is one outstanding correction notice 07/05/04 FSY
related to the approval of plan revisions.
Page 2 of 3 VANIR F 503
VANIR VROGRESS MEETING MINUTES•
Meeting#: 19
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
19 3h As Built Status Review:
3h.19 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
309 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.19 Kleinfelder has been on site this week to N/A Info
erform welding and masonry inspection.
5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. L. Campbell has been visiting Mr.
Green on a daily basis. Issues that Green had with
the City of Temecula letter have been resolved.
Campbell showed Greene the approximate new
property line yesterday and Green's concerns appear
to have been satisfied. Green to advise when he
wants assistance in moving materials. (7115104)
5g.9 Revised Grading Plan: The revised grading plan was 07/09/04 SCE
received Tuesday, 05/25/04, and is being priced. (05/27/04). A
meeting held with SCE, Turnkey, and TSCI following the
meeting resulted in SCE to prepare new work order with an
expected date of receipt of 07108104. 06117104
5g.19 Reconciliation of Changes to Building Dept. N/A Info
Approved Plans: Dean Lee turned in 4 sets of
stamped plans and narrative following the
meeting. This issue should be resolved.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 3 of 3 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting#: 18
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: July 8, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, City of Kevin Terry,Tovey Ed Deleeuw,Tovey Shultz
Temecula DPW Shultz Construction (TSCI) Construction (TSCI)
Larry Campbell,Vanir
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
18 1.0 Approval Of Previous Meeting Minutes:
1.18 There are no exceptions to the minutes of N/A Info
Meeting No. 17.
2.0 Construction Progress Update:
2.18 During the past week, concrete was placed for N/A Info
footings. . Forms were stripped and materials
removed from the site. Erection of structural steel
began on Friday, 7/2, and continued on Tuesday,
7/6. Due to an elevation issue, work on welding
columns has ceased until the issue is resolved.
Frahm continued work in the Mercantile Bldg
following the holiday weekend and began laying
out retaining walls that are scheduled to begin
tomorrow.
3.0 Technical Concerns:
3a Schedule Review:
3a.18 Tovey Shultz' 3-week look-ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3a.17a TSCI has made some preliminary revisions to its 07/16/04 TSCI
schedule to reflect the re-sequencing of work and
still has to incorporate the work related to the
new storm drain to arrive at a revised project
completion date. Revised SCE drawings related
to the storm drain work are scheduled to be
complete by next Friday, 07/09/04.
3b.18 83 submittals (including resubmittals) have been 07/14/04 FSY
received to date. 13 submittals remain
outstanding. Of those thirteen, eight have
been outstanding in excess of two weeks.
Page 1 of 3
VAN 1 R •OGRESS MEETING MINUTE•
Meeting#: 18
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
18 3c Request For Information Status Review:
3c.18 168 RFI's (including revisions) have been submitted . 07/14/04 FSY
to date. 18 RFI's are outstanding. Of those
18, 7 have been outstanding in excess of two
weeks and 1 has been outstanding for 68
da s.
3d Field Clarification Status Review:
3d.18 No new field clarifications have been issued. N/A Info
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 1, incorporating COR Nos. N/A Info
3e.1.17 17 and 19 and Change Order No. 2,
incorporating COR Nos. 5 and 8 have been
executed by the City.
3e.2 Proposed Change Orders
3e.2.17 Thirty seven potential change requests have 07/14/04 VCM
been identified. Of those, 19 have been
submitted. 4 of the change requests have
been incorporated in Change Orders. 6 of the
16 have been negotiated with Campbell
Certified and will be resubmitted. 3 have been
negotiated with Turnkey and will be
incorporated into a change order. 4 of the
COR's have been voided.
An RFP will be issued early next week for the 07/23/04 TSCI
deletion of the ticket booth, storage closet, and
3e.2.17.a lighting from the Mercantile Building and the
addition of sewer, water, and gas stub-outs.
(RFP No. 8 was issued yesterday,0710704.
3f Payment Status Review:
3f.18 TSCI Payment Request No. 4 was forwarded 08/08/04 City of
to the City of Temecula for processing and Temecula
payment today.
3g Notice Of Non Conformance Status:
3g.17 There is one outstanding correction notice 07/05/04 FSY
related to the approval of plan revisions.
3h As Built Status Review:
3h.17 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
Page 2 of 3 VANIR F 503
VAN I R •PROGRESS MEETING MINUTE
Meeting#: 18
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
18 3i Safety Items:
308 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/inspection:
4.18 Kleinfelder is scheduled for welding and As Noted VCM
masonry inspection Monday, 07/12/04.
5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. D. McBride and L. Campbell met
with Mr. Green following the meeting. Greene
advised that we will be able to start moving materials
next week. L. Campbell will follow up with Greene on
a daily basis. (07/08/04)
5g.9 Revised Grading Plan: The revised grading plan was 07/09/04 SCE
received Tuesday, 05/25/04, and is being priced. (05/27/04). A
meeting held with SCE, Turnkey, and TSCI following the
meeting resulted in SCE to prepare new work order with an
ex ecled date of receipt of 07108104. 08/17104
5g.18 Reconciliation of Changes to Building Dept. 07/09/04 FSY
Approved Plans: Dean Lee met with the Plan
Check Section on Tuesday, 07/07, and was
informed that a narrative is required to be
submitted with the revised drawings. Lee was
led to believe that no plan check is required.
Lee is scheduled to submit the narrative
tomorrow, 07/09/04.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely, _
Signature
Name: Larry E. Campbell _
Title: Project Manager
Page 3 of 3 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting#: 17
Owner: City of Temecula
Project Old Town Temecula
Community Theater
Date: July 1, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, City of Kevin Terry,Tovey Ed Deleeuw,Tovey Shultz
Temecula DPW Shultz Construction (TSCI) Construction (TSCI)
Larry Campbell,Vanir Dean Lee, FSY Architects
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
17 1.0 Approval Of Previous Meeting Minutes:
1.17 There are no exceptions to the minutes of N/A Info
Meeting No. 16.
2.0 Construction Progress Update:
2.17 Work over the past week has been directed N/A Info
toward the placement of concrete for footings for
the Scene Shop, Classroom Building, Dance
Studio, Restroom and Concession Buildings as
well as the walkway and property wall on the east
side of the Mercantile Building. Erection of
structural steel, scheduled for today, was
postponed until tomorrow by Campbell Certified.
Work today is concentrated on stripping of forms
and grading of access for steel delivery.
3.0 Technical Concerns:
3a Schedule Review:
3a.17 Tovey Shultz' 3-week look-ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3a.17a TSCI has made some preliminary revisions to its 07/16/04 TSCI
schedule to reflect the re-sequencing of work and
still has to incorporate the work related to the
new storm drain to arrive at a revised project
completion date. Revised SCE drawings related
to the storm drain work are scheduled to be
complete by next Friday, 07/09/04.
Page 7 of 4
VANIR PROGRESS MEETING MINUTE
Meeting#: 17
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # item # Description Due Action
17 315 Submittal Status Review:
3b.17 83 submittals (including resubmittals) have been 07/07/04 FSY
received to date. 15 submittals remain
outstanding. Of those fifteen, seven have been
outstanding in excess of two weeks and three
have been submitted within the last three
da s.
3c Request For Information Status Review:
3c.17 159 RFI's (including revisions) have been submitted 07/07/04 FSY
to date. 15 RFI's are outstanding. Of those
15, 6 have been outstanding in excess of two
weeks.
3d Field Clarification Status Review:
3d.17 No new field clarifications have been issued. N/A Info
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 1, incorporating COR Nos. N/A Info
17 and 19 and Change Order No. 2,
3e.1.17 incorporating COR Nos. 5 and 8 have been
executed by the City.
3e.2 Proposed Change Orders
07/07/04 VCM
3e.2.17 Thirty six potential change requests have been
identified. Of those, 19 have been submitted.
4 of the change requests have been
incorporated in Change Orders. 6 of the 16
have been negotiated with Campbell Certified
and will be resubmitted. 3 have been
negotiated with Turnkey and will be
incorporated into a change order. 2 of the
COR's will be voided and two are expected to
be no cost changes.
An RFP will be issued early next week for the 07/06/04 VCM
deletion of the ticket booth, storage closet, and
3e.2.17.a lighting from the Mercantile Building and the
addition of sewer, water, and gas stub-outs.
Page 2 of 4 VANIR F 503
VANIR PROGRESS MEETING MINUTES
Meeting#: 17
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
17 3f Payment Status Review:
3f.14 The draft of payment request No. 4 was 07/08/04 TSCI
reviewed prior to the meeting. It was noted
that all outstanding certified payrolls (through
the month of May) must be received prior to
processing the formal payment request.
3g Notice Of Non Conformance Status:
3g.17 There is one outstanding correction notice 07/05/04 FSY
related to the approval of plan revisions.
3h As Built Status Review:
3h.17 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.17 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.17 Kleinfelder is scheduled for welding inspection As Noted VCM
tomorrow, 07/02/04 and masonry inspection
beginning Wednesday, 07/07/04.
5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. D. McBride and L. Campbell met
with Mr. Green following the meeting. Greene
advised that we will be able to start moving materials
late next week. (07101/04)
5g.9 Revised Grading Plan: The revised grading plan was 07/08/04 SCE
received Tuesday, 05/25/04, and is being priced. (05/27/04). A
meeting held with SCE, Turnkey, and TSCI following the
meeting resulted in SCE to prepare new work order with an
ex ected date of receipt of 07108104. 06117104
5g.12 Reconciliation of Changes to Building Dept. 07/06/04 FSY
Approved Plans: P. Donaldson asked when
changes between the Building Department
approved plans and the bid set will be
reconciled. FSY has committed to a
completion date of 06/20/04.
D. Lee will submit revised architectural and structural
drawings to the Building Department on Tuesday,
07/06/04.
Page 3 of 4 VANIR F 503
VANIR PROGRESS MEETING MINUTE•
Meeting#: 17
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR •
PROGRESS MEETING MINUTES
Meeting #: 16
Owner: o ofTeme`cula
Project: Old Town Temecula
Community Theater
Date: June 24, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File# 15.6
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, City of Kevin Terry,Tovey Ed Deleeuw,Tovey Shultz
Temecula DPW Shultz Construction (TSCI) Construction (TSCI)
Larry Campbell,Vanir
Construction Mgmt(VCM)
Meeting # Item # Description Due Action
16 1.0 Approval Of Previous Meeting Minutes:
1.16 There are no exceptions to the minutes of N/A Info
Meeting No. 15.
2.0 Construction Progress Update:
2.16 During the past week, work has concentrated on N/A Info
the excavation and forming of footings.
Installation of reinforcing steel began Tuesday
and is continuing today. Removal of plaster and
grout from the interior of the Mercantile Building
is continuing.
3.0 Technical Concerns:
3a Schedule Review:
3a.16 Tovey Shultz' 3-week look-ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3a.14a TSCI advised that the project is approximately 6 06/30/04 TSCI
weeks behind schedule based upon scheduled
installation of structural steel. TSCI to evaluate
impact of design changes on structural steel in
conjunction with the impact of the new storm
drain to determine potential concurrencies.
TSCI is still working with Campbell Certified to derive delays
attributable to design revisions. (6/17/04)
Following the meeting, TSCI advised that Campbell
Certified has developed a revised schedule for erection
of structural steel that would eliminate extension of the
schedule. This revision is being evaluated to assure
that a safe work environment will be maintained. TSCI
to advise. (6/24/04)
Page 1 of 4
VANIR PROGRESS MEETING MINUTES
Meeting#: 16
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
16 3b Submittal Status Review:
3b.16 79 submittals (including resubmittals) have been 06/28/04 FSY
received to date. 17 submittals remain
outstanding. Of those seventeen, ten have
been outstanding in excess of two weeks and
seven have been submitted within the last
three days.
3c Request For Information Status Review:
3c.16 152 RFI's (including revisions) have been submitted 06/28/04 FSY
to date. 11 RFI's are outstanding. Of those
11, 6 have been outstanding in excess of two
weeks.
3d Field Clarification Status Review:
3d.16 No new field clarifications have been issued. N/A Info
3e Change Order/Proposed Change Order
Status:
3e.1 Change Orders
Change Order No. 1, incorporating COR Nos. 06/30/04 City of
17 and 19 has been executed by the City. Temecula
3e.1.16 Change Order No. 2, incorporating COR Nos.
5 and 8 has been signed by TSCI and
returned to the City for execution.
3e.2 Proposed Change Orders
3e.2.16 Thirty three potential change requests have 06/30/04 TSCINCM
been identified. Of those, 21 have been
submitted. 4 of the change requests have
been incorporated in Change Orders. 6 of the
16 have been negotiated with Campbell
Certified and will be resubmitted. 2 have been
negotiated with Turnkey and, although
resubmitted, the justification for a composite
labor rate is outstanding. Of the remaining 9
submitted CORs, 3 are Campbell, 3 are
Turnkey and 1 was submitted during the
course of the meeting.
3f Payment Status Review:
3f.14 Payment Request No. 3 was forwarded to the 07/07/04 City of
City for payment June 7, 2004. Temecula
3g Notice Of Non Conformance Status:
3g.16 There are no outstanding non-conformance N/A Info
notices at this date.
Page 2 of 4 VANIR F 503
VAN 1 R •OGRESS MEETING MINUTES•
Meeting#: 16
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
16 3h As Built Status Review:
3h.16 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
306 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.16 Kleinfelder is scheduled for rebar inspection As Noted VCM
on Friday, concrete inspection on Tuesday,
and, tentatively, welding inspection beginning
Tuesday, 7/6.
6.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Info
Pottery Shop. D. McBride and L. Campbell met
with Mr. Green following the meeting. Greene
advised that we will be able to start moving materials
late next week. (06/24104)
5g.6 Potential Delay Claim by Campbell Certified: N/A Closed
This item is discussed in Item 3a.14a, above and will be
deleted fromfuture meeting minutes. 06117104
5g.9 Revised Grading Plan: The revised grading plan was 07/08/04 SCE
received Tuesday, 05/25/04, and is being priced. (05/27/04). A
meeting held with SCE, Turnkey, and TSCI following the
meeting resulted in SCE to prepare new work order with an
expected date of receipt of 07108104. 06117104
5g.12 Reconciliation of Changes to Building Dept. 06/28/04 VCM
Approved Plans: P. Donaldson asked when
changes between the Building Department
approved plans and the bid set will be
reconciled. FSY has committed to a
completion date of 06/20/04.
FSY advised that structural revisions will be forwarded
tomorrow with the remaining changes to be submitted by
the agreed upon date. (06110/04)
FSY advised that drawings will be received Monday,06/21/04.
Clouded drawings were received Tuesday,06122104.
L. Campbell will meet with A Donaldson to determine the best
means to get the clouded drawings incorporated
Page 3 of 4 VANIR F 503
VAN 1 R PROGRESS MEETING MINUTES•
Meeting#: 16
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of VANIR F 503
VANIR •
PROGRESS MEETING MINUTES
Meeting#: 15
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: June 17, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, City of Dean Lee, FSY Architects Kevin Terry,Tovey
Temecula DPW Shultz Construction(TSCI)
Ed Deleeuw,Tovey Shultz Larry Campbell,Vanir
Construction (TSCI) Construction Mgmt(VCM)
Meeting # Item # Description Due Action
15 1.0 Approval Of Previous Meeting'Minutes:
1.15 The minutes of Meeting No. 14 are corrected to N/A Info
reflect the attendance of Dean Lee, FSY
Architects.
2.0 Construction Progress Update:
2.15 During the past week, underground plumbing N/A Info
was relocated from under footings or sleeved
where relocation was impractical. Underground
waste and vent lines were installed at the
Concession and Restroom Buildings and are
presently being backfilled. Layout and
excavation of footings is in progress.
3.0 Technical Concerns:
3a Schedule Review:
3a.15 Tovey S hultz' 3-week I ook-ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3a.14a TSCI advised that the project is approximately 6 06/25/04 TSCI
weeks behind schedule based upon scheduled
installation of structural steel. TSCI to evaluate
impact of design changes on structural steel in
conjunction with the impact of the new storm
drain to determine potential concurrencies. ( TSCI
is still working with Campbell Certified to derive delays
attributable to design revisions.)(6/17/04
3b Submittal Status Review:
31b. 55 72 submittals (including resubmittals)_have been 06/23/04 FSY
received--to---date-43--submittats—remain— —
outstanding. Of those thirteen, eight have
been outstanding in excess of two weeks.
TSCI noted that the submittal for waterproofing
is dependent upon the response to RFI 83
which has been outstanding since 4/28/04.
Page i of 3
VANIR PROGRESS MEETING MINUTES•
Meeting#: 15
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
15 3c Request For Information Status Review:
3c. 55 139 RFI's (including revisions) have been submitted 06/23/04 FSY
to date. 9 RFI's are outstanding. Of those 9,
5 have been outstanding in excess of two
weeks.
3d Field Clarification Status Review:
3d.15 No new field clarifications have been issued. N/A Info
3e.1 Change Order/Proposed Change Order
Status: _ .
3e.15 Thirty two potential change requests have 06/25/04 TSCINCM
been identified of which, 16 have been
submitted. Four of the change requests have
been incorporated in Change Orders. 6 of the
16 have been negotiated with Campbell
Certified and will be resubmitted. 2 have been
negotiated with Turnkey and, although
resubmitted, the justification for a composite
labor rate is outstanding. One new change
request from Campbell was submitted during
the course of the meeting.
3f Payment Status Review:
3f.14 Payment Request No. 3 was forwarded to the 07/07/04 City of
City for payment June 7, 2004. Temecula
3g Notice Of Non Conformance Status:
3g.15 There are no outstanding non-conformance N/A Info
notices at this date.
3h As Built Status Review:
3h.15 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
305 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/inspection:
4.15 Kleinfelder is scheduled for compaction testing As Noted VCM
for plumbing trench later today and footing
ns ection Monday.
5;0 New Business:
5f.4b Resolution of the Encroachment by the 06/ 77/04 VCM
Pottery Shop. L. Campbell will meet with Mr.
Green following the meeting to determine whether he
has made a decision as to where to move materials.
(06/17/04)
Page 2 of 3 VANIR F 503
VANIR PROGRESS MEETING MINUTES•
Meeting#: 15
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
14 5g.6 Potential Delay Claim by Campbell Certified: N/A Closed
This item is discussed in Item 3a.14a, above and will be
deleted from future meeting minutes. 06117104
5g.9 Revised Grading Plan: The revised grading plan was 07/08/04 SCE
received Tuesday, 05/25104, and is being priced. (05/27104). A
meeting held with SCE, Turnkey, and TSCI following the
meeting resulted in SCE to prepare new work order with an
expected date of receipt of 07108104. 06117/04
5g.12 Reconciliation of Changes to Building Dept. 06/21/04 FSY
Approved Plans: P. Donaldson asked when
changes between the Building Department
approved plans and the bid set will be
reconciled. FSY has committed to a
completion date of 06/20/04.
FSY advised that structural revisions will be forwarded
tomorrow with the remaining changes to be submitted by
the agreed upon date. (06/10/04)
FSY advised that drawings will be received Monday,06121104.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
IPage 3 of 3 VANIR F 503
w -
VANIR •
PROGRESS MEETING MINUTES
Meeting#: 14
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: June 10, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File# 15.6
Time: 10:00 a.m. Enclosure: 3-Week Look-Ahead Schedule
Attendees: David McBride, City of Paul Donaldson, City of Kevin Terry, Tovey
Temecula DPW Temecula, Bldg&Safety Shultz Construction (TSCI)
Ed Deleeuw, Tovey Larry Campbell, Vanir
Shultz Construction (TSCI) Construction Mgmt(vcM)
Meeting # Item # Description Due Action
14 1.0 Approval Of Previous Meeting Minutes:
1.14 No exceptions were taken to the minutes of N/A Info
Meeting No. 13.
2.0 Construction Progress Update:
2.14 Efforts during the past week have been N/A Info
concentrated on installation of underground
plumbing lines.
3.0 Technical Concerns:
3a Schedule Review:
3a.14 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3a.14a TSCI advised that the project is approximately 6 06/14/04 TSCI
weeks behind schedule based upon scheduled
installation of structural steel. TSCI to evaluate
impact of design changes on structural steel in
conjunction with the impact of the new storm
drain to determine potential concurrencies.
3b Submittal Status Review:
3b.14 66 submittals (including resubmittals) have been 06/14/04 FSY
received to date. Currently, 8 submittals
remain outstanding. Of those eight, three have
been outstanding in excess of two weeks.
3c Request For Information Status Review:
3c.14 131 RFI's (Including revisions)have been submitted 06/14/04 FSY
to date. Currently, 9 RFI's are outstanding. Of
those 9, 5 have been outstanding in excess of
two weeks.
Page 1 of 3
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 14
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
14 3d Field Clarification Status Review:
3d.14 No new field clarifications have been issued. N/A Info
3e.1 Change Order/Proposed Change Order
Status:
3e.14 Twenty nine potential change requests have 06/10/04 DPW
been identified of which, 16 have been
submitted. COR Nos. 17 and 19 have been
incorporated into Change Order No. 1. 6 of
the 15 have been negotiated with Campbell
Certified and will be resubmitted. DPW
approved the price for re-pointing of brick at
the Mercantile Bldg. during the course of the
meeting and will prepare a change order for
this work.
3f Payment Status Review:
3f.14 Payment Request No. 3 was forwarded to the 07/07/04 City of
City for payment June 7, 2004. Temecula
3g Notice Of Non Conformance Status:
3g.14 There is one outstanding non-conformance 06/11/04 TSCI
notice related to underground plumbing.
Corrective action is underway and re-
inspection is scheduled for tomorrow.
3h As Built Status Review:
3h.14 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
304 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.14 Kleinfelder is scheduled for compaction testing N/A Info
for plumbing trench backfill tomorrow.
5.0 New Business:
5f.4b Resolution of the Encroachment by the 06/10/04 DPWNCM
Pottery Shop. D. McBride w and L. Campbell will
meet with Mr. Green following the meeting to
determine whether he has made a decision as to
where to move materials. (06110/04)
Page 2 of 3 VANIR F 503
VAN 1 R •PROGRESS MEETING MINUTES
Meeting#: 14
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
14 5g.6 Potential Delay Claim by Campbell Certified: N/A Info
Alleged delays are identified in submitted CORs.
5g.9 Revised Grading Plan: The revised grading plan was 06/09/04 TSCI
received Tuesday,05125104,and is being priced.(05127104)
5g.12 Reconciliation of Changes to Building Dept. 06/20/04 FSY
Approved Plans: P. Donaldson asked when
changes between the Building Department
approved plans and the bid set will be
reconciled. FSY has committed to a
completion date of 06/20104. FSY advised that
structural revisions will be forwarded tomorrow with
the remaining changes to be submitted by the agreed
upon date. 06/10/04
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 3 of 3 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting#: 13
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: June 3, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File# 15.6
Time: 10:00 a.m. Enclosure: None
Attendees: Steve Tovey, Tovey Kevin Terry, Tovey Ed Deleeuw, Tovey Shultz
Shultz Construction (Tsci) Shultz Construction (Tsci) Construction (TSCi)
Larry Campbell, Vanir
Construction Mgmt(vcm)
Meeting # Item # Description Due Action
13 1.0 Approval Of Previous Meeting Minutes:
1.13 No exceptions were taken to the minutes of N/A Info
Meeting No. 12.
2.0 Construction Progress Update:
2.13 Efforts during the past week have been N/A Info
concentrated on backfill of electrical trenches and
excavation for and installation of underground
plumbing lines.
3.0 Technical Concerns:
3a Schedule Review:
3a.2b The base line schedule was approved 05/05/04. N/A Complete
3a.13 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3b Submittal Status Review:
3b.13 63 submittals (including resubmittals)have been 06/07/04 FSY
received to date. Currently, 7 submittals
remain outstanding. Of those seven, four have
been outstanding in excess of two weeks.
3c Request For Information Status Review:
3c.13 121 RFI's (including revisions)have been submitted 06/07/04 FSY
to date. Currently, 9 RFI's are outstanding. Of
those 9, 5 have been outstanding in excess of
two weeks.
3d Field Clarification Status Review:
3d.13 No new field clarifications have been issued. N/A Info
Page 1 of 3
VAN 1 R •ROGRESS MEETING MINUTES
Meeting#: 13
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
13 3e.1 Change Order/Proposed Change Order
Status:
3e.13 Twenty eight potential change requests have 06/09/04 TSCI
been identified of which, 15 have been
submitted. COR Nos. 17 and 19 have been
incorporated into Change Order No. 1. 6 of
the 15 have been negotiated with Campbell
Certified and will be resubmitted.
3f Payment Status Review:
3f.13 Payment Request No. 3 was submitted during 06/04/04 VCMI
the course of the meeting. The payment
request will be reviewed and, if correct,
forwarded to the City for payment.
3g Notice Of Non Conformance Status:
3g.13 There are no outstanding non-conformance N/A Info
notices.
3h As Built Status Review:
3h.13 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
303 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.13 Kleinfelder performed compaction tests for N/A Info
electrical trench backfill yesterday as required.
5.0 New Business:
5f.4b Resolution of the Encroachment by the 06/03/04 TSCl/VCM
Pottery Shop. E. Deleeuw and L. Campbell met
with Mr. Green yesterday to determine whether he
has determined where to move materials and advise
that TSCI will provide labor to assist. Another
meeting will be held later today as a follow up.
(6I3/04)
5g.6 Potential Delay Claim by Campbell Certified: 05/27/04 VCM/FSY
Alleged delays are identified in submitted CORs.
5g.9 Revised Grading Plan: The revised grading plan was 06/09/04 TSCI
received Tuesday,05125104,and is being priced.(05127104)
Page 2 of 3 VANIR F 503
VAN 1 R •ROGRESS MEETING MINUTES•
Meeting#: 13
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
5g.12 Reconciliation of Changes to Building Dept. 06/20/04 FSY
Approved Plans: P. Donaldson asked when
changes between the Building Department
approved plans and the bid set will be
reconciled. FSY has committed to a
completion date of 06/20/04.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting. _
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 3 of 3 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting #: 12
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: May 27, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File# 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: Paul Donaldson Kevin Terry, Tovey Ed Deleeuw, Tovey Shultz
Bldg. & Safety Shultz Construction (Tscl) Construction (Tsci)
Larry Campbell, Vanir
Construction Mgmt(vcM)
Meeting # Item # Description Due Action
12 1.0 Approval Of Previous Meeting Minutes:
1.12 No exceptions were taken to the minutes of N/A Info
Meeting No. 11.
2.0 Construction Progress Update:
2.12 Efforts during the past week have been N/A Info
concentrated on installation of underground
electrical and backfill of electrical trenches. The
remaining electrical trenches are scheduled to be
slurried this afternoon and backfilled tomorrow.
3.0 Technical Concerns:
3a Schedule Review:
3a.2b The base line schedule was approved 05/05/04. N/A Complete
3a.12 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3b Submittal Status Review:
3b.12 61 submittals (including resubmittals) have been 06/02/04 FSY
received to date. Currently, 10 submittals
remain outstanding. Of those ten, four have
been outstanding in excess of two weeks.
3c Request For Information Status Review:
3c.11 117 RFI's have been submitted to date. 06/02/04 FSY
Currently, 10 RFI's are outstanding. Of those
10, S have been outstanding in excess of two
weeks.
Page 1 of 3
VANIR • PROGRESS MEETING MINUTES
Meeting #: 12
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
12 3d Field Clarification Status Review:
3d.12 No new field clarifications have been issued. N/A Info
3e.1 Change Order/Proposed Change Order
Status:
3e.12 Twenty eight potential change requests have 06/09/04 TSCl/VCM
been identified of which, 15 have been
submitted. COR Nos. 17 and 19 have been
incorporated into Change Order No. 1. 6 of
the 15 have been negotiated with Campbell
Certified and will be resubmitted. 4 were
submitted during the course of the meeting.
3f Payment Status Review:
3f.12 A draft of Payment Request No. 3 was 06/02/04 TSCI
reviewed following the meeting. TSCI to
submit corrected payment request for
processing.
3g Notice Of Non Conformance Status:
3g 12 There are no outstanding non-conformance N/A Info
notices.
3h As Built Status Review:
3h.12 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.12 Weekly Foreman's Toolbox Safety Meetings are N/A Info
held Tuesday mornings. At this time, there are
no safety issues unresolved.
4.0 Testing/Inspection:
4.12 Kleinfelder is scheduled for compaction tests N/A Info
for electrical and plumbing trench backfill next
week as required.
5.0 New Business:
5f.4b Resolution of the Encroachment by the 06/03/04 TSCl/VCM
Pottery Shop. E. Deleeuw and L. Campbell met
with Mr. Green yesterday to determine whether he
has determined where to move materials and advise
that TSCI will provide labor to assist. Another meeting
will be held next week as a follow up.
Page 2 of 3 VANIR F 503
VANIR • PROGRESS MEETING MINUTES
Meeting #: 12
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
12 5g.6 Potential Delay Claim by Campbell Certified: 05/27/04 VCM/FSY
Alleged delays are identified in submitted CORs.
5g.9 Revised Grading Plan: The finalized plan is 06/09/04 TSCI
expected early next week. There was discussion
regarding the potential impact associated with the
storm drain work. TSCI will contact Builders Power
to investigate the possibility of providing temporary
electrical feeds to the Antique Faire and the Pottery
Yard. (05/20/04). The revised grading plan was received
Tuesday, 05125104,and is being priced. 05127104
5g.12 Reconciliation of Changes to Building Dept. 06/20/04 FSY
Approved Plans: P. Donaldson asked when
changes between the Building Department
approved plans and the bid set will be
reconciled. FSY has committed to a
completion date of 06/20/04. Donaldson
asked if the structural portion might be
completed earlier.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 3 of 3 VANIR F 503
Message • • Page 1 of 1
Larry Campbell
From: David McBride [David.McBride@cityoftemecula.org]
Sent: Friday, May 21, 2004 9:30 AM
To: Larry Campbell
Subject: RE: Weekly Progress Meeting #11
Larry:
Item 3e.11: note english error"will formalized"to will be formalized.
Item 5g.6: : reference to 3e.8 (3e.11 -does not exist?).
Item 5g.11: Rewrite to state that that (one) seat wall at the theater entrance only and that it is was not priced and
not required as part of the bid.
No other comments.
Regards, David
-----Original Message-----
From: Larry Campbell [mailto:Larry.Campbell@Vanir.com]
Sent: Friday, May 21, 2004 7:11 AM
To: David McBride; 'Dave Anderson'; 'Dean Lee'; Paul Donaldson; 'Kevin Terry'; Ed Deleeuw
(Ed Deleeuw@toveysh u Itz.com)
Cc: ayanez@fsyarchitects.com
Subject: Weekly Progress Meeting #11
Gentlemen:
Attached for your use and information. Please call me if there are comments or corrections.
5/21/2004
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: 11 ............ ............. .....
Owner: City_of_Temecula---------—--—---------------
Project: Old Town Temecula
Community Theater
Date: May 20, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File # 15.13
Time: 09:00 a.m. Enclosure: None
David McBride Steve Tovey, Tovey Kevin Terry, Tovey
Attendees: Dept. Public Works (DPW) Shultz Construction (TSCI) Shultz Construction (TSCI)
Ed Deleeuw, Tovey Dean Lee, FSY Architects Larry Campbell, Vanir
Shultz Construction (TSCI) (FSY) Construction Mgmt (vcm)
Meeting # Item # Description Due Action
11 1.0 Approval Of Previous Meeting Minutes:
1.11 No exceptions were taken to the minutes of N/A Info
Meeting No. 10.
2.0 Construction Progress Update:
2.11 Concrete for grade beams and footings was N/A Info
placed on Tuesday, 05/18/04. Presently, forms
are being stripped and bolts and columns are
being cleaned. Underground plumbing and
electrical are progressing.
3.0 Technical Concerns:
3a Schedule Review:
3a.21b The base line schedule was approved 05/05/04. N/A Complete
3a.1 1 Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Following the meeting, a copy of this
schedule was provided to Paul Donaldson and
Kleinfelder.
3b Submittal Status Review:
3b.1 1 42 submittals have been received to date. 05/22/04 FSY
Currently, 9 submittals remain outstanding. Of
those nine, five have been outstanding in
excess of two weeks.
3c Request For Information Status Review:
3c.1 1 106 RFI's have been submitted to date. 05/22/04 FSY
Currently, 7 RFI's are outstanding. None of
those 7 has been outstanding in excess of two
weeks.
Page 1 of 3
VANIR •ROGRESS MEETING MINUTES
Meeting #: 11
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
11 3d Field Clarification Status Review:
3d.11 No new field clarifications have been issued. N/A Info
3e.1 Change Order/Proposed Change Order
Status:
3e.11 Twenty three potential change requests have 05/27/04 VCM
been identified of which, 11 have been
submitted. COR Nos. 17 and 19 were verbally
approved during the course of the meeting and
will formalized in a change order prior to the
next meeting.
3f Payment Status Review:
3f.11 Payment Request No. 2 is being processed for 06/04/04 City of
payment. Temecula
3g Notice Of Non Conformance Status:
3g 11 Notice of Non Conformance No. 1 for rebar N/A Info
issues was issued on Friday, 05/14/04. Those
issues have been corrected and were signed
off by Paul Donaldson on 05/17/04.
3h As Built Status Review:
3h.1 1 Revisions are being posted on a regular basis N/A Info
and are prerequisite to inspections.
3i Safety Items:
3i.11 Weekly Foreman's Toolbox Safety Meetings N/A Info
are held Tuesday mornings. At this time, there
are no safety issues unresolved.
4.0 Testing/Inspection:
4.11 Kleinfelder is scheduled for compaction tests N/A Info
for electrical and plumbing trench backfill next
week as required. Inspection of electrical
conduit prior to backfill is the only City
ns ection required within the next week.
5.0 New Business:
5f.4b Resolution of the Encroachment by the 06/11/04 VCM/DPW
Pottery Shop. D. McBride and L. Campbell met
with Mr. Green following the meeting. Mr. Greene
agreed to three weeks to move materials.
Page 2 of 3 VANIR F 503
VANIR PROGRESS MEETING MINES
Meeting #:
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
11 5g.6 Potential Delay Claim by Campbell Certified: 05/27/04 VCM/FSY
See Item 3e.8,above.(04129104)
5g.9 Revised Grading Plan: The finalized plan is 05/27/04 TSCI
expected early next week. There was
discussion regarding the potential impact
associated with the storm drain work. TSCI will
contact Builders Power to investigate the
possibility of providing temporary electrical
feeds to the Antique Faire and the Pottery Yard.
05/20/04.
5g.11 Granite Seat Walls: TSCI noted that Sheet N/A Info
A2.04 identifies granite seat walls and refers to
the Landscaping Plan. No seat walls are
shown on the Landscaping drawings.
Following discussion, it was determined that
the granite seat walls were not priced and can
be eliminated.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 3 of 3 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting #. ,1.0
Owner: _City of Temecula
Project: Old Town Temecula
Community Theater
Date: May 13, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File# 15.8
Time: 09:00 a.m. Enclosure: None
Attendees: David McBride Kevin Terry, Tovey Ed Deleeuw, Tovey Shultz
Dept, Public Works (DPW) Shultz Construction (TSCI) Construction (TSCI)
Larry Campbell, Vanir
Construction Mgmt (vcM)
Meeting # Item # Description Due Action
10 1.0 Approval Of Previous Meeting Minutes:
1.10 No exceptions were taken to the minutes of N/A Info
Meeting No. 9.
2.0 Construction Progress Update:
2.9 Installation of forms and anchor bolts in grade N/A Info
beams continued through the week.
Underground electrical and plumbing are in
progress. Inspection of reinforcing steel by the
Structural Engineer and Deputy Inspector are
scheduled today with City inspection scheduled
tomorrow. Concrete for grade beams is
scheduled for next Tuesday, 05/18/04.
3.0 Technical Concerns:
3a Schedule Review:
3a.2b The base line schedule was approved 05/05/04. N/A Complete
3a.10. Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Following the meeting, a copy of this
schedule was provided to Paul Donaldson and
Kleinfelder.
Meeting # Item # Description Due Action
09 3b Submittal Status Review:
315.10 40 submittals have been received to date. 05/18/04 FSY
Currently, 10 submittals remain outstanding.
Of those ten, eight have been outstanding in
excess of two weeks.
Page 1 of 3
VANIR •PROGRESS MEETING MINUTES
Meeting #: 10
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
10 3c Request For Information Status Review:
3c.10 102 RFI's have been submitted to date. 05/18/04 FSY
Currently, 15 RFI's are outstanding of which, 6
have been outstanding in excess of two
weeks.
3d Field Clarification Status Review:
3d.10 No new field clarifications have been issued. N/A Info
3e.1 Change Order/Proposed Change Order
Status:
3e.10 Twenty potential change requests have been 05/20/04 VCM/FSY
identified of which, 11 have been submitted.
3f Payment Status Review:
3f.10 TSCI advised receipt of a check for Payment 06/04/04 City of
Request No. 1. Payment Request No. 2 is Temecula
being processed for payment.
3g Notice Of Non Conformance Status:
3g.10 No Notices of Non Conformance have been N/A Info
issued to date.
3h As Built Status Review:
3 h.10 Revisions are being posted on a regular basis. N/A Info
3i Safety Items:
300 Weekly Foreman's Toolbox Safety Meetings N/A Info
are held Tuesday mornings. At this time, there
are no safety issues unresolved.
4.0 Testing/Inspection:
4.10 Kleinfelder is presently inspecting grade N/A Info
beams and is scheduled next week for
concrete.
5.0 New Business:
5f.4b Resolution of the Encroachment by the 05/20/04 DPW
Pottery Shop. It is noted that Mr. Greene has
made no efforts to vacate the area on the north
side. D. McBride will follow up with Mr. Greene.
Page 2 of 3 VANIR F 503
VANIR •PROGRESS MEETING MINUTES
Meeting #: 10
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
10 5g.6 Potential Delay Claim by Campbell Certified: 05/20/04 VCM/FSY
See Item 3e.8,above.(04129104)
5g.9 Revised Grading Plan: TSCI asked the status 05/20/04 City of
of the revised grading plan noting that Temecula
underground plumbing will begin next week. A
copy of the progress print was provided to TSCI
on 05110104. The finalized plan is expected
early next week. psit3lw)
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 3 of 3 VANIR F 503
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting #: 09.,.
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: May 6, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File # 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: Steve Tovey, Tovey Kevin Terry, Tovey Ed Deleeuw, Tovey Shultz
Shultz Construction (Tscl) Shultz Construction (TSCI) Construction (TSCI)
Larry Campbell, Vanir
Construction Mgmt(vcM)
Meeting # Item # Description Due Action
09 1.0 Approval Of Previous Meeting Minutes:
1.9 No exceptions were taken to the minutes of N/A Info
Meeting No. 8.
2.0 Construction Progress Update:
2.9 Installation of reinforcing steel for the grade N/A Info
beams continued through the week and will
continue into next week. Conduit from the SCE
transformer pad to the main service and MSA
have been installed, inspected, and will be
slurried today. Installation of forms and bolt
templates for grade beams and footings began
yesterday and will continue into next week.
3.0 Technical Concerns:
3a Schedule Review:
3a.2b A preliminary construction schedule was N/A Resolved
submitted during the course of the meeting.
VCM requested a CD of the schedule for review.
CD received 03122104. (03125104) Schedule review
comments were provided TSCI on Monday, 03129104.
Revised schedule will be submitted by next meeting.
TSCI's revised schedule incorporating correction
comments was received on Wednesday, 04/07/04.
VCM schedule review comments were forwarded to TSCI on
04/13/04. VCM and TSCI will meet on 04/20/04 to resolve
outstanding issues (04/15/04) Corrections are being made to the
base line schedule as discussed between VCM and TSCI on
Tuesday,04/20/04. (04/22/04) The revised schedule was
submitted o4/28/04(04129/04) The base line schedule was
approved yesterday, 05105104. (05106104)
3a.9. Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Following the meeting, a copy of this
schedule was provided to Paul Donaldson.
Page 1 of 3
VANIR •PROGRESS MEETING MINUTES
Meeting #: 09
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
09 3b Submittal Status Review:
3b.9 40 submittals have been received to date. 05/10/04 FSY
Currently, 9 submittals remain outstanding. Of
those nine, two have been outstanding in
excess of two weeks.
3c Request For Information Status Review:
3c.9 95 RFI's have been submitted to date. 05/10/04 FSY
Currently, 12 RFI's are outstanding with the
longest being 9 work days.
3d Field Clarification Status Review:
3d.8 Field Clarification No. 2 reflecting Architect's N/A Info
Supplemental Instruction No. 2 for depression
of steps in the audience chamber was issued
to TSCI 04/26/04.
3e.1 Change Order/Proposed Change Order
Status:
3e.9 An additional change request (#18) was 05/13/04 VCM/FSY
submitted by TSCI during the course of the
meeting for changes from 6" to 8" studs for a
plumbing wall.
3f Payment Status Review:
3f.9 Payment Request#2 was forwarded to the 05/06/04 TSCI
City of Temecula for payment on 05/04/04.
3g Notice Of Non Conformance Status:
3g 9 No Notices of Non Conformance have been N/A Info
issued to date.
3h As Built Status Review:
3h.9 Revisions are being posted on a regular basis. N/A Info
3i Safety Items:
3i.9 Weekly Foreman's Toolbox Safety Meetings N/A Info
are held Tuesday mornings. At this time, there
are no safety issues unresolved.
Page 2 of 3 VANIR F 503
VANIR •ROGRESS MEETING MINUTES
Meeting #: 09
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
09 4.0 Testing/Inspection:
4.8 There has been no deputy inspection required N/A Info
during the past week.
5.0 New Business:
5f.4b Resolution of the Encroachment by the N/A Resolved
Pottery Shop. David McBride advised that Mr.Greene will be
vacating the encroachment adjacent to the Children's Museum.
The fence between the Merchant Building and Mr.Greene's
property will remain. The new fence that is a part of this project will
be relocated toward to Merchant Building to allow construction
without impacting Mr.Greene's property. (04122/04) It is noted
that Mr. Greene has made no efforts to vacate the area on the
north side. This will impact any drainage improvements to be
made to the subject property. (05106104)
5g.6 Potential Delay Claim by Campbell Certified: 05/10/04 VCM/FSY
TSCI provided a copy of a letter received from
Campbell Certified dated 04/15/04 wherein
Campbell advises that it is being delayed in
completing its shop drawings by design
changes and the addition of steel. No specific
information is provided. Once detailed
information is received, a meeting will be
scheduled with Campbell, TSCI, and VCM to
review and resolve the issue. (04/15104)
See Item 3e.8,above.(04129104)
5g.9 Revised Grading Plan: TSCI asked the status 05/13/04 City of
of the revised grading plan noting that Temecula
underground plumbing will begin next week.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting.If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
..................................................._.
ig ture
Name: Larry E. Bmrplbell
Title: Project Manager
Page 3 of 3 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: _08
Owner: City of Temecula
Project: _Old Town Temecula
Community Theater
Date: April 29, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File # 15.13
Time: 10:00 a.m. Enclosure: None
Kevin Terry, Tovey Ed Deleeuw Tovey
Attendees: Shultz Construction (TSCI) Shultz Construction (TSCI) Dean Lee, FSY Architects
Larry Campbell, Vanir
Construction Mgmt (vCm)
Meeting # Item # Description Due Action
08 1.0 Approval Of Previous Meeting Minutes:
1.8 No exceptions were taken to the minutes of NIA Info
Meeting No. 7.
2.0 Construction Progress Update:
2.8 Short columns that were expected to be installed N/A Info
04/23/04, with the exception of one, were
installed 04/27/04. The remaining column is
scheduled for installation Monday, 05/03.
Conduit sweeps to the main service and MSA
have been installed. Installation of reinforcing
steel for grade beams began today and will
continue through next week.
3.0 Technical Concerns:
3a Schedule Review:
3a.2b A preliminary construction schedule was 05/06/04 VCM
submitted during the course of the meeting.
VCM requested a CD of the schedule for review.
CD received 03122104. (03125104) Schedule review
comments were provided TSCI on Monday, 03129104.
Revised schedule will be submitted by next meeting.
TSCI's revised schedule incorporating correction
comments was received on Wednesday, 04/07/04.
VCM schedule review comments were forwarded to TSCI on
04/13/04. VCM and TSCI will meet on 04/20/04 to resolve
outstanding issues(04/15/04) Corrections are being made to the
base line schedule as discussed between VCM and TSCI on
Tuesday,04120/04. (04/22104) The revised schedule was
submitted o4128104(04129104)
3a.7. Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Following the meeting, a copy of this
I I schedule was faxed to Paul Donaldson.
Page 1 of 3
VANIR •PROGRESS MEETING MINES
Meeting #: 08
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
08 3b Submittal Status Review:
3b.8 39 submittals have been received to date. 05/03/04 FSY
Currently, 7 submittals remain outstanding. Of
those seven, four have been outstanding in
excess of two weeks.
3c Request For Information Status Review:
3c.8 83 RFI's have been submitted to date. 05/03/04 FSY
Currently, 14 RFI's are outstanding with the
longest being 13 work days.
3d Field Clarification Status Review:
3d.8 Field Clarification No. 2 reflecting Architect's N/A Info
Supplemental Instruction No. 2 for depression
of steps in the audience chamber was issued
to TSCI 04/26/04.
3e.1 Change Order/Proposed Change Order
Status:
3e.8 Although seventeen potential items of change 05/06/04 VCM/FSY
have been identified by TSCI, only eight (8)
submittals of proposed changes orders have
been received. Six of those reflect requests
from Campbell Certified for additional costs
resulting from RFI responses. The remaining
two reflect costs for owner requested changes
for repointing brick at the Mercantile Building.
3f Payment Status Review:
3f.8 A draft of Payment Request#2 was reviewed 05/06/04 TSCI
following the meeting.
3g Notice Of Non Conformance Status:
3g 8 No Notices of Non Conformance have been N/A Info
issued to date.
3h As Built Status Review:
3 h.8 Revisions are being posted on a regular basis. N/A Info
3i Safety Items:
3i.8 Weekly Foreman's Toolbox Safety Meetings N/A Info
are held Tuesday mornings. At this time, there
are no safety issues unresolved.
Page 2 of 3 VANIR F 503
VANIR PROGRESS MEETING MINUTES
Meeting #: 08
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
08 4.0 Testing/Inspection:
4.8 There has been no inspection activity during N/A Info
the past week.
5.0 New Business:
5fAb Resolution of the Encroachment by the Pottery N/A Resolved
Shop. David McBride advised that Mr. Greene will be
vacating the encroachment adjacent to the Children's
Museum. The fence between the Merchant Building and Mr.
Greene's property will remain. The new fence that is a part
of this project will be relocated toward to Merchant Building
to allow construction without impacting Mr. Greene's
property. (04122104)
5g.6 Potential Delay Claim by Campbell Certified: 05/06/04 VCM/FSY
TSCI provided a copy of a letter received from
Campbell Certified dated 04/15/04 wherein
Campbell advises that it is being delayed in
completing its shop drawings by design
changes and the addition of steel. No specific
information is provided. Once detailed
information is received, a meeting will be
scheduled with Campbell. TSCI, and VCM to
review and resolve the issue. (04/15104)
No further information has been received from Campbell as of this
date. (04/22/04) See Item 3e.8,above. (04129104)
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting.If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
..._...._----------
Signature
Name: Larry E. Campbell
Title: Project Manager
------------
Page 3 of 3 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting #: 07
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: April 22, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File # 15.6
Time: 10:00 a.m. Enclosure: None
Attendees: Steve Tovey, Tovey Kevin Terry, Tovey Ed Deleeuw,Tovey Shultz
Shultz Construction (TSCI) Shultz Construction (TSCI) Construction (TSCI)
Paul Donaldson, Building Larry Campbell, Vanir
Dept. (Bldg) Construction Mgmt (VCM)
Meeting # Item # Description Due Action
07 1.0 Approval Of Previous Meeting Minutes:
1.7 No exceptions were taken to the minutes of N/A Info
Meeting No. 6.
2.0 Construction Progress Update:
2.7 Short columns are expected to be installed N/A Info
beginning tomorrow, 04/23/04. No other
construction activities have been achieved this
week.
3.0 Technical Concerns:
3a Schedule Review:
3a.2b A preliminary construction schedule was 04/29/04 TSCI
submitted during the course of the meeting.
VCM requested a CD of the schedule for review.
CD received 03122104. (03125104) Schedule review
comments were provided TSCI on Monday, 03129104.
Revised schedule will be submitted by next meeting.
TSCI's revised schedule incorporating correction
comments was received on Wednesday, 04/07/04.
VCM schedule review comments were forwarded to TSCI on
04/13/04. VCM and TSCI will meet on 04/20/04 to resolve
outstanding issues (04/15/04) Corrections are being made to
the base line schedule as discussed between VCM and TSCI on
Tuesday, 04/20/04. 04122104
3a.7. Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting. Following the meeting, copies of this
schedule were provided to Paul Donaldson.
3b Submittal Status Review:
3b.7 35 submittals have been received to date. 04/26/04 FSY
Currently, 7 submittals remain outstanding. Of
those seven, five have been outstanding in
excess of two weeks.
Page 1 of 3
VANIR •PROGRESS MEETING MINES
Meeting #: 07
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
07 3c Request For Information Status Review:
3c.7 64 RFI's have been submitted to date. 04/26/04 FSY
Currently, 9 RFI's are outstanding with the
longest being 8 work days.
3d Field Clarification Status Review:
3d.7 Field Clarification No. 1 reflecting Architect's N/A Info
Supplemental Instruction No. 1 regarding
protection of the elevator hydraulic lines was
issued to TSCI 04/14/04.
3e.1 Change Order/Proposed Change Order
Status:
3e.7 Although seven potential items of change have
been identified by TSCI, no formal submittals
of proposed changes orders have been
received.
3f Payment Status Review:
3f.7 Payment Request #1 was forwarded to the 05/14/04 City of
Cit for payment on 04/12/04. 04/15/04 Temecula
3g Notice Of Non Conformance Status:
3g 7 No Notices of Non Conformance have been N/A Info
issued to date.
3h As Built Status Review:
3 h.7 Revisions are being posted on a regular basis. N/A Info
3i Safety Items:
3i.7 Weekly Foreman's Toolbox Safety Meetings N/A Info
are held Tuesday mornings. At this time, there
are no safety issues unresolved.
4.0 Testing/inspection:
4.7 There has been no inspection activity during N/A Into
the past week.
5.0 New Business:
5f.4b Resolution of the Encroachment by the Pottery N/A Resolved
Shop. David McBride advised that Mr. Greene will be
vacating the encroachment adjacent to the Children's
Museum. The fence between the Merchant Building and Mr.
Greene's property will remain. The new fence that is a part
of this project will be relocated toward to Merchant Building
to allow construction without Impacting Mr. Greene's
property. (04/22/04)
Page 2 of 3 VANIR F 503
VANIR •PROGRESS MEETING MINES
Meeting #: 07
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
07 5g.6 Potential Delay Claim by Campbell Certified: 04/22/04 TSCI
TSCI provided a copy of a letter received from
Campbell Certified dated 04/15/04 wherein
Campbell advises that it is being delayed in
completing its shop drawings by design
changes and the addition of steel. No specific
information is provided. Once detailed
information is received, a meeting will be
scheduled with Campbell, TSCI, and VCM to
review and resolve the issue. (04/15/04)
No further Information has been received from Campbell as of
this date.(04122104)
5g.7 A preconstruction meeting was held yesterday N/A Info
involving the Building Inspector (Eric
Rodecker) and several of the subcontractors
involved in the early stages of the work.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 3 of 3 VANIR F 503
Message • • Page 1 of 1
Larry Campbell
From: David McBride [David.McBride@cityoftemecula.org]
Sent: Monday, April 12, 2004 9:23 AM
To: Larry Campbell
Subject: RE: Meeting Minutes
Thank you -they were a pleasure to read.
-----Original Message-----
From: Larry Campbell [mailto:Larry.Campbell@Vanir.com]
Sent: Monday, April 12, 2004 9:03 AM
To: ayanez@fsyarchitects.com; David McBride; Dean S. Lee; Ed Deleeuw (EdDeleeuw@toveyshultz.com);
Kevin Terry; Paul Donaldson; dave.anderson@vanir.com
Subject: Meeting Minutes
Gentlemen,
Please find attached Meeting Minutes for Weekly Progress Meeting #5 held Thursday, 4/8/04
4/12/2004
VANIR 0 0
PROGRESS MEETING MINUTES
Meeting #: 06
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: April 15, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File # 15.6
Time: 10:00 a.m. Enclosure: None
Attendees: Kevin Terry, Tovey Ed Deleeuw, Tovey Larry Campbell, Vanir
Shultz Construction Shultz Construction Construction Mgmt
Meeting # Item # Description Due Action
06 1.0 Approval Of Previous Meeting Minutes:
1.6 No exceptions were taken to the minutes of N/A Info
Meeting No. 5.
2.0 Construction Progress Update:
2.6 Concrete for column footings was placed on N/A Info
Monday, 04/12/04 and forms were stripped and
column base plates were leveled on Tuesday,
04/13/04. Shop welding of short columns is
scheduled for tomorrow, 04/16/04. It was
confirmed that welding inspection has been
scheduled. No other construction activities have
been achieved this week.
3.0 Technical Concerns:
3a Schedule Review:
3a.2b A preliminary construction schedule was 04/20/04 VCM/TSCI
submitted during the course of the meeting.
VCM requested a CD of the schedule for review.
CD received 03122104. (03125104) Schedule review
comments were provided TSCI on Monday, 03129104.
Revised schedule will be submitted by next meeting.
TSCI's revised schedule incorporating correction
comments was received on Wednesday, 04/07/04.
VCM schedule review comments were forwarded to
TSCI on 04113104. VCM and TSCI will meet on 04t20104
to resolve outstanding issues 04115104
3a.5. Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3b Submittal Status Review:
3b.6 35 submittals have been received to date. 04/20/04 FSY
Currently, 10 submittals remain outstanding.
Of those ten, seven have been outstanding in
excess of two weeks.
Page 1 of 4
VANIR •PROGRESS MEETING MINUTES
Meeting #: 06
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
06 3c Request For Information Status Review:
3c.6 50 RFI's have been submitted to date. 04/19/04 FSY
Currently, 4 RFI's are outstanding; all
submitted on 04/12/04.
3d Field Clarification Status Review:
3d.6 Field Clarification No. 1 reflecting Architect's N/A Info
Supplemental Instruction No. 1 regarding
protection of the elevator hydraulic lines was
issued to TSCI yesterday, 04/14/04.
3e.1 Change Order/Proposed Change Order
Status:
3e.6 Although seven potential items of change have
been identified by TSCI, no formal submittals
of proposed changes orders have been
received.
3f Payment Status Review:
3f.4 TSCI submitted a draft of Payment Request #1 05/14/04 City of
that was reviewed following the meeting. Temecula
Corrections will be incorporated in the
Payment Request to be submitted. TSCI
delivered Payment Request No. 1 during the
course of the meeting. (04.08.04)
Payment Request#1 was forwarded to the City for
payment on 04112104. (04115104)
3g Notice Of Non Conformance Status:
3g.6 No Notices of Non Conformance have been N/A Info
issued to date.
3h As Built Status Review:
3h.5 An informal review disclosed that RFI revisions N/A Info
are being posted on a regular basis.
06 3i Safety Items:
3i.6 Weekly Foreman's Toolbox Safety Meetings N/A N/A
are held Tuesday mornings. At this time, there
are no safety issues unresolved.
4.0 Testing/inspection:
4.6 Kleinf elder has confirmed that a welding 04/16/04 Kleinfelder
inspector has been assigned to inspect shop
welding for columns tomorrow, 04/16/04.
Page 2 of 4 VANIR F 503
VANIR •PROGRESS MEETING MINUTES
Meeting #: 06
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
06 5.0 New Business:
5.b.1 Location of Elevator Machine Room. Plans N/A Resolved
indicated the location of the elevator machine
room at Gridline 6.9/9 and the elevator
approximately 10.5 feet east of Line G at Line
8. No connecting structure is shown to
enclose the hydraulic lines. Tovey Shultz
asked if an alternate location for the elevator
machine room can be found. (03/11/04)
This question was forwarded to FSYArchitects. Response
remains outstanding. (03118104) Response remains
outstanding. (04/01/04) Architect's Supplemental Instruction
No. 1 was received on Monday, 04/05/04. This additional
information will be issued early next week. (04/08.04)
See Item 3d.6, above. (04115104)
5d.2 Review of Granite Slabs. Tovey Shultz 04/21/04 VCM/TSCI
requested a date to review the OFCI granite
for this project. (03/18/04). David McBride will follow
up to determine location of stored granite. (04/01/04).
Subsequent to the meeting, David McBride asked if this
issue can wait for approximately 2 weeks. (04/08/04)
The granite was reviewed by John Meyer, David
McBride,and VCM on Friday 04109104. VCM will review
with TSCI and its masonry subcontractor early next
week. (04115104)
5f.4b Resolution of the Encroachment by the Pottery N/A Info
Shop. While this is an on-going issue, D.
McBride updated the status of the resolution in
progress. (04/08/04)
5g.6 Potential Delay Claim by Campbell Certified: 04/22/04 TSCI
TSCI provided a copy of a letter received from
Campbell Certified dated 04/15/04 wherein
Campbell advises that it is being delayed in
completing its shop drawings by design
changes and the addition of steel. No specific
information is provided. Once detailed
information is received, a meeting will be
scheduled with Campbell, TSCI, and VCM to
review and resolve the issue. (04/15/04)
Page 3 of 4 VANIR F 503
VANIR •PROGRESS MEETING MINUTES
Meeting #: 06
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting.If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: 05
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: April 08, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File # 15.13
Time: 10:00 a.m. Enclosure: None
Attendees: David McBride, Paul Donaldson Kevin Terry, Tovey
Public Works Building Department Shultz Construction
Ed Deleeuw, Tovey Larry Campbell, Vanir
Shultz Construction Construction Mgmt
Meeting # Item # Description Due Action
05 1.0 Approval Of Previous Meeting Minutes:
1.5 No exceptions were taken to the minutes of N/A Info
Meeting No. 4.
2.0 Construction Progress Update:
2.3.b Excavation of the existing cesspool was halted at N/A Resolved
approximately 5-foot depth due to the presence
of an odor similar to that of turpentine. A sample
of the in-situ material was taken by Kleinfelder
today with the promise of results within 24 hours.
(03/25/04). Testing of sample did not provide
conclusive evidence of the potential contaminate.
Additional samples will be taken on Monday, 415,
in an attempt to determine the nature and extent of
the material. Test results are anticipated
Wednesday, 417. (oaoilw)
Sample results were negative. Cesspool was
backfilled on Wednesday, 47. (04/08/04)
2.4 The building pad has been certified by Adkan N/A Resolved
Engineers and Kleinfelder. Kleinfelder
documentation is expected tomorrow 4/2. Upon
receipt of the certification, TSCI will hand-carry
the information to Land Development for
recordation and obtain the building permit.
The Building Permit was obtained by TSCI on
Tuesday, 04106104. (wloalw)
Page 1 of 4
VANIR •PROGRESS MEETING MINUTES
Meeting #: 05
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
05 3.0 Technical Concerns:
3a Schedule Review:
3a.2b A preliminary construction schedule was 04/15/04 VCM
submitted during the course of the meeting.
VCM requested a CD of the schedule for review.
CD received 03122104. (03125104) Schedule review
comments were provided TSCI on Monday,
03129104. Revised schedule will be submitted by
next meeting.
TSCI's revised schedule incorporating correction
comments was received on Wednesday, 04/07/04.
3a.5. Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3b Submittal Status Review:
3b.4 TSCI requested the status of Submittal #14, N/A Info
Concrete Mix Designs. The submittal has
been reviewed and being returned via FedEx.
Submittal#14 was returned to TSCI on Monday,
04105104. (o4ioaro4)
3b.5 33 submittals have been received to date. 04/12/04 FSY
Currently, 12 submittals remain outstanding.
Of those twelve, only one has been
outstanding in excess of two weeks. Six of
those have been submitted within the last
week.
3c Request For Information Status Review:
3c.5 43 RFI's have been submitted to date. There N/A Info
are no BFI's outstanding at this date.
3d Field Clarification Status Review:
3d.5 Architect's Supplemental Instruction No. 1 04/19/04 VCM
regarding protection of the elevator hydraulic
lines has been received and will be issued
early next week.
3e.1 Change Order/Proposed Change Order
Status:
3e.5 Although seven potential items of change have
been identified by TSCI, no formal submittals
of proposed changes orders have been
received.
Page 2 of 4 VANIR F 503
VANIR *PROGRESS MEETING MINES
Meeting #: 05
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
05 3f Payment Status Review:
3f.4 TSCI submitted a draft of Payment Request #1 04/09/04 VCM
that was reviewed following the meeting.
Corrections will be incorporated in the
Payment Request to be submitted. TSCI
delivered Payment Request No. 1 during the
course of the meeting. (w.oa w)
3g Notice Of Non Conformance Status:
3g.5 No Notices of Non Conformance have been N/A Info
issued to date.
3h As Built Status Review:
3h.5 An informal review disclosed that RFI revisions N/A Info
are being posted on a regular basis.
3i Safety Items:
3i.2b Tovey Shultz submitted its Safety Program. N/A Resolved
Preliminary review of the plan reflects that the
plan is generic in nature and does not
specifically address this project. K. Terry will
provide specifics related to this particular
project. (03/18/04). To be submitted by next meeting
(04101104). An addendum to TSCI's safety plan to
address job specific issues was received on Monday,
04.05.04)
3i.2c There was discussion regarding crane N/A Resolved
placement and set-up for structural steel
erection. (03/18/04).
This issue is being addressed in TSCI's job-specific
safety plan. (03125104) To be submitted by next
meeting (04101104). An addendum to TSCI's safety
plan to address job specific issues was received on
Monday,04.05.04)
3i.5 Weekly Foreman's Toolbox Safety Meetings N/A N/A
are held Tuesday mornings. At this time, there
are no safety issues unresolved.
4.0 Testing/Inspection:
4.4 Kleinfelder will confirm compaction of footing N/A Resolved
excavation when all footings have been
completed. Footing compaction was confirmed by
Kleinfelder on Tuesday, 04106104.(04/09/04)
Page 3 of 4 VANIR F 503
VANIR *PROGRESS MEETING MINES
Meeting #: 05
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
05 5.0 New Business:
5.b.1 Location of Elevator Machine Room. Plans 04/12/04 VCM
indicated the location of the elevator machine
room at Gridline B.9/9 and the elevator
approximately 10.5 feet east of Line G at Line
8. No connecting structure is shown to
enclose the hydraulic lines. Tovey Shultz
asked if an alternate location for the elevator
machine room can be found. (03/11/04)
This question was forwarded to FSY Architects.,
Response remains outstanding. (03118104) Response
remains outstanding. (04/01/04) Architect's
Supplemental Instruction No. 1 was received on
Monday, 04105104. This additional information will be
issued early next week. (04108.04)
5d.2 Review of Granite Slabs. Tovey Shultz 04/26/04 PW
requested a date to review the OFCI granite
for this project. (03/18/04). David McBride will follow
up to determine location of stored granite. (04/01/04).
Subsequent to the meeting,David McBride asked if this
issue can wait for approximately 2 weeks. 04108104
5e.3 Tovey Shultz requested a key for the locks on N/A Resolved
the existing Mercantile Bldg. (03/25/04). The key
provided will not operate the front door lock. The
padlock on the rear door will be cut. (04/01/04) A new
key for the Mercantile Building was received on
Wednesday and the lock on the rear door has been
replaced. 04/o8/04
5fAb Resolution of the Encroachment by the Pottery N/A Info
Shop. While this is an on-going issue, D.
McBride updated the status of the resolution in
progress.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: 04
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: April 01, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File # 15.13
Time: 10:00 a.m. Enclosure: None
David McBride, Kevin Terry, Tovey Shultz Ed Deleeuw, Tovey Shultz
Attendees: Public Works Construction Construction
Larry Campbell, Vanir
Construction Mgmt.
Meeting # Item # Description Due Action
04 1.0 Approval Of Previous Meeting Minutes:
1.4 No exceptions were taken to the minutes of N/A Info
Meeting No. 3.
2.0 Construction Progress Update:
2.3.b Excavation of the existing cesspool was halted at 04/07/04 Kleinfelder
approximately 5-foot depth due to the presence
of an odor similar to that of turpentine. A sample
of the in-situ material was taken by Kleinfelder
today with the promise of results within 24 hours.
(03/25/04). Testing of sample did not provide
conclusive evidence of the potential contaminate.
Additional samples will be taken on Monday, 415,
in an attempt to determine the nature and extent of
the material. Test results are anticipated
Wednesday, 417. p4iavo4)
2.4 The building pad has been certified by Adkan 04/02/04 Kleinfelder
Engineers and Kleinfelder. Kleinfelder
documentation is expected tomorrow 4/2. Upon
receipt of the certification, TSCI will hand-carry
the information to Land Development for
recordation and obtain the building permit.
3.0 Technical Concerns:
3a Schedule Review:
3a.2b A preliminary construction schedule was 04/08/04 TSCI
submitted during the course of the meeting.
VCM requested a CD of the schedule for review.
CD received 03/22104. (03125104) Schedule review
comments were provided TSCI on Monday,
03129104. Revised schedule will be submitted by
next meeting.
Page 1 of 4
VANIR •ROGRESS MEETING MINUTES
Meeting #: 04
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
04 3a.4. Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3b Submittal Status Review:
3b.3 Tovey Shultz' submittal log was reviewed N/A Info
during the meeting. The most critical
outstanding submittal is Submittal #7, Rebar
for grade beams/SOG/footings. Submittal#7
was returned on 03131104.
3b.4 TSCI requested the status of Submittal #14, N/A Info
Concrete Mix Designs. The submittal has
been reviewed and being returned via FedEx.
3c Request For Information Status Review:
3c.4 38 RFI's have been submitted to date. 6 RFI's 04/05/04 FSY
remain outstanding with the longest being 3
da s.
3d Field Clarification Status Review:
3d.4 No Field Clarifications (FC's) have been N/A Into
issued to date.
3e.1 Change Order/Proposed Change Order
Status:
3e.4 No Proposed Change Orders (PCO's) have
been submitted at this date. Although 4 items N/A Info
were noted as changes in Tovey Shultz'
Submittal Log, they will be combined into 3.
3f Payment Status Review:
3f.2 Tovey Shultz submitted a preliminary N/A Resolved
Schedule of Values for review. (03/18/04)
VCM will provide a response to the Schedule of Values
by Monday, 03129104. (03125104). TSCI Schedule of
Values was approved on Monday,03129104.
3f.4 TSCI submitted a draft of Payment Request #1 04/08/04 TSCI
that was reviewed following the meeting.
Corrections will be incorporated in the
Pa ment Request to be submitted.
3g Notice Of Non Conformance Status:
3g.4 No Notices of Non Conformance have been N/A Info
issued to date.
Page 2 of 4 VANIR F 503
VANIR •ROGRESS MEETING MINUTES
Meeting #: 04
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
04 3h As Built Status Review:
3h.4 An informal review disclosed that RFI revisions N/A Info
are being posted on are ular basis.
3i Safety Items:
3i.2b Tovey Shultz submitted its Safety Program. 04/08/04 TSCI
Preliminary review of the plan reflects that the
plan is generic in nature and does not
specifically address this project. K. Terry will
provide specifics related to this particular
project. (03/18/04). To be submitted by next
meeting(04101104).
3i.2c There was discussion regarding crane 04/08/04 TSCI
placement and set-up for structural steel
erection. (03/18/04).
This issue is being addressed in TSCI's job-specific
safety plan. (03125104) To be submitted by next
meeting 04101104.
&A Weekly Foreman's Toolbox Safety Meetings N/A N/A
are held Tuesday mornings. At this time, there
are no safety issues unresolved.
4.0 Testing/inspection:
4.4 Kleinfelder will confirm compaction of footing 04/05/04 Kleinfelder
excavation when all footings have been
completed.
5.0 New Business:
5.b.1 Location of Elevator Machine Room. Plans 04/08/04 FSY
indicated the location of the elevator machine
room at Gridline 6.9/9 and the elevator
approximately 10.5 feet east of Line G at Line
8. No connecting structure is shown to
enclose the hydraulic lines. Tovey Shultz
asked if an alternate location for the elevator
machine room can be found. (03/11/04)
This question was forwarded to FSY Architects.
Response remains outstanding. (03118104)
Response remains outstanding. 04101104
Page 3 of 4 VANIR F 503
VANIR PROGRESS MEETING MINUTES
Meeting #: 04
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
04 5d.2 Review of Granite Slabs. Tovey Shultz 04/08/04 PW
requested a date to review the OFCI granite
for this project. (03/18/04). David McBride will
follow up to determine location of stored granite.
(04101104).
5e.3 Tovey Shultz requested a key for the locks on N/A Resolved
the existing Mercantile Bldg. (03/25/04). The key
provided will not operate the front door lock. The
padlock on the rear door will be cut. 04101104
5f.4a Pending Project Changes. David McBride 04/08/04 TSCI
updated the group on the project changes that
are anticipated at this time. Connections to
the existing 24-inch drain are in design as is
the addition of a stairway adjacent to the
existing Antique Faire. TSCI was asked to
obtain pricing for repointing the brick on the
interior of the Mercantile Building.
5f.4b Resolution of the Encroachment by the Pottery N/A Info
Shop. While this is an on-going issue, D.
McBride updated the status of the resolution in
progress.
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR
PROGRESS MEETING MINUTES
Meeting #: 03
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: March 25, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
File # 15.6
Time: 10:00 a.m. Enclosure: Short Interval Schedule
Attendees: Paul Donaldson, Kevin Terry, Tovey Shultz Ed Deleeuw, Tovey Shultz
Building & Safety Construction Construction
Steve Tovey, Tovey Larry Campbell, Vanir
Shultz Construction Construction Mgmt.
Meeting # Item # Description Due Action
03 1.0 Approval Of Previous Meeting Minutes:
1.3 No exceptions were taken to the minutes of N/A Info
Meeting No. 2.
2.0 Construction Progress Update:
2.1 Over-excavation for the building pad began on N/A Info
Wednesday, 3/10/04 along Slot #1. Based upon
the competency of the substrata, over-excavation
was terminated at approximately 4.5 feet beneath
existing grade. Work continues with the
excavation of Slot #2 with excavated material
being laced and compacted in Slot #1.
2.2 Over-excavation and fill placement for the N/A Info
building pad continues. Slot numbers 1 through
4 have been excavated to approximately 4.5 feet
below finish grade in accordance with the revised
direction of the Soils Engineer. Over-excavation
of Slot 5 at the northeast side of the Mercantile
Building is in progress. Slot numbers 1 and 3
have been filled and compacted to the bottom of
slab. Slot 2 has been partially backfilled and
compacted. The grade beam adjacent to the
existing Antique Faire has been excavated to 18-
inches below the grade beam and filled and
compacted to the top of footing.
2.3.a Over-excavation and fill placement for the N/A Info
building pad is ongoing. Import fill placement
began yesterday, 03/2404 and anticipated to be
complete by Friday, 03/26/04.
Page 1 of 4
VANIR •ROGRESS MEETING MINUTES
Meeting #: 03
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
3.0 2.3.b Excavation of the existing cesspool was halted at 03/26/04 Kleinfelder
approximately 5-foot depth due to the presence
of an odor similar to that of turpentine. A sample
of the in-situ material was taken by Kleinfelder
today with the promise of results within 24 hours.
3.0 Technical Concerns:
3a Schedule Review:
3a.2b A preliminary construction schedule was N/A Info
submitted during the course of the meeting.
VCM requested a CD of the schedule for review.
CD received 03122104. 03125104
3a.3. Tovey Shultz' 3-week look ahead schedule was N/A Info
presented and reviewed during the course of the
meeting.
3b Submittal Status Review:
3b.3 Tovey Shultz' submittal log was reviewed 03/29/04 FSY
during the meeting. The most critical
outstanding submittal is Submittal #7, Rebar
for grade beams/SOG/footin s.
3c Request For Information Status Review:
3c.3 31 RFI's have been submitted to date. 3 RFI's 03/29/04 FSY
remain outstanding.
3d Field Clarification Status Review:
3d.3 No Field Clarifications (FC's) have been N/A Info
issued to date.
3e.1 Change Order/Proposed Change Order
Status:
3e.3 No Proposed Change Orders (PCO's) have
been submitted at this date. 3 items were N/A Info
noted as changes in Tovey Shultz' Submittal
Lo .
3f Payment Status Review:
3f.2 Tovey Shultz submitted a preliminary 3/25/04 VCM
Schedule of Values for review. (03/1 a/04)
VCM will provide a response to the Schedule of Values
by Monday, 03129104. (03125104).
Page 2 of 4 VANIR F 503
VANIR •ROGRESS MEETING MINUTES
Meeting #: 03
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
3g Notice Of Non Conformance Status:
3g.3 No Notices of Non Conformance have been N/A Info
issued to date.
3h As Built Status Review:
3 h.3 An informal review disclosed that RFI revisions N/A Info
are being posted on a regular basis.
31 Safety Items:
3i.2b Tovey Shultz submitted its Safety Program. 04/01/04 Tovey Shultz
Preliminary review of the plan reflects that the
plan is generic in nature and does not
specifically address this project. K. Terry will
provide specifics related to this particular
project. (03/18/04).
3i.2c There was discussion regarding crane 04/01/04 Tovey Shultz
placement and set-up for structural steel
erection. (03/18/04).
This issue is being addressed in TSCI's job-specific
safety plan. 03125104
3i.3 Weekly Foreman's Toolbox Safety Meetings N/A N/A
are held Tuesday mornings. At this time, there
are no safety issues unresolved.
4.0 Testing/inspection:
4.3 Excavation, fill placement and compaction are N/A Info
being monitored on a full-time basis by
Kleinfelder.
5.0 New Business:
5.b.1 Location of Elevator Machine Room. Plans 04/01/04 FSY
indicated the location of the elevator machine
room at Gridline B.9/9 and the elevator
approximately 10.5 feet east of Line G at Line
8. No connecting structure is shown to
enclose the hydraulic lines. Tovey Shultz
asked if an alternate location for the elevator
machine room can be found. (03/11/04)
This question was forwarded to FSY Architects.
Res onse remains outstanding. 03118104
Page 3 of 4 VANIR F 503
VANIR •ROGRESS MEETING MINUTES
Meeting #: 03
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
5.0 Building Pad Certification. Tovey Schultz N/A Resolved
noted that the subgrade elevation for the
Orchestra Pit and grade beams are lower than
the building proper and asked how pad
certification will be determined for these areas.
(03/11/04)
This question was discussed with Paul Donaldson
during the course of the meeting. Donaldson will
meet with other City officials and advise. (03118104)
The pad will be certified at the various elevations.
This issue is resolved. 3/ "4
5d.2 Review of Granite Slabs. Tovey Shultz 04/01/04 VCM
requested a date to review the OFCI granite
for this project. 03/18/04 .
5e.3 Tovey Shultz requested a key for the locks on 04/01/04 VCM
the existing Mercantile Bldg. (03/25/04
5f.3 Paul Donaldson advised that effective N/A Info
04/05/04, Building Inspection staff will start in
the office at 7:00 a.m. and will be available
until 8:00 a.m. to receive telephone calls.
03/25/04
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: 02
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: March 18, 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
Senior CM
File # 1 S.B
Time: 10:00 a.m. Enclosure: Short Interval Schedule
Paul Donaldson, Kevin Terry, Tovey Ed Deleeuw, Tovey
Attendees: Building & Safety Shultz Construction Shultz Construction
Norman Biehn, Larry Campbell, Vanir
Kleinfelder Construction Mgmt.
Meeting # Item # Description Due Action
02 1.0 Approval Of Previous Meeting Minutes:
1.1 This is the first weekly progress meeting. N/A N/A
Therefore, no previous meeting minutes exist.
1.2 No exceptions were taken to the minutes of N/A N/A
Meeting No. 1
2.0 Construction Progress Update:
2.1 Over-excavation for the building pad began on N/A N/A
Wednesday, 3/10/04 along Slot #1. Based upon
the competency of the substrata, over-excavation
was terminated at approximately 4.5 feet beneath
existing grade. Work continues with the
excavation of Slot #2 with excavated material
being laced and compacted in Slot #1.
2.2 Over-excavation and fill placement for the N/A N/A
building pad continues. Slot numbers 1 through
4 have been excavated to approximately 4.5 feet
below finish grade in accordance with the revised
direction of the Soils Engineer. Over-excavation
of Slot 5 at the northeast side of the Mercantile
Building is in progress. Slot numbers 1 and 3
have been filled and compacted to the bottom of
slab. Slot 2 has been partially backfilled and
compacted. The grade beam adjacent to the
existing Antique Faire has been excavated to 18-
inches below the grade beam and filled and
compacted to the top of footing.
Page 1 of 5
VANIR •ROGRESS MEETING MINUTES
Meeting #: 02
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
2.0 3.0 Technical Concerns:
3a Schedule Review:
3a.1 Tovey Shultz provided a 3-week look ahead 03/18/04 Tovey Shultz
schedule during the course of the meeting.
The preliminary project schedule will be
submitted by the next meeting.
3a.2a. Tovey Shultz' 3-week look ahead schedule was Info
presented and reviewed during the course of the
meeting.
3a.2b A preliminary construction schedule was 03/22/04 Tovey Shultz
submitted during the course of the meeting.
VCM requested a CD of the schedule for review.
3b Submittal Status Review:
3b.1 Tovey Shultz provided a copy of its current 03/18/04 Tovey Shultz
submittal log. Following review and
discussion, it was determined that corrections
are required.
3b.2 Tovey Shultz provided a copy of its current 03/25/04 Tovey Shultz
submittal log. Following review and
discussion, it was determined that corrections
are required.
3c Request For Information Status Review:
3c.1 Tovey Shultz RFI log was reviewed during the N/A N/A
course of the meeting. At this date, four (4)
RFI's remain outstanding and all are current.
3c.2 Of the 24 RFI's submitted to date, 4 remain N/A N/A
outstanding. The longest outstanding RFI is 2
da s.
3d Field Clarification Status Review:
3d.1 No Field Clarifications (FC's) have been N/A N/A
issued to date.
3d.2 No Field Clarifications (FC's) have been N/A N/A
issued to date.
3e.1 Change Order/Proposed Change Order
Status:
3e.1 No Proposed Change Orders (PCO's) have
been submitted at this date. N/A N/A
Page 2 of 5 VANIR F 503
VANIR •ROGRESS MEETING MINES
Meeting #: 02
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
2.0 3e.2 While no PCO's have been submitted todate,
3 items were noted as changes in Tovey N/A N/A
Shultz' Submittal Log.
3f Payment Status Review:
3f.1 There are no payment requests in process at 3/18/04 Tovey Shultz
this time. Following discussion, it was
determined that Tovey Shultz will submit its
Schedule of Values by the next meeting.
3f.2 Tovey Shultz submitted a preliminary 3/25/04 VCM
Schedule of Values for review.
3g Notice Of Non Conformance Status:
3g 1 No Notices of Non Conformance have been N/A N/A
issued to date.
3g 2 No Notices of Non Conformance have been N/A N/A
issued to date.
3h As Built Status Review:
3h.1 An informal review disclosed that RFI revisions N/A N/A
are being posted on are ular basis.
3h.2 RFI revisions are being posted on a regular N/A N/A
basis.
3i Safety Items:
30 Weekly Foreman's Toolbox Safety Meetings N/A N/A
are scheduled for Tuesday mornings. At this
time, there are no safety issues unresolved.
3i.2a Minutes of last weeks Toolbox Safety Meeting
were forwarded to the CM.
3i.21b Tovey Shultz submitted its Safety Program. 03/25/04 03/25/04
Preliminary review of the plan reflects that the
plan is generic in nature and does not
specifically address this project. K. Terry will
provide specifics related to this particular
ro'ect.
3i.2c There was discussion regarding crane 04/10/04 03/25/04
placement and set-up for structural steel
erection.
Page 3 of 5 VANIR F 503
VANIR *PROGRESS MEETING MINES
Meeting #: 02
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
2.0 4.0 Testing/inspection:
4.1 Over excavation and compaction are being N/A N/A
monitored on a full-time basis by Kleinf elder.
4.2 Norman Biehn has been assigned as the N/A N/A
De uty Inspector for the project.
5.0 New Business:
5.a.1 Identify Trees to be removed. Project 03/18/04 VCM
documents required two trees to be removed
in the area between the theater project and the
Children's Museum. Given that the existing
cottonwood trees are mature, Tovey Shultz
requested that the trees to be removed be
clearly identified. 03/11/04
5.a.2 Following discussion between Larry Campbell N/A Resolved
and Jay Oldham, it was determined that the
driveway connecting the Theater Project to the
Children's Museum will be laid out and trees
that prevent clear access between the two
projects will be removed. This item is
resolved. 03/18/04
5.b.1 Location of Elevator Machine Room. Plans 03/18/04 VCM
indicated the location of the elevator machine
room at Gridline B.9/9 and the elevator
approximately 10.5 feet east of Line G at Line
8. No connecting structure is shown to
enclose the hydraulic lines. Tovey Shultz
asked if an alternate location for the elevator
machine room can be found. 03/11/04
5.1b.2 This question was forwarded to FSY 03/25/04 FSY
Architects. Response remains outstanding.
03/18/04
5.c.1 Building Pad Certification. Tovey Schultz 03/18/04 VCM
noted that the subgrade elevation for the
Orchestra Pit and grade beams are lower than
the building proper and asked how pad
certification will be determined for these areas.
03/11/04
Page 4 of 5 VANIR F 503
VANIR PROGRESS MEETING MINES
Meeting #: 02
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting # Item # Description Due Action
2.0 5.c.2 This question was discussed with Paul 03/25/04 Bldg &Safety
Donaldson during the course of the meeting.
Donaldson will meet with other City officials
and advise. 03/18/04
5d.2 Review of Granite Slabs. Tovey Shultz 03/25/04 VCM
requested a date to review the OFCI granite
for this project. 03/18/04
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting.If
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven days
after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and accurate
record of the meeting.
Sincerely,
Signature
Name: Larry E. Campbell
Title: Project Manager
Page 5 of 5 VANIR F 503
VANIR 0
PROGRESS MEETING MINUTES
Meeting #: 01
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Date: March 11 , 2004
Location: City of Temecula Distribution: Attendees
Project Office Owner: David McBride
Senior CM
File # 15.13
Time: 10:00 a.m. Enclosure: Short Interval Schedule
Attendees: Jay Oldham, Public Kevin Terry, Tovey Ed Deleeuw, Tovey
Works Shultz Construction Shultz Construction
Kevin Paul, Kleinfelder Larry Campbell, VCM
Meeting Item # Description Due Action
01 1 .0 Approval Of Previous Meeting Minutes: N/A N/A
This is the first weekly progress meeting.
Therefore, no previous meeting minutes
exist.
2.0 Construction Progress Update: N/A N/A
Over-excavation for the building pad began
on Wednesday, 3/10/04 along Slot #1 .
Based upon the competency of the
substrata, over-excavation was terminated
at approximately 4.5 feet beneath existing
grade. Work continues with the excavation
of Slot #2 with excavated material being
placed and compacted in Slot_#]_.
3.0 Technical Concerns:
3a.1 Schedule Review: 03/18/04 Tovey Shultz
Tovey Shultz provided a 3-week look
ahead schedule during the course of the
meeting. The preliminary project
schedule will be submitted by the next
meeting.
Page 1 of 4
VANIR F 503 C
Rev 1 11/01
VANIR •PROGRESS MEETING MINES
Meeting #: 01
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting Item # Description Due Action
01 3b.1 Submittal Status Review: 03/18/04 Tovey Shultz
Tovey Shultz provided a copy of its
current submittal log. Following review
and discussion, it was determined that
corrections are required.
— _ -
3c.1 Request For Information Status Review: N/A N/A
Tovey Shultz RFI log was reviewed during
the course of the meeting. At this date,
four (4) RFI's remain outstanding and all
are current.
3d.1 Field Clarification Status Review: N/A N/A
No Field Clarifications (FC's) have been —�
issued to date.
3e.1 Change Order/Proposed Change Order
Status: N/A N/A
No Proposed Change Orders (PCO's) have
been submitted at this date. _
3f.1 Payment Status Review 3/18/04 Tovey Shultz
There are no payment requests in process
at this time. Following discussion, it was j
determined that Tovey Shultz will submit
its Schedule of Values by the next
meeting.
39.1 Notice Of Non Conformance Status: N/A N/A
No Notices of Non Conformance have
been issued to date.
3h.1 As Built Status Review: N/A N/A j
An informal review disclosed that RFI
revisions are being posted on a regular
basis.
Page 2 of 4 VANIR F 503
C
Rev 1 11/01
VANIR •PROGRESS MEETING MINES
Meeting #: 01
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
Meeting Item # Description Due Action
01 3i.1 Safety Items: N/A N/A
Weekly Foreman's Toolbox Safety
Meetings are scheduled for Tuesday
mornings. At this time, there are no
safety issues unresolved.
4.0 Testing/Inspection: N/A N/A
Over excavation and compaction are being
monitored on a full-time basis by
Kleinfelder.
5.0 New Business:
5.a.1 Identify Trees to be removed. Project VCM 03/18/04
documents required two trees to be
removed in the area between the theater
project and the Children's Museum. Given
that the existing cottonwood trees are
mature, Tovey Shultz requested that the
trees to be removed be clearly identified.
5.b.1 Location of Elevator Machine Room. Plans VCM 03/18/04
indicated the location of the elevator
machine room at Gridline B.9/9 and the
elevator approximately 10.5 feet east of
Line G at Line 8. No connecting structure
is shown to enclose the hydraulic lines.
Tovey Shultz asked if an alternate location
for the elevator machine room can be
found.
5.c.1 Building Pad Certification. Tovey Schultz VCM 03/18/04
noted that the subgrade elevation for the
Orchestra Pit and grade beams are lower
than the building proper and asked how
pad certification will be determined for
these areas.
Page 3 of 4 VANIR F S03
c
Rev 1 11/01
VANIR •PROGRESS MEETING MINUPES
Meeting #: UC
Owner: City of Temecula
Project: Old Town Temecula
Community Theater
These minutes were prepared from notes taken by the Construction Manager during the course of the meeting. if
anyone present at the meeting has any changes or corrections, they are to notify Vanir CM in writing, within seven
days after receipt of these minutes. In the absence of such notice, these minutes will be considered a true and
accurate record of the meeting.
Sincerely,
ign ture
Name: Larry E. Campbell
Title: Project Manager
Page 4 of 4 VANIR F S03