HomeMy WebLinkAboutParcel Map 30404 Proposed Rough Grading ReportT. . E. Soils Co. Phone: (951) 894-2121 FAX. (951) 894-2122 41548 Eastman Drive, Unit G • Murrieta, CA 92562 August 31, 2007 Mr. Chuck Delgado 27349 Jefferson Avenue, Suite 201 Temecula, California 92590 SUBJECT: REPORT OF ROUGH GRADING Proposed 2 -Single -Family Residential Parcels 30207 Santiago Road APN: 945-080-009 Temecula, Riverside County, California Work Order No. 1197701.22 Dear Mr. Delgado: E-mail: thesoilsco@aol.com In accordance with your request, we have prepared this Report of Rough Grading presenting the results of our testing of the house pads located at the above subject site. Compaction test results are included in this report in Appendix C, Table 1. The subject pads were graded in accordance with the requirements of the City of Temecula and the 2001 California Building Code (CBC). The 40 -scale "Site Plan" prepared by MDMG, Inc., of Temecula, California, was utilized during grading to locate our field density tests. A reduced copy of the plan was utilized as a base map for our test locations presented as Plate 1. Lewis Valley Contractors performed the grading operations. ACCOMPANYING MAPS AND APPENDICES Site Location Map - Figure 1 Density Test Location Map - Plate I Appendix A - References Appendix B - Laboratory Test Results Appendix C - Results of Compaction Tests T.H.E. Soils Co. Inc. W.O. 1197701.22 0 Mr. Chuck Delgado August 31, 2007 Page 2 Proposed Development 0 The proposed development calls for the construction of two single-family residences. Based on our observation and the site plan, it is anticipated that the subject structures will be founded entirely in properly compacted engineered fill material and that conventional footings and typical slab -on - grade construction will be utilized. Site Description The subject site is located in the city of Temecula in Riverside County, California. The site is bordered on the east by Ormsby Road, on the south by Santiago Road, and on the west and north by large parcel single-family residential developments. The location of the site and surrounding area are shown on our Site Location Map, Figure 1. Prior to grading, the site consisted of moderately sloping terrain, which, for the most part, was vacant and undeveloped. Vegetation on the subject site consisted of a sparse growth of annual weeds and grasses, and overall relief at the site for the proposed development was approximately 60+ -ft. GRADING PROCEDURES Site Preparation The subject pads were cleared of weeds and debris prior to commencement of grading, which were disposed of offsite. The pads were overexcavated a minimum of 3.0 feet below pad grade and extended approximately 5 -ft outside the building footprint. The contractor staked the limits of the pad prior to overexcavation and recompaction. A keyway for parcel l was established for the approximately 5 -foot high fill slope along the southern portion of the proposed house pad. The keyway was established a minimum of 2 -feet into medium dense native materials at the toe and tilted a minimum of 2% into the hillside. The earth materials exposed at the keyway bottom were free of pinpoint pores and roots. A second keyway for parcel 2 was established for the approximately 6 -foot high fill slope along the southern portion of the proposed house pad. The keyway was established a minimum of 2 -feet into medium dense native materials at the toe and tilted a minimum of 2% into the hillside. The earth materials exposed at the keyway bottom were free of pinpoint pores and roots. Prior to placement of fill within the removal, the bottoms were scarified a minimum of 12 -inches, brought to near optimum moisture content, and compacted to at least 90% relative compaction as determined by ASTM D-1557 test method. The fill materials were leveled and mixed by a D4 T.H.E. Soils Co. Inc. W.O. 1197701.22 1] Mr. Chuck Delgado August 31, 2007 Page 3 0 dozer, a 623 scraper, a Cat blade and a loader, and compaction was achieved by wheel rolling by the water truck and loader and track walking by the dozers, and incidental contact from the loaded and unloaded scrapper. TESTING PROCEDURES Maximum Density Determinations Maximum Density/Optimum Moisture determinations were performed in the laboratory on representative samples of onsite soils used in the fill operations. The tests were performed in accordance with ASTM 131557, Test Method A. Test results, which were utilized in determining the degree of compaction achieved during fill placement, are presented in Appendix B, Table I. Fill Soils Soils utilized for compacted fill typically consisted of medium brown silty Sand (Unified Soils Classification -SM) derived from onsite colluvial/alluvial soils and sedimentary bedrock units. Compaction test results are presented in Appendix C, Results of Compaction Tests, Table I. Cut/Fill Transitions Rough grading operations at the site included overexcavation of the two house pads to a minimum of 5 -ft outside the building footprint to a minimum of 3 -ft below finish grade elevation as staked by the contractor, therefore, eliminating the cut/fill transition. Fill and Cut Slove Construction Fill slopes were constructed at a 2:1 (horizontal:vertical) slope ratio running along the southern portion of the proposed house pad on Parcel 1 at a maximum height of 5 -ft. and on Parcel 2 at a maximum height of 6-11. The fill slopes were constructed from existing colluvial/alluvial soils and sedmentary bedrock units. Cut slopes were constructed at a 2:1 (horizontal:vertical) slope ratio on the northerly portion of each pad at maximum heights of l I and 15 -ft. Field Density Testing Field density testing was performed in accordance with ASTM Test Method D2922-01 (nuclear gauge). Areas failing to meet the minimum compaction requirements were reworked and retested until the specified degree of compaction was achieved. The elevations and the results of the field density tests are presented in Appendix C, Results of Compaction Tests, Table 1. The approximate locations of the tests are shown on the Density Test Location Map, Plate 1. T.H.E. Soils Co. Inc. W.O. 1197701.22 0 PJ I 41t amt% • IR1 L r��• • ►� VRAM DRAW a .t 6 � :I i _ r AG ••�583T • f I / r rr I • r YR P4 VOW T 1SANTIAG ddPT/G PIBLD O� ` .��•� rrpi L7/RVF' DIiA.,05.00, - J� O )' arox t - eosa• ,• xxrsrrA�c rias ` � rrrnruxr ._ rJ I RSApWx 1 _ • kxK 7: � a.sedP=.s.+ W • � D•rr.TIR' p T.H.E. Soils Company, Inc. OENSRY TEST LOCATION MAP rRoroeE°:sARaraNClEsnnrREModiMLPAD 30207 e SANTIAGO ROAD 11 APN� 915-080-009 CRY O: TEMECULA, RIVERSIDE COUNTY, CALIFORNM Q woNraoeL �NIINL wn: •IrYr-MN rum � w r .nrornuumlia mwenM irn 0 Mr. Chuck Delgado August 31, 2007 Page 4 Expansion Testing 0 Expansion testing was performed at the completion of rough grading on a representative near surface soil sample obtained from each building pad area. The results, which are listed in Appendix B, Table II indicate that the expansion potential for the onsite soils varied between 13 and 19, which corresponds to a VERY LOW (0-20, Table 18-1-B, 2001 CBC) expansion potential. Sulfate & Chloride Content Soluble Sulfate Content testing was performed on a representative near surface soil sample exposed at each pad surface. The test results varied between a 0.001 to 0.033 (% by weight) amount of soluble sulfate, which equates to a negligible attack hazard (0.0 to 0.10 percentage by weight, Table 19-A-4, 2001 CBC). It is anticipated that, from a corrosivity standpoint, Type 11 Portland Cement can be used for construction. Prime Testing Laboratory, Inc. of Murrieta, California performed the laboratory testing and test results are presented in Appendix B, Table I11. Additionally, the representative samples of the near surface soils were also tested for chloride content. Chloride test results varied between 60 to 90 ppm (parts -per -million). T.H.E. Soils Company, Inc. does not practice corrosion engineering. If specific information or evaluation relating to the corrosivity of the onsite or any import soil is required, we recommend that a competent corrosion engineer be retained to interpret or provide additional corrosion analysis and mitigation. Prime Testing Laboratory, Inc. of Murrieta, California performed the testing; all test results are presented in Appendix B, Table IV. Foundation System Design It is anticipated that the foundation elements should be founded entirely in properly compacted materials. T.H.E. Soils Company, Inc. should perform a footing inspection, prior to placement of reinforcement, to insure the proposed footing excavations are in conformance with the job specifications. The structural engineer should design all footings and concrete slabs in accordance with the allowable foundation pressures and lateral bearing pressures presented for Class 4 soils on Table 18-1-A of the 2001 California Building Code (CBC). The allowable foundation and lateral pressures shall not exceed the values set forth in Table 18-1-A for Class 4 soils unless data to substantiate the use of higher values are submitted. Where the site is prepared as recommended, the proposed structures may bear on continuous and isolated footings. The footings should have a minimum width of 12 -inches, and be placed at least T.H.E. Soils Co. Inc. W.O. 1197701.22 0 Mr. Chuck Delgado August 31, 2007 Page 5 0 12 -inches below the lowest final adjacent grade for one-story houses, with a minimum width of 12 - inches, and be placed at least 18 -inches below the lowest final adjacent grade for two-story houses. Footings may be designed for a maximum safe soil bearing pressure for Class 4 soils as per Table 18-1-A of the 2001 CBC for dead plus live loads. Concrete slabs, in moisture sensitive areas, should be underlain with a vapor barrier consisting of a minimum of six mil polyvinyl chloride membrane with all laps sealed. A 2 -inch layer of clean sand should be placed above the moisture barrier. The 2 -inches of clean sand is recommended to protect the six mil polyvinyl chloride moisture barrier and aid in the curing of the concrete. Total settlements under static loads of footings supported on in-place bedrock materials and sized for the allowable bearing pressures are not expected to exceed about 1/2 to 3/4 of 1 inch. Differential settlements under dynamic loads of footings supported on properly compacted fill materials and sized for the allowable bearing pressures are not expected to exceed 1/4 -inches for a span of 40-fi. These settlements are expected to occur primarily during construction. Soil engineering parameters for imported soil may vary. Utility Trench Backfill Utility trench backfill should be compacted to a minimum of 90% of the maximum dry density, as determined by the ASTM 1557 test method. It is our opinion, that utility trench backfill consisting of onsite or approved sandy soils can best be placed by mechanical compaction to a minimum of 90% of the maximum dry density. All trench excavations should be conducted in accordance with Cal -OSHA standards, as a minimum. The soils encountered during rough grading are generally classified as Type "C" soil in accordance with the CAL/OSHA (California, State of 2007) excavation standards. Unless specifically evaluated by the project engineering geologist, all temporary excavations should be performed in accordance with CAL/OSHA (California, State of, 2007) excavation standards for Type "C" soil. Based upon a soil classification of Type "C", the temporary excavations should not be inclined steeper than 1.5:1 (horizontal: vertical) for a maximum depth of 20 -ft. For temporary excavations deeper than 20 -ft or for conditions that differ from those described for Type "C" in the CAL/OSHA excavation standards, the project geotechnical engineer should be contacted. Surface Drainage Surface drainage should be directed away from foundations of buildings or appurtenant structures. All drainage should be directed toward streets or approved permanent drainage devices. Where landscaping and planters are proposed adjacent to foundations, subsurface drains should be provided to prevent ponding or saturation of foundations by landscape water. T.H.E. Soils Co. Inc. W.O. 1197701.22 0 Mr. Chuck Delgado August 31, 2007 Page 6 Construction Monitoring 0 Observation and testing, by T.H.E. Soils Company, Inc. is essential to verify compliance with recommendations and to confirm that the geotechnical conditions encountered are consistent with the recommendations of this report. T.H.E. Soils Company, Inc. should conduct construction monitoring, at the following stages of construction: • At completion of excavation of footings for foundations • During till placement • During utility trench backfill operations LIMITATIONS This report is issued with the understanding that it is the responsibility of the owner, or his representative, to ensure that the information and recommendations contained herein are brought to the attention of the project architect and engineer. The project architect or engineer should incorporate such information and recommendations into the plans, and take the necessary steps to see that the contractor and subcontractors carry out such recommendations in the field. This firm does not practice or consult in the field of safety engineering. We do not direct the contractor's operations, and we cannot be responsible for other than our own personnel on the site. Therefore, the safety of others is the responsibility of the contractor. The contractor should notify the owner if he considers any of the recommended actions presented herein to be unsafe. This firm did not provide any surveying services at the subject site and does not represent that the building locations, contours, elevations, or slopes are accurately depicted on the plans. The findings of this report are valid as of the report date. However, changes in the conditions of a property can occur with the passage of time, whether due to natural processes or the works of man on this or adjacent properties. In addition, changes in applicable or appropriate standards may occur, whether they result from legislation or the broadening of knowledge. Accordingly, the findings of this report may be invalidated wholly or partially by changes outside our control. Therefore, this report is subject to review and revision as changed conditions are identified. SUMMARY Our description of rough grading operations, as well as testing services, is limited to rough grade testing only between April 12, 2007 and June 22, 2007. The conclusions and recommendations contained herein have been based upon our observation and testing, as noted. It is our opinion the work performed in the areas denoted has generally been accomplished in accordance with the job specifications and the requirements of the regulating agencies. No conclusions or warranties are T.H.E. Soils Co. Inc. W.O. 1197701.22 0 0 Mr. Chuck Delgado August 31, 2007 Page 7 made for the areas not tested or observed. This report is based on information obtained during rough grading. No warranty as to the current conditions can be made. This report should be considered subject to review by the controlling authorities. This opportunity to be of service is sincerely appreciated. If you have any questions, please call. Very truly yours, T.H.E. Soils Company, Inc. -INVI [Rii25 1287{/) y y/9�OrtAt- . Jo . Frey hn inhart, RCE 23464 P ject Geolog Civt Enb' eer, Expires 12-31-07 L2an���n�tia} J nes R. Harrison roject Manager JPF/JTR/JRH:jek T.H.E. Soils Co. Inc. W.O. 1197701.22 0 0 APPENDIX A References T.H.E. Soils Co. Inc. W.O. 1197701.22 0 0 W.C. Hobbs, Consulting Engineer, 2006, "Evaluation of Slope Stability, Cut Slopes on Proposed Grading and Street Improvement Plans, 30270 Santiago Road, City of Temecula, California, Project No: 02019-2", dated December H, 2006. W.C. Hobbs, Consulting Engineer, 2002, "Preliminary Soil Engineering Evaluation, Tentative Parcel Map 30404, Portion of Lot 6 of PM 6807, 30270 Santiago Road, City of Temecula, California, Project No: 02019-1," dated April 24, 2002. T.H.E. Sods Co. Inc. W.O. 1197701.22 0 APPENDIX B Laboratory Test Results 40 T.H.E. Soils Co. Inc. W.O. 1197701.22 0 TABLE Maximum Density/Optimum Moisture Test Location Description Lbs/Ft3 Moisture 1 Medium Brown Silty Sand 130.9 7.4 2 Grayish Brown Sandy Silt 129.5 8.5 3 Grayish Brown Clayey Silt 122.8 12.1 4 Olive Grey Sandy Silt 141.5 3.4 TABLE II Expansion Index Test Location Expansion Index Expansion Potential Parcel 1 13 Very Low Parcel 2 19 Very Low —11 TABLE III Soluble Sulfate Test Location Sulfate Content Sulfate Hazard Parcel 1 0.001 % by weight Negligible Parcel 2 0.033 % by weight Negligible TABLE IV Corrosivity Suite Test Location Saturated Resistivity pH F Chloride Content Parcel1 3700 7.1 90 PPM Parcel 2 2800 7.0 60 ppm T.H.E. Soils Co Inc. N.O. 1197701.22 JUN -12-2007 11:56R FROM:PRIME TE G (951)892-2683 TO*42122 ,m Prime Testing, Inc. 38372 Innovation Ct Ste 102 Murrieta, CA 92563 ph (951) 894.2682 - fx (951) 894.2683 Client: Report Date: Client No: Work Order: Project No: Project Name: T.H.E. Soils Company June 12, 2007 CO1 7F1 1197702.22 Delgado Laboratory lest(s) Results Summary The subject soil sample was processed in accordance with California Test Method CTM 643 and tested for pH / Minimum Resistivity (CTM 643), Sulfate Content (CTM 417) and Chloride Content (CTM 422). The test results follow. Client Data pH Minimum Resistivity Sulfate Content Sulfate Content Chloride Sample Location (ohm -cm) (mg/kg) (/R bywgt) 30270 Santiago Rd., Lower Pad 7.1 1 3,700 10 0.001 g0 'ND=No Detection We appreciate the opportunity to serve you. Please do not hesitate to contact us with any questions or clarifications regarding these results or procedures. �I M I eacM8 M 1 ER Ahmet K. Kaya, Laboratory Manager P.2 Form No. 0.111 Rev,05/06 JUN -1-2007 01:15P FROM:PRIME TING (951)892-2683 T(JW42122 Prime Testing, Inc. 38372 Innovation Ct Ste 102 Murrieta, CA 92563 ph (951) 894-2682 • fx (951) 894.2693 Client: Report Date: Client No: Work Order: Project No: Project Name: T.H.E. Soils Company 3une 1, 2007 C01 7E6 1197701.22 Delgado Laboratory Test(s) Results Summary The subject soil sample was processed in accordance with California Test Method CTM 643 and tested for pH / Minimum Resistivity (CTM 643), Sulfate Content (CTM 417) and Chloride Content (CTM 422). The test results follow: Client Data pH I Minimum I Resistivity Sulfate Content Sulfate Content I Chloride Content Sample Location (ohm -cm) (mg/kg) (% by wgt) (ppm) F/G Pad 7.0 2,800 1 330 0.033 60 'ND -No Detection We appreciate the opportunity to serve you. Please do not hesitate to contact us with any questions or clarifications regarding these results or procedures. az K r J- Ahmet K. Kaya, Laboratory Manager P.1 i a,ce�¢.rian.� M E M 0 E N Form No. 63R ---- Rev.05/06 i I] APPENDIX C Results of Compaction Tests 0 T.H.E. Soils Co. Inc. W.O. 1197701.22 Job No. 1197701.22 0 9 TABLE I RESULTS OF COMPACTION DELGADO August -07 Test No. Test Date Elev / Depth (ft.) Moisture Content (%) Unit Dry Density (PCF) Rel. Comp. (%) Soil Type Location 1 4/13/2007 1112.0 4.9 122.5 97 Na 1 SEE PLATE 2 4/13/2007 1114.0 4.9 123.8 98 NG 1 SEE PLATE 3 4/16/2007 1114.0 8.7 114.8 91 N 1 SEE PLATE 4 4/16/2007 1115.0 9.3 123.4 98 N 1 SEE PLATE 5 1 4/17/2007 1116.0 9.6 114.7 91 N 1 SEE PLATE 6 4/17/2007 1117.0 9.4 119.4 94 N 1 SEE PLATE 7 4/17/2007 1118.0 9.7 1 119.8 95 N 1 SEE PLATE 8 4/17/2007 1119.0 10.0 115.3 91 N 1 SEE PLATE 9 4/18/2007 1120.0 8.8 115.5 91 N 1 SEE PLATE 10 4/18/2007 1121.0 9.7 114.2 90 N l SEE PLATE 11 4/18/2007 122.0 8.9 116.1 92.N l SEE PLATE 12 1 4/18/2007 1123.0 9.4 120.1 95 N l SEE PLATE 13 4/19/2007 1124.0 1 9.9 113.8 90 N I SEE PLATE 14 4/19/2007 1124.0 8.8 120.8 95 N 1 SEE PLATE 15 4/19/2007 1102.0 5.6 107.7 85 No 1 SEE PLATE 16 4/19/2007 1108.0 5.2 112.8 89 Na 1 SEE PLATE 17 4/19/2007 1104.0 9.5 115.7 91.N 1 SEE PLATE 18 4/19/2007 1104.0 8.9 118.7 94 N 1 SEE PLATE 19 1 4/19/2007 1106.0 1 9.2 117.2 93 N 1 SEE PLATE 20 4/19/2007 1106.0 10.0 116.7 92 N l SEE PLATE 21 4/20/2007 1108.0 9.2 117.2 93 N 1 SEE PLATE 22 4/20/2007 1108.0 8.2 122.2 94 N 2 SEE PLATE 23 4/20/2007 1110.0 10.4 119.2 941N t SEE PLATE 24 4/20/2007 1110.0 11.0 120.1 95 N l SEE PLATE 25 4/20/2007 1112.0 12.6 118.5 94 N t SEE PLATE 26 4/20/2007 1112.0 9.3 116.4 92 N I SEE PLATE 27 4/23/2007 1114.0 11.7 117.2 93 N 1 SEE PLATE 28 4/23/2007 1114.0 10.8 125.6 97 N 2 SEE PLATE 29 4/23/2007 1116.0 10.0 121.1 96 N 1 SEE PLATE 30 4/23/2007 1116.0 1 10.6 118.3 94 N 1 SEE PLATE 31 4/23/2007 1118.0 9.1 117.9 93 N 1 SEE PLATE 32 4/23/2007 1118.0 8.8 120.4 95 N 1 SEE PLATE SEE PLANS FOR DETAILS SC -Sand Cone ASTM DI 556-64; DC-Dm,e Cylinder ASTM D2937-71; N -Nuclear ASTM D3017-93, and D2922-91; NG -Natural Ground + 85%- Passing Test; •'-Test Failed, See Retest Job No. 1 197701.22 0 0 TABLE I RESULTS OF COMPACTION DELGADO August -07 Test No. Test I Date Elev / Depth Moisture Content Unit Dry Density (PCF) Rel. Comp. (%) Soil Type Location 33 4/23/2007 1107.0 3.5 127.5 98 N 2 SEE PLATE 34 4/23/2007 1109.0 11.6 113.4 90 N l I SEE PLATE 35 4/24/2007 1126.0 8.9 119.6 95 N 1 SEE PLATE 36 4/24/2007 1126.0 9.2 120.7 95 N 1 SEE PLATE 37 1 4/24/2007 1120.0 9.7 117.1 931N 1 SEE PLATE 38 4/24/2007 1120.0 11.3 119.0 94 N 1 SEE PLATE 39 4/25/2007 1109.0 6.4 112.0 94 N 4 SEE PLATE 40 4/25/2007 1110.0 8.1 114.0 90 N 1 SEE PLATE 41 4/25/2007 1111.0 14.1 112.2 91 N 3 SEE PLATE 42 4/25/2007 1111.0 8.1 121.1 96 N 1 SEE PLATE 43 4/25/2007 1112.0 6.7 115.6 91,N 1 SEE PLATE 44 4/25/2007 1112.0 7.8 115.1 91 N 1 SEE PLATE 45 4/26/2007 1114.0 7.8 111.3 94 N 4 SEE PLATE 46 4/26/2007 1114.0 8.2 115.1 91 N 1 SEE PLATE 47 4/26/2007 1116.0 9.9 118.4 94 N 1 SEE PLATE 48 4/26/2007 1116.0 8.1 122.2 97 N 1 SEE PLATE 49 4/26/2007 1118.0 8.3 124.9 96,N 2 SEE PLATE 50 4/26/2007 1118.0 8.4 121.4 94 N 2 SEE PLATE 51 4/27/2007 1120.0 8.0 114.2 90 N 1 SEE PLATE 52 4/27/2007 1120.0 7.4 117.2 93 N 1 SEE PLATE 53 4/27/2007 1122.0 9.8 1 116.5 92 N 1 SEE PLATE 54 4/27/2007 1122.0 9.2 119.8 95 N 1 I SEE PLATE 55 4/27/2007 1122.0 7.5 121.6 941N 2 SEE PLATE 56 4/27/2007 1122.0 7.8 123.1 97 N 1 SEE PLATE 57 4/30/2007 1124.0 10.0 116.3 92 N 1 SEE PLATE 58 4/30/2007 1124.0 11.6 111.5 91 N 3 SEE PLATE 59 4/30/2007 1124.0 13.2 113.5 90 N 1 SEE PLATE 60 4/30/2007 1124.0 8.8 116.7 92 N i SEE PLATE 61 5/1/2007 1125.0 9.7 121.8 96 N 1 SEE PLATE 62 5/1/2007 1 1125.0 9.8 120.6 95 N 1 SEE PLATE 63 5/1/2007 1125.0 10.7 116.2 92 N 1 SEE PLATE 64 5/1/2007 1125.0 7.7 120.3 95 N 1 SEE PLATE SEE PLANS FOR DETAILS SC -Sand Cone ASTM D1556-64; DC -Drive Cylinder ASTM D2937-71, N -Nuclear ASTM D3017-93, and D2922-91; NG-Nalural Ground+ 85%= Passing Test; **-Test Failed, See Retest Job No. 1197701.22 0 0 TABLE I RESULTS OF COMPACTION DELGADO August -07 Test No. Test Date Elev / Depth (ft.) Moisture Content (%) Unit Dry Density (PCF) Rel. Comp. (%) Soil Type Location 65 5/3/2007 1124.0 7.4 114.0 90 N 1 SEE PLATE 66 5/3/2007 1129.0 4.5 115.9 92 N 1 SEE PLATE 67 5/4/2007 1127.0 8.0 122.7 97 N I SEE PLATE 68 5/4/2007 1127.0 8.0 123.2 97 N l j SEE PLATE 69 5/4/2007 1127.0 7.3 122.0 96 N 1 SEE PLATE 70 5/4/2007 1127.0 10.2 120.8 95 N 1 SEE PLATE 71 5/7/2007 1129.0 7.4 119.1 94 N l SEE PLATE 72 5/7/2007 1129.0 7.2 119.7 95 N I SEE PLATE 73 5/7/2007 1129.0 7.8 120.2 95 N 1 SEE PLATE 74 5/7/2007 1129.0 7.7 120.0 95.N 1 SEE PLATE 75 5/8/2007 1130.0 FG 120.1 95 N 1 SEE PLATE 76 5/8/2007 1130.0 FG 121.7 96 N I SEE PLATE 77 5/8/2007 1130.0 FG 119.7 95 N 1 SEE PLATE 78 5/8/2007 1130.0 FG 119.8 95 N 1 SEE PLATE 79 5/9/2007 1130.0 FG 119.7 95 N 1 SEE PLATE 80 5/9/2007 1130.0 1 FG 111.2 941N 4 SEE PLATE 81 5/9/2007 1130.0 FG 110.9 94 N 4 SEE PLATE 82 5/10/2007 1130.0 FG 112.2 95 N 4 SEE PLATE 83 5/10/2007 1130.0 FG 112.8 95 N 4 SEE PLATE 84 5/11/2007 1132.0 FG 113.2 95 N 4 SEE PLATE 85 5/11/2007 1132.0 FG 112.9 95 N 4 SEE PLATE 86 5/11/2007 1132.0 FG 117.0 92.N 1 SEE PLATE 87 5/22/2007 1092.0 12.8 111.4 94 N 4 SEE PLATE 88 5/22/2007 1092.0 8.0 113.5 90 N 1 SEE PLATE 89 5/22/2007 1098.0 4.3 109.4 92 N 4 SEE PLATE 90 5/22/2007 1102.0 4.0 113.6 90 N 1 SEE PLATE 91 5/22/2007 1094.0 9.5 116.4 92 N 1 SEE PLATE 92 5/23/2007 1094.0 12.1 113.1 95 N 4 SEE PLATE 93 5/23/2007 1096.0 10.7 115.6 91 N l SEE PLATE 94 5/23/2007 1096.0 9.1 114.0 90 N l SEE PLATE 95 5/23/2007 1098.0 11.0 119.6 95 N 1 SEE PLATE 96 5/23/2007 1098.0 11.5 114.6 91 N 1 SEE PLATE SEE PLANS FOR DETAILS SC -Sand Cone ASTM D1556-64; DC -Drive Cylinder ASTM D2937-71; N -Nuclear ASTM D3017-93, and D2922-91; NG -Natural Ground + 85%= Passing Test; **-Test Failed, See Retest Job No. 1197701.22 0 0 TABLE I RESULTS OF COMPACTION DELGADO August -07 Test No. Test Date Elev / Depth (ft.) Moisture Content (%) Unit Dry Density (PCF) Rel. Comp. (%) Soil Type Location 97 5/23/2007 1100.0 11.1 116.4 92 N 1 SEE PLATE 98 5/23/2007 1100.0 11.5 117.5 93 N 1 SEE PLATE 99 5/23/2007 1102.0 11.6 117.7 93 N 1 SEE PLATE 100 5/23/2007 1102.0 8.5 121.3 96 N 1 SEE PLATE 101 5/23/2007 1101.0 3.4 115.2 91 N 1 SEE PLATE 102 5/23/2007 1101.0 1.4 109.0 92 N 4 SEE PLATE 103 5/24/2007 1103.0 11.4 117.0 92 N 1 SEE PLATE 104 5/24/2007 1103.0 11.0 114.7 91 N 1 SEE PLATE 105 5/24/2007 1104.0 8.3 113.6 90 N 1 SEE PLATE 106 5/24/2007 1104.0 12.1 113.3 90.N l SEE PLATE 107 5/24/2007 1104.0 9.7 116.8 92 N 1 SEE PLATE 108 5/24/2007 1104.0 1 10.6 118.1 93 N 1 SEE PLATE 109 5/24/2007 1100.0 11.4 119.2 94 N I SEE PLATE 110 5/24/2007 1102.0 9.9 117.0 92 N 1 SEE PLATE 111 5/24/2007 1100.0 3.2 116.2 92 N 1 SEE PLATE 112 5/24/2007 1096.0 2.2 113.6 90 N 1 SEE PLATE 113 1 5/24/2007 1104.0 9.7 115.1 91 N 1 I SEE PLATE 114 5/24/2007 1104.0 1 9.8 116.3 92 N 1 SEE PLATE 115 5/24/2007 1106.0 9.6 115.8 92 N 1 SEE PLATE 116 5/24/2007 1106.0 8.6 113.4 90 N 1 SEE PLATE 117 5/24/2007 1098.0 7.4 1 l L8 94 N 4 SEE PLATE 118 5/24/2007 1100.0 9.6 117.4 93 N 1 SEE PLATE 119 5/24/2007 1102.0 6.9 110.3 931N 4 SEE PLATE 120 5/25/2007 1104.0 7.7 116.8 92 N 1 SEE PLATE 121 5/25/2007 1104.0 8.6 119.3 94 N 1 SEE PLATE 122 5/25/2007 1106.0 8.2 120.1 95 N l SEE PLATE 123 5/25/2007 1106.0 9.2 119.0 94 N 1 SEE PLATE 124 5/25/2007 1108.0 10.5 1 118.6 94 N I SEE PLATE 125 5/25/2007 1108.0 10.3 117.7 93 N 1 SEE PLATE 126 5/25/2007 1108.0 13.9 115.9 1 92 N 1 I SEE PLATE 127 5/25/2007 1108.0 12.2 112.2 1 91 INI 3 1 SEE PLATE 128 5/25/2007 1098.0 6.7 112.6 1 921NI 3 1 SEE PLATE SEE PLANS FOR DETAILS SC -Sand Cone ASTM D1556-64; DC -Drive Cylinder ASTM D2937-71; N -Nuclear ASTM D3017-93, and D2922-91; NG -Natural Ground+ 95%= Passing Test; **-Test Failed, See Retest Job No. 1197701.22 0 TABLE I RESULTS OF COMPACTION DELGADO August -07 Test No. Test Elev / Date Depth Moisture Content Unit Dry Density (PCF) Rel.Soil Comp. Type (%) Location 129 5/25/2007 1104.0 11.9 114.6 93 N 3 SEE PLATE 130 5/25/2007 1100.0 12.5 114.3 90 N 1 SEE PLATE 131 5/25/2007 1102.0 7.1 109.6 92 N 4 SEE PLATE 132 5/29/2007 1104.0 8.8 115.3 91 N l SEE PLATE 133 1 5/29/2007 1104.0 9.3 116.8 921N 1 SEE PLATE 134 5/29/2007 1106.0 9.7 117.0 92 N 1 SEE PLATE 135 5/29/2007 1106.0 10.1 115.1 91 N l SEE PLATE 136 5/29/2007 1108.0 10.6 119.7 95 N I SEE PLATE 137 5/30/2007 1108.0 10.7 119.3 94 N 1 SEE PLATE 138 5/30/2007 1108.0 10.8 121.8 96 N 1 SEE PLATE 139 1 5/30/2007 1108.0 1 11.6 119.1 941N 1 SEE PLATE 140 5/30/2007 1108.0 10.3 121.6 96 N 1 I SEE PLATE 141 5/30/2007 1108.0 10.4 119.4 94 N 1 SEE PLATE 142 5/30/2007 FG 9.9 120.4 95 N 1 SEE PLATE 143 5/30/2007 FG 8.5 124.5 98 N 1 SEE PLATE 144 5/30/2007 FG 11.6 118.1 93 N 1 SEE PLATE 145 5/30/2007 FG 10.9 119.5 94 N l SEE PLATE 146 5/30/2007 FG 12.0 118.2 93 N 1 SEE PLATE 147 6/22/2007 FG 10.1 112.1 91 N 3 SEE PLATE 148 6/22/2007 FG 12.0 110.0 1 901N! 3 SEE PLATE SEE PLANS FOR DETAILS SC -Sand Cone ASTM DI556-64; DC -Drive Cylinder ASTM D2937-71; N -Nuclear ASTM D3017-93, and D2922-91; NG -Natural Ground+ 85%= Passing Test; **-Test Failed, See Retest